Site Inspection Summary
Date: |
7 May 2008 |
Time: |
14:30 |
Site: |
Tseung Kwan O Area 137 |
Inspection No.: |
252 |
|
Nil |
|
|
|
Follow up Observation |
|
|
1. |
The scrap metal stockpiled underneath the VGF tipping hall in Area A
had been removed. (Closed) |
|
|
|
New Observations |
|
|
2. |
Deposited silt was accumulated inside the trapezoidal channel in Area
A. The Contractor was reminded to remove the silt regularly and properly
maintain the drainage system. |
|
|
3. |
Oil seepage on ground was found underneath an excavator C8 (under
maintenance) next to the trapezoidal channel in Area A, although a tarpaulin
sheet was provided under the excavator. The Contractor was requested to clear
the oil stain and dispose of as chemical waste. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
During the site inspection, dump truck drivers were on strike. No
transportation of materials / waste inside the sorting facility was observed. |
Site Inspection Summary
Date: |
15 May 2008 |
Time: |
14:30 |
Site: |
Tseung Kwan O Area 137 |
Inspection No.: |
254 |
|
Nil |
|
|
|
Follow up Observations |
|
|
1. |
Deposited silt inside the trapezoidal channel in Area A had been
removed. (Closed) |
|
|
2. |
Oil stain was still observed underneath an excavator C8 (under
maintenance) next to the trapezoidal channel in Area A. The Contractor was
requested to clear the oil stain and dispose of as chemical waste, as well as
provide a larger tarpaulin sheet under the excavator. |
|
|
|
New Observation |
|
|
|
Nil |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
During the site inspection, dump truck drivers were on strike. No
transportation of materials / waste inside the sorting facility was observed. |
Site Inspection Summary
Date: |
22 May 2008 |
Time: |
15:00 |
Site: |
Tseung Kwan O Area 137 |
Inspection No.: |
256 |
|
Nil |
|
|
|
Follow up Observation |
|
|
1. |
The oil stain underneath excavator C8 (under maintenance) next to the
trapezoidal channel in Area A had been cleared. (Closed) |
|
|
|
|
|
|
|
New Observation |
|
|
2. |
General refuse was observed inside the U-channel in Area B2 and inside
the desilting pit near the tipping hall next to the trapezoidal channel in
Area A. The Contractor was reminded to remove the refuse and properly
maintain the drainage system. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
During the site inspection, dump truck drivers were on strike. No
transportation of materials / waste inside the sorting facility was observed. Fireman was still putting out the fire started on 19 April 2008 at the
non-inert stockpile in Area A2. |
Site Inspection Summary
Date: |
29 May 2008 |
Time: |
14:30 |
Site: |
Tseung Kwan O Area 137 |
Inspection No.: |
258 |
|
Nil |
|
|
|
Follow up Observation |
|
|
1. |
General refuse inside the U-channel in Area B2 and inside the
desilting pit near the tipping hall next to the trapezoidal channel in Area A
had been cleared. However, general refuse was observed inside the trapezoidal
channel in Area A2. The Contractor was reminded to remove the refuse and
properly maintain the drainage system. |
|
|
|
|
|
|
|
New Observation |
|
|
2. |
The Contractor was reminded to provide sandbags along the edge of the
trapezoidal channel in Area A2 to divert the site runoff to the desilting
facility and to prevent the site runoff from entering the drainage system
before treatment. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |