Site Inspection Summary
Date: |
4 November 2008 |
Time: |
15:00 |
Inspection No.: |
032 |
|
Nil |
|
Follow Up Observation |
|
|
1. |
Soil nail installation controllers at Row AF10 and Row PD19 had been
provided with drip trays. The chemical container at Row AF10 had been
removed. (Closed) |
|
|
|
|
|
|
|
|
|
|
|
New Observation |
|
|
|
Nil |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site Inspection Summary
Date: |
11 November 2008 |
Time: |
15:00 |
Inspection No.: |
033 |
|
Nil |
|
Follow Up Observation |
|
|
|
Nil |
|
|
|
|
|
|
|
|
|
|
|
New Observations |
|
|
1. |
Deposited silt was observed accumulated inside the u-channel at Row T.
The Contractor was requested to clear the deposited silt more frequently. |
|
|
2. |
Soil nail installation controllers and chemical containers were found
placed on ground without drip tray at Row AM, Row AO and Row AW. The
Contractor was reminded to provide drip trays to all plants and chemical
containers on site. |
|
|
3. |
Exposed earth / sediment was observed accumulated on the slope of |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site Inspection Summary
Date: |
18 November 2008 |
Time: |
15:00 |
Inspection No.: |
034 |
|
Nil |
|
Follow Up Observations |
|
|
1. |
Deposited silt inside the u-channel at Row T had been cleared.
(Closed) |
|
|
2. |
Soil nail installation controllers and chemical containers at Row AM, Row AO and Row AW had been provided with drip trays. However, two chemical containers at Row AF were found placed on ground without drip tray. The Contractor was reminded to provide drip trays to all chemical containers on site. |
|
|
3. |
Exposed earth / sediment on the slope of |
|
|
|
|
|
|
|
New Observation |
|
|
|
Nil |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site Inspection Summary
Date: |
25 November 2008 |
Time: |
15:00 |
Inspection No.: |
035 |
|
Nil |
|
Follow Up Observation |
|
|
1. |
A chemical container at Row
AF and on the slope of Row AP respectively was observed placed on ground
without drip tray. The Contractor was reminded to provide drip tray to all
chemical containers on site. |
|
|
|
|
|
|
|
New Observation |
|
|
|
Nil |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |