EXECUTIVE SUMMARY

 

Introduction

 

This is the twenty-fourth monthly Environmental Monitoring and Audit (EM&A) report prepared by Maunsell Environmental Management Consultants Limited (MEMCL), which changed the name to ENSR Asia (HK) Ltd. (ENSR) on 1 May 2007 for the “Temporary Construction Waste Sorting Facility at Tseung Kwan O Area 137” (the Project). This report documents the findings of EM&A Works conducted during the impact period in October 2007 for Tseung Kwan O Area 137.

 

As advised by the Contractor, the project commenced on 12 November 2005. The construction activities in October 2007 were:

 

l             Operation of Construction Waste Sorting Facilities (CWSF) by mechanical sorting plant;

l             Modification of conveyor belt of mechanical sorting plant;

l             Maintenance of haul road surface; and

l             Modification of mist blower at Red Zone.

 

Environmental Monitoring Works

 

Air Quality

 

1-hr TSP Monitoring

 

All the monitoring data complied with the AL levels in the reporting month. The 1-hr TSP monitoring results remained at an acceptable level during the construction and operation of the temporary CWSF.

 

24-hr TSP Monitoring

 

All the monitoring data complied with the AL levels in the reporting month. The 24-hr TSP monitoring results remained at an acceptable level during the construction and operation of the temporary CWSF.

 

Complaints, Non-compliance and Prosecutions

 

No environmental complaint, non-compliances or prosecutions were received in the reporting month.

 

Permits and Licences

 

No new permit or license was obtained in the reporting month.

 

Environmental Site Inspection

 

There were 4 site inspections conducted in October 2007. Due to the dry weather conditions, fugitive dust was occasionally observed during dumping and manual sorting of non-inert waste and during vehicle movement along the haul road in Area A. Improving the water spraying at the non-inert waste stockpile and to provide longer water spraying time to the load of the trucks at the weigh-bridge in Area B1 in order to maintain the load damp prior dumping in Area A were recommended.

 

The Contractor was reminded to prevent any silty materials or waste from entering the trapezoidal channel by providing bunding along the banks of the channel. The Contractor was also reminded to properly store the chemicals on site to prevent spillage.


Future Key Issues

 

The weather is expected to be dry and windy in the forthcoming month and as such, the Contractor should provide preventive measures to maintain sufficient dust suppression measures for vehicle movement along haul roads and during dumping and manual sorting of non-inert waste. It is recommended to implement sufficient mitigation measures to eliminate dust generation from dumping and sorting activities.

 

It is also recommended to implement all necessary preventive measures to avoid oil leakage on ground/soil, such as provision of drip trays for all oil drums/chemical containers and placement of tarpaulin sheets on the ground during maintenance of equipment on site. In the event of any oil leakage problem, the Contractor should properly remove the leaked oil and handle the contaminated soil as chemical waste.