TABLE OF CONTENTS
Summary of EM&A Programme Requirements
Monitoring
Parameters, Frequency and Duration
6. ENVIRONMENTAL SITE INSPECTION
AND AUDIT
Assessment of
Environmental Monitoring Results
Advice on the
Solid and Liquid Waste Management Status
Environmental
Licenses and Permits
Implementation
Status of Environmental Mitigation Measures
Summary of
Exceedances of the Environmental Quality Performance Limit
Summary of
Complaints, Notification of Summons and Successful Prosecutions
Construction
Programme for the Coming Months
Monitoring
Schedule for the Coming Months
8. CONCLUSIONS AND RECOMMENDATIONS
List
of Tables
Table
1.1 Contact
Information of Key Personnel
Table 2.1 Air Quality Monitoring
Equipment
Table 2.2 Air Quality Monitoring
Parameters, Frequency and Duration
Table 2.3 Locations of Air Quality Monitoring
Stations
Table 2.4 Summary of 1-hour TSP
Monitoring Results in the Reporting Period
Table 2.5 Summary of 24-hour TSP
Monitoring Results in the Reporting Period
Table 3.1 Noise Monitoring Equipment
Table 3.2 Locations of Noise
Monitoring Stations
Table 3.3 Summary of Noise Monitoring
Results in the Reporting Period
Table 6.1 Summary of Environmental
Licensing and Permit Status
List of Figures
Figure 2.1 Locations of Air Quality and Noise
Monitoring Stations
Figure 6.1 Environmental Complaint Handling
Procedures
List of Appendices
Appendix A Project Organization Structure
Appendix B Construction Programme
Appendix C Implementation Schedule of Mitigation
Measures (EMIS)
Appendix
D Action and Limit Levels for Air Quality and Noise
Appendix
E Calibration Certificates
Appendix F Air Quality Monitoring Results and Graphical
Presentation
Appendix
I Noise Monitoring Results and
Graphical Presentation
Appendix
J Detailed Landscape and Visual Monitoring
Report
Appendix
K ET’s Site Inspection Summaries
Appendix
L Monitoring Schedules
The Project “Landslide Preventive Works at Po Shan,
Mid-levels – Design and Construction (Natural Terrain Risk Mitigation Works)”
(hereafter called “the Project”) includes the installation of about 700 numbers
of soil nails and about 60 numbers of raking drains on the natural terrain
within the concerned area.
China State – China Railway Joint Venture (CCJV) was
commissioned as the Contractor of the Project. ENSR Asia (HK) Ltd. was employed
by CCJV as the Environmental Team to carry out the EM&A programme.
The impact environmental monitoring and audit for the
Project includes the air quality, noise, ecology, landscape and visual
monitoring. The construction of the Project and the EM&A programme
commenced on 1 April 2008.
This report documented the findings of EM&A works
conducted in the period between 1 and 30 June 2008. As informed by the
Contractor, construction activity in the reporting period was:
-
Soil nail installation at Portion A1.
Breaches of Action and Limit
Levels
There was no action / limit level exceedance recorded
for 1-hour and 24-hour TSP monitoring.
In the reporting month, all noise level recorded
complied with the limit level.
Complaint, Notification of
Summons and Successful Prosecution
There was no complaint, notification of summons and
successful prosecution received in the reporting month.
Reporting Change
There was no reporting change required in the
reporting month.
Future Key Issues
The weather in the forthcoming month is expected to be
wet and windy. The Contractor should provide preventive measures to prevent any
muddy runoff, such as proper collection and treatment of the runoff and provide
a functional temporary drainage system in site.
It is also recommended to implement all necessary
preventive measures to avoid oil leakage on ground / soil, such as provision of
drip trays for all oil drums / chemical containers. In the event of oil
leakage, the Contractor should properly remove the contaminated soil and
dispose of as chemical waste. Construction waste and general refuse should be
properly collected and disposed of.
1.1
The project site is located at the mostly
undeveloped hillside above the residential development at Po Shan Road and
adjacent to the trimmed back slope on the site of the catastrophic 1972 Po Shan
Road failure. Previous studies had been carried out and results indicated that
the natural hillside above Po Shan Road is affected by high groundwater level
and unfavourable geology. Sub-surface drainage measures by means of
sub-horizontal drains had been installed in 1984-85. These measures have been
successful in lowering the main ground water table, thus improving the
stability of the slopes such that large-scale failure have not occurred in the
last twenty years.
1.2
The objective of the Project “Landslide Preventive
Works at Po Shan, Mid-levels – Design and Construction (Natural Terrain Risk Mitigation
Works)” under Contract CE 28/2004 (GE) is to carry out detailed design and
supervision of landslide preventive works on local repair of the hillside to
minimize slope deterioration and shallow instability.
1.3
The proposed landslide preventive works would be
constructed to protect the existing residential developments at the toe of the
project site.
1.4
The scope of works of this Project includes the
installation about 700 numbers of soil nails and about 60 numbers of raking drains
on the natural terrain within the concerned area. The length of the soil nails
is about
1.5
The Project is anticipated to complete in 10 months
after the commencement of construction.
1.6
According to the Environmental Permit
(EP-235/2005/B) and the EM&A Manual of the Project, there is a need of an
EM&A programme including air quality, noise, ecology, and landscape and
visual monitoring.
1.7
ENSR Asia (HK) Ltd. (ENSR) was employed by the
Contractor, China State – China Railway Joint Venture, as the Environmental
Team (ET) to undertake the Environmental Monitoring and Audit (EM&A) works
for the Project. In accordance with the EM&A Manual of the Project,
environmental monitoring of air quality, noise, ecology, landscape and visual
and environmental site inspections would be required for this Project.
1.8
This is the third monthly Environmental Monitoring
and Audit (EM&A) Report under the Contract CE 28/2004 (GE) – Landslide
Preventive Works at Po Shan Road, Mid-Levels – Design and Construction (Natural
Terrain Risk Mitigation Works). This report presented a summary of the
environmental monitoring and audit works, list of activities, and mitigation
measures proposed by the ET for the Project in June 2008.
1.9
The project organization is
shown in Appendix A. The key personnel contact names and numbers are summarized
in Table 1.1
.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
CEDD |
Senior Engineer |
H. W. Sun |
2762 5375 |
2714 0247 |
ER (MGS) |
Resident Engineer |
Andrew J. Westmoreland |
3188 0400 |
3188 0775 |
Assistant Resident Engineer |
S. F. Chau |
3188 0400 |
3188 0775 |
|
IEC
(ENVIRON) |
Independent
Environmental Checker |
David
Yeung |
3743
0788 |
3548
6988 |
Contractor
(CCJV) |
Project
Manager |
Eddie
Tang |
3188
0538 |
3188
1710 |
Safety
and Environmental Officer |
Ken
Fong |
3188
0538 |
3188
1710 |
|
ET
(ENSR) |
ET
Leader |
Alex
Chan |
3105
8525 |
2891
0305 |
1.10 The Contactor has carried out major activities in the reporting month.
Details of the works undertaken in this reporting period are listed below:
-
Soil nail installation at Portion A1.
1.11 The general layout plan of the Project site showing the contract area is
shown in Figure 1.1. The construction programme is provided in Appendix B.
1.12 The mitigation measures implementation schedule are presented in
Appendix C.
Summary
of EM&A Programme Requirements
1.13 The EM&A programme required environmental monitoring for air
quality, noise, ecology and landscape and visual and environmental site
inspections for air quality, noise, ecology, landscape and visual and waste
management. The EM&A requirements for each parameter described in the
following sections include:
-
All monitoring parameters;
-
Monitoring schedules for
the reporting month and forthcoming months;
-
Action and Limit levels for
all environmental parameters;
-
Event / Action Plan;
-
Environmental mitigation
measures, as recommended in the Project EIA study final report; and
-
Environmental requirement
in contract documents.
2. AIR QUALITY
2.1
In accordance with the EM&A Manual, 1-hour and 24-hour
TSP levels at 2 air quality monitoring stations were established. Impact 1-hour
and 24-hour TSP monitoring was conducted for at least once every 7 days during
the construction phase of the Project. The Action and Limit level of the air
quality monitoring is provided in Appendix D.
2.2
24-hour TSP air quality monitoring was performed
using High Volume Sampler (HVS) located at each designated monitoring station.
The HVS meets all the requirements of the EM&A Manual. Portable direct reading
dust meters were used to carry out the 1-hour TSP monitoring. Table 2.1
summarises the equipment used.
Table 2.1 Air Quality Monitoring Equipment
Equipment |
Model |
High
Volume Sampler |
GS
2310 Accu-vol system |
Calibrator |
GMW 25 |
1-hour
TSP Dust Meter |
Laser
Dust Monitor – Model LD-3 |
Monitoring
Parameters, Frequency and Duration
2.3
Table 2.2 summarizes the monitoring parameters,
frequency and duration of impact TSP monitoring.
Table 2.2 Air Quality
Monitoring Parameters, Frequency and
Duration
Parameter |
Frequency and Duration |
|
CA1 & CA2 |
24-hour
TSP |
At least once every 7 days |
1-hour TSP |
At least 3 times every 7 days |
2.4
Both monitoring stations were set up at the
proposed locations in accordance with EM&A Manual. Table 2.3 describes
details of the two monitoring stations. The monitoring locations are shown in
Figure 2.1.
Table 2.3 Locations
of Air Quality Monitoring Stations
Monitoring Station |
Identity / Description |
CA1 |
Access
road to Po Shan Mansions |
CA2 |
Podium
of Hamilton Court |
24-hour TSP Monitoring
Installation
2.5
The HVS was installed in the vicinity of the air
sensitive receivers. The following
criteria were considered in the installation of the HVS.
·
A horizontal platform with appropriate support to
secure the sampler against gusty wind was provided.
·
The distance between the HVS and any obstacles,
such as buildings, was at least twice the height that the obstacle protrudes
above the HVS.
·
A minimum of 2 meters separation from walls,
parapets and penthouse was required for rooftop sampler.
·
No furnace or incinerator flues were nearby.
·
Airflow around the sampler was unrestricted.
·
Permission was obtained to set up the samplers and
to obtain access to the monitoring stations.
·
A secured supply of electricity is needed to
operate the samplers.
Preparation of Filter Papers
·
Glass fibre filters, G810 were labeled and sufficient filters that were
clean and without pinholes were selected.
·
All filters were equilibrated in the conditioning environment for 24
hours before weighing. The conditioning environment
temperature was around
·
ALS Technichem (HK) Pty Ltd. has comprehensive quality
assurance and quality control programmes.
Field Monitoring
·
The power supply was checked to ensure the HVS works properly.
·
The filter holder and the area surrounding the filter were cleaned.
·
The filter holder was removed by loosening the four bolts and a new
filter, with stamped number upward, on a supporting screen was aligned
carefully.
·
The filter was properly aligned on the screen so that the gasket formed
an airtight seal on the outer edges of the filter.
·
The swing bolts were fastened to hold the filter holder down to the
frame. The pressure applied should be
sufficient to avoid air leakage at the edges.
·
Then the shelter lid was closed and was secured with the aluminum strip.
·
The HVS was warmed-up for about 5 minutes to establish run-temperature
conditions.
·
A new flowrate record sheet was set into the flow recorder.
·
The range specified in the EM&A Manual was between 0.6
·
The programmable timer was set for a sampling period of 24 hrs +
1 hr, and the starting time, weather condition and the filter number were recorded.
·
The initial elapsed time was recorded.
·
At the end of sampling, the sampled filter was removed carefully and
folded in half length so that only surfaces with collected particulate matter
were in contact.
·
It was then placed in a clean plastic envelope and sealed.
·
All monitoring information was recorded on a
standard data sheet.
·
Filters were sent to ALS Technichem (HK) Pty Ltd. for
analysis.
Maintenance and Calibration
·
The HVS and its accessories are maintained in good working condition,
such as replacing motor brushes routinely and checking electrical wiring to
ensure a continuous power supply.
·
HVSs are calibrated using GMW-25 Calibration Kit prior to the
commencement of baseline air quality monitoring, and will be calibrated at
bi-monthly intervals throughout all stages of the impact monitoring.
·
Calibration records are shown in Appendix E.
1-hour TSP Monitoring
Measuring Procedures
2.6
The measuring procedures of the 1-hour dust meter
are in accordance with the Manufacturer’s Instruction Manual as follows:
· Set POWER to “ON”, push BATTERY
button, make sure that the meter’s indicator is in the range with a red line
and allow the instrument to stand for about 3 minutes (Then, the air sampling
inlet has been capped).
· Push the knob at MEASURE
position.
· Push “O-ADJ” button. (Then
meter’s indication is 0).
· Push the knob at SENSI ADJ
position and set the meter’s indication to S value described on the Test Report
using the trimmer for SENSI ADJ.
· Pull out the knob and return it
to MEASURE position.
· Push “START” button.
Maintenance and Calibration
· The 1-hour TSP meter would be
checked at 3-month intervals and calibrated at 1-year intervals throughout all
stages of the air quality baseline monitoring. Calibration records are shown in
Appendix E.
2.7
The monitoring results for 1-hour TSP and 24-hour
TSP are summarized in Table 2.4 and 2.5 respectively and the monitoring results
are provided in Appendix F.
Table
2.4 Summary of 1-hour TSP Monitoring
Results in the Reporting Period
|
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
CA1 |
77.9 |
65.5 – 85.7 |
309.3 |
500 |
CA2 |
71.7 |
62.4 – 80.3 |
319.6 |
500 |
Table
2.5 Summary of 24-hour TSP
Monitoring Results in the Reporting Period
|
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
CA1 |
50.9 |
38.2 – 89.1 |
166.8 |
260 |
CA2 |
26.4 |
16.0 – 34.9 |
187.0 |
260 |
2.8
Air quality monitoring was
carried out for both 1-hour TSP and 24-hour TSP at all the monitoring stations
in the reporting month.
2.9
The air quality monitoring results, in terms of 1-hour
TSP and 24-hour TSP, were below the action and limit level at both monitoring
locations in the reporting month. The event action plan is annexed in Appendix
G.
2.10
Weather information including wind speed and wind
direction is annexed in Appendix H. The information was obtained from Hong Kong
Observatory Victoria Peak Automatic Weather Station and Central Pier Anemometer
Station.
3.1
In accordance with the EM&A Manual, impact noise levels should be obtained
at 2 noise monitoring stations. Impact noise monitoring was conducted for at
least once per week during the construction phase of the Project. The Action
and Limit level of the noise monitoring is provided in Appendix D.
3.2
Integrating Sound Level Meter was employed for noise monitoring. They were Type 1 sound level meters capable
of giving a continuous readout of the noise level readings including equivalent
continuous sound pressure level (Leq) and percentile sound pressure
level (Lx). They comply with International Electrotechnical Commission
Publications 651:1979 (Type 1) and 804:1985 (Type 1). Portable electronic wind speed indicator
capable of measuring wind speed in m/s was employed to check the wind
speed. Table 3.1 details the noise
monitoring equipment used.
Table 3.1 Noise Monitoring
Equipment
Equipment |
Model |
Integrating Sound Level Meter |
Rion NL-31 |
Calibrator |
Rion NC73 |
3.3
Two monitoring stations were set up in accordance
with EM&A Manual. Table 3.2 describes details of the two monitoring
stations. The monitoring locations are shown in Figure 2.1.
Table
3.2 Locations of Noise Monitoring
Stations
Monitoring Station |
Identity / Description |
CN1 |
Block A, Po Shan Mansions |
CN2 |
Block A, Po Shan Mansions |
3.4
One set of 30-mins measurement at each monitoring station between 0700 and
1900 on normal weekdays at a frequency of once per week was required to
determine the impact noise level. Leq, L10 and L90
would be recorded.
Monitoring Procedures
·
The Sound Level Meter was set on a tripod at a
height of
·
Façade measurements were made at all three
monitoring locations.
·
The battery condition was checked to ensure the
correct functioning of the meter.
·
Parameters such as frequency weighting, the time weighting
and the measurement time were set as follows:
-
frequency weighting: A
-
time weighting: Fast
-
time measurement: Leq(30 minutes) during
non-restricted hours i.e. between 07:00 and 19:00 on normal weekdays
·
Prior to and after each noise measurement, the
meter was calibrated using a Calibrator for 94 dB at 1000 Hz. If the difference in the calibration level
before and after measurement was more than 1 dB(A), the measurement would be
considered invalid and repeat of noise measurement would be required after
re-calibration or repair of the equipment.
·
The wind speed was frequently checked with a
portable wind meter.
·
During the monitoring period, the Leq ,
L10 and L90 were recorded. In addition, site conditions and noise
sources were recorded on a standard record sheet.
·
Noise measurement was paused during periods of high
intrusive noise (e.g. dog barking, helicopter noise) if possible. Observations
were recorded when intrusive noise was unavoidable.
·
Noise monitoring was cancelled in the presence of fog,
rain, wind with a steady speed exceeding
Maintenance and Calibration
·
The microphone head of the sound level meter and
calibrator is cleaned with soft cloth at quarterly intervals.
·
The meter should be checked and calibrated at yearly intervals.
·
Calibration details for the sound level meter and calibrator are
provided in Appendix E.
3.5
The monitoring results for noise are summarized in
Table 3.3 and the monitoring data is provided in Appendix I.
Table
3.3 Summary of Noise Monitoring
Results in the Reporting Period
|
Average, dB(A), Leq (30 mins) |
Range, dB(A), Leq (30 mins) |
Limit Level, dB(A), Leq (30 mins) |
CN1 |
62.6 |
59.8 – 64.1 |
75.0 |
CN2 |
61.6 |
59.5 – 63.5 |
75.0 |
3.6
There was no noise complaint received in the reporting month, hence, no
action level exceedance was recorded. At both monitoring locations, CN1 and
CN2, all the monitoring results (daytime) were below the limit level of 75
dB(A).
3.7
All the monitoring results lied within the range of the predicted noise
levels in the EIA report.
3.8
Major noise sources during the noise monitoring included the
construction activities from the Project and another project under the same
contract (concurrent project) carried out in the vicinity and nearby traffic
noise.
4. VEGETATION MONITORING
4.1
As required under Environmental Permit No. EP-235/2005/B, the Permit
Holder is required to carry out monitoring of the plant species of conservation
interest to check on the health and condition of the plants twice a month
during the construction period of the Project.
4.2
It is required to undertake the ecological tasks to fulfill the
requirements of the Environmental Permit (EP).
As required by Conditions 2.11 and 3.5 of the EP, a suitably qualified ecologist with 7 or more years
of relevant experience shall be employed to conduct the ecological monitoring.
4.3
The ecological monitoring was carried out for plant individuals of
conservation interest identified within the proposed works area.
4.4
The ecological monitoring was conducted twice in the reporting month on
3 and 17 June 2008 by Ms. Gigi C C Lam, who had over 7 years of relevant ecological
experience.
4.5
The plants of conservation interest, which were tagged during the
baseline survey, were checked during each monitoring.
4.6
Soil nailing works were in progress during the monitoring visits. A total of 13 plant species of conservation
interest (i.e. V001 to V013) were identified within the above works area during
an earlier Detailed Vegetation Survey conducted under this Project. The tagged vegetation was found to be fenced
off and in good condition during the monitoring visits in June 2008.
4.7
The bark of two individuals of vegetation located adjacent to the
temporary conveyor belt was found to be slightly damaged during visits in May
2008, it was recommended that hessian sacking should be wrapped around the
trunk of vegetation to prevent damage during the transportation of construction
materials. The concerned trunks were
found to be wrapped during the second visit of this month.
4.8
Construction materials such as planks, metal rods were found to be
placed over or near the lower trunks of some trees. It was recommended that these materials
should be kept in proper place to avoid damage to vegetation within works
area. The said materials were
immediately removed.
4.9
Concrete was found to be spilled over from the soil nailing works zones
onto nearby areas. It was recommended
that the concrete should be removed from the soil surface. The Contractor advised that the concrete will
be removed and measures will be implemented to avoid any further spillage.
5.1
During the construction
phase of the Project, landscape and visual monitoring should be carried out
bi-weekly by a Registered Landscape Architect (RLA) to check if the design,
implementation and maintenance of the landscape and visual mitigation measures
are fully realized. A detailed report is annexed in Appendix J.
Summary of Inspection – 3 June 2008
Matters Arising from Previous Inspections
5.2
It was observed that the
strapping of wooden slats for enhanced protection of the tree trunks on
platforms was still outstanding. The
Contractor was reminded to provide adequate tree protection works for the trees
so as not to allow the chance of the trees being accidentally damaged by the
works.
Site Clearance and Soil Nail Works
5.3
Drilling of soil nails was
observed carried out mainly in works area E.
5.4
Setting up of scaffolding was
observed carried out for new drilling area above footpath south of area E.
Protection of Existing Trees
5.5
No particular observation
was made during the inspection.
Recommendations
5.6
The Contractor was recommended
to provide more protection to existing trees which are surrounded by drilling
platforms in order to prevent the trees from being easily damaged.
Summary
of Inspection – 17 June 2008
Matters
Arising from Previous Inspections
5.7
It was observed that the
strapping of wooden slats for enhanced protection of the tree trunks on
platforms was still outstanding. The
Contractor was reminded to provide adequate tree protection works for the trees
so as not to allow the chance of the trees being accidentally damaged by the
works.
Site Clearance and Soil Nail Works
5.8
Drilling of soil nails was
observed carried out mainly in works area E.
5.9
Setting out of soil nail
locations was observed carried out for new drilling area above footpath south of
area E.
Protection of Existing Trees
5.10 It was observed that the Contractor had stockpiled / rested the metal
pipes / steel bars against the existing tree trunks at various locations on
site. The Contractor was requested to
urgently remove all metal pipes / steel bars away from the existing tree trunks
in order to prevent damage to the trees.
Recommendations
5.11 The Contractor was recommended to provide more protection to existing
trees which are surrounded by drilling platforms in order to prevent the trees
from being easily damaged.
5.12 The Contractor was reminded not to stockpile any construction materials
/ equipments against or near existing trees in order to minimize any possible
damage to the trees.
Next Landscape and Visual Audit Schedule
5.13
The landscape and visual audits in the next reporting month was tentatively
scheduled to 2, 15 and 29 July 2008.
6. ENVIRONMENTAL SITE INSPECTION AND AUDIT
6.1
Site Inspections were carried
out on a weekly basis to monitor the implementation of proper environmental
pollution control and mitigation measures for the Project. In the reporting
month, 4 site inspections were carried out on 3, 10, 17 and 24 June 2008. The
detail findings of the landscape and visual audits in the reporting month are
presented separately in Section 5. The environmental site inspection summaries
are attached in Appendix K. Particular observations are described below.
Air Quality
6.2
No adverse observation was identified
in the reporting month.
Noise
6.3
No adverse observation was
identified in the reporting month.
Water Quality
6.4
Leaves were observed accumulated inside the
u-channel at Row H. The Contractor was reminded to remove the leaves and properly
maintain the drainage system.
6.5
Exposed earth surface was observed on the slope
above Row H. The Contractor was reminded to cover the slope and provide bunding
along the edge of the u-channel under the slope to prevent muddy runoff prior to
clearing the mud.
Chemical and Waste Management
6.6
An oil drum was found without drip tray at Row O.
The Contractor was reminded to provide a drip tray to the oil drum.
Ecology
6.7
Construction materials
placed near tree trunks and spillage of concrete near soil nailing areas were
observed.
Landscape and Visual
6.8
The Contractor was
recommended to provide more protection to existing trees which are surrounded by
drilling platforms and avoid stockpiling of any construction materials /
equipments against or near existing trees.
Assessment
of Environmental Monitoring Results
6.9
All monitoring results were
audited against the Action / Limit levels and any exceedance would be validated
and issued when necessary.
6.10 The monitoring results in the reporting period were comparable with the
EIA predictions. Detailed discussions are given in Section 2 and 3.
Advice on
the Solid and Liquid Waste Management Status
6.11 The Contractor is registered as a chemical waste producer for this
Project. The Chemical Waste Storage Area located at the Contractor’s site
office area was properly maintained in the reporting month.
6.12 No waste disposal was made in the reporting month. Most of the C&D
waste generated was reused on site.
Environmental
Licenses and Permits
6.13 The environmental licenses and permits for this Project and valid in the
reporting month is summarized in Table 6.1.
Table 6.1 Summary of Environmental Licensing and Permit Status
Description |
Permit No. |
Valid Period |
Remarks |
|
From |
To |
|||
Environmental Permit |
EP-235/2005/B |
23/11/07 |
-- |
-
Installation of about 700
nos. of soil nails and about 60 nos. of raking drains in the natural terrain; -
Rock slope stabilisation
works at upper portion of the natural terrain; and -
Other associated works. |
Registration as a Chemical Waste Producer |
5213-141-C3250-02 |
13/12/06 |
-- |
Spent lubricating oil and mineral oil |
Effluent Discharge License |
EP880/W10/XX0261 |
07/11/06 |
31/12/11 |
-- |
Notification of Constriction Work under APCO (Construction Dust) |
001012125 |
18/07/06 |
17/07/08 |
-- |
Implementation
Status of Environmental Mitigation Measures
6.14 In response to the site audit findings, the Contractor carried out
corrective actions.
6.15 A summary of the Implementation Schedule of Mitigation Measures (EMIS)
is presented in Appendix C. Most of the necessary mitigation measures were
implemented properly.
Summary
of Exceedances of the Environmental Quality Performance Limit
6.16 All 1-hour TSP, 24-hour TSP and noise monitoring results complied with
the Action / Limit levels.
6.17 No exceedance was recorded in the reporting month.
Summary
of Complaints, Notification of Summons and Successful Prosecutions
6.18 The Environmental Complaint Handling Procedure is annexed in Figure 6.1.
6.19 No environmental
complaint, notification of summons and successful prosecutions was received in
the reporting month.
Construction
Programme for the Coming Months
7.1
The construction programme
for the Project is provided in Appendix B.
7.2
The major construction work
in July 2008 will be:
-
Soil Nail installaton at Portion A1 and
Portion A2.
7.3
Key issues to be considered
in the coming month included:
-
Properly store and label
oils and chemicals on site;
-
Collection of construction
waste should be carried out regularly;
-
Site runoff should be
properly collected and treated prior to discharge;
-
Construction activities
should avoid causing damage to the trees and to plants species of conservation
interest;
-
Quieter powered mechanical
equipment should be used.
7.4
The following mitigation
measures are required:
Air Quality Impact
-
Regular watering should be
used during soil nailing;
-
Dusty material stockpiled
should be completely covered;
-
Dusty activities should be
re-scheduled if high-wind conditions encountered;
-
Open burning should be
strictly prohibited;
-
All dusty vehicle loads transporting
to, from and between site locations should be covered with tarpaulin;
-
Vehicle wheel and body
washing facilities should be used at all exit points of the site;
-
Wind shield, dust
extraction units or water spraying should be used at the loading points.
Construction Noise Impact
-
Quieter powered mechanical
equipment should be used;
-
Insulating fabric should be
used for drill rigs during drilling process;
-
Noise generating
construction works should be carried out during daytime only;
-
Noise barriers or other
measures should be used to minimize disturbance to the bat roost;
-
Plant on site should be
properly maintained and serviced regularly;
-
Mobile plants should be
sited as far from NSRs as possible;
-
Machines and plant in
intermittent use should be throttled down;
-
Strong noise emitting
plants, wherever possible, should be oriented so that noise is directed away
from the nearby NSRs;
-
Material stockpiles,
wherever possible, should be effectively utilized to screen noise from
construction activities;
-
Movable noise barrier with
surface mass in excess of 7kg/m2 should be used for PME wherever
possible;
-
Noise insulating fabric
should be adopted for drill rig operating in Works Area E.
Water Quality Impact
-
Prevent runoff water from entering
the nearby water-bodies;
-
Silt traps and oil / grease
separators should be regularly cleaned and maintained;
-
Outlet pipe extending above
the slope surface should be installed;
-
Air should be used as the
flushing medium of the drilling equipment;
-
Earth bunds or sand bag
barriers should be provided on-site to direct storm water to silt removal
facilities;
-
Exposed slope / soil
surface and opened stockpile of more than 50m3 should be covered
with tarpaulin;
-
Oils and fuels should be
used and stored in designated area.
Chemical and Waste
Management
-
Debris and rubbish on-site
should be collected, handled and disposed of properly;
-
Waste skips should be
provided to collect general refuse and construction wastes;
-
Soil contamination with
fuel leaked from construction plants should be removed off-site;
-
Sufficient waste disposal
points with regular collection should be provided;
-
Appropriate measures should
be provided to minimize windblown litter and dust during transportation of
waste;
-
Different containers should
be used to segregate and store different types of waste;
-
Encourage collection of
aluminum cans, PET bottles and paper by providing separate bins;
-
Unused chemicals should be
recycles wherever possible;
-
Proper storage and site practices
should be adopted to minimize the potential for damage and contamination of
construction materials;
-
Oils and fuels should be
stored in designated area;
-
Plan and stock construction
materials carefully to minimize waste generation.
Ecological Impact
-
Soil nail installation
should avoid / minimize damage of root system to the existing plants;
-
Fences should be erected
along the boundary of the works area
-
Disturbance to the natural
woodland and shrubland habitats should be minimized by preventing tipping,
vehicle movements and encroachment of personnel onto the adjacent area;
-
Permanent casing should be
provided to the drillhole of soil nail;
-
Placement of equipment or
stockpile should be located in designated areas to minimize disturbance to
natural or moderate-high ecological value habitats;
-
Construction activities
should be restricted to works areas;
-
Disturbance to existing
vegetation should be minimized wherever possible.
Landscape and Visual Impact
-
Designation of “no-intrusion
zones” and record any trespass and damage to existing vegetation;
-
Soil nails on site should
avoid tree trunks and tree roots;
-
Dust and erosion control
should be provided for exposed soil;
-
For tree planting
operations, method statement should be checked against specification
requirements;
-
All retained trees within
the working boundary should be checked regularly;
-
Control over appearance of
hoarding, construction plants / machines;
-
Security floodlights should
be carefully selected to avoid light pollution.
Monitoring
Schedule for the Coming Months
7.5
The tentative schedule for
environmental monitoring in July 2008 is provided in Appendix L.
8. CONCLUSIONS AND RECOMMENDATIONS
8.1
The construction phase of
the project commenced in April 2008.
8.2
1-hour TSP and 24-hour TSP
monitoring was carried out in the reporting month. All monitoring results
complied with the action / limit level. No exceedance was recorded.
8.3
All impact daytime noise
monitoring results complied with the limit level in the reporting month.
8.4
Environmental site inspections were carried out 4
times in June 2008. Recommendations on remedial actions were given to the
Contractor for the deficiencies identified during the site audit.
8.5
Two landscape and visual audits
were carried out in the reporting month. The Contractor was recommended to provide more
adequate protection to existing trees in the work areas and not to use the
trees as temporary supports.
8.6
Construction materials placed
near tree trunks and spillage of concrete on the soil surface near soil nailing
areas were observed.
8.7
No environmental complaint,
notification of summons and prosecution was received in the reporting month.
8.8
According to the environmental
site inspections performed in the reporting month, the following
recommendations were provided:
Air Quality Impact
-
Soil nail workstations on
site should be fully enclosed;
-
Exposed earth surface
should be covered with tarpaulin sheets; and
-
Bunding should be provided
along the edge of the u-channel under slope with exposed earth surface.
Construction Noise Impact
-
Nil
Water Quality Impact
-
U-channels should be kept
clear of mud, construction waste and leaves.
Chemical and Waste
Management
-
Drip trays should be
provided to all plants and oil drums on site;
-
Oils and fuels should be
stored in designated area;
-
C&D waste, debris and
general refuse on-site should be collected, handled and disposed of properly;
and
-
Waste skips should be
provided to collect general refuse and construction wastes.
Ecological Impact
-
Hessian sacking should be
wrapped around the trunk of vegetation to prevent damage during the
transportation of construction materials.
Landscape and Visual Impact
-
Soil nails on site should
avoid tree trunks and tree roots;
-
More adequate protection
should be provided to existing trees in the work areas; and
-
Stockpiling of any
construction materials / equipments against or near existing tree should be
avoided.