Site Inspection Summary

 

Inspection Information

Date:

2 September 2008

Time:

15:00

Inspection No.:

023

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

 

1.

The soil nail installation controller at Row C and the oil drum at Row Y had been provided with drip trays. (Closed)

 

 

2.

Exposed earth around the area of soil nail installation at Row Y and Row AF had been cleared. (Closed)

 

 

 

New Observation

 

 

 

Nil

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Date:

9 September 2008

Time:

15:00

Inspection No.:

024

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

Nil

 

 

 

 

 

 

 

New Observation

 

 

1.

Small amount of cement slurry was found run off into the u-channel at Row R. The Contractor was reminded to clean up the slurry inside the u-channel and prevent further runoff.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

A dead tree was observed tiled and hanged against another tree next to Row Y.

 

 


Site Inspection Summary

 

Inspection Information

Date:

16 September 2008

Time:

15:00

Inspection No.:

025

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

1.

Cement slurry inside the u-channel at Row R had been cleared. No slurry runoff was observed. (Closed)

 

 

 

 

 

 

 

New Observations

 

 

2.

Exposed earth was observed on the slope at Row Y. The Contractor was reminded to clear the earth.

 

 

3.

An oil drum and a soil nail installation controller were found placed on ground without drip tray at Row Z. The Contractor was reminded to provide drip trays to all plants and chemical containers on site.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Date:

23 September 2008

Time:

15:00

Inspection No.:

026

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

 

1.

The condition of exposed earth on the slope at Row Y was to be inspected.

 

 

2.

The condition of the oil drums and soil nail installation controller placed on ground at Row Z was to be inspected.

 

 

 

New Observation

 

 

 

Nil

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Cyclone typhoon signal no. 3 was hoisted. Strong wind and heavy rain occurred during the inspection. No construction activity was taken place.

 

 


Site Inspection Summary

 

Inspection Information

Date:

30 September 2008

Time:

15:00

Inspection No.:

027

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

 

1.

Exposed earth was observed on the slope at Row Y and Row Z. The Contractor was reminded to clear the exposed earth.

 

 

2.

Oil drums and oil nail installation controllers at Row V, Row AA and Row AF were found placed on ground without drip trays. The Contractor was reminded to provide drip tray to all chemical containers and plants on site.

 

 

 

 

 

 

 

New Observations

 

 

3.

Deposited silt was observed accumulated inside the u-channel at Row R and Row V. The Contractor was reminded to clear the u-channel more frequently.

 

 

4.

Sand bags at Row R and Row V were found damaged. The Contractor was advised to replace the sand bags.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil