TABLE OF CONTENTS

 

EXECUTIVE SUMMARY

1.         INTRODUCTION

Scope of Report

Project Organization and Contacts of Key Management

Summary of Construction Works

2.         ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS

Monitoring Parameters

Environmental Quality Performance Limits (Action/Limit Levels)

Environmental Mitigation Measures

3.         MONITORING RESULTS

Air Quality

Ecology

Landscape and Visual

Environmental Site Inspection

4.         Advice on Solid and liquid Waste Mangement Status

5.         Summary of Non-Compliance (Exceedances) of environmental qualitY

Summary of Exceedances and Review of the Reasons for non-compliance

6.         Environmental complaints, notification of summons and successful prosecutioN

7.         Comments, Recommendations and Conclusions

Comments on Mitigation Measures

Recommendations on EM&A Programme

Conclusions

 

List of Tables

 

Table 1.1           Contact Information of Key Personnel

 

List of Figures

 

Figure 1.1          Site Layout Plan

Figure 2.1          Locations of Air Quality and Noise Monitoring Stations

 

 

List of Appendices

 

Appendix A Project Organization Structure

Appendix B Construction Programme

Appendix C         Implementation Schedule of Mitigation Measures (EMIS)

Appendix D Action and Limit Levels for Air Quality  and Noise

Appendix E Graphical Presentation of Air Quality Monitoring Results

Appendix F Graphical Presentation of Noise Monitoring Results


 

 

 

EXECUTIVE SUMMARY

The Project “Landslide Preventive Works at Po Shan, Mid-levels – Design and Construction (Natural Terrain Risk Mitigation Works)” (hereafter called “the Project”) includes the installation of about 700 numbers of soil nails and about 60 numbers of raking drains on the natural terrain within the concerned area.

China State – China Railway Joint Venture (CCJV) was commissioned as the Contractor of the Project. ENSR Asia (HK) Ltd. was employed by CCJV as the Environmental Team to carry out the EM&A programme.

The impact environmental monitoring and audit for the Project includes the air quality, noise, ecology, landscape and visual monitoring. The construction of the Project and the EM&A programme commenced on 1 April 2008.

This report documented the findings of EM&A works conducted in the period from July 2008 to September 2008. As informed by the Contractor, construction activities carried out in the reporting quarter were:

-         Installation of Soil Nail at Portion A1, Portion A2 and Portion B1;

-         Erection of scaffolded platform at Portion A2 and B1;

-         Soil nail head preparatory works at Portion A1; and

-         Erection of working platform for soil nail installation at Portion C.

 

Environmental Monitoring Works

 

EM&A Programme

 

A summary of monitoring and audit activities conducted in the reporting quarter is listed below:

 

24-hour TSP monitoring

15

sessions

1-hour TSP monitoring

48

sessions

Daytime Noise monitoring

13

sessions

Ecology monitoring

6

sessions

Landscape and Visual Audit

  7

sessions

Environmental Site Inspection

14

sessions

Breaches of Action and Limit Levels

There was no action / limit level exceedance recorded for 1-hour and 24-hour TSP monitoring.

In the reporting quarter, all noise level recorded complied with the limit level.

Complaint, Notification of Summons and Successful Prosecution

There was no complaint, notification of summons and successful prosecution received in the reporting quarter.

.

 

 


1.      INTRODUCTION

Scope of Report

1.1          This is the second Quarterly Environmental Monitoring and Audit (EM&A) Summary Report under the Contract CE 28/2004 (GE) – Landslide Preventive Works at Po Shan Road, Mid-Levels – Design and Construction (Natural Terrain Risk Mitigation Works). This report presented a summary of the environmental monitoring and audit works, and list of activities carried out by the ET for the Project for the period from July 2008 to September 2008.

 

Project Organization and Contacts of Key Management

1.2          The project organization is shown in Appendix A. The key personnel contact names and numbers are summarised in Table 1.1

 

Table 1.1       Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

CEDD

Senior Engineer

H. W. Sun

2762 5375

2714 0247

ER (MGS)

Resident Engineer

Andrew J. Westmoreland

3188 0400

3188 0775

Assistant Resident Engineer

S. F. Chau

3188 0400

3188 0775

IEC (ENVIRON)

Independent Environmental Checker

David Yeung

3743 0788

3548 6988

Contractor (CCJV)

Project Manager

Eddie Tang

3188 0538

3188 1710

Safety and Environmental Officer

Ken Fong

3188 0538

3188 1710

ET (ENSR)

ET Leader

Edith Ng

3105 8525

2891 0305

 

Summary of Construction Works

1.3          The Contactor has carried out major activities in the reporting quarter. Details of the works undertaken in this reporting period are listed below:

 

-         Installation of Soil Nail at Portion A1, Portion A2 and Portion B1;

-         Erection of scaffolded platform at Portion A2 and B1;

-         Soil nail head preparatory works at Portion A1; and

-         Erection of working platform for soil nail installation at Portion C.

 

1.4          The general layout plan of the Project site showing the contract area is shown in Figure 1.1.

 

1.5          The construction programme is provided in Appendix B.

 

1.6          The mitigation measures implementation schedule are presented in Appendix C.

 


2.      ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS

Monitoring Parameters

2.1          The EM&A Manual designated two monitoring stations to monitor environmental impacts on air quality and noise due to the Project. The monitoring locations are depicted in Figure 2.1.

 

2.2          The EM&A Manual also required ecology monitoring, bi-weekly landscape and visual audits, and environmental site inspections for air quality, noise, water quality, chemical, waste management, ecology and landscape and visual.

Environmental Quality Performance Limits (Action/Limit Levels)

2.3          The environmental quality performance limits (i.e. Action/Limit Levels) were derived from the baseline air quality monitoring results of Access road to Po Shan Mansions (CA1) and Podium of Hamilton Court (CA2) and / or as defined in the EM&A Manual (CN1 & CN2), and are given in Appendix D.

Environmental Mitigation Measures

2.4          Relevant environmental mitigation measures were stipulated in the Particular Specification and EP (No.: EP-235/2005/B) for the Contractor to adopt. A list of mitigation measures and their implementation statuses are given in Appendix C.

 

 

 


3.             MONITORING RESULTS

Air Quality

3.1          Air quality monitoring, including 1-hr and 24-hr TSP, was conducted at least 3 times every 7 days and at least once every 7 days respectively at the 2 monitoring stations (CA1 and CA2), in accordance with the EM&A Manual. Forty-eight 1-hr TSP and fifteen 24-hr TSP monitoring events were carried out in this reporting quarter.

3.2          The weather was either sunny or rainy in the reporting quarter. The trend of air quality for the reporting quarter are given in Appendix E. Major dust source of the construction works area included soil nail installation activities from the Project, construction activities of another project under the same contract (concurrent project) carried out in the vicinity and nearby traffic emissions.

3.3          There was no Action and Limit Level exceedance recorded for both 1-hr and 24-hr TSP in the reporting quarter.

3.4          Table 3.1 presents the number of exceedances recorded in each month of the reporting quarter. The number of monitoring events included regular monitoring events and additional ones, if any.

 

Table 3.1       Summary of Number of Exceedances for 1-hr & 24-hr TSP Concentration

Monitoring Parameter

Location

Level of Exceedance

Month

Jul 08

Aug 08

Sep 08

1-hr TSP

CA1

No. of monitoring events

18

15

15

Action

0

0

0

Limit

0

0

0

CA2

No. of monitoring events

18

15

15

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

24-hr TSP

CA1

No. of monitoring events

5

5

5

Action

0

0

0

Limit

0

0

0

CA2

No. of monitoring events

5

5

5

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

 

Construction Noise

3.5          Noise monitoring was conducted at the 2 monitoring stations (CN1 and CN2) for at least once per week during 0700 – 1900 of the reporting quarter. Thirteen noise monitoring events were conducted in the reporting quarter.

3.6          As no noise complaint was received in the reporting quarter, no Action Level exceedance was recorded. All measured noise levels were below the Limit Level and the graphical plots of trends of the monitoring results are provided in Appendix F.

3.7          Table 3.2 presents the number of exceedances recorded in each month of the reporting quarter. The number of monitoring events included regular monitoring events and additional ones, if any.

 

Table 3.2       Summary of Number of Exceedances for Daytime Noise

Monitoring Parameter

Location

Level of Exceedance

Month

Jul 08

Aug 08

Sep 08

Daytime Noise

CN1

No. of monitoring events

5

4

4

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

CN2

No. of monitoring events

5

4

4

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

3.8          Major noise sources during the noise monitoring included the construction activities from the Project and another project under the same contract (concurrent project) carried out in the vicinity and nearby traffic noise.

 

Ecology

3.9          Ecological monitoring was carried out twice a month by a suitably qualified local ecologist to check on the health and condition of the plant species of conservation interest. Six ecological monitoring were conducted in the reporting quarter.

3.10      A total of 13 plant species of conservation interest (i.e. V001 to V013) were identified within the area during an earlier Detailed Vegetation Survey conducted under this Project.  V001 to V013 were found to be in good condition during the monitoring visits in the reporting period.

3.11      Construction materials such as planks, sand bags, metal rods were found to be placed over or near the lower trunks of some trees in Row C, L, O and R.  It was recommended that these materials should be kept in proper place to avoid damage to vegetation within works area. 

3.12      Concrete was found to be spilled over from the soil nailing works zones onto nearby areas.  It was recommended that the concrete should be removed from the soil surface.  The Contractor advised that the concrete will be removed and measures will be implemented to avoid any further spillage.

3.13      The leaves, branches and trunk of a tree (Machilus sp.) located in Row O was found to be covered with sand and mud probably generated from nearby soil nailing works.

3.14      Two trees, Celtis sinensis and Machilus sp., located near the conveyor belt and above Row Q were found to be dead and in very poor condition respectively.  A dead tree (tree tag number T238) was collapsed within works area.  It was recommended that all dead trees found within the construction site should be recorded and reported to relevant departments without delay.

3.15      Two main roots of a big tree (Acacia confusa of tree tag number T247) were cut due to the construction of soil nail number I6 (Figure 4.1).

3.16      The trunk of a tree (tree tag number T344) located next to a soil nailing area in Row O was covered with concrete.

3.17      Site clearance, soil nailing and scaffolding works were in progress during the monitoring visits.  V042, V043, V048 to 51 and V057 to 59 were identified with the above works area.  All of them has been fenced off and were in good condition.

3.18      One of the main branches of a plant (Glochidion wrightii) on Soil Nailing Row X was cut to give way to machinery.  The Contractor was advised that trimming of plant within works area is not allowed.

3.19      A proper handrail for site access to the south of Row AF should be set up instead of tying ropes on trees as support.

3.20      Tree No. T611 (Schefflera heptaphylla) on Row R was found to be in very poor condition.  A recently dead tree on Row AF was tipped to one side.

3.21      The lower trunk of Tree No. T5955 adjacent to soil nailing position on Row AF was covered with grout.

3.22      Vegetation located between Row AO to AU was excessively removed during site clearance.  The plant debris was dumped in the adjacent woodland habitat outside the works area.

 

 

 

Landscape and Visual

3.23      Bi-weekly landscape and visual audit was conducted by a Registered Landscape Architect (RLA) to monitor the implementation of landscape and visual mitigation measures. Seven landscape and visual audits were conducted in the reporting quarter.

3.24      It was still noted that no tree protection with wooden slats was made for trees enclosed within the drilling platforms.  The Contractor was reminded to provide adequate tree protection works near the trees in order to prevent accidentally damaging the trees.

3.25      Construction equipments, metal pipes / steel bars were observed being placed against the tree trunks of existing trees at several locations on site.  The Contractor was requested to clear the equipment and construction materials and not to place them against trees in future in order to prevent damage to the trees.

3.26      Soil bags were observed placed on slopes and rested at the base of the tree trunks.  The Contractor was requested to clear the soil bags away from the base of the tree as soon as possible.

3.27      Construction waste pile was observed on the slope.  The Contractor was requested to clear it away as soon as possible.

3.28      Sealing of the root wounds for tree T247 was still outstanding.  The Contractor was reminded to apply protective sealant to prevent the roots from rotting as soon as possible.

3.29      Construction waste was observed placed at the base of several trees.  The Contractor was requested to clear it away as soon as possible.

3.30      A number of minor tree branches were observed damaged by typhoon. The Contractor was requested to prune the broken tree branches back to living tissues as soon as possible.

3.31      A couple of dead trees, including a tree with rotten trunk at the base were observed near existing tree T534. The Contractor was recommended to remove all the dead and dying trees away from the footpath area for the safety of workers.

3.32      Many of the trees numbers were obscured by recently wrapped hessian tree protection.  The Contractor was requested to re-instate the tree numbers on existing trees for ease of identification.

3.33      The leaves of existing tree T611 were wilted due to dry soil condition.  The Contractor was recommended to water the tree on a daily basis and to monitor the condition of the tree.

3.34      It was observed that the Contractor had stacked pipe sleeves near the base of the existing tree.  The Contractor was requested to remove the pipes away from the tree as soon as possible.

3.35      It was still observed that the Contractor had not removed the dead trees, including a tree with rotten trunk at the base located near existing tree T534.  The Contractor was recommended to remove all the dead and rotten trees away from the footpath area for safety.

3.36      It was still observed that rectification of many of the tree identification numbers for the existing retained trees were outstanding.  The Contractor was reminded to re-instate the tree numbers on existing trees for ease of reference as soon as possible.

3.37      The leaves of previously wilted tree T611 had dried out and dying.

3.38      It was observed that the Contractor had tied the toe board onto the existing tree trunk.  The Contractor was requested to remove it as soon as possible.

 

Environmental Site Inspection

3.39      There were 14 site inspections conducted in the reporting quarter to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. The major concerns for the Project are air quality, noise, water quality, waste management, ecology and landscape and visual. Observations recorded are described below. All the observations were rectified by the Contractor within the agreed time frame.

Air Quality

3.40      No adverse observation was identified in the reporting quarter.

Noise

3.41      No adverse observation was identified in the reporting quarter.

Water Quality

3.42      Debris and leaves were observed inside the u-channel at Row D and near Row R and Row S. The Contractor was reminded to clear the u-channel more frequently.

3.43      Minor muddy water was observed running down the u-channel near Row K and Row M. The Contractor was reminded to clear the exposed earth at all working platforms and properly maintain the desilting tank next to Row D.

3.44      Exposed earth was observed around the area of soil nail installation at Row Y and Row AF and on the slope at Row Y and Row Z. The Contractor was advised to clean up the earth as soon as the operation was completed.

3.45      Deposited silt was observed accumulated inside the u-channel at Row R and Row V. The Contractor was reminded to clear the u-channel more frequently.

3.46      Sand bags at Row R and Row V were found damaged. The Contractor was advised to replace the sand bags.

Chemical and Waste Management

3.47      Oil drums and soil nail installation controller were found placed on ground without drip tray at Row C, Row Q, Row R, Row S, Row Y, Row V, Row Z, Row AA and Row AF. The Contractor was reminded to provide drip trays to the chemical containers and all plants on site.

3.48      Small amount of cement slurry was found run off into the u-channel at Row R. The Contractor was reminded to clean up the slurry inside the u-channel and prevent further runoff.

Ecology

3.49      Sand bags and C&D materials were observed placed against the trees at Row C, Row D, Row E and Row R. The Contractor was reminded to keep the C&D materials away from the trees.

3.50      Construction materials placed near tree trunks and spillage of concrete near soil nailing areas were observed.  Some of the plants were not properly protected during soil nailing works and serious damages to root systems were recorded.  One recently dead tree was found within the works area.

3.51      Pruning of tree was observed in Row X.

3.52      Vegetation located between Row AO to AU was excessively removed during site clearance.

3.53      The plant debris from site clearance was dumped in the adjacent woodland habitat outside works area.

Landscape and Visual

3.54      The Contractor was recommended to provide more protection to existing trees which are surrounded by drilling platforms and avoid stockpiling of any construction materials / equipments / sand bags against or near existing trees.

3.55      The Contractor was recommended to apply root protective sealant to the wounded roots.  The Contractor was recommended to seek the Engineer’s agreement for excavation works near existing tree roots in order to minimize damage to the tree root system.  If root pruning is required, prior approval from Engineer is required.

3.56      The Contractor was recommended to clean the material fines off the tree trunks and to provide tree protection in future when carried out drilling works.

3.57      The Contractor was recommended to provide treatment to the damaged tree roots to prevent further damage to the roots.

3.58      The Contractor was recommended to keep all construction waste and soil bags away from existing trees and to keep the site clean and tidy.

3.59      The Contractor was recommended to re-instate all missing tree numbers for existing trees on site for easy identification.

3.60      The Contractor was recommended to clear away all dead trees as found on site, including the rotten tree for safety consideration.  The Contractor was also reminded to record and report all dead trees as found on site to the Engineer for record.

3.61      The Contractor was recommended to provide moist hessian wrapping to the exposed cut roots to prevent the roots from drying out.

3.62      The Contractor was recommended to clear away all construction materials away from existing trees and not to place it against or near the trees in future.

3.63      The Contractor was recommended to remove dead / rotten trees from site for safety.

3.64      The Contractor was recommended to water the existing tree T611 to help improve the stressed condition of the tree, and to monitor the tree daily.

3.65      The Contractor was requested to remove the toe board away from existing tree and not to use tree for anchorage.

3.66      The Contractor was reminded to rectify all ineligible tree identification numbers for all existing trees.


 

4.      Advice on Solid and liquid Waste Mangement Status

 

4.1          The Contractor has registered as a chemical waste producer for this Project. The Chemical Waste Storage Area located at the Contractor’s site office area was properly maintained in the reporting quarter.

4.2          As advised by the Contractor, 32.08 ton of inert C&D waste was disposed offsite to Public Filling Barging Point at Quarry Bay in September 2008. C&D waste generated was reused on site as much as possible.

 

 

5.      Summary of Non-Compliance (Exceedances) of environmental qualitY

Summary of Exceedances and Review of the Reasons for non-compliance

5.1          There was no 1-hr TSP, 24-hr TSP and noise exceedance recorded in the reporting quarter.

 

 

6.      Environmental complaints, notification of summons and successful prosecutioN

 

6.1          No environmental complaints, notification of summons and prosecution was received in the reporting quarter. Table 6.1 summarized the complaint, summons and successful prosecution received in the reporting period.

 

       Table 6.1      Summary of Environmental Complaints and Prosecutions

 

July 2008

August 2008

September 2008

Total

Complaint Logged

0

0

0

0

Summons

Served

0

0

0

0

Successful Prosecution

0

0

0

0

Total

0

0

0

0

 

 

 

7.      Comments, Recommendations and Conclusions

Comments on Mitigation Measures

7.1          According to the environmental site inspections performed in the reporting quarter, the following comments are provided:

 

Air Quality

-         N/A

Noise

-         N/A

Water Quality

-         Debris, leaves and deposited silt inside the u-channel should be cleared more frequently.

-         Exposed earth at all working platforms should be cleared as soon as the soil nailing operation was completed.

-         The desilting tank next to Row D should be properly maintained.

-         Damaged sand bags on site should be replaced.

Chemical and Waste Management

-         All plants and chemical containers on site should be provided with drip tray.

-         Cement slurry during grouting works should be prevented from running off into u-channel.

Ecology

 

-         Hessian sacking should be wrapped around the trunk of vegetation to prevent damage during the transportation of construction materials.

 

-         Pruning of tree branches should be avoided.

 

-         Vegetation removal to a minimum level and clearance should only be conducted in area where necessary.

 

-         The plant debris from site clearance should be removed from works area in a timely manner.

 

-         The spilt grout should be removed from the tree trunk / root immediately.

 

-         Proper handrail for site access should be set up instead of using trees as support.

 

Landscape and Visual

 

-         Soil nails on site should avoid tree trunks and tree roots.

 

-         More adequate protection should be provided to existing trees in the work areas and during drilling works.

 

-         Stockpiling of any construction materials / equipments / sand bags against or near existing tree should be avoided.

 

-         All missing tree numbers for existing trees on site should be re-instated.

 

-         All dead trees, including rotten trees, found on site should be removed for safety concern.

 

-         Moist hessian wrapping should be provided to the exposed cut roots to prevent the roots from drying out.

 

-         All construction materials should be kept away from existing trees.

 

-         Trees should not be used to support or anchorage of any construction material.

 

-         All ineligible tree identification numbers for all existing trees should be rectified.

 

-         All dead trees found on site should be recorded and reported to the Engineer for record.

 

Recommendations on EM&A Programme

7.2          The impact air quality and noise monitoring programme ensured that any environmental impact to the receivers would be readily detected and timely actions could be taken to rectify any non-compliance.  Assessment and analysis of monitoring results collected demonstrated the environmental acceptability of the Project.  The ecological monitoring, bi-weekly landscape and visual audit and weekly site inspection ensured that all the environmental mitigation measures recommended in the EIA report were effectively implemented.

7.3          The EM&A programme effectively monitored the environmental impacts from the construction activities and no particular recommendation was advised for the improvement of the programme.

Conclusions

7.4          Air quality and noise monitoring, ecological monitoring, bi-weekly landscape and visual audit and weekly site inspection were carried out from July 2008 to September 2008, in accordance with the EM&A Manual.

7.5          No Action and Limit Level exceedance or non-compliance was recorded for the monitoring works in the reporting quarter.

7.6          No environmental complaint, summons or prosecution was made against the Project in the reporting quarter.