EXECUTIVE SUMMARY

 

Introduction

 

This is the thirtieth monthly Environmental Monitoring and Audit (EM&A) report prepared by Maunsell Environmental Management Consultants Limited (MEMCL), which changed the name to ENSR Asia (HK) Ltd. (ENSR) on 1 May 2007 for the “Temporary Construction Waste Sorting Facility at Tseung Kwan O Area 137” (the Project). This report documents the findings of EM&A Works conducted during the impact period in April 2008 for Tseung Kwan O Area 137.

 

As advised by the Contractor, the project commenced on 12 November 2005. The construction activities in April 2008 were:

 

l             Operation of Construction Waste Sorting Facilities (CWSF) by mechanical sorting plant;

l             Disposal of sorted waste to Landfill and Fill Bank;

l             Maintenance work for haul road and mechanical sorting plant;

l             Operation of sorting facility at Area B3; and

l             Survey of inert content of the construction waste.

 

Environmental Monitoring Works

 

Air Quality

 

1-hr TSP Monitoring

 

All the monitoring data complied with the AL levels in the reporting month. The 1-hr TSP monitoring results remained at an acceptable level during the construction and operation of the temporary CWSF.

 

24-hr TSP Monitoring

 

All the monitoring data complied with the AL levels in the reporting month. The 24-hr TSP monitoring results remained at an acceptable level during the construction and operation of the temporary CWSF.

 

Complaints, Non-compliance and Prosecutions

 

No complaint, non-compliance or prosecution was received in the reporting month.

 

Permits and Licences

 

No new permit or license was obtained in the reporting month.

 

Environmental Site Inspection

 

There were 5 site inspections conducted in April 2008. Minor fugitive dust was occasionally observed during vehicle movement along the haul road in Area B2 near the access bridge. The Contractor was reminded to provide water spraying at the area, particularly during sunny and dry weather.

 

Silt was observed accumulated in the trapezoidal channel in Area A. The Contractor was reminded to clear the silt regularly. The Contractor was also reminded to properly maintain the plants on site to prevent oil leakage.


Future Key Issues

 

The weather is expected to be wet and windy in the forthcoming month and as such, the Contractor should provide preventive measures to prevent surface runoff, such as bunding around the site boundaries, and to confirm that a functional temporary drainage system is in place around the site. The Contractor should also maintain sufficient dust suppression measures for vehicle movement along haul roads and during sorting activities. It is recommended to implement sufficient mitigation measures to eliminate dust generation from dumping and sorting activities.

 

It is also recommended to implement all necessary preventive measures to avoid oil leakage on ground/soil, such as provision of drip trays for all oil drums/chemical containers and placement of tarpaulin sheets on the ground during maintenance of equipment on site. In the event of any oil leakage problem, the Contractor should properly remove the leaked oil and handle the contaminated soil as chemical waste.