1.1
The project site is located at the mostly
undeveloped hillside above the residential development at
1.2
The objective of the Project “Landslide Preventive
Works at Po Shan, Mid-levels – Design and Construction (Natural Terrain Risk
Mitigation Works)” under Contract CE 28/2004 (GE) is to carry out detailed
design and supervision of landslide preventive works on local repair of the
hillside to minimize slope deterioration and shallow instability.
1.3
The proposed landslide preventive works would be
constructed to protect the existing residential developments at the toe of the
project site.
1.4
The scope of works of this Project includes the
installation about 700 numbers of soil nails and about 60 numbers of raking
drains on the natural terrain within the concerned area. The length of the soil
nails is about
1.5
The Project is anticipated to complete in 10 months
after the commencement of construction.
1.6
According to the Environmental Permit (EP-235/2005/B)
and the EM&A Manual of the Project, there is a need of an EM&A
programme including air quality, noise, ecology, and landscape and visual
monitoring.
1.7
ENSR Asia (HK) Ltd. (ENSR) was employed by the
Contractor,
1.8
This is the first monthly Environmental Monitoring
and Audit (EM&A) Report under the Contract CE 28/2004 (GE) – Landslide
Preventive Works at
1.9
The project organization is
shown in Appendix A. The key personnel contact names and numbers are summarized
in Table 1.1
.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
CEDD |
Senior Engineer |
Jerry Ho |
2760 5700 |
2714 0247 |
ER (MGS) |
Resident Engineer |
Andrew J.
Westmoreland |
3188 0400 |
3188 0775 |
Assistant Resident
Engineer |
S. F. Chau |
3188 0400 |
3188 0775 |
|
IEC (ENVIRON) |
Independent Environmental Checker |
David Yeung |
3743 0788 |
3548 6988 |
Contractor (CCJV) |
Project Manager |
Eddie Tang |
3188 0538 |
3188 1710 |
Safety and Environmental Officer |
Ken Fong |
3188 0538 |
3188 1710 |
|
ET (ENSR) |
ET Leader |
Alex Chan |
3105 8525 |
2891 0305 |
1.10
The Contactor has carried
out major activities in the reporting month. Details of the works undertaken in
this reporting period are listed below:
-
Test Nails (5
nos.) for Pull Out Test at Portion A1 (i.e. from Row A to Row P);
-
Permanent Nails
installation at Portion A1; and
-
Site Clearance for
soil nail setting out to Portion B2 (i.e. from Row X to
1.11
The general layout plan of
the Project site showing the contract area is shown in Figure 1.1. The
construction programme is provided in Appendix B.
1.12
The mitigation measures
implementation schedule are presented in Appendix C.
Summary of EM&A Programme Requirements
1.13
The EM&A programme required environmental monitoring for air
quality, noise, ecology and landscape and visual and environmental site
inspections for air quality, noise, ecology, landscape and visual and waste
management. The EM&A requirements for each parameter described in the
following sections include:
-
All monitoring parameters;
-
Monitoring schedules for
the reporting month and forthcoming months;
-
Action and Limit levels for
all environmental parameters;
-
Event / Action Plan;
-
Environmental mitigation
measures, as recommended in the Project EIA study final report; and
-
Environmental requirement
in contract documents.