Site Inspection Summary
Date: |
8 October 2008 |
Time: |
15:00 |
Inspection No.: |
028 |
|
Nil |
|
Follow Up Observations |
|
|
1. |
Exposed earth was observed on the slope at Row Y, Row Z and above Row
R. The Contractor was reminded to clear the exposed earth. |
|
|
2. |
The soil nail installation controller at
Row V had been removed. However, the oil drums at Row AA and Row AF, and the soil
nail installation controllers at |
|
|
3. |
Deposited silt inside the u-channel at Row R and
Row V had been cleared. (Closed) |
|
|
4. |
The damaged sand bags at Row R and Row V had been
replaced. (Closed) |
|
|
|
|
|
|
|
|
|
|
|
New Observation |
|
|
|
Nil |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site Inspection Summary
Date: |
14 October 2008 |
Time: |
15:00 |
Inspection No.: |
029 |
|
Nil |
|
Follow Up Observations |
|
|
1. |
Exposed earth was still observed on the slope at Row Y, Row Z and
below Row T. The Contractor was reminded to clear the exposed earth on the
slope. |
|
|
2. |
The oil drums at Row AA and Row AF had been
removed. However, the soil nail installation controller at |
|
|
|
|
|
|
|
|
|
|
|
New Observation |
|
|
3. |
Muddy water was observed running down the u-channel along the site due
to water-spraying to a soil nail installation operation at Row T. The
Contractor was reminded not to spray water directly on exposed earth and make
sure the effluent would be treated before discharged to public drain. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site Inspection Summary
Date: |
21 October 2008 |
Time: |
15:00 |
Inspection No.: |
030 |
|
Nil |
|
Follow Up Observations |
|
|
1. |
The exposed earth at Row Z and below Row T had been cleared. However,
small amount of exposed earth was still observed on the slope at Row Y. The
Contractor was reminded to clear the earth at Row Y. |
|
|
2. |
The soil nail installation controller at |
|
|
3. |
Water running down the u-channel along the site was
clear. (Closed) |
|
|
|
|
|
|
|
New Observation |
|
|
|
Nil |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site Inspection Summary
Date: |
28 October 2008 |
Time: |
15:00 |
Inspection No.: |
031 |
|
Nil |
|
Follow Up Observation |
|
|
1. |
The exposed earth at Row Y had been cleared. (Closed) |
|
|
|
|
|
|
|
|
|
|
|
New Observation |
|
|
2. |
Soil nail installation controllers at Row AF10 and Row PD19, and a
chemical container at Row AF10 were found placed on ground without drip tray.
The Contractor was reminded to provide drip tray to all plants and chemical
containers on site. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |