TABLE OF CONTENTS

EXECUTIVE SUMMARY

1.         INTRODUCTION

Scope of Report

Project Organization and Contacts of Key Management

Summary of Construction Works

2.         ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS

Monitoring Parameters

Environmental Quality Performance Limits (Action/Limit Levels)

Environmental Mitigation Measures

3.         MONITORING RESULTS

Air Quality

Ecology

Landscape and Visual

Environmental Site Inspection

4.         Advice on Solid and liquid Waste Mangement Status

5.         Summary of Non-Compliance (Exceedances) of environmental qualitY

Summary of Exceedances and Review of the Reasons for non-compliance

6.         Environmental complaints, notification of summons and successful prosecutioN

7.         Comments, Recommendations and Conclusions

Comments on Mitigation Measures

Recommendations on EM&A Programme

Conclusions

 


List of Tables

 

Table 1.1           Contact Information of Key Personnel

Table 3.1           Summary of Number of Exceedances for 1-hr & 24-hr TSP Concentration

Table 3.2           Summary of Number of Exceedances for Daytime Noise

Table 6.1           Summary of Environmental Complaints and Prosecutions

 

 

List of Figures

 

Figure 1.1          Site Layout Plan

Figure 2.1          Locations of Air Quality and Noise Monitoring Stations

 

 

List of Appendices

 

Appendix A Project Organization Structure

Appendix B Construction Programme

Appendix C         Implementation Schedule of Mitigation Measures (EMIS)

Appendix D Action and Limit Levels for Air Quality  and Noise

Appendix E Graphical Presentation of Air Quality Monitoring Results

Appendix F Graphical Presentation of Noise Monitoring Results








EXECUTIVE SUMMARY

The Project “Landslide Preventive Works at Po Shan, Mid-levels – Design and Construction (Natural Terrain Risk Mitigation Works)” (hereafter called “the Project”) includes the installation of about 700 numbers of soil nails and about 60 numbers of raking drains on the natural terrain within the concerned area.

China State – China Railway Joint Venture (CCJV) was commissioned as the Contractor of the Project. ENSR Asia (HK) Ltd. was employed by CCJV as the Environmental Team to carry out the EM&A programme.

The impact environmental monitoring and audit for the Project includes the air quality, noise, ecology, landscape and visual monitoring. The construction of the Project and the EM&A programme commenced on 1 April 2008.

This report documented the findings of EM&A works conducted in the period from April 2008 to June 2008. As informed by the Contractor, construction activities carried out in the reporting quarter were:

-         Test Nails (5 nos.) for Pull Out Test at Portion A1 (i.e. from Row A to Row P);

-         Permanent Nails installation at Portion A1;

-         Site Clearance for soil nail setting out to Portion B2 (i.e. from Row X to Row AK); and

-         Setting out of Locations of Soil Nail at Portion A2, B1 and B2.

 

Environmental Monitoring Works

 

EM&A Programme

 

A summary of monitoring and audit activities conducted in the reporting quarter is listed below:

 

24-hour TSP monitoring

14(CA1)/16(CA2)

sessions

1-hour TSP monitoring

48

sessions

Daytime Noise monitoring

13

sessions

Ecology monitoring

6

sessions

Landscape and Visual Audit

  6

sessions

Environmental Site Inspection

13

sessions

Breaches of Action and Limit Levels

There was no action / limit level exceedance recorded for 1-hour and 24-hour TSP monitoring.

In the reporting quarter, all noise level recorded complied with the limit level.

Complaint, Notification of Summons and Successful Prosecution

There was no complaint, notification of summons and successful prosecution received in the reporting quarter.

.

 

 


1.      INTRODUCTION

Scope of Report

1.1          This is the first Quarterly Environmental Monitoring and Audit (EM&A) Summary Report under the Contract CE 28/2004 (GE) – Landslide Preventive Works at Po Shan Road, Mid-Levels – Design and Construction (Natural Terrain Risk Mitigation Works). This report presented a summary of the environmental monitoring and audit works, and list of activities carried out by the ET for the Project for the period from April 2008 to June 2008.

 

Project Organization and Contacts of Key Management

1.2          The project organization is shown in Appendix A. The key personnel contact names and numbers are summarised in Table 1.1

 

Table 1.1       Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

CEDD

Senior Engineer

H. W. Sun

2762 5375

2714 0247

ER (MGS)

Resident Engineer

Andrew J. Westmoreland

3188 0400

3188 0775

Assistant Resident Engineer

S. F. Chau

3188 0400

3188 0775

IEC (ENVIRON)

Independent Environmental Checker

David Yeung

3743 0788

3548 6988

Contractor (CCJV)

Project Manager

Eddie Tang

3188 0538

3188 1710

Safety and Environmental Officer

Ken Fong

3188 0538

3188 1710

ET (ENSR)

ET Leader

Alex Chan

3105 8525

2891 0305

 

Summary of Construction Works

1.3          The Contactor has carried out major activities in the reporting quarter. Details of the works undertaken in this reporting period are listed below:

 

-         Test Nails (5 nos.) for Pull Out Test at Portion A1 (i.e. from Row A to Row P);

-         Permanent Nails installation at Portion A1;

-         Site Clearance for soil nail setting out to Portion B2 (i.e. from Row X to Row AK); and

-         Setting out of Locations of Soil Nail at Portion A2, B1 and B2.

 

1.4          The general layout plan of the Project site showing the contract area is shown in Figure 1.1.

 

1.5          The construction programme is provided in Appendix B.

 

1.6          The mitigation measures implementation schedule are presented in Appendix C.

 


2.      ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS

Monitoring Parameters

2.1          The EM&A Manual designated two monitoring stations to monitor environmental impacts on air quality and noise due to the Project. The monitoring locations are depicted in Figure 2.1.

 

2.2          The EM&A Manual also required ecology monitoring, bi-weekly landscape and visual audits, and environmental site inspections for air quality, noise, water quality, chemical, waste management, ecology and landscape and visual.

Environmental Quality Performance Limits (Action/Limit Levels)

2.3          The environmental quality performance limits (i.e. Action/Limit Levels) were derived from the baseline air quality monitoring results of Access road to Po Shan Mansions (CA1) and Podium of Hamilton Court (CA2) and / or as defined in the EM&A Manual (CN1 & CN2), and are given in Appendix D.

Environmental Mitigation Measures

2.4          Relevant environmental mitigation measures were stipulated in the Particular Specification and EP (No.: EP-235/2005/B) for the Contractor to adopt. A list of mitigation measures and their implementation statuses are given in Appendix C.

 

 

 


3.             MONITORING RESULTS

Air Quality

3.1          Air quality monitoring, including 1-hr and 24-hr TSP, was conducted at least 3 times every 7 days and at least once every 7 days respectively at the 2 monitoring stations (CA1 and CA2), in accordance with the EM&A Manual. Forty-eight 1-hr TSP monitoring events were carried out in this reporting quarter.

3.2          24-hour TSP monitoring at CA1 (Po Shan Mansions) was temporary suspended on 10, 16 and 22 April 2008 due to the complaint received from the Management Office regarding the noise generated from the HVS during operation. The HVS was relocated to an adjacent location closer to the site on 24 April 2008 and the 24-hour TSP monitoring resume on the same day. Fourteen 24-hr TSP monitoring events were conducted for CA1, while sixteen 24-hr TSP monitoring events were carried out for CA2 in the reporting quarter.

3.3          The weather was mostly sunny in April and May 2008, but was becoming wet in June 2008. The trend of air quality for the reporting quarter are given in Appendix E. Major dust source of the construction works area included soil nail installation activities from the Project, construction activities of another project under the same contract (concurrent project) carried out in the vicinity and nearby traffic emissions.

3.4          There was no Action and Limit Level exceedance recorded for both 1-hr and 24-hr TSP in the reporting quarter.

3.5          Table 3.1 presents the number of exceedances recorded in each month of the reporting quarter. The number of monitoring events included regular monitoring events and additional ones, if any.

 

Table 3.1       Summary of Number of Exceedances for 1-hr & 24-hr TSP Concentration

Monitoring Parameter

Location

Level of Exceedance

Month

Apr 08

May 08

Jun 08

1-hr TSP

CA1

No. of monitoring events

18

15

15

Action

0

0

0

Limit

0

0

0

CA2

No. of monitoring events

18

15

15

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

24-hr TSP

CA1

No. of monitoring events

3

5

6

Action

0

0

0

Limit

0

0

0

CA2

No. of monitoring events

5

5

6

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

Construction Noise

3.6          Noise monitoring was conducted at the 2 monitoring stations (CN1 and CN2) for at least once per week during 0700 – 1900 of the reporting quarter. Thirteen noise monitoring events were conducted in the reporting quarter.

3.7          As no noise complaint was received in the reporting quarter, no Action Level exceedance was recorded. All measured noise levels were below the Limit Level and the graphical plots of trends of the monitoring results are provided in Appendix F.

3.8          Table 3.2 presents the number of exceedances recorded in each month of the reporting quarter. The number of monitoring events included regular monitoring events and additional ones, if any.

 

Table 3.2       Summary of Number of Exceedances for Daytime Noise

Monitoring Parameter

Location

Level of Exceedance

Month

Apr 08

May 08

Jun 08

Daytime Noise

CN1

No. of monitoring events

5

4

4

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

CN2

No. of monitoring events

5

4

4

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

3.9          Trends of construction noise levels at all monitoring stations did not significantly change in the reporting quarter. Major noise sources during the noise monitoring included the construction activities from the Project and another project under the same contract (concurrent project) carried out in the vicinity and nearby traffic noise.

 

Ecology

3.10      Ecological monitoring was carried out twice a month by a suitably qualified local ecologist to check on the health and condition of the plant species of conservation interest. Six ecological monitoring were conducted in the reporting quarter.

3.11      A total of 13 plant species of conservation interest (i.e. V001 to V013) were identified within the area during an earlier Detailed Vegetation Survey conducted under this Project.  V001 to V013 were found to be in good condition during the monitoring visits in the reporting period, nevertheless, plastic fencings supported by strong poles were recommended to demarcate plant locations clearly to prevent tipping and entry of personnel in order to avoid damage to the plants. Fencings had been set up in the area during the monitoring visits in May 2008.

3.12      The bark of two individuals of vegetation located adjacent to the temporary conveyor belt was found to be slightly damaged. It was recommended that hessian sacking should be wrapped around the trunk of vegetation to prevent damage during the transportation of construction materials.  The concerned trunks were found to be wrapped during the second visit in May 2008.

3.13      Construction materials such as planks, metal rods were found to be placed over or near the lower trunks of some trees.  It was recommended that these materials should be kept in proper place to avoid damage to vegetation within works area.  The said materials were immediately removed.

3.14      Concrete was found spilled over from the soil nailing works zones onto nearby areas.  It was recommended that the concrete should be removed from the soil surface.  The Contractor advised that the concrete will be removed and measures will be implemented to avoid any further spillage.

 

Landscape and Visual

3.15      Bi-weekly landscape and visual audit was conducted by a Registered Landscape Architect (RLA) to monitor the implementation of landscape and visual mitigation measures. Six landscape and visual audits were conducted in the reporting quarter.

3.16      The bark of existing tree T254 was damaged by the works as no tree protection was provided.  The Contractor was requested to carry out tree protection works for the tree as soon as possible.

3.17      The tree bark of one existing was damaged by the erection of the temporary conveyor / pulley system on the slope just immediately outside of the site boundary of Landslide Preventive Works.  The Engineer was requested to clarify if it is considered part of the soil nail works.

3.18      An existing dead tree was partially uprooted and fallen over.  The Contractor was requested to clear the dead tree for safety consideration.

3.19      One of the temporary shelter areas was installed against some branches of an existing tree.  The Contractor was requested to re-adjust the temporary shelter to clear of the tree branches so as not to cause damage to the tree.

3.20      The wrapping of hessian for the tree protection of some of the trees had been wrapped with two tree trunks together.  The Contractor was reminded to individually wrap the trees and not to force the tree trunks together.

3.21      Overhead plastic sheets for rain shelter were tied to existing tree branches.  The Contractor was reminded that the trees should not be used for temporary anchoring of works and to untie from tree branches as soon as possible.

3.22      The construction of some of the soil nail drilling platforms surrounds existing trees, which was protected with only hessian clothes.  The Contractor was requested to provide more protection to these trees by the use of wooden slats strapping around the trunks to prevent accidental damage to tree barks by heavy equipment / tools during the drilling works.

3.23      Minor damage to the tree bark at the base of one tree on slope was observed.  The Contractor was reminded to be more carefully when carry out works near existing trees.

3.24      The Contractor had stockpiled / rested the metal pipes / steel bars against the existing tree trunks at various locations on site.  The Contractor was requested to urgently remove all metal pipes / steel bars away from the existing tree trunks in order to prevent damage to the trees.

 

Environmental Site Inspection

3.25      There were 13 site inspections conducted in the reporting quarter to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. The major concerns for the Project are air quality, noise, water quality, waste management, ecology and landscape and visual. Observations recorded are described below. All the observations were rectified by the Contractor within the agreed time frame.

Air Quality

3.26      The soil nail workstation at Row O was not fully enclosed. Although immediate action had been taken to provide tarpaulin sheet for covering the soil nail extraction outlet, the Contractor was still reminded to fully enclose the workstation.

Noise

3.27      No adverse observation was identified in the reporting quarter.

Water Quality

3.28      Mud and construction waste was found inside the U-channel at Row J and Row P. The Contractor was reminded to clear the waste to prevent blockage of the drainage system and prevent muddy water discharge during rainfall.

3.29      Leaves were observed accumulated inside the u-channel at Row H. The Contractor was reminded to remove the leaves and properly maintain the drainage system.

3.30      Exposed earth surface was observed on the slope above Row H. The Contractor was reminded to cover the slope and provide bunding along the edge of the u-channel under the slope to prevent muddy runoff prior to clearing the mud.

Chemical and Waste Management

3.31      Oil stain was found under a drill rig at Row K. The Contractor was reminded to clear the oil stain and provide a drip tray.

3.32      A few chemical containers and oil containers at Row M, Row D and Row O were placed on ground without drip tray. The Contractor was reminded to provide drip tray to all chemicals on site.

3.33      Stockpile of C&D waste was found at Row E. The Contractor was reminded to clear the C&D waste off-site regularly.

3.34      Small amount of construction waste and general refuse was found on slope of Row O. The Contractor was reminded to clear the waste.

3.35      Drill rigs at Row I, Row J and Row P were found without drip trays. The Contractor was reminded to provide drip trays to the plants on site.

3.36      C&D materials were observed scattered on the slope between Row O and Row P. The Contractor was reminded to properly collect and recycle the materials.

Ecology

3.37      V001 to V013 were found to be in good condition during the monitoring visits, nevertheless, plastic fencings supported by strong poles were recommended to demarcate plant locations clearly to prevent tipping and entry of personnel in order to avoid damage to the plants.

3.38      The bark of two individuals of vegetation located adjacent to the temporary conveyor belt was found to be slightly damaged, it was recommended that hessian sacking should be wrapped around the trunk of vegetation to prevent damage during the transportation of construction materials.

3.39      Construction materials placed near tree trunks and spillage of concrete near soil nailing areas were observed.

Landscape and Visual

3.40      The Contractor was advised that retained trees should be properly protected before installation of scaffolding at PT3. Immediate action had been undertaken by the Contractor and status / condition was to be followed up.

3.41      The Contractor was recommended to provide more adequate protection to existing trees in the work areas and not to use the trees as temporary supports

3.42      The Contractor was recommended to provide more protection to existing trees which are surrounded by drilling platforms and avoid stockpiling of any construction materials / equipments against or near existing trees.

 

 

 


 

4.      Advice on Solid and liquid Waste Mangement Status

 

4.1          The Contractor has registered as a chemical waste producer for this Project. The Chemical Waste Storage Area located at the Contractor’s site office area was properly maintained in the reporting quarter.

4.2          No waste disposal was made in the reporting quarter. Most of the C&D waste generated was reused on site.

 

 

 

5.      Summary of Non-Compliance (Exceedances) of environmental qualitY

Summary of Exceedances and Review of the Reasons for non-compliance

5.1          There was no 1-hr TSP, 24-hr TSP and noise exceedance recorded in the reporting quarter.

 

 

 

6.      Environmental complaints, notification of summons and successful prosecutioN

 

6.1          No environmental complaints, notification of summons and prosecution was received in the reporting quarter. Table 6.1 summarized the complaint, summons and successful prosecution received in the reporting period.

 

       Table 6.1      Summary of Environmental Complaints and Prosecutions

 

April 2008

May 2008

June 2008

Total

Complaint Logged

0

0

0

0

Summons

Served

0

0

0

0

Successful Prosecution

0

0

0

0

Total

0

0

0

0

 

 

 

7.      Comments, Recommendations and Conclusions

Comments on Mitigation Measures

7.1          According to the environmental site inspections performed in the reporting quarter, the following comments are provided:

 

Air Quality

-         Soil nail installation workstation should be fully enclosed.

Noise

-         N/A

Water Quality

-         Blockage of the drainage system and muddy water discharge during rainfall should be prevented.

-         Exposed earth surface should be covered and bunding along the edge of the u-channel under the slope should be provided.

Chemical and Waste Management

-         Oil stains should be cleared and the contaminated soil should be disposed of as chemical waste.

-         Drip tray should be provided to all the plants and chemical containers on site.

-         Stockpile of C&D waste should be cleared off-site regularly.

-         Construction waste and general refuse should be removed regularly.

-         C&D materials should be properly collected and recycled.

Ecology

-         Plastic fencings supported by strong poles are recommended to demarcate plant locations clearly to prevent tipping and entry of personnel in order to avoid damage to the plants.

-         Hessian sacking should be wrapped around the trunk of vegetation to prevent damage during the transportation of construction materials.

-         Spillage of concrete near soil nailing areas should be prevented.

Landscape and Visual

-         Retained trees should be properly protected before installation of scaffolding.

-         More adequate protection to existing trees should be provided in the work areas and near drilling platforms.

-         The use of trees as temporary supports should be avoided.

-         Stockpiling of any construction materials / equipments against or near existing trees should be avoided.

 

 

 

Recommendations on EM&A Programme

7.2          The impact air quality and noise monitoring programme ensured that any environmental impact to the receivers would be readily detected and timely actions could be taken to rectify any non-compliance.  Assessment and analysis of monitoring results collected demonstrated the environmental acceptability of the Project.  The ecological monitoring, bi-weekly landscape and visual audit and weekly site inspection ensured that all the environmental mitigation measures recommended in the EIA report were effectively implemented.

7.3          The EM&A programme effectively monitored the environmental impacts from the construction activities and no particular recommendation was advised for the improvement of the programme.

Conclusions

7.4          Air quality and noise monitoring, ecological monitoring, bi-weekly landscape and visual audit and weekly site inspection were carried out from April 2008 to June 2008, in accordance with the EM&A Manual.

7.5          No Action and Limit Level exceedance or non-compliance was recorded for the monitoring works in the reporting quarter.

7.6          No environmental complaint, summons or prosecution was made against the Project in the reporting quarter.