Civil Engineering and Development Department
Fill Management
Division
5/F, Civil
Engineering and
Homantin,
Demolition
of Buildings and Structures in the Proposed Kennedy Town Comprehensive
Development Area Site
Environmental Permit No.
EP-136/2002/B
Monthly
EM&A Report for Oct 2007
(Phase
1 Part 1) Rev A
November 2007
Mott Connell Limited,
40/F,
183 Queen’s Road East
Wanchai,
Tel: 2828 5757
Fax: 2827 1823
This document
has been prepared for the titled project or named part thereof and should not
be relied upon or used for any other project without an independent check being
carried out as to its suitability and prior written authority of Mott Connell
being obtained. Mott Connell accepts no
responsibility or liability for the consequence of this document being used for
a purpose other than the purposes for which it was commissioned. Any person using or relying on the document
for such other purpose agrees, and will by such use or reliance be taken to
confirm his agreement to indemnify Mott Connell for all loss or damage
resulting therefrom. Mott Connell
accepts no responsibility or liability for this document to any party other
than the person by whom it was commissioned.
Pursuant to Condition 3.5 of the Environmental Permit
EP-136/2002/B
This Monthly EM&A Report (Oct 2007) for Phase1 Part 1
Has been reviewed, certified and verified by
The following EM&A members
Certified by:
Roger Leung
Environmental
Team (ET) Leader
Mott
Connell Ltd.
Date 14 November
2007
Verified by:
Adi Lee
Independent
Environmental Checker (IEC)
Hyder Consulting Limited
Date 14
November 2007
List of Contents Page
1.2 Coverage of this EM&A
Report
1.3 Project Management Organisation
1.5 Works Undertaken in the
Reporting Month
2.1 Summary of EM&A
Requirements
2.2 Environmental Quality
Performance Limits
2.4 Implementation of Environmental
Mitigation Measures
3.1 Impact Monitoring Schedule
3.5 Results of Impact Monitoring
4. Project Environmental Status
4.2 Status of Environmental
Submissions, Permits and Licenses
4.4 Review of Environmental
Monitoring Procedures
4.5 Implementation Status of
Environmental Mitigation Measures
5. Environmental COMPLIANTS AND
NON-COMPLIANCE
5.1 Summary of Environmental
Complaints, Notifications of Summons and Successful Prosecutions
5.4 Environmental Exceedance/
Non-compliance
6.1 Key Issues and Recommendations
for Coming Month
7. conclusion and recommendation
APPENDIX I -
Environmental Quality Performance Limits
APPENDIX II
- Event and Action Plans
Appendix III
- Schedule of Mitigation Measures from the eia/ EM&A Manual
APPENDIX IV
- Environmental Monitoring and Audit Schedules
APPENDIX V -
Air Quality Monitoring Results and Graphical Presentation
APPENDIX VI
- Noise Monitoring Results and Graphical Presentation
List of Tables
Table 2‑1............. Summary of Impact EM&A Requirements.......................................................... 5
Table 3‑1............. TSP Monitoring Equipment............................................................................... 13
Table 3‑2............. Air-borne Asbestos Fibre Monitoring Equipment................................................ 13
Table 3‑3............. Noise Monitoring Equipment............................................................................. 13
Table 3‑4............. Equipment Calibration Frequencies.................................................................... 14
Table 3‑5............. Monthly Summary Waste Flow Table for 2007.................................................. 15
Table 4‑1............. Status of Environmental Submissions, Permits and
Licenses................................ 16
Table 5‑1............. Summary of Environmental Complaints and Prosecutions................................... 17
Table 5‑2............. Summary of Environmental Site Inspections....................................................... 18
Table AB‑1.......... Event/Action Plan for Air Quality..................................................................... 24
Table AB‑2.......... Event/Action Plan for Noise Impact.................................................................. 25
Table AC‑1.......... Implementation Schedule of Recommended Mitigation Measures........................ 27
Table AC-2.......... Implementation Schedule of Recommended Mitigation Measures........................ 30
Table AC‑3.......... Event Contingency Plan for Environmental Complaints....................................... 41
List of Figures
Figure 1.1............. Layout
Plan of Work Site and Neighbouring Sensitive Receivers.
Figure 1.2............. Project
Organisation Chart
Figure 2.1............. Location of Dust
Monitoring Stations
Figure 2.2............. Location
of Airborne Asbestos Fibre Monitoring Stations
Figure 2.3............. Location of Noise
Monitoring Stations
The EM&A programme for this Project commenced on 28 Sep 2007. This report presents a summary of the environmental monitoring and audit works, list of activities, and mitigation measures implemented during the reporting month of October 2007 (i.e. from 28 Sep 2007 to 31 October 2007).
This is the 1st Monthly EM&A Report for the works carried out during the reporting month.
The following construction activities have taken place during the reporting month: -
· General site clearance works;
· Erection of site office
· Pre-fabrication of steel members for site hoarding to be erected later
· No removal work for asbestos containing materials (“ACM”) and dioxin/ furan contaminated materials (“DCM”) has been conducted;
As no asbestos abatement, dusty and noisy activities have been undertaken on-site, no dust, airborne fibre and noise monitoring has been conducted. In general, the Contractor is preparing to implement all required mitigation measures and has been reasonably responsive to the ET’s recommendations on any discrepancies observed during the weekly environmental site inspection of this reporting month.
No environmental complaint, notification of summons and prosecution was received or made against the Project in the month.
Site inspection is to be carried out on a weekly basis to monitor proper implementation of environmental pollution control and mitigation measures for the Project. In this reporting month, only one site inspection was carried out on 24 Oct 2007.
No non-compliances with regard to site environmental audit were recorded in this reporting month.
Future key issues to be considered in the coming month include: -
· Completion of the baseline condition survey of the surface cracks by Contractor
· Confirmation of date of hoarding erection so that air quality and noise monitoring may commence
1.1.1 This Project – “Demolition of Buildings and Structures in the Proposed Kennedy Town Comprehensive Development Area Site” is a Designated Project defined under the EIA Ordinance. An Environmental Permit (“EP”) was issued on 22 May 2002 [Permit No. EP-136/2002] and was subsequently varied. The latest EP [Permit No. EP-136/2002/B] in force was granted on 18 Oct 2007.
1.1.2 This Contract [No.: CV/2007/05] for Phase 1 Part 1 of the Project was awarded to the Contractor - Hang Kee Construction & Engineering Co. Ltd. and contractually commenced on 28 September 2007. The main Contract will last for 18 months. In accordance with Condition 1.12 of the Environmental Permit EP-136/2002/B, the Director of Environmental Protection (“DEP”) was notified that the commencement date of Phase 1 Part 1 of the Project was 12 October 2007 within the context of the Environmental Permit.
1.1.3 The scope of Phase 1 Part 1 of the Project includes demolition and clearance of all existing chimneys, buildings and ancillary structures above the existing concrete ground slab where the former Kennedy Town Incinerator Plant (“KTIP”) and the Kennedy Town Abattoir (“KTA”) are located, and the demolition and clearance of existing piers at the waterfront adjacent to the KTIP and KTA. It also includes the removal of asbestos containing materials (“ACM”) and dioxin/ furan contaminated materials (“DCM”) prior to demolition of structures and final capping of the underground facilities with clean soil and concrete cover of not less than 130mm thick as required in EP Condition 2.5(e).
1.1.4 A layout plan of the Project site and locations for nearby sensitive receivers is given in Figure 1.1.
1.1.5 Mott Connell Limited (MCL) has been commissioned by the Project Proponent – Civil Engineering and Development Department (“CEDD”) as the Environmental Team (“ET”) to undertake the Environmental Monitoring and Audit (EM&A) programme described in the approved EM&A Manual and the subsequent Updated EM&A Manual for Phase 1 Part 1 of the Project.
1.2 Coverage of this EM&A Report
1.2.1 The EM&A programme for this Project commenced on 28 Sep 2007. This report presents a summary of the environmental monitoring and audit works, list of activities, and mitigation measures implemented during the reporting month in October 2007 (i.e. from 28 Sep 2007 to 31 October 2007).
1.2.2 This is the 1st Monthly EM&A Report for the works carried out during the reporting month.
1.3 Project Management Organisation
1.3.1 The project organisation chart is presented in Figure 1.2.
1.4.1 This Contract for Phase 1 Part 1 of the Project contractually commenced on 28 September 2007. The main Contract will last for 18 months.
1.5 Works Undertaken in the Reporting Month
1.5.1 The following construction activities have taken place during the reporting month: -
· General site clearance works;
· Erection of site accommodation/ office
· Pre-fabrication of steel members for site hoarding to be erected later
· No removal work for asbestos containing materials (“ACM”) and dioxin/ furan contaminated materials (“DCM”) has been conducted;
Figure 1.1 Layout Plan of Work Site and Neighbouring Sensitive Receivers
2.1 Summary of EM&A Requirements
2.1.1 The EM&A programme requires environmental monitoring for air quality, noise, waste management as specified in the Updated EM&A Manual.
2.1.2 1-hour TSP and 24-hour TSP levels at 2 dust monitoring stations and airborne asbestos fibre at 3 fibre monitoring stations are to be monitored during the course of dusty and asbestos abatement work in every reporting month. These air quality monitoring stations for 24-hour TSP and 1-hour TSP measurements and airborne fibre are shown in Figure 2.1 and Figure 2.2.
2.1.3 Noise levels at 3 designated monitoring stations are to be monitored during the course of noisy work in every reporting month. These noise monitoring stations are shown in Figure 2.3.
2.1.4 A summary of impact EM&A requirements is presented in Table 2‑1 below.
Table 2‑1 Summary of
Impact EM&A Requirements
Descriptions |
Locations |
Frequencies |
Duration |
|
Air Quality |
24-Hour TSP |
2 Locations -A1& A2a |
Once every 6 days |
During dust generating construction works |
1-Hour TSP |
2 Locations -A1& A2a |
3 times every 6 days |
During dust generating construction works |
|
Airborne Asbestos Fibre |
3 locations – AF1, AF2 and AF3 |
daily |
During asbestos abatement works |
|
Noise |
Leq (30 min), L10, L90, |
3 Location |
Once per week |
|
Waste |
On-Site Waste Audit |
Active Work Sites |
Weekly |
During Construction |
On-Site Waste Inspection |
||||
General Site Conditions |
Environmental Site Inspection |
Works areas and areas affected by works |
Weekly |
During Construction |
N.B.
A1, AF1, N1 - East of Kennedy Town Abattoir at ground
level
A2a, AF2 - Near Sai See
Street at ground level
AF3 – Kennedy Town Incineration Plant at ground level
N2 - Southeast of Kennedy Town Abattoir at ground
level
N3 - West of Kennedy Town Abattoir at ground level
2.2 Environmental Quality Performance Limits
2.2.1 Environmental Quality Performance Limits for air quality and noise are shown in APPENDIX I.
2.3.1 The Event/ Action Plans for air quality and noise are shown in APPENDIX II.
2.4 Implementation of Environmental Mitigation Measures
2.4.1 The Contractor is required to implement mitigation measures listed in the latest EP, EIA Report and EM&A Manual. During routine site inspections, the Contractor's implementation of mitigation measures are to inspected and reviewed. A schedule of the implementation of mitigation measures identified at the EIA stage is given in APPENDIX III.
Figure 2.1 Location of Dust Monitoring Stations
Figure 2.2 Location of Airborne Asbestos Fibre Monitoring Stations
3.1 Impact Monitoring Schedule
3.1.1 Regular site inspection was carried out on 24 Oct 2007 in this reporting month to assess the compliance with environmental requirements. Monitoring schedule for air quality and noise is given in APPENDIX IV, where applicable.
3.1.2 However, no air quality and noise monitoring was conducted because of insignificant site work undertaken during this reporting month.
24-hour TSP Monitoring
Installation
3.2.1 The HVS has been installed close to representative air sensitive receivers. The following criteria have been considered in the installation of the HVS.
· A horizontal platform with appropriate support to secure the sampler against gusty wind was provided.
· The distance between the HVS and any obstacles, such as buildings, was at least twice the height that the obstacle protrudes above the HVS.
· A minimum of 2m separation from walls, parapets and penthouse was required for rooftop sampler.
· No furnace or incinerator flues were nearby.
· Airflow around the sampler was unrestricted.
· Permission was obtained to set up the samplers and to obtain access to the monitoring stations.
· A secured supply of electricity is needed to operate the samplers.
Preparation of Filter Papers
· Glass fibre filters, G810 are to be labelled with sufficient filters that are clean and without pinholes.
· All filters are to be equilibrated in the conditioning environment for 24 hours before weighing. The conditioning environment temperature is to be around 25 °C and not variable by more than ±3°C, the relative humidity (RH) is to be < 50% and not variable by more than ±5 %. A convenient working RH is 40%.
Field Monitoring
· The power supply is to be secured to ensure the HVS works properly.
· The filter holder and the area surrounding the filter are to be cleaned.
· The filter holder is to be removed by loosening the 4 bolts and a new filter, with stamped number upward, on a supporting screen to be aligned carefully.
· The filter is to be properly aligned on the screen so that the gasket forms an airtight seal on the outer edges of the filter.
· The swing bolts are to be fastened to hold the filter holder down to the frame. The pressure applied is to sufficient to avoid air leakage at the edges.
· The shelter lid is then closed and is secured with the aluminium strip.
· The HVS shall be warmed-up for about 5 minutes to establish run-temperature conditions.
· A new flow rate record sheet is to be set into the flow recorder.
· The flow rate of the HVS is to be checked and adjusted at around 1.1 m3/min. The range specified in the updated EM&A Manual is between 0.6-1.7 m3/min.
· The programmable timer is set for a sampling period of 24 hrs + 1 hr, and the starting time, weather condition and the filter number are to be recorded.
· The initial elapsed time is to be recorded.
· At the end of sampling, the sampled filter is to be removed carefully and folded in half length so that only surfaces with collected particulate matter are in contact.
· It was then placed in a clean plastic envelope and sealed.
· All monitoring information is to be recorded on a standard data sheet.
· Filters are to be sent to a HOKLAS accredited laboratory for analysis.
Maintenance and Calibration
· The HVS and its accessories are to be maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.
· HVSs are to be calibrated at a bi-monthly intervals using GMW-25 Calibration Kit throughout all stages of the air quality monitoring.
1-hour TSP Monitoring
Field Monitoring
3.2.2 The measuring procedures of the 1-hour dust meter are in accordance with the Manufacturer’s Instruction Manual as follows:
·
Set POWER to “ON”, push
· Push the knob at MEASURE position.
· Push “O-ADJ” button. (Then meter’s indication is 0).
· Push the knob at SENSI ADJ position and set the meter’s indication to S value described on the Test Report using the trimmer for SENSI ADJ.
· Pull out the knob and return it to MEASURE position.
· Push “START” button.
Maintenance and Calibration
· The 1-hour TSP meter would be checked at 3-month intervals and calibrated at 1-year intervals throughout all stages of the air quality baseline monitoring.
3.2.3 However, no dust monitoring was carried out because of absence of dusty activities. As per the Updated EM&A Manual, dust monitoring stations are located as shown in Figure 2.1.
Airborne Asbestos Fibre Monitoring
3.2.4 All airborne sampling procedures and specification shall comply with EH10 guidance note and MDHS 39/3 (HSE UK). All air test results and log sheets prepared by the Contractor shall be submitted to ET Leader for reporting purpose.
3.2.5 Air measurement of a minimum of 480 L shall be taken after commencement of abatement work. Results must be below 0.01 fibre/ ml.
3.2.6 However, no dust monitoring was carried out because of absence of asbestos abatement activities. As per the Updated EM&A Manual, airborne asbestos fibre monitoring stations are located as shown in Figure 2.2.
Noise Monitoring
Field Monitoring
· The Sound Level Meter is to be set on a tripod at a height of 1.2 m above the ground.
· Facade measurements are to be made at all 3 monitoring locations.
· The battery condition is to be checked to ensure the correct functioning of the meter.
· Parameters such as frequency weighting, the time weighting and the measurement time are to be set as follows:
-
Frequency weighting: A
-
Time weighting: Fast
-
Time measurement: Three 30 minutes intervals (between
07:00 and 19:00 on normal weekdays) / Three 15 minutes intervals (average 3
consecutives Leq (5min)) (between 0700-1900 hrs on
general holidays)
· Prior to and after each noise measurement, the meter is to be calibrated using a Calibrator for 94 dB at 1000 Hz. If the difference in the calibration level before and after measurement is more than 1 dB, the measurement would be considered invalid and repeat of noise measurement would be required after re-calibration or repair of the equipment.
· During the monitoring period, the Leq, L10 and L90 would be recorded. In addition, site conditions and noise sources are to be recorded on a standard record sheet.
· Noise measurement should be paused during periods of high intrusive noise (e.g. dog barking, helicopter noise) if possible. Observations should be recorded when intrusive noise is unavoidable.
· Noise monitoring is to be cancelled in the presence of fog, rain, wind with a steady speed exceeding 5 m/s, or wind with gusts exceeding 10 m/s.
Maintenance and Calibration
· The microphone head of the sound level meter and calibrator is to be cleaned with soft cloth at quarterly intervals.
· The meter and calibrator are sent to the supplier or HOKLAS laboratory to check and calibrate at yearly intervals.
3.2.7 However, no noise monitoring was carried out because of absence of noisy activities. As per the Updated EM&A Manual, noise monitoring stations are located as shown in Figure 2.3.
Air Quality (Dust)
3.3.1 The equipment used for air quality (dust) monitoring is listed in Table 3‑5.
Table 3‑1 TSP Monitoring Equipment
Equipment |
Model |
HVS Sampler |
GMWS 2310 Accu-vol
system |
Calibrator |
GMW 25 |
1-hour TSP Dust Meter |
8520 Dust Track Aerosol Monitor |
Air Quality (Airborne Asbestos Fibre)
3.3.2 To be confirmed by the Contractor undertaking the airborne asbestos fibre monitoring.
Table 3‑2 Air-borne Asbestos Fibre
Monitoring Equipment
Equipment |
Model |
To be confirmed |
To be confirmed |
Noise
3.3.3 The equipment used for noise monitoring is listed in Table 3‑3.
Table 3‑3 Noise
Monitoring Equipment
Equipment |
Model |
Integrating Sound Level Meter |
Rion NL-31 |
Calibrator |
Rion NC-73 |
3.4.1 The calibration frequencies of the monitoring equipment are provided in Table 3‑4.
Table 3‑4 Equipment Calibration Frequencies
Equipment |
Calibration Frequency |
Latest Calibration Date |
High Volume Sampler GMWS 2310 Accu-vol system |
Every two months |
10 Sep 2007 |
1-hour TSP Dust
Meter 8520 Dust Track Aerosol Monitor |
Every year |
22 Sep 2006 |
Integrated SLM, Rion NL-31 |
Every year |
29 March 2007 |
Sound level calibrator Rion NC-73 |
Every year |
25 June 2007 |
3.5 Results of Impact Monitoring
Air Quality Monitoring Results
3.5.1 No air quality monitoring results collected for this reporting month.
Noise Monitoring Results
3.5.2 No noise monitoring results collected for this reporting month.
Waste Management
Table 3‑5 Monthly
Summary Waste Flow Table for 2007
Month |
Actual
Quantities of Inert C&D Materials Generated Monthly |
Actual
Quantities of C&D Wastes Generated Monthly |
||||||||||||||||||
Total
Quantity Generated |
Broken
Concrete |
Reused
in the Contract |
Reused
in other Projects |
Disposed
of at Public Fill |
Metals |
Paper/
Cardboard |
Plastics |
Chemical
waste |
Others
(e.g. refuse) |
|||||||||||
(In
‘000 tons) |
(In
‘000 tons) |
(In
‘000 tons) |
(In
‘000 tons) |
(In
‘000 tons) |
(In
‘000 kg) |
(In
‘000 kg) |
(In
‘000 kg) |
(In
‘000 kg) |
(In
‘000 tons) |
|||||||||||
Est.
|
Act. |
Est.
|
Act. |
Est.
|
Act. |
Est.
|
Act. |
Est.
|
Act. |
Est.
|
Act. |
Est.
|
Act. |
Est.
|
Act. |
Est.
|
Act. |
Est.
|
Act. |
|
Jan |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Feb |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Mar |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Apr |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
May |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
June |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sub-total |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Jul |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Aug |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Sep |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Oct |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Nov |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Dec |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Total |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
4.1.1 One environmental meeting was held on day of site inspection on 24 Oct 2007.
4.2 Status of Environmental Submissions, Permits and Licenses
4.2.1 A summary of status of all environmental submissions, permits, licenses, and/or notifications to EPD for this Project during the reporting period is presented in Table 4‑1 below.
Table 4‑1 Status of Environmental Submissions, Permits and Licenses
Item |
Description |
Date of Application |
Status |
1. |
Environmental Permit (EP No. EP-136/2002/B) |
27 Sep 2007 |
Valid |
New submissions |
|||
2. |
No submissions/ applications this month |
N/A |
N/A |
4.3.1 The actual quantities of inert C&D materials and non-inert C&D wastes generated by activities of the Project in the month are provided in Table 3‑5. A trip ticket system will implemented for all offsite waste disposals.
4.4 Review of Environmental Monitoring Procedures
4.4.1 The monitoring works conducted by the Environmental Team has been inspected regularly. No changes in the environmental monitoring procedures are considered necessary at this early stage.
4.5 Implementation Status of Environmental Mitigation Measures
4.5.1 An updated Implementation Schedule of Mitigation Measures from the EIA/ EM&A Manual has been given in APPENDIX III.
4.5.2 During this reporting month, there has not been major progress that warrants the implementation of the listed mitigation measures.
5.1 Summary of Environmental Complaints, Notifications of Summons and Successful Prosecutions
5.1.1 No environmental complaints were received during the reporting month. APPENDIX II presents the environmental complaint event contingency plan of the Project and Table 5‑1 below presents a statistics of complaints, notification of summons and successful prosecution since the commencement of the Project.
Table 5‑1 Summary of Environmental Complaints
and Prosecutions
Complaints Logged |
Summons Served |
Successful Prosecution |
|||
Oct 2007 |
Cumulative |
Oct 2007 |
Cumulative |
Oct 2007 |
Cumulative |
0 |
0 |
0 |
0 |
0 |
0 |
5.1.2 No environmental complaint, notification of summons and prosecution was received or made against the Project in the month.
5.2.1 No environmental enquiries were received during the reporting month.
5.3.1 No unusual events were recorded during the reporting month.
5.4 Environmental Exceedance/ Non-compliance
5.4.1 The Event and Action Plans for air quality and noise are presented in APPENDIX II. No exceedance of Action and Limit Levels for 1-hour and 24-hour TSP and noise levels was recorded in the month.
Air Quality - Dust
5.4.2 Not applicable. No dust monitoring was undertaken during this reporting month.
Air Quality – Airborne Asbestos Fibre
5.4.3 Not applicable. No airborne asbestos fibre monitoring was undertaken during this reporting month.
Noise Impact
5.4.4 Not applicable. No noise monitoring was undertaken during this reporting month.
Waste Management
5.4.5 Not applicable.
Site Environmental Audit
5.4.6 Site inspection is to be carried out on a weekly basis to monitor proper implementation of environmental pollution control and mitigation measures for the Project. In this reporting month, only one (monthly) site inspection was carried out jointly by the ET and IEC on 24 Oct 2007.
5.4.7 Major findings jointly provided by the ET and IEC from the site inspection is summarised in Table 5‑2 below.
Table 5‑2 Summary of Environmental Site Inspections
Date of Inspection |
Major Observations |
Action(s) |
24 October 2007 |
Latest EP not displayed at the site entrance |
Contractor reminded at the site meeting to rectify |
Surface cracks observed on ground. Conditions are varied. Most of them are minor but some exhibit slight lifting of the concrete slab. |
Contractor to conduct baseline condition survey for these cracks for use of subsequent repair and monitoring for signs of deterioration |
|
· Waste oil (free product) found floating on a water- filled trough below the removed oil tank inside the incineration plant · Oil soaked soil found on either sides of the trough |
Contractor asked to propose the method statement for clean-up |
5.4.8 No non-compliances with regard to site environmental audit were observed in this reporting month.
6.1 Key Issues and Recommendations for Coming Month
6.1.1 Key issues to be considered in the coming month include: -
· Completion of the baseline condition survey of the surface cracks by Contractor
· Confirmation of date of hoarding erection so that air quality and noise monitoring may commence
7.1.1 EM&A was performed in October 2007. All monitoring and audit results, if any, in the month were checked and reviewed.
7.1.2 As no asbestos abatement, dusty and noisy activities have been undertaken on-site, no dust, airborne fibre and noise monitoring was conducted. In general, the Contractor is preparing to implement all required mitigation measures and has been reasonably responsive to the ET’s recommendations on any discrepancies observed during the weekly environmental site inspection of this reporting month.
7.1.3 No environmental complaints, notification summons or successful prosecutions have been received or made against this Project in the month.
7.2.1 No recommendations made at this stage pending more site progress achieved.
Action and Limit Levels for 24-hour TSP
Monitoring Station |
Action Level (mg/m3) |
Limit Level (mg/m3) |
A1 |
180.4 |
260 |
A2a |
177.8 |
260 |
Action and Limit Levels for 1-hour TSP
Monitoring Station |
Action Level (mg/m3) |
Limit Level (mg/m3) |
A1 |
369.1 |
500 |
A2a |
357.3 |
500 |
Action and Limit Levels (Leq)
for Construction Noise
Time
Period |
Action
Level |
Limit
Level |
||
N1 |
N2 |
N3 |
||
0700 – 1900 hours on normal weekdays |
When one documented complaint is received from any one of the sensitive receivers |
75 |
75 |
75 |
0700 – 2300 hours on public holidays including Sundays and 1900 – 2300 hours on all days |
Subject to requirements stipulated in future Construction Noise Permits |
|||
2300 – 0700 on all days |
Table AB‑1 Event/Action
Plan for Air Quality
EVENT |
|
|
ACTION |
|
ET |
IEC |
ER |
CONTRACTOR |
|
ACTION LEVEL |
||||
1. Exceedance
for one sample |
1. Identify
source 2. Inform IEC
and ER 3. Repeat
measurement to confirm finding 4. Increase
monitoring frequency to daily |
1. Check
monitoring data submitted by ET 2. Check
Contractor’s working method |
1. Notify Contractor 2. Check monitoring data and Contractor's
working methods |
1. Rectify any
unacceptable practice 2. Amend working
methods if appropriate |
2. Exceedance for two or more consecutive
samples |
1. Identify
source 2. Inform IEC
and ER 3. Repeat
measurements to confirm findings 4. Increase
monitoring frequency to daily 5. Discuss with
Contractor , IEC and ER for remedial actions required 6. If exceedance
continues, arrange meeting with IEC and ER 7. If exceedance
stops, cease additional monitoring |
1. Checking
monitoring data submitted by ET 2. Check
Contractor’s working method 3. Discuss with
ET and Contractor on possible remedial measures 4. Advise the ER
on the effectiveness of the proposed remedial measures 5. Supervise
implementation of remedial measures |
1. Confirm receipt of notification of failure in
writing 2. Notify Contractor 3. Check monitoring data and Contractor's
working methods 4. Discuss with IEC and Contractor on potential
remedial actions 5. Ensure remedial actions properly implemented |
1. Submit
proposals for remedial actions to ER within 3 working days of notification 2. Implement the
agreed proposals 3. Amend
proposal if appropriate |
LIMIT LEVEL |
||||
1. Exceedance
for one sample |
1. Identify source 2. Inform ER and EPD 3. Repeat measurement to confirm finding 4. Increase monitoring frequency to daily 5. Assess effectiveness of Contractor's remedial
actions and keep IEC, EPD and ER informed of the results |
1. Checking monitoring data submitted by ET 2. Check Contractor’s working method 3. Discuss with ET and Contractor on possible
remedial measures 4. Advise the ER on the effectiveness of the
proposed remedial measures 5. Supervisor implementation of remedial
measures |
1. Confirm receipt of notification of failure in
writing 2. Notify Contractor 3. Check monitoring data and Contractor's
working methods 4. Discuss with ET Leader and Contractor
potential remedial actions 5. Ensure remedial actions properly implemented |
1. Take immediate action to avoid further
exceedance 2. Submit proposals for remedial actions to ER
within 3 working days of notification 3. Implement the agreed proposals 4. Amend proposal if appropriate |
2. Exceedance for two or more consecutive
samples |
1. Identify source 2. Inform IEC, ER and EPD the causes &
actions taken for the exceedances 3. Repeat measurement to confirm findings 4. Increase monitoring frequency to daily 5. Investigate the causes of exceedance,
Contractor’s working procedures to identify possible mitigation 6. Arrange meeting with IEC and ER to discuss
the remedial actions to be taken 7. Assess effectiveness of Contractor's remedial
actions and keep IEC, EPD and ER informed of the results 8. If exceedance stops, cease additional
monitoring |
1. Discuss amongst ER, ET and Contractor as the
potential remedial actions 2. Review Contractor’s remedial actions whenever
necessary to ensure their effectiveness and advise the ER accordingly 3 Supervise the implementation of remedial
measures |
1. Confirm receipt of notification of failure in
writing 2. Notify Contractor 3. Carry out analysis of Contractor's working
procedures with IEC to determine possible mitigation to be implemented 4. Discuss amongst Environmental Team Leader and
the Contractor potential remedial actions 5. Review Contractor's remedial actions whenever
necessary to assure their effectiveness 6. If exceedance continues, consider what
portion of the work is responsible and instruct the Contractor to stop that
portion of work until the exceedance is abated |
1. Take immediate action to avoid further
exceedance 2. Submit proposals for remedial actions to ER
within 3 working days of notification 3. Implement the agreed proposals 4. Resubmit proposals if problem still not under
control 5. Stop the relevant portion of works as
determined by the ER until the exceedance is abated |
Table AB‑2 Event/Action Plan for Noise Impact
EVENT |
ACTION |
|||
ET |
IEC |
ER |
CONTRACTOR |
|
Action
Level is reached |
1.
Inform IEC and ER 2.
Carry out investigation 3.
Report the results of the investigation to the IEC
and Contractor 4.
Discuss with the Contractor and formulate remedial
measures |
1.
Discuss amongst ER, ET and Contractor on the
potential remedial actions 2.
Review Contractor's remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly 3.
Supervise the implementation of remedial measures |
1.
Confirm receipt of notification of failure in writing 2.
Notify Contractor 3.
Require Contractor to propose remedial measures for
the analyzed noise problem 4.
Ensure remedial measures are properly implemented |
1.
Submit noise mitigation proposal to IEC 2.
Implement noise mitigation proposals |
Limit
Level is reached |
1.
Inform IEC, ER, EPD and Contractor 2.
Identify source 3.
Repeat measurement to confirm findings 4.
Carry out analysis of Contractor's working procedures
to determine possible mitigation to be implemented 5.
Inform IEC, ER and EPD the causes & actions taken
for the exceedances 6.
Assess effectiveness of Contractor's remedial actions
and keep IEC, EPD and ER informed of the results 7.
If exceedance stops cease additional monitoring |
1.
Discuss amongst ER, ET and Contractor on the
potential remedial actions 2.
Review Contractor's remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly 3.
Supervise the implementation of remedial measures |
1.
Confirm receipt of notification of failure in writing 2.
Notify Contractor 3.
Require Contractor to propose remedial measures for
the analyzed noise problem 4.
Ensure remedial measures are properly implemented 5.
If exceedance continues, consider what portion of the
work is responsible and instruct the Contractor to stop that portion or work
until the exceedance is abated |
1.
Take immediate action to avoid further exceedance 2.
Submit proposals for remedial actions to IEC within 3
working days of notification 3.
Implement the agreed proposals 4.
Resubmit proposals if problem still not under control 5.
Stop the relevant portion of works as determined by
the ER until the exceedance is abated |
Table AC‑1 Implementation Schedule of Recommended Mitigation
Measures
No. |
Activity |
Mitigation/ EIA
Recommendations |
Responsibility for
Implementation |
Location Duration completion Of measures |
Implementation Stage |
Relevant Guidelines
Legislation |
1 |
Ash Disposal |
|
|
|
|
|
I |
Treatment |
The
ash deposits are mainly contaminated by dioxins and furans and mixed with
asbestos containing materials. Handling, transportation and disposal of the
ash waste in line with relevant regulations. Collection, immobilisation and
testing of waste for disposal to landfill shall be carried out according to
the relevant regulations and recommendations of the EIA including
immobilisation by collection and mixing the ash material with cement. Pilot mixing and TCLP tests should establish
the ratio of cement to ash to the satisfaction of EPD. Ash waste to be treated and placed into
steel drums lined with plastic sheeting.
The drums should be adequately sealed and in new or good condition. Prior agreement of the disposal criteria
from EPD and agreement to disposal from the landfill operator must be
obtained. As an
additional measure, release of contaminants from disturbed ash should be
minimised prior to gathering up the ash materials and amended water
containing a wetting agent should be sprayed on the ash. The wetting agent will assist in water
penetration to thoroughly soak the ash and ensure dust levels are reduced without
using excessive water. The use of amended water for dust suppression will
minimise the use of excessive water that would result in surface runoff in
the removal process. Dust suppression
can be carried out in a controlled manner and no insurmountable environmental
problem would result |
CEDD’s Contractor |
KTCDA work areas. Duration of the ash
removal |
A@ |
1, 10, EIA |
II |
Disposal |
To monitor the disposal of waste at landfills, a
“trip-ticket” system (WBTC No. 5/99) for all solid waste transfer/disposal
operations should be implemented. The
system should be included as a contractual requirement, and monitored by the
Environmental Team and audited by the Independent Checker (Environment). |
CEDD’s Contractor |
As above |
A |
1, 5, 9 |
III |
Asbestos
Removal |
An asbestos abatement programme should be submitted to EPD
for approval prior to the commencement of the asbestos abatement work. |
CEDD and
Contractor |
As above |
A |
4 |
2 |
Demolition |
|
|
|
|
|
A |
Non-blasting
Methodology |
Waste
Management Plan to be submitted to EPD.
Demolition by Non-Blasting Methodology Only. All structures and buildings should be
demolished and removed prior to demolition of chimneys |
CEDD |
KTCDA work areas. Duration of the
demolition |
C# |
8 |
B |
Material
Storage |
Covers for dusty stockpiles and control of dust emissions from construction
(demolition) works requires appropriate dust control measures to be
implemented in accordance with the requirements in the Air Pollution Control
(Construction Dust) Regulation. |
CEDD’s Contractor |
As above |
C |
4 |
C |
Vehicle
movement |
Haul
road watering, vehicle wheel wash prior to exit. Where practical, access roads should be
protected with crushed gravel. |
CEDD’s Contractor |
As above |
C |
4 |
D |
Plant
maintenance |
All
plant shall be maintained to prevent any undue air emissions. |
CEDD’s Contractor |
As above |
Prior to start of works |
4 |
E |
Improved
Site Hoarding |
Boundary hoarding to be
modified in form of noise barrier to provide effective noise screening and
made of panels with a superficial surface density of at least 10 kg/m3 |
CEDD’s Contractor |
As above |
C |
Env. Permit |
F |
Demolition
Sequence |
Include
careful consideration and positioning of portable noise barriers to allow
noise attenuation. |
CEDD’s Contractor |
As above |
C |
8 |
G |
Portable
Noise Barriers |
Moveable noise barriers
shall be provided close to PME in cases where, in the opinion of the
Engineer, such PME has the potential to cause noise nuisance to sensitive receivers
and where a benefit will result. Such
barriers shall be made of panels with superficial surface density not less
than 10 kg/m3. |
CEDD’s Contractor |
As above |
C |
Env. Permit |
H |
Plant
Operation |
Modify
continuous operational periods for noisy plant to comply with noise criteria.
|
CEDD’s Contractor |
As above |
C |
Env Permit |
I |
Demolition
Techniques |
Selection
of non-blasting demolition techniques to minimise noise and vibration. |
CEDD’s Contractor |
As above |
C |
8 |
J |
Plant
maintenance |
All
plant shall be maintained to prevent any undue noise nuisance. |
CEDD’s Contractor |
As above |
C |
2, 3 |
K |
Wheel
wash |
All
wheel wash water shall be diverted to a sediment pit. |
CEDD’s Contractor |
As above |
C |
5 |
L |
Sediment
control |
Sediment
removal facilities shall provided and be maintained and excavated as
necessary to prevent sedimentation of channels. Perimeter channels should be provided.
Works should be programmed for the dry season where feasible. Environmental
guidelines for the handling and disposal of discharges from construction
sites, as stipulated in the Practice Note for Professional Persons,
Construction Site Drainage (ProPECC PN 1/94) to be followed. |
CEDD’s Contractor |
As above |
C |
5, 12 |
M |
Surface
water diversion |
All
clean surface water shall be diverted around the site. |
CEDD’s Contractor |
As above |
C |
5, 12 |
N |
Fuel can
storage |
All fuel
cans shall be placed within a bunded area. Any fuel spills shall be mopped up
as necessary. |
CEDD’s Contractor |
As above |
C |
5,6 |
O |
Material,
plant move-ment & fuel can filling. |
Any fuel
or oil spills shall be excavated and disposed of. |
CEDD’s Contractor |
As above |
C |
6,7 |
P |
Generators
|
All
generators shall be placed within a bunded area. Any fuel spills shall be
mopped up as necessary. |
CEDD’s Contractor |
As above |
C |
5,6,7 |
Q |
Material
containers |
All
empty bags and containers shall be collected for disposal. |
CEDD’s Contractor |
As above |
C |
6,7 |
R |
Worker
generated litter and Waste |
Litter
receptacles shall be placed around the site. Litter shall be taken regularly
to the refuse collection points. Chemical toilets (or suitable equivalent)
should be provided for workers. Any canteens should have grease traps. |
CEDD’s Contractor |
As above |
C |
6 |
S |
Neighbourhood
nuisance |
All
complaints regarding construction works shall be relayed to the environmental
team. |
CEDD’s Contractor |
As above |
C |
1, 6 |
T |
Legal
requirements |
Different
types of waste should be segregated, stored, transported and disposed of in
accordance with the relevant legislative requirements and guidelines |
CEDD’s Contractor |
As above |
C |
1,6 |
U |
On-site
separation |
On-site
separation of municipal solid waste and construction/demolition wastes shall
be conducted in order to minimise the amount of solid waste to be disposed to
landfill. |
CEDD’s Contractor |
As above |
C |
1, 11 |
V |
Temporary
storage area |
Separated
wastes should be stored in different containers, skips, or stockpiles to
enhance reuse or recycling of materials and encourage their proper disposal. |
CEDD’s Contractor |
As above |
C |
1, 11 |
W |
Record
of wastes |
Records
of quantities of wastes generated, recycled and disposed (with locations)
shall be kept. |
CEDD’s Contractor |
As above |
C |
1, 9 |
X |
Trip-ticket
system |
To
monitor the disposal of waste at landfills and control fly-tipping, a
“trip-ticket” system under WBTC N0.5/99 for all solid waste transfer/disposal
operations should be implemented. The
system should be included as a contractual requirement, and monitored by the
Environmental Team and audited by the Independent Checker (Environment). |
CEDD’s Contractor |
As above |
C |
1, 9 |
|
|
|
|
|
|
|
4 |
Monitoring and Audit |
To be
carried out in accordance with the Implementation Schedule in Table AC-2. |
CEDD*/
Contractor/ RSS |
KTCDA works areas During demolition |
C |
1 |
* Normally undertaken by a
specialist monitoring team employed directly by the proponent and audited by
the IEC
@ A = during ash removal (before
demolition)
# C
= during construction (i.e. demolition phase).
1.
Environmental Impact Assessment Ordinance Technical Memorandum (EIAO)
2.
Noise Control Ordinance
3.
The ProPECC Note PN2/93 (Construction Noise
daytime limits)
4.
Air Pollution Control Ordinance (APCO)
5.
Water Pollution Control Ordinance (WPCO)(Cap. 358)
6.
Waste Disposal Ordinance (Cap 354)
7.
Waste Disposal (Chemical Waste)(General) Regulation (Cap 354)
8.
Draft Code of Practice on Demolition of Buildings (BD, 1998)
9.
Works Bureau Technical Circular No. 5/99, Trip-ticket System for
Disposal of Construction and Demolition Material
10. Guidance Notes for
Investigation and Remediation of Contaminated Sites
11.
Works Bureau Technical Circular No. 5/98, On Site Sorting of
Construction Waste on Demolition Sites
12.
ProPECC Note PN 1/94Construction Site Drainage
Table AC-2 Implementation
Schedule of Recommended Mitigation Measures
EIA Ref. |
EM&A Ref. |
Environmental Protection Measures / Mitigation Measures |
Location / Timing |
Implementation Agent |
Implementation Stage |
Relevant Legislation and Guidelines |
||
D |
C |
O |
||||||
Air
Quality |
||||||||
6.3.2 |
|
Adoption of good site practices and avoid practices likely to raise dust level |
KTCDA Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
6.3.2 |
|
Frequent
cleaning and damping down of stockpiles and dusty areas of the Site. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
APCO (Cap. 311); Air Pollution Control
(Construction Dust) Regulation; EIAO-TM |
6.3.2 |
|
Reducing
drop height during material handling or wall felling. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
APCO (Cap. 311); Air Pollution Control
(Construction Dust) Regulation; EIAO-TM |
6.3.2 |
|
Imposing
a vehicle speed restriction of 15 km/hr within the Site and confine haulage and waste
collection vehicles to designated roadways inside the site. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
APCO (Cap. 311); Air Pollution Control
(Construction Dust) Regulation; EIAO-TM |
6.3.2 |
|
Provision
of wheel washes facilities for Site vehicles leaving the Site. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
APCO (Cap. 311); Air Pollution Control
(Construction Dust) Regulation; EIAO-TM |
6.3.2 |
|
Regular
plant maintenance to minimise exhaust emission. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
APCO (Cap. 311); Air Pollution Control
(Construction Dust) Regulation; EIAO-TM |
6.3.2 |
|
Sweep
up dust and debris at the end of each shift. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
APCO (Cap. 311); Air Pollution Control
(Construction Dust) Regulation; EIAO-TM |
|
2.9.1 |
Stockpiles of dusty waste materials greater than
20m3 shall be enclosed on three sides, with walls extending above
the pile and 2 metres beyond the front of the pile. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
APCO (Cap. 311); Air Pollution Control
(Construction Dust) Regulation; EIAO-TM |
|
2.9.1 |
Any vehicle with an open load carrying area used
for moving potentially dusty material shall have properly fitting side and
tail-boards. Materials having the
potential to create dust shall not be loaded to a level higher than the side
and tail boards and shall be covered by a clean tarpaulin in good
condition. The tarpaulin shall be
properly secured and shall extend at least 300m over the edges of the side
and tail-boards. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
APCO (Cap. 311); Air Pollution Control
(Construction Dust) Regulation; EIAO-TM |
|
2.9.1 |
Effective water sprays shall be used during the
collection and loading of dusty wastes and other similar materials, when dust
is likely to be created and to dampen all stored materials during dry and
windy weather. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
APCO (Cap. 311); Air Pollution Control
(Construction Dust) Regulation; EIAO-TM |
|
2.9.1 |
Areas within the KTCDA site where there is a
regular movement of vehicles, shall have an approved hard surface and be kept
clean of loose surface material. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
APCO (Cap. 311); Air Pollution Control
(Construction Dust) Regulation; EIAO-TM |
|
2.9.1 |
Conveyor belts shall be fitted with wind-boards,
and conveyor transfer points and hopper discharge areas shall be enclosed to
minimize dust emission. All conveyors
carrying materials which have the potential to create dust shall be totally enclosed
and fitted with belt cleaners. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
APCO (Cap. 311); Air Pollution Control
(Construction Dust) Regulation; EIAO-TM |
|
2.9.1 |
Adequate dust suppression plant including water
bowers with spray bars shall be provided. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
APCO (Cap. 311); Air Pollution Control
(Construction Dust) Regulation; EIAO-TM |
Noise |
||||||||
5.8.1
& 5.8.2 |
|
Movable
barriers as noise shields shall be considered for deployment close to noisy
equipment. Where required, these
should be made of panels with a superficial surface density of at least 7
kg/m2. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
NCO (Cap. 400);
EIAO-TM; PN 2/93 |
5.8.2 |
3.8.3 |
Silenced
and super silenced type equipment. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
NCO (Cap. 400);
EIAO-TM; PN 2/93 |
5.8.2 |
|
Reduction
in number of plant operating simultaneously. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
NCO (Cap. 400);
EIAO-TM; PN 2/93 |
5.8.2 |
|
Use
of modified site hoarding to a perimeter noise barrier as a noise shield. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
NCO (Cap. 400);
EIAO-TM; PN 2/93 |
5.8.2 |
|
Re-scheduling
and restricting hours of operation of noisy tasks. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
NCO (Cap. 400);
EIAO-TM; PN 2/93 |
Water
Quality |
||||||||
|
4.3.2 |
Use
of sediment traps, where appropriate. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
PN
1/94, WPCO (Cap. 358) |
|
4.3.2 |
Adequate maintenance of drainage systems to
prevent flooding and overflow. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
PN
1/94, WPCO (Cap. 358) |
|
4.3.3 |
Provision of temporary channels to facilitate
run-off discharge into the appropriate watercourses, via a silt retention
pond, and permanent drainage channels to incorporate sediment basins or traps
and baffles to enhance deposition rates. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
PN
1/94, WPCO (Cap. 358) |
|
4.3.4 |
Provision of temporary and permanent drainage
pipes and culverts to facilitate run-off discharge and shall be adequately
designed for the controlled release of storm flows. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
PN
1/94, WPCO (Cap. 358) |
|
4.3.4 |
Regular cleaning and maintenance of all sediment
traps. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
PN
1/94, WPCO (Cap. 358) |
|
4.3.4 |
When construction works has finished or the
temporary diversion is no longer required, temporarily diverted drainage
shall be reinstated to its original condition. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
PN
1/94, WPCO (Cap. 358) |
|
4.3.5 |
Installation of wheel washing facilities to
ensure no earth, mud and debris is deposited on roads. Sand and silt in the wash water from such
facilities shall be settled out and removed prior to discharge of the used
water into storm drains. A section of
the road between the wheel washing bay and the public road shall be paved
with backfall to prevent wash water or other site
run-off from entering the public road drains. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
PN
1/94, WPCO (Cap. 358) |
|
4.3.6 |
Provision of oil interception facilities in
appropriate areas in the drainage system, where oil spills may occur, and
regularly emptied to prevent the release of oil and grease into the storm
water drainage system after accidental spillage. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s Contractor |
|
ü |
|
PN
1/94, WPCO (Cap. 358) |
|
4.3.9 |
Debris
and rubbish on site should be collected, handled and disposed or properly to
prevent such material from entering the water column and causing water
quality impacts. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s Contractor |
|
ü |
|
PN
1/94, WPCO (Cap. 358) |
|
4.3.10 |
Fuel
storage areas should be provided with locks and be sited on sealed areas if
required, within bunds of a capacity equal to 110% of the storage capacity of
the largest container (to provide a safety margin) and control spilt fuel
oils. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
Waste Management – General |
||||||||
7.11.2 |
5.2.33 |
The
Waste Management Plan shall be prepared in accordance with WBTC No. 29/2000
(superseded by ETWB TC(W) No. 15/2003) and shall provide details of the
measures and procedures considered necessary to control and manage the
storage, transportation and disposal of all wastes generated during the
demolition. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
ü |
ü |
|
ETWB
TC(W) No. 15/2003 |
7.10.30 |
5.2.37 |
Wastes
should be handled and stored in a manner which ensures that they are held
securely without loss or leakage thereby minimising the potential for
pollution. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.30 |
5.2.37 |
Only
reputable waste collectors authorised to collect the specific category of
waste concerned should be employed. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.30 |
5.2.37 |
Appropriate
measures should be employed to minimise windblown litter and dust during
transportation by either covering trucks or transporting wastes in enclosed
containers. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.30 |
5.2.37 |
The
necessary waste disposal permits should be obtained from the appropriate
authorities, if they are required, in accordance with the Waste Disposal
Ordinance (Cap 354), Waste Disposal (Chemical Waste) (General) Regulation
(Cap 354) and Government Land Ordinance (Cap 28). |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
Waste
Disposal Ordinance (Cap 354), Waste Disposal (Chemical Waste) (General)
Regulation (Cap 354), |
7.10.30 |
5.2.37 |
Collection
of general refuse should be carried out frequently, preferably daily. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.30 |
5.2.37 |
Waste
should only be disposed of at licensed sites and site staff and the civil
engineering Contractor should develop procedures to ensure that illegal
disposal of wastes does not occur. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.30 |
5.2.37 |
Waste
storage areas should be well maintained and cleaned regularly. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.30 |
5.2.37 |
Records
should be maintained of the quantities of wastes generated, recycled and
disposed, determined by weighing each load. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
Waste Management - General Refuse |
||||||||
7.10.20 |
5.2.27 |
Office
wastes can be reduced through the policies for re-use of paper in printers
and copiers for draft documents. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
The
policies of recycling e.g. paper and toners or cartridges if volumes are
large enough to warrant collection, should be
encouraged with participation in a local collection scheme if one is
available. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
In
order to reduce waste, the number of photocopies shall be reduced to a
minimum while internal documents and external documents shall be copied on
both sides of paper where appropriate.
Recycling bins for paper and toners will be provided in site office to
facilitate the recycling of paper. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.19 |
5.2.26 |
General
refuse is generated largely by food service activities on site, so reusable
rather than disposable dishware should be used if feasible. Aluminium cans are often recovered from the
waste stream by individual collectors if they are segregated or easily
accessible, so separate, labelled bins for their deposit should be provided if
feasible. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
Putrescible
wastes, such as lunch box, and domestic wastes generated on-site shall be
stored in enclosed bins or compaction units separate from C&D and
chemical wastes. Waste paper will be
stored in containers clearly marked as recyclable or waste. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
Public Health and Municipal Services Ordinance
(Cap. 132) |
7.10.18 |
5.2.25 |
A
reputable waste collector should be employed by the Contractor to remove
general refuse, separately from C&D material and chemical wastes,
preferably daily to minimise odour, pest and litter impacts. The burning of refuse on construction sites
is prohibited by law. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
Public Health and Municipal Services Ordinance (Cap.
132), Air
Pollution Control (Open Burning) Regulation |
|
|
Waste
disposal records shall be obtained from the appropriate authorities and
collection of general refuse and general site housekeeping should be carried
out. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
Waste Disposal Ordinance (Cap. 354); Waste
Disposal (Chemical Waste) (General) Regulation (Cap. 354); |
Waste Management - C&D Materials |
||||||||
7.10.7 |
5.2.7 |
The
Contractor should recycle C&D material on-site as far as possible. Planning, careful design and good site
management of the demolition process can minimise over ordering and avoidable
waste. Areas within the Site areas can
be segregated for the separation and storage.
Proper segregation of wastes on Site will increase the feasibility of
utilising recycling contractors to recycle certain components of the waste
stream. Concrete and masonry can be
crushed and used as fill to level the Site after demolition. However there will be little or no
excavation of any underground structures therefore the majority of inert
waste will need to be delivered to public filling areas. Steel reinforcing bars can be re-used by
scrap steel mills. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
ü |
ü |
|
ETWB TC(PS) No. 25/99,
12/2000; ETWB TC(W) No. 15/2003 |
|
|
“Selective
Demolition” involves demolition and removal of wastes of the same category
one at a time. In general, domestic
wastes such as furniture, household appliances; metal components such as
window frames, pipes; timber components such as doors, wooden floors; and
other wastes such as tiles, asphalt materials, ceramic products should be
removed first. The building demolition
shall begin after all the above non-structural materials have been stripped
and removed. To avoid mixing the
non-recyclable bricks with the broken concrete, the demolition sequence
should be planned in such a way that brick walls are demolished first and
stockpiled separately before the demolition of structural members. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
All
C&D materials arising from the demolition work shall be sorted on-site
and separated into different groups for off-site disposal at landfills,
public filling areas, in filling areas provided by the Contractor, or
recycling at the C&D waste recycling facilities as appropriate. All fill to be disposed of at public
filling areas have to be sorted and broken down to meet the requirements of
the Dumping Licence conditions. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
ETWB TC(PS) No. 12/2000 |
|
|
Designated
areas for segregation and temporary storage of reusable and recyclable
materials should be identified in the Waste Management Plan to be prepared by
the Contractor. The Contractor should
recycle as much of the C&D material as possible on site. Different areas of the work site should be
designated for such segregation and storage wherever site conditions permit. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
C&D
material should be removed from site as soon as practicable to avoid adverse
environmental impacts due to on-site storage of the material. It should be sorted/separated at the
construction site as far as practicable into two main types: inert (including
soil, rock, concrete, brick, aggregates and asphalt) and non-inert (wood,
paper, general garbage and other inorganic).
Recyclable C&D materials such as broken concrete and rock should
be further sorted out from the inert portion and be delivered to recycling
facilities as designated by the Engineer’s Representative for processing into
recycled aggregates for use in construction.
The non-recyclable inert portion can be used as public fill for
dumping in public filling areas whilst the non-inert portion is classified as
C&D waste which will require to be disposed of at the WENT Landfill Site
or other areas as designated by EPD. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
The
Environment, Transport and Works Bureau Technical Circular (Works) No.
31/2004 – Trip Ticket System for Disposal of Construction & Demolition
Materials promulgates the amended trip ticket system (TTS) for public works
contracts including capital works contracts, where C&D materials
including waste generated on site require disposal. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
ETWB TC(W) No. 31/2004 |
Waste Management - Chemical Waste |
||||||||
7.10.10 |
5.2.10 |
For
those processes that generate chemical waste, it may be possible to find
alternatives which generate reduced quantities or even no chemical waste, or less
dangerous types of chemical waste. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.11 |
5.2.11 |
Chemical
waste that is produced, as defined under Section 3 of the Waste Disposal
(Chemical Waste) (General) Regulation, should be handled in accordance with
the Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
Waste
Disposal (Chemical Waste) (General) Regulation |
7.10.12 |
5.2.12 |
Containers
used for the storage of chemical wastes should: a) Be
suitable for the substance they are holding, resistant to corrosion,
maintained in a good condition, and securely closed; b)
Have a capacity of less than 450 l unless the specifications have been
approved by the EPD; and; c)
Display a label in English and Chinese in accordance with instructions
prescribed in Schedule 2 of the Regulations. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.13 |
5.2.13 |
The
storage area for chemical wastes should: a) Be
clearly labelled and used solely for the storage of chemical waste; b) Be
enclosed on at least 3 sides; c)
Have an impermeable floor and bunding, of capacity to accommodate 100% of the
volume of the largest container or 20% by volume of the chemical waste stored
in that area, whichever is the greatest; d)
Have adequate ventilation; e) Be
covered to prevent rainfall entering (water collected within the bund must be
tested and disposed as chemical waste if necessary); and f) Be
arranged so that incompatible materials are adequately separated. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.14 |
5.2.14 |
Disposal
of chemical waste should: a) Be
via a licensed waste collector; and b) Be
to a facility licensed to receive chemical waste, such as CWTC, which also
offers a chemical waste collection service and can supply the necessary
storage containers; or c) Be
to a recycling or reprocessing facility licensed by EPD. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.16 |
5.2.15 |
Asbestos
waste that is produced should be handled in accordance with the Code of
Practice on the Handling, Transportation and Disposal of Asbestos
Wastes. Detailed requirements have
been presented in the Asbestos Study Report. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
Type
1 asbestos wastes (bonded asbestos wastes (other than blue or brown asbestos)
in good condition) shall be packed with 2 individual layers of strong
transparent plastic sheets of not less than 0.15 mm thickness and completely
sealed with adhesive tapes. Type 1
waste shall be packed in suitable sizes for easy handling. The height of each
package shall not exceed 750 mm. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
Type
2 asbestos wastes (any waste containing loose asbestos fibres (other than
blue or brown asbestos)) must be contained, as soon as it is produced, in
strong bags made from plastic or other containers approved by EPD. The bags should be goose-neck sealed by
means of adhesive tapes. A bag filled
with asbestos waste should be placed inside another plastic bag to provide
additional protection. The colour of
the inner bag should be white while the outer bag should be transparent to
facilitate visual inspection. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
The
handling of Type 3 asbestos wastes (all blue asbestos (crocidolite) and brown
asbestos (amosite), whether in good condition or not, or any articles
contaminated by blue or brown asbestos) should be similar to that of Type 2
except that the colour of the inner bags should be orange. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
All
storage of asbestos waste should be carried out properly in a secure place
isolated from other substances so as to prevent any possible release of
asbestos fibres into the atmosphere and contamination of other substances. Type 1 asbestos waste should not be stored
together with Types 2 and 3 asbestos wastes so as to avoid damage to the
plastic bags of Type 2 or 3 asbestos waste, unless the bags are packed in
boxes or drums for additional protection. Bagged asbestos waste should not be
stacked more than 3 bags high in order to avoid damage to the bottom
bag. The storage area should be
isolated from other working areas and bear warning panels to alert people of
the presence of asbestos waste. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
Disposal
of asbestos wastes shall not commence before a designated notification has
been given to EPD and confirmed.
Before being transported for disposal, all the asbestos waste produced
should be stored in a temporary storage area. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
Section
7 of the Code of Practice on the
Handling, Transportation and Disposal of Asbestos Waste. |
|
|
All
asbestos wastes for disposal should be transported by an asbestos waste
collector licensed by EPD and in a designated vehicle equipped as stated in
the Code of Practice. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
The
ash/rubble in between the Chimneys A and B on-site shall be treated by
solidification / stabilisation with cement, and the treated ash shall be
sealed into steel drums lined with plastic sheeting prior to disposal at
designated areas in the landfill. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
The
proposed disposal method for ash waste is to be collected up and stabilised
to meet landfill disposal criteria of EPD.
In such case, it is envisaged that the process would involve
collection and mixing the ash material with cement. Pilot mixing and TCLP tests would establish
the ratio of cement to ash to the satisfaction of EPD. The materials for disposal would then be
treated and the extracted material placed into polythene lined steel
drums. Transparent plastic sheeting of
0.15mm thickness low-density polythene or PVC should be employed. The drums should be 16 gauge steel or
thicker and fitted with double bung fixed ends adequately sealed and well
labelled in new or good condition.
Prior agreement of the disposal criteria from EPD and agreement to
disposal from the landfill operator must be obtained. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
The
release of contaminants from disturbed ash should be minimised prior to
gathering up the ash materials and amended water containing a wetting agent
should be sprayed on the ash. The
wetting agent will assist in water penetration to thoroughly soak the ash and
ensure dust levels are reduced without using excessive water. (Spray shall comprise 50% polyoxyethylene
ester and 50% polyoxyethylene ether, or equivalent, diluted to specific
concentration in accordance with the manufacturer’s instructions). The use of amended water for dust
suppression will minimise the use of excessive water that would result in
surface runoff in the removal process.
Dust suppression can be carried out in a controlled manner and no
insurmountable environmental problem would result. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
Where
the level of dioxin contaminants exceeded the USEPA criterion of 1ppb (parts
per billion) by weight, the remediation strategies for contaminated material
are recommended as follows: a)
Ash/rubble waste shall be collected up and stabilised / solidified to meet
landfill disposal criteria of EPD, 1 part per billion (1ppb TEQ) TCLP; b) It
is envisaged that the process would involve collection and mixing the ash/rubble
material with cement followed by sealing in polythene lined steel drums; c)
Pilot mixing of the ash with progressively greater proportions of cement
would precede the treatment; and d)
The stabilised / solidified DCM that is contained in polythene lined steel
drums shall be transported for landfill disposal. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
The
chimney interior shall be brushed clean.
The brushed out materials including ash and dust shall be sealed in
steel drums before disposal at the CWTC.
Subsequently the internal brick lining shall be scrabbled and HEPA
vacuumed to thoroughly remove the ash attached. The clean bricks shall then be dismantled
from top to bottom and placed inside steel drums before disposal at the
landfill. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
Proper
decontamination facilities similar to that employed in asbestos removal works
(i.e. 3-chamber decontamination units) shall be adopted. Workers shall be
protected with disposable coveralls and appropriate respirators suitable for
protection against asbestos fibre and dioxin, as well as to fulfil confined
space requirements. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
The
flue sections shall either be thoroughly cleaned with high efficiency vacuum
and wet cloth to remove all dioxin-contaminated ash, or the dismantled
sections, considered as chemical wastes, wrapped with impermeable polythene
sheets for proper disposal to landfill following the requirements of the Waste Disposal (Chemical Waste) (General)
Regulation. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
Waste Disposal (Chemical Waste) (General)
Regulation. |
|
|
The
required decontamination shall be conducted under negative pressure with all
openings and uncontaminated areas sealed with impermeable plastics. This requirement is analogous to the ‘full
containment’ requirements for asbestos removal works. The chimney flues should be taken down in
manageable sections within the containment, and any ash deposits scrapped off
and sealed in drums for disposal to landfill site. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
The
flue sections shall either be cleaned with high efficiency vacuum and wet
cloth, or wrapped with impermeable plastics for disposal to landfill
site. The flues will be removed from
top down and hence the ACM will be removed when the removal of chimney flue
sections has proceeded down to the levels where the ACM is located. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
|
|
Given
the nature of the work and the contaminants involved consideration should be
given to the use of decontamination facilities (showers) that should be
provided for the workforce to remove contamination after work. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.21 |
5.2.28 |
Different
types of waste should be segregated and stored in different containers, skips
or stockpiles to enhance reuse or recycling of materials and their proper
disposal. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.22 |
5.2.39 |
An
on-site temporary storage area should also be provided. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
|
7.10.25 |
5.2.32 |
A
recording system for the amount of wastes generated, recycled and disposed
(including the disposal sites) should be proposed. |
KTCDA
Site - Phase 1 Part 1 |
CEDD’s
Contractor |
|
ü |
|
ETWB
TC(W) No. 15/2003 |
Table AC‑3 Event
Contingency Plan for Environmental Complaints
Step |
Day |
Action |
Contractor |
ER |
ET |
IEC |
1 |
1 |
Party receiving complaint shall create a new
complaint record. If the Contractor receives a complaint, he shall pass the
information to the ER. |
¨ |
¨ |
¨ |
|
2 |
1 |
ER to ensure details of complaint provided
to Contractor (if complaint not originally received by the Contractor), ET
and IEC |
|
¨ |
|
|
3 |
2 |
Within 1 working day after the receipt of
the Notification of Complaint, provide ER relevant works site information,
e.g. types and locations of construction works. |
¨ |
|
|
à |
4 |
2 |
Investigate the complaint to determine its
validity, and to assess whether the source of the problem is due to the works
activities. Report the validity of the
complaint to ER. |
|
|
|
¨à |
5 |
2 |
If complaint is valid and due to works, ER
shall notify the Contractor. If
complaint is invalid or not due to works, Go to Step 12. |
|
¨ |
|
|
6 |
2 |
Propose mitigation measures to ER within 1
working day of the receipt of the Notification. |
¨ |
|
|
à |
7 |
2 |
Review and agree with the proposed
mitigation measures and make recommendations where necessary. |
|
¨à |
|
¨à |
8 |
2 |
Implement the mitigation measures once they
have been agreed. |
¨ |
|
|
|
9 |
4 |
Audit the implementation of the proposed
mitigation measures on site within 2 working days after measures have been
agreed. |
|
¨à |
|
¨à |
10 |
- |
Undertake additional monitoring to verify
the situation where necessary. |
|
|
¨ |
|
11 |
4 |
Report the investigation results and subsequent
actions taken to ER within 2 working days after the implementation of
mitigation measures. |
¨ |
|
¨ |
|
12 |
5 |
Respond to the complainant within 1 working
day after receiving the investigation report. |
|
¨ |
|
|
13 |
25 |
If no further comments or complaints are
received from the complainant within 20 working days after responding to the
complainant, close the complaint record.
If the complainant has further comments or complaints on the same
issue, notify other parties on the same day and go to step 2. |
|
¨ |
|
¨à |
¨ Action
Party
à Enter
comments/ proposals into appropriate complaint record where applicable
Not Applicable for this Reporting Month
Not Applicable for this Reporting Month