Agreement
No. CE 28/2004 (GE)
Landslide
Preventive Works at
Design
and Construction
(Natural
Terrain Risk Mitigation Works)
Landscape
& Visual Audit and Monitoring
(September
2008)
Prepared by
URBIS LIMITED
Prepared
by : |
|
|
|
|
Tran
Tuan Huy |
|
|
Approved by : |
|
|
|
|
Alexander
Duggie |
|
|
1.0 INTRODUCTION
The Landscape and Visual Audit
& Monitoring are conducted to fulfill the requirements of the EIA Report during
the Construction and Operational Phases of the project, and are based on the
procedures and requirements as set out in the Agreement No. CE 28/2004 (GE)
Landslide Preventive Works at
As stated in section 3.5 and 3.6 of the EM&A Manual, all landscape and visual mitigation measures undertaken by the Contractor during the construction phase and the first 12 months of the operational phase shall be audited on a bi-weekly and monthly basis respectively to ensure compliance with the intended aims of the mitigation measures.
2.0 SCOPE OF AUDIT and MONITORING
The broad scope of landscape and visual monitoring and audit on mitigation measures is as detailed below:
2.1
Construction Phase
Indentify any potential conflicts between the proposed landscape measures and any other project works or operation requirements, and recorded for the contractor to resolve in early stage, without compromising the intention of the mitigation measures. Also, the followings shall be monitored:
·
designation of ‘no-intrusion zones’, and to record
any trespass by the contractor, including damage to existing vegetation;
·
allowance for adjustment of soil nails on site for
the avoidance of tree trunks and tree roots;
·
dust and erosion control for exposed soil;
·
tree planting operations, checking method statement
against specification requirements;
·
all retained trees within the working boundary shall
be regularly checked and reported to the engineer, including damage to the tree
canopy edge.
Considerations shall also be made to address the appearance and view by
public through:
·
control over the appearance of construction workers,
hoarding, construction plants / machines
·
careful selection of security floodlights to avoid
light pollution
2.2 Operation Phase
Ensure the compensatory planting and horticultural maintenance operations are properly carried out during the 12 months establishment period, including:
· Inspection for fungal / viral attacks and pest infestations
· Litter collection
· Watering
· Weeding removal
· Replacement of defective planting material
· Grass cutting / groundcover trimming and removal of arisings
· Fertilizing application as required in specification
· Aeration / mulching application
3.0 INSPECTIONS
3.1
Summary of Inspection
3.1.1 Matters Arising from Previous Inspections
·
It was observed that the Contractor had cleared away
the remainder of soil bags away from the base of the tree trunks.
·
The Contractor had cleared away all remaining
construction waste previously placed at the base of trees.
·
The Contractor had removed minor damaged tree
branches caused by the recent typhoon.
·
The Contractor still had not carried out any
remedial measures for the exposed cut roots to prevent the roots from dried
out. The Contractor was reminded to
carry out remedial actions as soon as possible.
·
It was observed that the Contractor had not removed
a couple of the dead trees, including a tree with rotten trunk at the base
located near existing tree T534.
The Contractor was recommended to remove all the dead and rotten trees
away from the footpath area for safety.
·
It was observed that rectification of many of the
tree identification numbers for the existing retained trees were outstanding. The Contractor was reminded to
re-instate the tree numbers on existing trees for ease of reference as soon as
possible.
3.1.2 Protection of Existing Trees
·
It was observed that the leaves of existing tree
T611 were wilted due to dry soil condition. The Contractor was recommended to water
the tree on a daily basis and to monitor the condition of the tree.
·
It was observed that the Contractor had stacked pipe
sleeves near the base of the existing tree. The Contractor was requested to remove
the pipes away from the tree as soon as possible.
3.1.3 Recommendations
·
The Contractor was recommended to provide moist
hessian wrapping to the exposed cut roots to prevent the roots from drying out.
·
The Contractor was recommended to clear away all construction
materials away from existing trees and not to place it against or near the trees
in future.
·
The Contractor was recommended to remove dead /
rotten trees from site for safety.
·
The Contractor was reminded to rectify all
ineligible tree identification numbers for all existing trees.
·
The Contractor was recommended to water the existing
tree T611 to help improve the stressed condition of the tree, and to monitor
the tree daily.
3.2
Summary of Inspection
3.2.1 Matters Arising from Previous Inspections
·
The Contractor had provided hessian wrappings as
remedial measures for the exposed cut roots to prevent the roots from dried
out.
·
The Contractor had removed the stacked pipe sleeves
previously placed near the base of the existing tree.
·
It was still observed that the Contractor had not
removed the dead trees, including a tree with rotten trunk at the base located
near existing tree T534. The
Contractor was recommended to remove all the dead and rotten trees away from
the footpath area for safety.
·
It was still observed that rectification of many of
the tree identification numbers for the existing retained trees were
outstanding. The Contractor was
reminded to re-instate the tree numbers on existing trees for ease of reference
as soon as possible.
·
It was observed that the leaves of previously wilted
tree T611 had dried out and dying.
3.2.2 Protection of Existing Trees
·
It was observed that the Contractor had tied the toe
board onto the existing tree trunk.
The Contractor was requested to remove it as soon as possible.
·
It was observed an existing tree (tree no. unknown)
was fallen over during recent typhoon.
The Contractor was requested to clear away the dead tree as soon as
possible.
3.2.3 Recommendations
·
The Contractor was requested to remove the toe board
away from existing tree and not to use tree for anchorage.
·
The Contractor was reminded to rectify all
ineligible tree identification numbers for all existing trees.
·
The Contractor was recommended to remove dead /
rotten trees from site for safety. The Contractor was also reminded to record
and report all dead trees as found on site to the Engineer for record.
4.0 AUDIT SCHEULE
4.1 Audit Schedule for October 2008
The next audits are
scheduled to be conduct on 8th and