TABLE OF CONTENTS
Page
EXECUTIVE SUMMARY............................................................................................................................ 1
1. INTRODUCTION..............................................................................................................................
Background....................................................................................................................................
Scope of Report..............................................................................................................................
Project Organization........................................................................................................................
Summary of Construction Works..................................................................................................... 3
Summary of EM&A Programme Requirements................................................................................. 3
2. AIR QUALITY................................................................................................................................ 4
Monitoring Requirements................................................................................................................ 4
Monitoring Equipment.................................................................................................................... 4
Monitoring Parameters, Frequency and Duration............................................................................... 4
Monitoring Locations...................................................................................................................... 4
Monitoring Methodology................................................................................................................. 5
Monitoring Results......................................................................................................................... 6
3. NOISE
MONITORING..................................................................................................................... 7
Monitoring Requirements................................................................................................................ 7
Monitoring Equipment.................................................................................................................... 7
Monitoring Locations...................................................................................................................... 7
Monitoring Parameters................................................................................................................... 7
Monitoring Methodology................................................................................................................. 7
Monitoring Results......................................................................................................................... 8
4. VEGETATION
MONITORING.......................................................................................................... 9
Monitoring Requirement.................................................................................................................. 9
Monitoring Location........................................................................................................................ 9
Monitoring Methodology................................................................................................................. 9
Monitoring Results......................................................................................................................... 9
5. LANDSCAPE
AND VISUAL.......................................................................................................... 10
Monitoring Requirement................................................................................................................ 10
Summary of Inspection ?5 May 2009............................................................................................ 10
Summary of Inspection ?19 May 2009........................................................................................... 11
Next Landscape and Visual Audit Schedule.................................................................................... 11
6. ENVIRONMENTAL
SITE INSPECTION AND AUDIT........................................................................ 12
Site Inspection............................................................................................................................. 12
Assessment of Environmental Monitoring Results........................................................................... 13
Advice on the Solid and Liquid Waste Management
Status.............................................................. 13
Environmental Licenses and Permits............................................................................................. 13
Implementation Status of Environmental Mitigation
Measures........................................................... 14
Summary of Exceedances of the Environmental Quality
Performance Limit....................................... 14
Summary of Complaints, Notification of Summons and
Successful Prosecutions............................... 14
7. FUTURE KEY
ISSUES................................................................................................................. 15
Construction Programme for the Coming Months............................................................................ 15
Key Issues for Coming Month....................................................................................................... 15
Monitoring Schedule for the Coming Months................................................................................... 16
8. CONCLUSIONS
AND RECOMMENDATIONS................................................................................. 17
Conclusions................................................................................................................................ 17
Recommendations....................................................................................................................... 17
EXECUTIVE SUMMARY........................................................................................................................... 11
1. INTRODUCTION........................................................................................................................... 21
Background................................................................................................................................. 21
Scope of Report........................................................................................................................... 21
Project Organization..................................................................................................................... 21
Summary of Construction
Works................................................................................................... 31
Summary of EM&A
Programme Requirements................................................................................ 31
2. AIR QUALITY.............................................................................................................................. 41
Monitoring Requirements.............................................................................................................. 41
Monitoring Equipment................................................................................................................... 41
Monitoring Parameters,
Frequency and Duration............................................................................. 41
Monitoring Locations.................................................................................................................... 41
Monitoring Methodology................................................................................................................ 51
Monitoring Results....................................................................................................................... 61
3. NOISE MONITORING................................................................................................................. 718
Monitoring Requirements............................................................................................................ 718
Monitoring Equipment................................................................................................................. 718
Monitoring Locations.................................................................................................................. 718
Monitoring Parameters................................................................................................................ 718
Monitoring Methodology.............................................................................................................. 718
Monitoring Results..................................................................................................................... 819
4. VEGETATION SURVEY............................................................................................................ 9110
Monitoring Requirement............................................................................................................. 9110
Monitoring Location................................................................................................................... 9110
Monitoring Methodology.............................................................................................................. 101
Monitoring Results..................................................................................................................... 101
5. LANDSCAPE AND VISUAL..................................................................................................... 10111
Monitoring Requirement........................................................................................................... 10111
Summary of the Landscape and
Visual Monitoring on 8 April 2008............................................... 10111
Summary of the Landscape and
Visual Monitoring on 22 April 2008............................................. 12111
Next Landscape and Visual
Audit Schedule............................................................................... 12112
6. ENVIRONMENTAL SITE INSPECTION AND AUDIT................................................................... 12113
Site Inspection........................................................................................................................ 12113
Assessment of Environmental
Monitoring Results...................................................................... 13113
Advice on the Solid and
Liquid Waste Management Status......................................................... 13114
Environmental Licenses and
Permits........................................................................................ 13114
Implementation Status of
Environmental Mitigation Measures...................................................... 13114
Summary of Exceedances of
the Environmental Quality Performance Limit.................................. 13114
Summary of Complaints,
Notification of Summons and Successful Prosecutions.......................... 14114
7. FUTURE KEY ISSUES........................................................................................................... 15115
Construction Programme for
the Coming Months....................................................................... 15115
Key Issues for Coming Month.................................................................................................. 15115
Monitoring Schedule for the
Coming Months.............................................................................. 16116
8. CONCLUSIONS AND RECOMMENDATIONS............................................................................ 17117
Conclusions........................................................................................................................... 17117
Recommendations.................................................................................................................. 17117
Executive summary................................................................................................................................... 1
1. INTRODUCTION............................................................................................................................ 2
Background................................................................................................................................... 2
Purpose of the Baseline Report....................................................................................................... 2
2. BASELINE AIR QUALITY MONITORING........................................................................................ 33
Monitoring Requirements.............................................................................................................. 33
Monitoring Equipment................................................................................................................... 33
Monitoring Parameters, Frequency and Duration............................................................................. 33
Monitoring Locations.................................................................................................................... 33
Monitoring Methodology................................................................................................................ 33
Results....................................................................................................................................... 55
Action and Limit Levels................................................................................................................. 55
3. BASELINE NOISE MONITORING.................................................................................................. 77
Monitoring
Requirements.............................................................................................................. 77
Monitoring
Equipment................................................................................................................... 77
Monitoring
Locations.................................................................................................................... 77
Monitoring
Parameters................................................................................................................. 77
Monitoring
Methodology................................................................................................................ 77
Monitoring................................................................................................................................... 88
Results....................................................................................................................................... 88
Action
and Limit Levels................................................................................................................. 88
4. VEGETATION
SURVEY............................................................................................................ 1010
Monitoring
Requirement............................................................................................................ 1010
Monitoring
Location.................................................................................................................. 1010
Monitoring
Methodology............................................................................................................ 1010
Monitoring
Results.................................................................................................................... 1010
5. LANDSCAPE
AND VISUAL BASELINE REVIEW........................................................................ 1212
Review
Requirement................................................................................................................. 1212
Baseline
Review Methodology.................................................................................................... 1212
Baseline
Review Results........................................................................................................... 1313
Landscape
Character................................................................................................................ 1313
Visually
Sensitive Receivers...................................................................................................... 1414
6. CONCLUSION.......................................................................................................................... 1515
Summary of
EM&A Programme Requirements
Monitoring
Parameters, Frequency and Duration
Summary of
Inspection ?5 May 2009
Summary of
Inspection ?19 May 2009
Next Landscape and
Visual Audit Schedule
6. ENVIRONMENTAL SITE INSPECTION
AND AUDIT
Assessment of
Environmental Monitoring Results
Advice on the Solid and Liquid Waste Management Status
Environmental
Licenses and Permits
Implementation
Status of Environmental Mitigation Measures
Summary of
Exceedances of the Environmental Quality Performance Limit
Summary of
Complaints, Notification of Summons and Successful Prosecutions
Construction
Programme for the Coming Months
Monitoring Schedule for the Coming Months
8. CONCLUSIONS AND RECOMMENDATIONS
List of Tables
Table 1.1 Contact
Information of Key Personnel.......................................................................... 3
Table 2.1 Air Quality
Monitoring Equipment................................................................................ 4
Table 2.2 Air Quality
Monitoring Parameters, Frequency and Duration.......................................... 4
Table 2.3 Locations of
Air Quality Monitoring Stations.................................................................. 4
Table 2.4 Summary of
1-hour TSP Monitoring Results in the Reporting Period............................... 6
Table 2.5 Summary of
24-hour TSP Monitoring Results in the Reporting Period............................. 6
Table 3.1 Noise
Monitoring Equipment....................................................................................... 7
Table 3.2 Locations of
Noise Monitoring Stations........................................................................ 7
Table 3.3 Summary of
Noise Monitoring Results in the Reporting Period....................................... 8
Table 6.1 Summary of
Environmental Licensing and Permit Status.............................................. 14
Table 1.1 Contact Information of Key
Personnel............................................................................
Table 2.1 Air Quality Monitoring
Equipment..................................................................................
Table 2.2 Air Quality Monitoring
Parameters, Frequency and Duration............................................
Table 2.3 Locations of Air Quality
Monitoring Stations...................................................................
Table 2.4 Summary of 1-hour TSP
Monitoring Results in the Reporting Period.................................
Table 2.5 Summary of 24-hour TSP
Monitoring Results in the Reporting Period...............................
Table 3.1 Noise Monitoring Equipment.........................................................................................
Table 3.2 Locations of Noise
Monitoring Stations..........................................................................
Table 3.3 Summary of Noise Monitoring
Results in the Reporting Period.........................................
Table 6.1 Summary of Environmental
Licensing and Permit Status.................................................
Table 1.1 Contact Information of Key Personnel.......................................................................... 1
Table 2.1 Air Quality Monitoring Equipment................................................................................ 1
Table 2.2 Air Quality Monitoring Parameters, Frequency and
Duration.......................................... 1
Table 2.3 Locations of Air Quality Monitoring Stations.................................................................. 1
Table 2.4 Summary of 1-hour TSP Monitoring Results During Reporting Period.............................. 1
Table 2.5 Summary of 24-hour TSP Monitoring Results During Reporting Period............................ 1
Table 3.1 Noise Monitoring Equipment..................................................................................... 18
Table 3.2 Locations of Noise Monitoring Stations....................................................................... 18
Table 3.3 Summary of Noise Monitoring Results in the
Reporting Period..................................... 19
Table 6.1 Summary of Environmental Licensing and Permit
Status............................................ 114
Table 2.1 ?Air
Quality Monitoring Parameters, Frequency and Duration............................................ 3
Table 2.2 ?Locations
of Air Quality Monitoring Stations................................................................... 3
Table 2.3 ?Summary
of 1-hour TSP Monitoring Results During Baseline Period................................. 5
Table 2.4 ?Summary
of 24-hour TSP Monitoring Results During Baseline Period............................... 5
Table 2.5 ?Derivation
of Action and Limit Levels for Air Quality......................................................... 5
Table 2.6 ?
Action and Limit Levels for Air Quality........................................................................... 6
Table 3.1 ?Noise
Monitoring Equipment......................................................................................... 7
Table 3.2 ?Locations
of Noise Monitoring Stations.......................................................................... 7
Table 3.3 ?Summary
of Noise Monitoring Results During Baseline Period......................................... 8
Table 3.4 ?Criteria
for Action and Limit Levels for Construction Noise................................................ 8
Table 3.5 ?Action
and Limit Levels for Construction Noise of the Project........................................... 9
Table 4.1 ?Vegetation
Species of Conservation Importance within and in Close Proximity to the
Boundary of the Part II Project Area............................................................................................................ 11
Table 1.1 Contact Information of Key Personnel
Table 2.1 Air Quality Monitoring Equipment
Table 2.2 Air Quality Monitoring Parameters, Frequency and Duration
Table 2.3 Locations of Air Quality Monitoring Stations
Table 2.4 Summary of 1-hour TSP Monitoring Results in the Reporting Period
Table 2.5 Summary of 24-hour TSP Monitoring Results in the
Reporting Period
Table 3.1 Noise Monitoring Equipment
Table 3.2 Locations of Noise Monitoring Stations
Table 3.3 Summary of Noise Monitoring Results in the Reporting Period
Table 6.1 Summary of Environmental Licensing and
Permit Status
List
of Figures
Locations of Air Quality and
Noise Monitoring Stations
Figure 24.1 ?Locations of Air Quality and Noise
Monitoring Stations
Figure 6.1 ?Environmental Complaint Handling
Procedures Location of Vegetation Survey
Figure
4.2A ? ?/span>Locations of Plant Species of Conservation
Importance
Figure 4.2B Locations of Plant Species of Conservation
Importance
Figure 5.1 ?Landscape Resources
Figure 5.2 ?Photos of Landscape Resources
Figure 5.3 ?Landscape Character Area
Figure 5.4 ?Photos of Landscape Character Area
Figure 5.5 ?Zone of Visual Influence and Visual
Sensitive Receivers
Figure 5.6 ?Photos of Visually Sensitive Receivers
Figure 5.7 ?Photos of Key Viewpoints (Sheet 1 of
2)
Figure 5.8 ?Photos of Key Viewpoints (Sheet 2 of
2)
List of Appendices
Appendix A ?Project Organization Structure
Appendix B Construction Programme
Appendix C ?Implementation
Schedule of Mitigation Measures (EMIS)
Appendix D Action and Limit Levels for Air Quality? and Noise
Appendix E ?Appendix A ?Calibration
Certificates
Appendix F ?Air Quality Monitoring Results and
Graphical Presentation
Appendix I ?Noise Monitoring
Results and Graphical Presentation
Appendix J ?Detailed
Landscape and Visual Monitoring Report
Appendix K ET’s Site
Inspection Summaries
Appendix L ?Monitoring Schedules
Appendix M Cumulative Statistics of Complaints, Notifications
of Summons and Successful Prosecutions
Appendix B Baseline Air Quality Monitoring Results
Appendix C Baseline Noise Monitoring Results
Appendix D Schedule of Plant Species of Conservation
Importance
Appendix E Photographic Records of Plant Species of
Conservation Importance
Appendix F ?Coordinates for Plant Species of
Conservation Importance
The Project
“Landslide Preventive Works at Po Shan, Mid-levels ?Design and Construction
(Natural Terrain Risk Mitigation Works)?(hereafter called “the Project?
includes the installation of about 700 numbers of soil nails and about 60
numbers of raking drains on the natural terrain within the concerned area.
The impact environmental baseline monitoring and audit for the
Project includes the air quality, noise, ecology, landscape and visual monitoring.
The construction of the Project and the EM&A programme commenced on 1 April
2008.
This report
documented the findings of EM&A works conducted in the period between 1 and
331 0 AprilMay 20089. As informed
by the Contractor, construction activitiesies
in the reporting period wereere:
Tes
-
Soil nailing works at Portion B2;
-
Soil nail head construction at Portion C;
-
Rock slope stabilization
works at Portion D; and
-
Slope reinstatement works at
Portion A1 and Portion A2.
-
t Nails (5
nos.) for Pull Out Test at Portion A1 (i.e. from Row A to Row P);
-
Permanent
Nails installation at Portion A1; and
-
Site
Clearance for soil nail setting out to Portion B2 (i.e. from Row X to Row AK).
Breaches of Action and Limit
LevelsThe baseline monitoring of air quality was carried
out between 14 and 31 January 2007 at two designated locations. Air quality was
recorded in terms of 1-hour Total Suspended Particulates (TSP) and 24-hour TSP.
The weather during the monitoring period was mainly fine with a few occasions
of rains. For baseline noise levels, the regular noise monitoring results carried
out at the designated monitoring stations under the requirements of
Environmental Permit (EP-235/2005/A) were referenced.
There
was no action / limit level exceedance
recorded for 1-hour and 24-hour TSP monitoring.
In
the reporting month, all noise level recorded complied with the limit level.
Complaint, Notification of
Summons and Successful Prosecution
EPD referred EPtwo complaints from residents nearby Po
Shan Mansions, regarding construction dust
emission from the
slope work at
D received an enquiry regarding
the dust emission on
hillside behind Po Shan Mansions and conveyed their concerns
to ER and Contractor in the
reporting month. Improved mitigation
measures to
prevent excessive dust emission during soil nail drilling were
taken by the Contractor. EPD had inspected the site
on 26 May 2009
and had no adverse comment on the
dust control measures currently carried out on site.
There
was no complaint, notification of summons and
successful prosecution received in the reporting month.
Reporting Change
There
was no reporting change required in the reporting month.
Future Key Issues
The weather in the forthcoming month is expected to
be wet and windy. The Contractor should provide preventive measures to prevent
any muddy runoff, such as proper collection and treatment of the runoff and
provide a functional temporary drainage system in site.
It is also recommended to implement all necessary
preventive measures to avoid oil leakage on ground / soil, such as provision of
drip trays for all oil drums / chemical containers. In the event of oil
leakage, the Contractor should properly remove the contaminated soil and
dispose of as chemical waste. Construction waste and general refuse should be
properly collected and disposed of.
1.1
The project site is located
at the mostly undeveloped hillside above the residential development at
1.2
The objective of the Project
“Landslide Preventive Works at Po Shan, Mid-levels ?Design and Construction
(Natural Terrain Risk Mitigation Works)?under Contract CE 28/2004 (GE) is to
carry out detailed design and supervision of landslide preventive works on
local repair of the hillside to minimize slope deterioration and shallow
instability.
1.3
The proposed landslide
preventive works would be constructed to protect the existing residential
developments at the toe of the project site.
1.4
The scope of works of this
Project includes the installation about 700 numbers of soil nails and about 60
numbers of raking drains on the natural terrain within the concerned area. The
length of the soil nails is about
1.5
The Project is anticipated
to complete in 10 months after the commencement of construction.
1.6
According to the
Environmental Permit (EP-235/2005/B) and the EM&A Manual of the Project,
there is a need of an EM&A programme including air quality, noise, ecology,
and landscape and visual monitoring.
1.7
ENSR Asia (HK) Ltd., which was integrated into AECOM Asia Company Limited as
of 1 May 2009, was employed by the Contractor,
1.8
This is the fourteenth
monthly Environmental Monitoring and Audit (EM&A) Report under the Contract
CE 28/2004 (GE) ?Landslide Preventive Works at
1.9
The project organization is
shown in Appendix A. The key personnel contact names and numbers are summarized
in Table 1.1
.
Table 1.1 ?Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
CEDD |
Senior Engineer |
H. W. Sun |
2762 5375 |
2714 0247 |
ER (MGS) |
Resident Engineer |
Freddie Chan |
3188 0400 |
3188 0775 |
Assistant Resident
Engineer |
S. F. Chau |
3188 0400 |
3188 0775 |
|
IEC (ENVIRON) |
Independent Environmental
Checker |
David Yeung |
3743 0788 |
3548 6988 |
Contractor (CCJV) |
Project Manager |
C. Y. Mak |
3188 0538 |
3188 1710 |
Safety and Environmental Officer |
Brian Yam |
3188 0538 |
3188 1710 |
|
ET (ENSR) |
ET Leader |
Edith Ng |
3105 8525 |
2891 0305 |
1.10
The Contactor has carried
out major activities in the reporting month. Details of the works undertaken in
this reporting period are listed below:
-
Soil
nailing works at Portion B2;
-
Soil nail head construction
at Portion C;
-
Rock slope stabilization
works at Portion D; and
-
Slope reinstatement works at
Portion A1 and Portion A2.
1.11
The general layout plan of
the Project site showing the contract area is shown in Figure 1.1. The
construction programme is provided in Appendix B.
1.12
The mitigation measures
implementation schedule are presented in Appendix C.
Summary of EM&A
Programme Requirements
1.13
The EM&A programme
required environmental monitoring for air quality, noise, ecology and landscape
and visual and environmental site inspections for air quality, noise, ecology,
landscape and visual and waste management. The EM&A requirements for each
parameter described in the following sections include:
-
All monitoring parameters;
-
Monitoring schedules for the
reporting month and forthcoming months;
-
Action and Limit levels for
all environmental parameters;
-
Event / Action Plan;
-
Environmental mitigation
measures, as recommended in the Project EIA study final report; and
-
Environmental requirement in
contract documents.
2.1
In accordance with the
EM&A Manual, 1-hour and 24-hour TSP levels at 2 air quality monitoring
stations were established. Impact 1-hour and 24-hour TSP monitoring was
conducted for at least once every 7 days during the construction phase of the
Project. The Action and Limit level of the air quality monitoring is provided
in Appendix D.
2.2
24-hour TSP air quality
monitoring was performed using High Volume Sampler (HVS) located at each
designated monitoring station. The HVS meets all the requirements of the
EM&A Manual. Portable direct reading dust meters were used to carry out the
1-hour TSP monitoring. Table 2.1 summarises the equipment used.
Table 2.1 ?Air Quality Monitoring Equipment
Equipment |
Model |
High Volume Sampler |
GS 2310 Accu-vol system |
Calibrator |
GMW 25 |
1-hour TSP Dust Meter |
Laser Dust Monitor ?Model LD-3 |
Monitoring Parameters,
Frequency and Duration
2.3
Table 2.2 summarizes the monitoring
parameters, frequency and duration of impact TSP monitoring.
Table 2.2 ?Air Quality Monitoring Parameters,
Frequency and Duration
Monitoring Station |
Parameter |
Frequency and Duration |
CA1
& CA2 |
24-hour TSP |
At least
once every 7 days |
1-hour
TSP |
At least
3 times every 7 days |
2.4
Both monitoring stations
were set up at the proposed locations in accordance with EM&A Manual. Table
2.3 describes details of the two monitoring stations. The monitoring locations
are shown in Figure 2.1.
Table 2.3 ?Locations of Air Quality Monitoring
Stations
Monitoring
Station |
Identity
/ Description |
CA1 |
Access road to Po Shan Mansions |
CA2 |
Podium of |
24-hour
TSP Monitoring
Installation
2.5
The HVS was installed in the
vicinity of the air sensitive receivers.?
The following criteria were considered in the installation of the HVS.
?span style='font:7.0pt "Times New Roman"'>
A horizontal platform with appropriate support to
secure the sampler against gusty wind was provided.
?span style='font:7.0pt "Times New Roman"'>
The distance between the HVS and any obstacles,
such as buildings, was at least twice the height that the obstacle protrudes
above the HVS.
?span style='font:7.0pt "Times New Roman"'>
A minimum of 2 meters separation from walls,
parapets and penthouse was required for rooftop sampler.
?span style='font:7.0pt "Times New Roman"'>
No furnace or incinerator flues were nearby.
?span style='font:7.0pt "Times New Roman"'>
Airflow around the sampler was unrestricted.
?span style='font:7.0pt "Times New Roman"'>
Permission was obtained to set up the samplers and
to obtain access to the monitoring stations.
?span style='font:7.0pt "Times New Roman"'>
A secured supply of electricity is needed to
operate the samplers.
Preparation of Filter Papers
?span
style='font:7.0pt "Times New Roman"'>
Glass fibre filters, G810 were labeled and
sufficient filters that were clean and without pinholes were selected.
?span
style='font:7.0pt "Times New Roman"'>
All filters were equilibrated in the conditioning
environment for 24 hours before weighing.?
The conditioning environment temperature was around
?span
style='font:7.0pt "Times New Roman"'>
ALS Technichem (HK) Pty Ltd.
has
comprehensive quality assurance and quality control programmes.
Field Monitoring
?span
style='font:7.0pt "Times New Roman"'>
The power supply was checked to ensure the HVS
works properly.
?span
style='font:7.0pt "Times New Roman"'>
The filter holder and the area surrounding the
filter were cleaned.
?span
style='font:7.0pt "Times New Roman"'>
The filter holder was removed by loosening the four
bolts and a new filter, with stamped number upward, on a supporting screen was
aligned carefully.
?span
style='font:7.0pt "Times New Roman"'>
The filter was properly aligned on the screen so
that the gasket formed an airtight seal on the outer edges of the filter.
?span
style='font:7.0pt "Times New Roman"'>
The swing bolts were fastened to hold the filter
holder down to the frame.?The pressure
applied should be sufficient to avoid air leakage at the edges.
?span
style='font:7.0pt "Times New Roman"'>
Then the shelter lid was closed and was secured
with the aluminum strip.
?span
style='font:7.0pt "Times New Roman"'>
The HVS was warmed-up for about 5 minutes to
establish run-temperature conditions.
?span
style='font:7.0pt "Times New Roman"'>
A new flowrate record sheet was set into the flow
recorder.
?span
style='font:7.0pt "Times New Roman"'>
The range specified in the EM&A Manual was
between 0.6
?span
style='font:7.0pt "Times New Roman"'>
The programmable timer was set for a sampling
period of 24 hrs + 1 hr, and the starting time, weather condition and
the filter number were recorded.
?span
style='font:7.0pt "Times New Roman"'>
The initial elapsed time was recorded.
?span
style='font:7.0pt "Times New Roman"'>
At the end of sampling, the sampled filter was
removed carefully and folded in half length so that only surfaces with
collected particulate matter were in contact.
?span
style='font:7.0pt "Times New Roman"'>
It was then placed in a clean plastic envelope and
sealed.
?span style='font:7.0pt "Times New Roman"'>
All monitoring information was recorded on a
standard data sheet.
?span style='font:7.0pt "Times New Roman"'>
Filters were sent to ALS Technichem (HK) Pty Ltd.?for
analysis.
Maintenance and Calibration
?span
style='font:7.0pt "Times New Roman"'>
The HVS and its accessories are maintained in good
working condition, such as replacing motor brushes routinely and checking
electrical wiring to ensure a continuous power supply.
?span
style='font:7.0pt "Times New Roman"'>
HVSs are calibrated using GMW-25 Calibration Kit
prior to the commencement of baseline air quality monitoring, and will be
calibrated at bi-monthly intervals throughout all stages of the impact
monitoring.
?span
style='font:7.0pt "Times New Roman"'>
Calibration records are shown in Appendix E.
1-hour TSP
Monitoring
Measuring Procedures
2.6
The measuring procedures of
the 1-hour dust meter are in accordance with the Manufacturer’s Instruction
Manual as follows:
?span
style='font:7.0pt "Times New Roman"'>
Set POWER to “ON? push
?span
style='font:7.0pt "Times New Roman"'>
Push the knob at MEASURE position.
?span
style='font:7.0pt "Times New Roman"'>
Push “O-ADJ?button. (Then meter’s indication is
0).
?span
style='font:7.0pt "Times New Roman"'>
Push the knob at SENSI ADJ position and set the
meter’s indication to S value described on the Test Report using the trimmer
for SENSI ADJ.
?span
style='font:7.0pt "Times New Roman"'>
Pull out the knob and return it to MEASURE
position.
?span
style='font:7.0pt "Times New Roman"'>
Push “START?button.
Maintenance and Calibration
?span
style='font:7.0pt "Times New Roman"'>
The 1-hour TSP meter would be checked at 3-month
intervals and calibrated at 1-year intervals throughout all stages of the air
quality baseline monitoring. Calibration records are shown in Appendix E.
2.7
The monitoring results for
1-hour TSP and 24-hour TSP are summarized in Table 2.4 and 2.5 respectively and
the monitoring results are provided in Appendix F.
Table 2.4 ?Summary of 1-hour TSP Monitoring Results
in the Reporting Period
|
Average (mg/m3) |
Range (mg/m3) |
Action Level?(mg/m3) |
Limit Level (mg/m3) |
CA1 |
80.7 |
77.0 ?83.5 |
309.3 |
500 |
CA2 |
77.6 |
73.0 ?80.6 |
319.6 |
500 |
Table 2.5 ?Summary of 24-hour TSP Monitoring Results
in the Reporting Period
|
Average (mg/m3) |
Range (mg/m3) |
Action Level?(mg/m3) |
Limit Level (mg/m3) |
CA1 |
22.7 |
9.7 ?40.3 |
166.8 |
260 |
CA2 |
33.4 |
24.9 ?58.0 |
187.0 |
260 |
2.8
Air quality monitoring was
carried out for both 1-hour TSP and 24-hour TSP at all the monitoring stations
in the reporting month.
2.9
The air quality monitoring
results, in terms of 1-hour TSP and 24-hour TSP, were below the action and limit
level at both monitoring locations in the reporting month. The event action
plan is annexed in Appendix G.
2.10
Weather information
including wind speed and wind direction is annexed in Appendix H. The
information was obtained from Hong Kong Observatory Victoria Peak Automatic
Weather Station and Central Pier Anemometer Station.
3.1
In accordance with the EM&A Manual, impact
noise levels should be obtained at 2 noise monitoring stations. Impact noise
monitoring was conducted for at least once per week during the construction
phase of the Project. The Action and Limit level of the noise monitoring is
provided in Appendix D.
3.2
Integrating Sound Level Meter was employed for
noise monitoring.?They were Type 1 sound
level meters capable of giving a continuous readout of the noise level readings
including equivalent continuous sound pressure level (Leq) and
percentile sound pressure level (Lx). They comply with International
Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type
1).?Portable electronic wind speed
indicator capable of measuring wind speed in m/s was employed to check the wind
speed.?Table 3.1 details the noise
monitoring equipment used.
Table 3.1 ?Noise Monitoring Equipment
Equipment |
Model |
Integrating Sound Level Meter |
Rion NL-31 |
Calibrator |
Rion NC-73 |
3.3
Two monitoring stations were
set up in accordance with EM&A Manual. Table 3.2 describes details of the
two monitoring stations. The monitoring locations are shown in Figure 2.1.
Table 3.2 ?Locations of Noise Monitoring Stations
Monitoring
Station |
Identity
/ Description |
CN1 |
Block A, |
CN2 |
Block A, |
3.4
One set of 30-mins measurement at each monitoring
station between 0700 and 1900 on normal weekdays at a frequency of once per
week was required to determine the impact noise level. Leq, L10
and L90 would be recorded.
Monitoring
Procedures
?span
style='font:7.0pt "Times New Roman"'>
The Sound Level Meter was set on a tripod at a
height of
?span
style='font:7.0pt "Times New Roman"'>
Façade measurements were made at all three
monitoring locations.
?span
style='font:7.0pt "Times New Roman"'>
The battery condition was checked to ensure the
correct functioning of the meter.
?span
style='font:7.0pt "Times New Roman"'>
Parameters such as frequency weighting, the time
weighting and the measurement time were set as follows:
-
frequency weighting: A
-
time weighting: Fast
-
time measurement: Leq(30 minutes) during
non-restricted hours i.e. between 07:00 and 19:00 on normal weekdays
?span
style='font:7.0pt "Times New Roman"'>
Prior to and after each noise measurement, the
meter was calibrated using a Calibrator for 94 dB at 1000 Hz.?If the difference in the calibration level
before and after measurement was more than 1 dB(A), the measurement would be
considered invalid and repeat of noise measurement would be required after
re-calibration or repair of the equipment.
?span
style='font:7.0pt "Times New Roman"'>
The wind speed was frequently checked with a
portable wind meter.
?span
style='font:7.0pt "Times New Roman"'>
During the monitoring period, the Leq ,
L10 and L90 were recorded.?In addition, site conditions and noise
sources were recorded on a standard record sheet.
?span
style='font:7.0pt "Times New Roman"'>
Noise measurement was paused during periods of high
intrusive noise (e.g. dog barking, helicopter noise) if possible. Observations
were recorded when intrusive noise was unavoidable.
?span
style='font:7.0pt "Times New Roman"'>
Noise monitoring was cancelled in the presence of
fog, rain, wind with a steady speed exceeding
Maintenance
and Calibration
?span
style='font:7.0pt "Times New Roman"'>
The microphone head of the sound level meter and
calibrator is cleaned with soft cloth at quarterly intervals.
?span
style='font:7.0pt "Times New Roman"'>
The meter should be checked and calibrated at
yearly intervals.
?span
style='font:7.0pt "Times New Roman"'>
Calibration details for the sound level meter and
calibrator are provided in Appendix E.
3.5
The monitoring results for
noise are summarized in Table 3.3 and the monitoring data is provided in
Appendix I.
Table 3.3 ?Summary of Noise Monitoring Results in the
Reporting Period
|
Average, dB(A), Leq
(30 mins) |
Range, dB(A), Leq (30
mins) |
Limit Level, dB(A), Leq
(30 mins) |
CN1 |
61.7 |
61.0 ?62.7 |
75.0 |
CN2 |
60.8 |
60.4 ?61.0 |
75.0 |
3.6
There was no noise complaint received in the
reporting month, hence, no action level exceedance was recorded. At both
monitoring locations, CN1 and CN2, all the monitoring results (daytime) were
below the limit level of 75 dB(A).
3.7
All the monitoring results lied within the range of
the predicted noise levels in the EIA report.
3.8
Major noise sources during the noise monitoring
included the construction activities from the Project and another project under
the same contract (concurrent project) carried out in the vicinity and nearby
traffic noise.
4.1
As required under Environmental Permit No.
EP-235/2005/B, the Permit Holder is required to carry out monitoring of the
plant species of conservation interest to check on the health and condition of
the plants twice a month during the construction period of the Project.
4.2
It is required to undertake the ecological tasks to
fulfill the requirements of the Environmental Permit (EP).?As required by Conditions 2.11 and 3.5 of the
EP, a suitably qualified ecologist with 7 or more years
of relevant experience shall be employed to conduct the ecological monitoring.
4.3
The ecological monitoring was carried out for plant
individuals of conservation interest identified within the proposed works area.
4.4
The ecological monitoring was conducted twice in
the reporting month on 5 May 2009 by Mr. Ryan H W Wong and on 26 May 2009 by
Ms. Gigi C C Lam, who had over 7 years of relevant ecological experience.
4.5
The plants of conservation interest, which were
tagged during the baseline survey, were checked during each monitoring.
4.6
Soil nailing works were in progress during the
monitoring visits.?
4.7
A vegetation of conservation
V018 located during the last monitoring visit was found to be in very poor condition.?
4.8
Part of the plant species of conservation interest
were not properly fenced off or tagged, particularly in works area above Row AD.?The Contractor was advised to fence off and
label the vegetation properly with a clear sign notable to all the construction
workers and restrict any unauthorized access to the area.
4.9
Some vegetation and plant species of conservation
interest located near soil nailing work areas were densely covered with soil
and dust.
4.10
Hardened grout was found in the natural habitat
near the Project area.?To prevent the
plant from being affected by grout leakage and muddy site run-off, the
Contractor was reminded to remove any grout from the natural habitat as soon as
possible and add sand bags around the hardened grout.
5.1
During the construction
phase of the Project, landscape and visual monitoring should be carried out
bi-weekly by a Registered Landscape Architect (RLA) to check if the design,
implementation and maintenance of the landscape and visual mitigation measures
are fully realized. A detailed report is annexed in Appendix J.
Summary of Inspection ?5
May 2009
Matters Arising from
Previous Inspections
5.2
It was still observed that
the termite infected dead tree T534 along the footpath stair was still not
removed.?The Contractor was reminded to
urgently remove the infected dead tree for consideration of safety of the
workers and the public in future.
5.3
It was still observed that
no further rectification of tree ID numbers was carried out since the last
couple of inspections.?The Contractor
was reminded to rectify the missing tree ID numbers on the remaining existing
trees as soon as possible.
5.4
It was noted that
compensatory planting proposal for the replacement of dead tree T611 was
outstanding.?The Contractor was
recommended to seek Engineer’s agreement on the replacement planting as soon as
possible.
5.5
It was noted that the
Contractor’s clarification of the status of existing trees T516, T517, T666,
and T698 located immediately outside of the works boundary was
outstanding.?The Contractor was reminded
to provide necessary information as soon as possible.
Protection of Existing Trees
5.6
It was observed that
electrical cables were strung overhead and hanged from tree branches.?The Contractor was requested to remove the
electrical cables away from the trees as soon as possible.
Recommendations
5.7
The Contractor was
recommended to remove the dead tree T534 from site for safety considerations,
especially the tree was found infected by termite.?The Contractor was also reminded to record
and report all dead trees as found on site to the Engineer for record.
5.8
The Contractor was again
reminded to rectify all remaining ineligible tree ID numbers for all existing
trees.
5.9
The Contractor was again
reminded d to clarify the status of missing trees as soon as possible.
5.10
The Contractor was again
reminded to seek Engineer’s agreement on the replacement planting for dead
tree.
5.11
The Contractor was
recommended to remove the electrical cables away from existing trees and not to
use trees as support in future.
Summary of Inspection ?19
May 2009
Matters Arising from
Previous Inspections
5.12
The Contractor had cleared
the overhead electrical cables from existing trees.
5.13
Removal of the termite
infected dead tree T534 along the footpath stair was still outstanding.?The Contractor was reminded to urgently
remove the infected dead tree as soon as possible.
5.14
It was still observed that
no further rectification of tree ID numbers was carried out since the last few
inspections.?The Contractor was reminded
to rectify the missing tree ID numbers on the remaining existing trees as soon
as possible.
5.15
It was noted that
compensatory planting proposal for the replacement of dead tree T611 was
outstanding.?The Contractor was
recommended to seek Engineer’s agreement on the replacement planting as soon as
possible.
5.16
It was noted that the
Contractor’s clarification of the status of existing trees T516, T517, T666,
and T698 located immediately outside of the works boundary was
outstanding.?The Contractor was reminded
to provide necessary information as soon as possible.
Protection of Existing Trees
5.17
It was observed that the
Contractor had tied safety ropes around the base of several existing
trees.?The Contractor was reminded that
the practice was not acceptable and was requested to remove the ropes as soon
as possible.
Recommendations
5.18
The Contractor was again
reminded to remove the dead tree T534 from site for safety considerations as
soon as possible, especially the tree was found infected by termite.?The Contractor was also reminded to record
and report all dead trees as found on site to the Engineer for record.
5.19
The Contractor was reminded
to rectify all remaining ineligible / missing tree ID numbers for all existing
trees.
5.20
The Contractor was again
reminded to clarify the status of missing trees as soon as possible.
5.21
The Contractor was again
reminded to seek Engineer’s agreement on the replacement planting for dead
trees.
5.22
The Contractor was
recommended to remove the safety ropes away from the base of the existing trees
and not to use trees as support in future.
Next Landscape and Visual
Audit Schedule
5.23
The landscape and visual
audits in the next reporting month was tentatively scheduled to 2, 16 and 30 June
2009.
6.1
Site Inspections were
carried out on a weekly basis to monitor the implementation of proper
environmental pollution control and mitigation measures for the Project. In the
reporting month, 4 site inspections were carried out on 5, 12, 19 and 26 May
2009. The detail findings of the landscape and visual audits in the reporting
month are presented separately in Section 5. The environmental site inspection
summaries are attached in Appendix K. Particular observations are described
below.
Air Quality
6.2
No adverse observation was
identified in the reporting month.
Noise
6.3
No adverse observation was
identified in the reporting month.
Water Quality
6.4
Loose sediment was observed
accumulated on the platform at Row AF. The Contractor was reminded to clear the
sediment regularly and as soon as the soil nailing operation finishes.
Chemical and Waste
Management
6.5
A chemical container was
observed placed on ground without drip tray at Row AH. The Contractor was reminded
to provide drip trays to all chemicals on site.
6.6
A hole was found on the drip
tray at Row AA and oily water was running out. The Contractor was requested to
fix the drip tray as soon as possible.
6.7
Cement powder was observed
scattered on the platform at Row AH. While immediate action by Contractor to
clear the cement powder into sand bags, the Contractor was still reminded to
properly handle all chemicals on site.
Ecology
6.8
A plant species of
conservation interest (V018) was in very poor condition
6.9
Some vegetation of
conservation interest were not properly fenced off and not tagged.
6.10
Vegetation and plant species
of conservation interest located near soil nailing work areas were densely
covered with soil and dust.
6.11
Hardened grout was found in
the natural habitat near the Project area.?
Landscape and Visual
6.12
It was still observed that
the termite infected dead tree T534 along the footpath stair was still not
removed.?The Contractor was reminded to
urgently remove the infected dead tree for consideration of safety of the
workers and the public in future.
6.13
It was still observed that
no further rectification of tree ID numbers was carried out since the last
couple of inspections.?The Contractor
was reminded to rectify the missing tree ID numbers on the remaining existing
trees as soon as possible.
6.14
It was noted that
compensatory planting proposal for the replacement of dead tree T611 was
outstanding.?The Contractor was
recommended to seek Engineer’s agreement on the replacement planting as soon as
possible.
6.15
It was noted that the
Contractor’s clarification of the status of existing trees T516, T517, T666,
and T698 located immediately outside of the works boundary was
outstanding.?The Contractor was reminded
to provide necessary information as soon as possible.
6.16
It was observed that
electrical cables were strung overhead and hanged from tree branches.?The Contractor was requested to remove the
electrical cables away from the trees as soon as possible.
6.17
It was observed that the
Contractor had tied safety ropes around the base of several existing
trees.?The Contractor was reminded that
the practice was not acceptable and was requested to remove the ropes as soon
as possible.
Assessment of Environmental
Monitoring Results
6.18
All monitoring results were
audited against the Action / Limit levels and any exceedance would be validated
and issued when necessary.
6.19
The monitoring results in
the reporting period were comparable with the EIA predictions. Detailed
discussions are given in Section 2 and 3.
Advice on the Solid and
Liquid Waste Management Status
6.20
The Contractor is registered
as a chemical waste producer for this Project. The Chemical Waste Storage Area
located at the Contractor’s site office area was properly maintained in the
reporting month.
6.21
As advised by the
Contractor, 34.18 ton of non-inert C&D waste and 15.93 ton of inert C&D
waste were disposed offsite to SENT landfill and Chai Wan respectively in the
reporting month. Also 20kg of chemical waste was collected by licenced waste
collector in the reporting month. C&D waste generated was reused on site as
much as possible.
Environmental Licenses and
Permits
6.22
The environmental licenses
and permits for this Project and valid in the reporting month is summarized in
Table 6.1.
Table 6.1 ?Summary of Environmental Licensing and
Permit Status
Description |
Permit No. |
Valid Period |
Remarks |
|
From |
To |
|||
Environmental Permit |
EP-235/2005/B |
|
-- |
- Installation of about 700 nos. of soil nails and
about 60 nos. of raking drains in the natural terrain; - Rock slope stabilisation works at upper portion
of the natural terrain; and - Other associated works. |
Registration as a Chemical Waste Producer |
5213-141-C3250-02 |
|
-- |
Spent lubricating oil and mineral oil |
Effluent Discharge License |
EP880/W10/XX0261 |
|
|
-- |
Notification of Constriction Work under APCO
(Construction Dust) |
001012125 |
|
-- |
-- |
Implementation Status of
Environmental Mitigation Measures
6.23
In response to the site
audit findings, the Contractor carried out corrective actions.
6.24
A summary of the
Implementation Schedule of Mitigation Measures (EMIS) is presented in Appendix
C. Most of the necessary mitigation measures were implemented properly.
Summary of Exceedances of
the Environmental Quality Performance Limit
6.25
All 1-hour TSP, 24-hour TSP
and noise monitoring results complied with the Action / Limit levels.
6.26
No exceedance was recorded
in the reporting month.
Summary of Complaints,
Notification of Summons and Successful Prosecutions
6.27
The Environmental Complaint
Handling Procedure is annexed in Figure 6.1.
6.28
EPD referred two complaints,
one on 15 May 2009 and one on 19 May 2009, from residents nearby Po Shan
Mansions, regarding construction dust emission from the slope work at
6.29
No notification of summons
and successful prosecutions was received in the reporting month.
Construction Programme for
the Coming Months
7.1
The construction programme
for the Project is provided in Appendix B.
7.2
The major construction work
in June 2009 will be:
-
Rock slope
stabilization works at Portion D;
-
Soil nail heads
construction at Portion B2 and Portion C;
-
Soil nailing
works at Portion B2; and
-
Slope
reinstatement works at Portion A2 and Portion B1.
7.3
Key issues to be considered
in the coming month included:
-
Sufficient dust suppression
measures should be maintained;
-
Collection of construction
waste should be carried out regularly;
-
Site runoff should be
properly collected and treated prior to discharge;
-
Construction activities
should avoid causing damage to the trees and to plants species of conservation
interest; and
-
Quieter powered mechanical
equipment should be used.
7.4
The following mitigation
measures are required:
Air Quality Impact
-
Regular watering should be
used during soil nailing;
-
Dusty material stockpiled
should be completely covered;
-
Dusty activities should be
re-scheduled if high-wind conditions encountered;
-
Open burning should be
strictly prohibited;
-
All dusty vehicle loads
transporting to, from and between site locations should be covered with
tarpaulin;
-
Vehicle wheel and body
washing facilities should be used at all exit points of the site;
-
Wind shield, dust extraction
units or water spraying should be used at the loading points.
Construction Noise Impact
-
Quieter powered mechanical
equipment should be used;
-
Insulating fabric should be
used for drill rigs during drilling process;
-
Noise generating
construction works should be carried out during daytime only;
-
Noise barriers or other
measures should be used to minimize disturbance to the bat roost;
-
Plant on site should be
properly maintained and serviced regularly;
-
Mobile plants should be
sited as far from NSRs as possible;
-
Machines and plant in
intermittent use should be throttled down;
-
Strong noise emitting
plants, wherever possible, should be oriented so that noise is directed away
from the nearby NSRs;
-
Material stockpiles,
wherever possible, should be effectively utilized to screen noise from
construction activities;
-
Movable noise barrier with
surface mass in excess of
-
Noise insulating fabric
should be adopted for drill rig operating in Works Area E.
Water Quality Impact
-
Prevent runoff water from
entering the nearby water-bodies;
-
Silt traps and oil / grease
separators should be regularly cleaned and maintained;
-
Outlet pipe extending above
the slope surface should be installed;
-
Air should be used as the
flushing medium of the drilling equipment;
-
Earth bunds or sand bag
barriers should be provided on-site to direct storm water to silt removal
facilities;
-
Exposed slope / soil surface
and opened stockpile of more than
-
Oils and fuels should be
used and stored in designated area.
Chemical and Waste
Management
-
Debris and rubbish on-site
should be collected, handled and disposed of properly;
-
Waste skips should be
provided to collect general refuse and construction wastes;
-
Soil contamination with fuel
leaked from construction plants should be removed off-site;
-
Sufficient waste disposal
points with regular collection should be provided;
-
Appropriate measures should
be provided to minimize windblown litter and dust during transportation of
waste;
-
Different containers should
be used to segregate and store different types of waste;
-
Encourage collection of
aluminum cans, PET bottles and paper by providing separate bins;
-
Unused chemicals should be
recycles wherever possible;
-
Proper storage and site
practices should be adopted to minimize the potential for damage and
contamination of construction materials;
-
Oils and fuels should be
stored in designated area;
-
Plan and stock construction
materials carefully to minimize waste generation.
Ecological Impact
-
Soil nail installation
should avoid / minimize damage of root system to the existing plants;
-
Fences should be erected
along the boundary of the works area
-
Disturbance to the natural
woodland and shrubland habitats should be minimized by preventing tipping,
vehicle movements and encroachment of personnel onto the adjacent area;
-
Permanent casing should be
provided to the drillhole of soil nail;
-
Placement of equipment or
stockpile should be located in designated areas to minimize disturbance to
natural or moderate-high ecological value habitats;
-
Construction activities
should be restricted to works areas;
-
Disturbance to existing
vegetation should be minimized wherever possible.
Landscape and Visual Impact
-
Designation of “no-intrusion
zones?and record any trespass and damage to existing vegetation;
-
Soil nails on site should
avoid tree trunks and tree roots;
-
Dust and erosion control
should be provided for exposed soil;
-
For tree planting
operations, method statement should be checked against specification
requirements;
-
All retained trees within
the working boundary should be checked regularly;
-
Control over appearance of
hoarding, construction plants / machines;
-
Security floodlights should
be carefully selected to avoid light pollution.
Monitoring Schedule for the
Coming Months
7.5
The tentative schedule for
environmental monitoring in June 2009 is provided in Appendix L.
8.1
The construction phase of
the project commenced in April 2008.
8.2
1-hour TSP and 24-hour TSP
monitoring was carried out in the reporting month. All monitoring results
complied with the action / limit level. No exceedance was recorded.
8.3
All impact daytime noise
monitoring results complied with the limit level in the reporting month.
8.4
Environmental site
inspections were carried out 4 times in May 2009. Recommendations on remedial
actions were given to the Contractor for the deficiencies identified during the
site audit.
8.5
Two landscape and visual
audits were carried out in the reporting month. The Contractor had tied safety
ropes around the base of several existing trees.?The Contractor was reminded that the practice
was not acceptable and was requested to remove the ropes as soon as possible.
8.6
Two ecological audits were
carried out in the reporting month.?The
Contractor was reminded to properly tag all the vegetation of conservation
interest and all tagged plants of conservation interest in the affected area should
be located and fenced off properly with clear sign to avoid any further damage
and restrict any unauthorized access of site workers to the area.?The leaves of vegetation within works areas
should be washed regularly to avoid excessive dust deposition. To further
protect the other vegetation/tree, the Contractor was recommended to remove any
grout and soil nailing machine from the natural habitat as well as add sand
bags around the hardened grout.
8.7
Two
environmental complaints, and no notification of summons and prosecution, were
received in the reporting month.
8.8
According to the
environmental site inspections performed in the reporting month, the following
recommendations were provided:
Air Quality Impact
-
Soil nail workstations on
site should be properly enclosed; and
-
Water spraying should be
provided during soil nailing works.
Construction Noise Impact
-
Nil
Water Quality Impact
-
Sedimentation tanks on site
should be properly maintained;
-
Site effluent must be
collected and treated prior to discharge to public drain;
-
U-channels should be kept
clear of mud, debris, leaves, construction waste and materials; and
-
Soil and exposed earth at
all working platforms and slopes should be cleaned up.
Chemical and Waste
Management
-
Drip trays should be
provided to all plants and chemical containers on site;
-
Oils and fuels should be
stored in designated area;
-
Empty chemical containers
should be disposed of as chemical waste;
-
C&D waste, debris and
general refuse on-site should be collected, handled and disposed of properly;
and
-
Waste skips should be
provided to collect general refuse and construction wastes.
Ecological Impact
-
The Contractor was reminded
to take all necessary actions to prevent grout leakage and muddy run-off to the
surrounding natural environment;
-
All identified vegetation of
conservation interest should be preserved;
-
All site access should be
clearly demarcated and no excessive removal of vegetation in natural areas
adjacent to the site access should be allowed;
-
All plant species of
conservation interest should be fenced off and tagged properly with clear sign,
especially for those located near major access road and areas likely to be impacted
by construction activities;
-
The Contractor was
recommended to take necessary measures to prevent damage to all vegetation
within the construction site; and
-
Dust and soil on vegetation
should be washed away in a timely manner.
Landscape and Visual Impact
-
The Contractor was reminded
to remove the dead tree T534 from site for safety considerations as soon as
possible, especially the tree was found infected by termite.?The Contractor was also reminded to record
and report all dead trees as found on site to the Engineer for record;
-
The Contractor was reminded
to rectify all remaining ineligible / missing tree ID numbers for all existing
trees;
-
The Contractor was again
reminded to clarify the status of missing trees as soon as possible;
-
The Contractor was again
reminded to seek Engineer’s agreement on the replacement planting for dead
trees;
-
The Contractor was
recommended to remove the safety ropes away from the base of the existing trees
and not to use trees as support in future; and
-
The Contractor was
recommended to remove the electrical cables away from existing trees and not to
use trees as support in future.
Future Key Issues
The
weather in the forthcoming month is expected to be wet and
windy. The Contractor should provide preventive measures
to maintain sufficient dust suppression measuresprevent any muddy
runoff, such as proper collection and treatment of the
runoff and provide a functional temporary drainage system in
site.
It is also
recommended to implement all necessary preventive measures to avoid oil leakage
on ground / soil, such as provision of drip trays for all oil drums / chemical
containers. In the event of oil leakage,
the Contractor should properly remove the contaminated soil and dispose of as
chemical waste. Construction
waste and general refuse should be properly collected and disposed of.
The
averaged 1-hour TSP was 91.3 mg/m3
at CA1 and 107.1 mg/m3
at CA2, with the highest concentration recorded at CA2 on 18 January 2008. The
averaged 24-hour TSP was 56.6 mg/m3
at CA1 and 87.7 mg/m3
at CA2, with the highest concentration recorded at CA2 on 20 January 2008.
Baseline
noise monitoring data was obtained from daytime noise monitoring results of the
existing noise monitoring locations at Po Shan Mansions as required under the
Environmental Permit EP-235/2005/A.
For
the baseline vegetation survey, a total of 12 species of 129 individuals of
floral species of conservation importance were identified and tagged during the
detailed vegetation survey. Their coordinates were also recorded for avoidance
of damage during the design of soil nail of raking drains.
Baseline
landscape and visual review was carried out in November 2007. The landscape
resources in the survey area ranged from low (including southern side of Po
Shan Mansions and Piccadilly Mansion) to high (including the woodland within
the Pok Fu Lam Country Park, Green Belt above Po Shan Road and roadside
planting along Conduit Road, Kotewall Road and Po Shan Road). The survey area
consists of two distinct landscape character areas, greenbelt / country park
character area and mid-levels residential character area, both are classified
as of high landscape sensitivity. The zone of visual influence (ZVI) is quite
extensive. There has been no change in the ZVI or VSRs as originally identified
in the EIA stage, except the addition of VSR R1E, the future residents of no.
55 Conduit Road.
Background
1.11.13The
project site is located at the mostly undeveloped hillside above the
residential development at Po Shan Road and adjacent to the trimmed back slope
on the site of the catastrophic 1972 Po Shan Road failure. Previous studies had
been carried out and results indicated that the natural hillside above Po Shan
Road is affected by high groundwater level and unfavourable geology.
Sub-surface drainage measures by means of sub-horizontal drains had been
installed in 1984-85. These measures have been successful in lowering the main
ground water table, thus improving the stability of the slopes such that
large-scale failure have not occurred in the last twenty years.
1.21.13The
objective of the Project “Landslide Preventive Works at Po Shan, Mid-levels ?
Design and Construction (Natural Terrain Risk Mitigation Works)?under Contract
CE 28/2004 (GE) is to
carry out detailed design and supervision of landslide preventive works on
local repair of the hillside to minimize slope deterioration and shallow
instability.
1.31.13The proposed landslide
preventive works would be constructed to protect the existing residential
developments at the toe of the project site.
1.41.13The scope of works of this
Project includes the installation about 700 numbers of soil nails and about 60
numbers of raking drains on the natural terrain within the concerned area. The
length of the soil nails is about 20m with a spacing of 2m horizontally and 3m
vertically; the length of raking drains is about 10m with a spacing of 5m
horizontally and 15m vertically.
1.51.13The Project is anticipated
to complete in 10 months after the commencement of construction.
1.61.13According
to the Environmental Permit (EP-235/2005/B) and the EM&A Manual of the Project,
there is a need of an EM&A programme including air quality, noise, ecology, and
landscape and visual monitoring.
1.81.13ENSR Asia
(HK) Ltd. (ENSR) was employed by the
Contractor, China State ?China Railway Joint Venture,
as the Environmental Team (ET) to undertake the Environmental Monitoring and
Audit (EM&A) works for the Project. In accordance with the EM&A Manual
of the Project, environmental baseline monitoring of air quality,
noise, ecology, landscape and visual and environmental site inspections
would be required for this Project.
Purpose
of the Baseline ?/span>Scope of Report
1.81.13This is
the first monthly Environmental
Monitoring and Audit (EM&A) Report under the Contract CE 28/2004 (GE) ?/del> Landslide
Preventive Works at Po Shan Road, Mid-Levels ?/del> Design and
Construction (Natural Terrain Risk Mitigation Works). This report
presented a summary of the environmental monitoring and audit works, list of
activities, and mitigation measures proposed by the ET
for the Project in April 2008.
Project Organization
1.13
The project organization is
shown in Appendix A. The key personnel contact
names and numbers are summarized in Table 1.1
.
Table 1.1 ?Contact Information of Key Personnel
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Summary of Construction Works
1.101.13The Contactor has carried
out major activities in the reporting month. Details of the works undertaken in
this reporting period are listed below:
-
Test Nails
(5 nos.) for Pull Out Test at Portion A1 (i.e. from Row A to Row P);
Permanent
Nails installation at Portion A1; and
Site
Clearance for soil nail setting out to Portion B2 (i.e. from Row X to Row AK).
1.13
The general layout plan of
the Project
site showing the contract area is shown in
Figure 1.1. The construction programme
is provided in Appendix B.
1.13
The mitigation measures
implementation schedule are presented in Appendix C.
Summary of EM&A Programme Requirements
1.13
The EM&A programme required environmental
monitoring for air quality, noise, ecology and landscape and
visual and environmental site inspections for air quality, noise, ecology, landscape and visual and waste management. The
EM&A requirements for each parameter described in the following sections
include:
-
All monitoring parameters;
-
Monitoring schedules for the
reporting month and forthcoming months;
-
Action and Limit levels for
all environmental parameters;
-
Event / Action Plan;
-
Environmental mitigation
measures, as recommended in the Project EIA study
final report; and
-
Environmental requirement in
contract documents.
2.12.10In
accordance with the EM&A Manual, baseline 1-hour and 24-hour TSP levels at
2 air quality monitoring stations were established. Baseline Impact 1-hour
and 24-hour TSP monitoring was conducted for at least once every 7 days prior
to commencement during the of construction phase of
the Project. The Action and Limit level of the air quality
monitoring is provided in Appendix D.
2.22.10Continuous 24-hour
TSP air quality monitoring was performed using High Volume Sampler (HVS)
located at each designated monitoring station. The HVS meets all the
requirements of the EM&A Manual. Portable direct reading dust meters were
used to carry out the 1-hour TSP monitoring. Table 2.1 summarises the
equipment used.
Table 2.1 ?Air Quality Monitoring Equipment
|
|
|
|
|
|
|
|
Monitoring Parameters, Frequency and Duration
2.32.10Table 2.12
summarizes the monitoring parameters, frequency and duration of baseline impact TSP
monitoring.
Table 2.21 ?Air
Quality Monitoring Parameters, Frequency and
Duration
|
|
|
|
|
|
|
|
2.42.10Both monitoring stations were
set up at the proposed locations in accordance with EM&A Manual. Table 2.32
describes details of the two monitoring stations. The monitoring locations are
shown in Figure 2.1.
Table 2.32 ?Locations of Air Quality Monitoring Stations
|
|
|
|
|
|
2.10
As requested by the
Management Office of the air sensitive receiver Po Shan Mansions, the monitoring station CA1 was
relocated to an adjacent location closer to the site, which is still located
along the access road to Po Shan Mansions, on 24 April 2008.
Monitoring Methodology
24-hour TSP Monitoring
Installation
2.52.10The HVS
was installed in the vicinity of the air sensitive receivers.?The following criteria were considered in the
installation of the HVS.
?/span>A
horizontal platform with appropriate support to secure the sampler against
gusty wind was provided.
?/span>The
distance between the HVS and any obstacles, such as buildings, was at least
twice the height that the obstacle protrudes above the HVS.
?/span>A minimum
of 2 meters separation from walls, parapets and penthouse was required for
rooftop sampler.
?/span>No furnace
or incinerator flues were nearby.
?/span>Airflow
around the sampler was unrestricted.
?/span>Permission
was obtained to set up the samplers and to obtain access to the monitoring
stations.
?/span>A secured
supply of electricity is needed to operate the samplers.
Preparation of Filter Papers
?/span>Glass fibre filters, G810
were labeled and sufficient filters that were clean and without pinholes were
selected.
?/span>All filters were
equilibrated in the conditioning environment for 24 hours before weighing.?The conditioning environment temperature was
around 25 °C and not variable by more than ? °C; the relative humidity (RH) was
< 50% and not variable by more than ?%.?
A convenient working RH was 40%.
?/span>ALS Technichem (HK) Pty Ltd. has comprehensive quality
assurance and quality control programmes.
Field Monitoring
?/span>The power supply was checked
to ensure the HVS works properly.
?/span>The filter holder and the
area surrounding the filter were cleaned.
?/span>The filter holder was
removed by loosening the four bolts and a new filter, with stamped number
upward, on a supporting screen was aligned carefully.
?/span>The filter was properly
aligned on the screen so that the gasket formed an airtight seal on the outer
edges of the filter.
?/span>The swing bolts were
fastened to hold the
filter holder down to the frame.?The
pressure applied should be sufficient to avoid air leakage at the edges.
?/span>Then the shelter lid was closed and was secured
with the aluminum strip.
?/span>The HVS was warmed-up for about 5 minutes to
establish run-temperature conditions.
?/span>A new flowrate record sheet was set into the flow
recorder.
?/span>The range specified in the EM&A Manual was
between 0.6-1.7 m3/min.
?/span>The programmable timer was set for a sampling
period of 24 hrs + 1 hr, and the starting time, weather condition and
the filter number were recorded.
?/span>The initial elapsed time was recorded.
?/span>At the end of sampling, the sampled filter was
removed carefully and folded in half length so that only surfaces with
collected particulate matter were in contact.
?/span>It was then placed in a clean plastic envelope and
sealed.
?/span>All monitoring information
was recorded on a standard data sheet.
?/span>Filters were sent to ALS Technichem (HK) Pty Ltd.?for analysis.
Maintenance
and Calibration
?/span>The HVS and its accessories are maintained in good
working condition, such as replacing motor brushes routinely and checking
electrical wiring to ensure a continuous power supply.
?/span>HVSs are calibrated using GMW-25 Calibration Kit prior
to the commencement of baseline air quality monitoring, and will be calibrated
at bi-monthly intervals throughout all stages of the impact monitoring.
?/span>Calibration records are shown in Appendix EA.
1-hour TSP Monitoring
Measuring Procedures
2.62.10The
measuring procedures of the 1-hour dust meter are in accordance with the
Manufacturer’s Instruction Manual as follows:
?/span>Set POWER to “ON? push
BATTERY button, make sure that the meter’s indicator is in the range with a red
line and allow the instrument to stand for about 3 minutes (Then, the air
sampling inlet has been capped).
?/span>Push the knob at MEASURE
position.
?/span>Push “O-ADJ?button. (Then
meter’s indication is 0).
?/span>Push the knob at SENSI ADJ
position and set the meter’s indication to S value described on the Test Report
using the trimmer for SENSI ADJ.
?/span>Pull out the knob and return
it to MEASURE position.
?/span>Push “START?button.
Maintenance and Calibration
?/span>The 1-hour TSP meter would
be checked at 3-month intervals and calibrated at 1-year intervals throughout
all stages of the air quality baseline monitoring. Calibration records are
shown in Appendix EA.
2.72.10The
monitoring results for 1-hour TSP and 24-hour TSP are summarized in Table 2.43
and 2.45
respectively and the monitoring results are provided in Appendix FB.
Table 2.43 ?Summary of 1-hour TSP Monitoring Results During Baseline Reporting Period
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||
Table 2.54 ?Summary of 24-hour TSP Monitoring Results During Baseline Reporting Period
|
|
|
|
|
|||
|
|
|
|
|
|||
|
|
|
|
|
|||
|
|
|
|||||
|
|
|
|||||
|
|
|
|||||
|
|
|
|||||
Action and Limit Levels
2.10
Air
quality monitoring was carried out for both 1-hour TSP and 24-hour TSP at all
the monitoring stations in the reporting month. 24-hour
TSP monitoring at CA1 (Po Shan Mansions) was temporary suspended from 10 April
2008 due to the complaint received from the
Management Office regarding the noise
generated from the HVS during operation. The HVS was relocated to an adjacent location
closer to the site on 24 April 2008 and the 24-hour TSP monitoring resume on
the same day. Thus, no 24-hour
TSP monitoring was carried out on
10, 16 and 22 April 2008.
2.82.10The air
quality monitoring results, in terms of 1-hour TSP and 24-hour TSP, were below
the
action and limit level as set out in the Air Quality Objective
(AQO) at both monitoring locations in the reporting month. The event
action plan is annexed in Appendix G.
2.10
Weather information
including wind speed and wind direction is annexed in Appendix H. The
information was obtained from Hong Kong Observatory Victoria
Peak Automatic Weather Station and Central Pier Anemometer
Station.
2.10
2.92.10The baseline monitoring was
carried out in January 2008, during which, the weather was mainly fine, with
occasions of rainfall events. Major dust sources were from nearby traffic
emissions.
2.10The Action and Limit levels for
air quality impact monitoring were based on the criteria adopted from the
EM&A Manual as presented in Table 2.5.
Table
2.5 ?Derivation of Action and Limit
Levels for Air Quality
2.112.10Table 2.6 shows the derived
Action and Limit Levels for air quality impact monitoring for the Project.
Table 2.6 ?Action and Limit Levels for Air
Quality
3.13.8In accordance with the EM&A Manual, baseline impact noise
levels shall should be obtained at 2 noise monitoring stations.
Impact noise monitoring was conducted for at least once per week during the
construction phase of the Project.from the monitoring stations
designated by the adjacent CEDD Project under the requirement of an
Environmental Permit (EP-235/2005/A) The Action and Limit level of
the noise monitoring is provided in Appendix D..
3.23.8Integrating Sound Level Meter was employed for
noise monitoring.?They were Type 1 sound
level meters capable of giving a continuous readout of the noise level readings
including equivalent continuous sound pressure level (Leq) and
percentile sound pressure level (Lx). They comply with International
Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type
1).?Portable electronic wind speed
indicator capable of measuring wind speed in m/s was employed to check the wind
speed.?Table 3.1 details the noise
monitoring equipment used.
Table 3.1 ?Noise Monitoring Equipment
|
|
|
|
|
|
Monitoring
Locations
3.33.8Two monitoring stations were
set up at the proposed locations in accordance with EM&A Manual. Table 3.2
describes details of the two monitoring stations. The monitoring locations are shown in
Figure 2.1.
Table 3.2 ?Locations of Noise Monitoring Stations
|
|
|
|
|
|
Monitoring
Parameters
3.43.8One set of Measurement of 30-mins Leq
(daytime) measurement at each
monitoring station between 0700 and 1900
on normal weekdays at a frequency of once per week was
required to determine the baseline impact noise level. Leq, L10
and L90 would be recorded.
Monitoring Methodology
Monitoring Procedures
?/span>The Sound
Level Meter was set on a tripod at a height of 1.2 m above the ground.
?/span>Façade
measurements were made at all three monitoring locations.
?/span>The
battery condition was checked to ensure the correct functioning of the meter.
?/span>Parameters
such as frequency weighting, the time weighting and the measurement time were
set as follows:
-
frequency weighting: A
-
time weighting: Fast
-
time measurement: Leq(30 minutes) during
non-restricted hours i.e. between 07:00 and 19:00 on normal weekdays
?/span>Prior to
and after each noise measurement, the meter was calibrated using a Calibrator
for 94 dB at 1000 Hz.?If the difference
in the calibration level before and after measurement was more than 1 dB(A),
the measurement would be considered invalid and repeat of noise measurement
would be required after re-calibration or repair of the equipment.
?/span>The wind
speed was frequently checked with a portable wind meter.
?/span>During the
monitoring period, the Leq , L10 and L90 were
recorded.?In addition, site conditions
and noise sources were recorded on a standard record sheet.
?/span>Noise
measurement was paused during periods of high intrusive noise (e.g. dog barking,
helicopter noise) if possible. Observations were recorded when intrusive noise
was unavoidable.
?/span>Noise
monitoring was cancelled in the presence of fog, rain, wind with a steady speed
exceeding 5 m/s, or wind with gusts exceeding 10 m/s.
Maintenance and Calibration
?/span>The
microphone head of the sound level meter and calibrator is cleaned with soft
cloth at quarterly intervals.
?/span>The meter should be checked
and calibrated at yearly intervals.
?/span>Calibration details for the
sound level meter and calibrator are provided in Appendix EA.
Monitoring
Results
3.53.8The monitoring results for
noise are summarized in Table 3.3 and the monitoring data is provided in
Appendix IC.
Table 3.3 ?Summary of Noise Monitoring Results During
Baseline in
the Reporting Period
|
|
|
|
|||
|
|
|
|
|||
|
|
|
|
|||
|
|
|||||
|
|
|||||
|
|
|||||
|
|
|||||
3.6At
both monitoring locations, CN1 and CN2, the average baseline results (daytime) are within the criteria of 75 dB(A), yet the average baseline
result at CN1 was close to the criteria. There were a few measured baseline noise results
exceeded the criteria at CN1.
3.8
There was
no noise complaint received in the reporting month, hence, no
action level exceedance was recorded. At both monitoring locations, CN1 and
CN2, all the monitoring results (daytime) were below the limit level of 75
dB(A).
3.8
All the
monitoring results lied within the range of the predicted noise levels in the
EIA report.
3.7
3.73.8Major noise sources during the noise monitoring
included the construction activities from the Project and another project under
the same contract (concurrent project) carried out in the vicinity and nearby traffic
noise.According
to the EIA report, there was another project under the same contract
(concurrent project) carried out in the vicinity. Although it is believe that
there would be a cumulative impact at the sensitive receivers, the predicted
cumulative construction noise levels at the sensitive receivers would comply
with the criteria with the EIA recommended mitigation measures in place.
Action and Limit Levels
3.8The
Action and Limit Levels (AL levels) of noise monitoring have been set in
accordance with the derivation criteria specified in the EM&A Manual. This
is shown in Table 3.4 below.
Table 3.4 ?Criteria
for Action and Limit Levels for Construction Noise
|
|
|
|
|
|
|
|
|
|
|
*
?/span>Remarks: To be selected based on the
Area Sensitivity Rating of A/B/C, and the conditions of the applicable CNP(s)
must be followed.
3.93.8Both
Area Sensitivity Ratings of the noise sensitive receivers (NSRs), CN1 and CN2,
of the Project are considered as “A? The Limit Levels for impact noise
monitoring are derived and presented in Table 3.5.
Table 3.5 ?Action
and Limit Levels for Construction Noise of the Project
|
|
|
|
|
|
|
|
|
|
|
4.14.10As required under
Environmental Permit No. EP-235/2005/B, the Permit Holder is required to carry out monitoring of the trees, shrubs and herbs plant species of
conservation interest to check on
the health and condition of the plants twice a month during the construction period of the Project.
4.10
submit a detailed vegetation survey report on the
Part II Project area prior to the commencement of construction of the Project.
4.24.10It is required to undertake
the ecological tasks to fulfill the requirements of the
Environmental Permit (EP).?As required
by Conditions 2.11 and 3.5
of the EP, a suitably
qualified ecologist with 7 or more years of relevant experience shall be
employed to conduct the
ecological monitoring.
4.10
a detailed vegetation survey
prior to the commencement of construction in order to identify and label the
affected plant species of conservation interest, including but not limited to
Small Persimmon, Common Tutcheria, Bird-nest Fern and Chinese Pholidota.
4.34.10The ecological monitoring
was carried out for plant individuals of conservation interest identified
within the proposed works area.
Monitoring
Methodology
4.10
Soil
nailing works were in progress during the monitoring visits.?
4.10
A vegetation
of conservation V018 located during the last monitoring visit was found to be
in very poor condition.?
4.10
Part of the
plant species of conservation interest were not properly fenced off or
tagged, particularly in works area above Row AD.?The
Contractor was advised to fence off and label the
vegetation properly with a
clear sign notable to all the construction workers and
restrict any unauthorized access to the area.
4.10
Some vegetation
and plant species of conservation interest located near soil nailing work areas
were densely covered with soil and dust.
4.10
Hardened
grout was found in the natural habitat near the Project area.?To prevent the plant from being affected by
grout leakage and muddy site run-off, the Contractor was reminded to remove any
grout from the natural habitat as soon as possible and add sand bags around the
hardened grout.
4.44.10The
ecological monitoring was conducted twice in the reporting month on 20
3rd and 2717th ?/span>MayJune 2008 by Ms. Gigi C C Lam, who had
over 7 years of relevant ecological experience.
4.54.10The plants
of conservation interest, which were tagged during the baseline survey, were
checked during each monitoring.
4.64.10Soil
nailing scaffolding works were
in progress in the area between Row A and R during the
monitoring visits.?A total of 13 plant
species of conservation interest (i.e. V001 to V013) were identified within the
above works area during an earlier Detailed Vegetation Survey conducted under
this Project.?Plastic fencings supported by
strong poles were recommended in the previous monitoring visits conducted in
April 2008 to demarcate plant locations clearly to prevent tipping and entry of
personnel in order to avoid damage to the plants.?Fencings had been set up in the area and tThe tagged
vegetation was found to be ?/span>in good
condition during the monitoring visits in May July 2008.
4.74.10The bark of two individuals of
vegetation located adjacent to the temporary conveyor belt was found to be
slightly damaged, it was recommended that hessian sacking should be wrapped
around the trunk of vegetation to prevent damage during the transportation of
construction materials.
4.10
Construction
materials such as planks, sand bags,
metal rods
were found to be placed over or near the lower trunks of
some trees in Row C,
L, O and R.?It was recommended that these materials should be
kept in proper place to avoid
damage to vegetation within
works area.?
4.10
Concrete
was found to be spilled over from the soil
nailing works zones onto nearby areas.?It was recommended that the
concrete should be removed from the soil surface.?The Contractor advised
that the concrete will be removed and measures will be implemented to avoid any
further spillage.
4.10
The leaves, branches and trunk of a tree
(Machilus sp.) located in Row O was found
to be covered with sand and mud probably generated from nearby soil
nailing works.?
4.10
Two trees, Celtis
sinensis and Machilus sp., located
near the conveyor belt and above Row Q were found
to be dead and in very poor condition respectively.?A dead
tree (tree tag number T238) was collapsed within works area.?It was recommended that all dead trees found within the
construction site should be recorded and reported to relevant departments without delay. ?/span>
4.10
Two main roots of a big tree
(Acacia confusa of tree tag number T247) were cut
due to the construction of soil nail number I6 (Photo 1 refers).
4.10
The trunk of a tree (tree tag number T344) located
next to a soil nailing area in Row O was covered with concrete.
Review RequirementMonitoring
Requirement
During the construction
phase of the
Project, landscape and visual monitoring should be carried out bi-weekly
by a Registered Landscape Architect (RLA) to check
if the design, implementation and maintenance of the landscape and visual
mitigation measures are fully realized. A
detailed report is annexed in Appendix J.
Site
Inspection
6.29
Site Inspections were carried out on a weekly basis to monitor the
implementation of proper environmental pollution control and mitigation measures for the
Project. In the reporting month, 5 site inspections were
carried out on 1, 8, 15, 22 and 29 April 2008. The detail findings of the landscape and visual audits in the reporting
month are presented separately in Section 5. The environmental site inspection
summaries are attached in Appendix K. Particular observations
are described below.
Air Quality
6.29
?/span>No adverse observation was
identified in the reporting month.
6.29
?/span>Noise
6.29
No adverse
observation was identified in the reporting month.
Water
Quality
6.29
No adverse
observation was identified in the reporting month.
Chemical and
Waste Management
Oil stain was found under a
drill rig at Row K. The Contractor was reminded to clear the oil stain and
provide a drip tray.
A few chemical containers at
Row M were placed on ground without drip tray. The Contractor was reminded to
provide drip tray to all chemicals on site.
One oil container at Row D was placed
on ground without a drip tray. The Contractor was
advised to provide drip tray to all chemicals on site.
Stockpile of C&D waste
was found at Row E. The Contractor was reminded to clear the C&D waste
off-site regularly.
Ecology
6.29
A plant species of conservation
interest (V018) was in very poor
condition
6.29
Some vegetation of conservation
interest were not properly fenced off and not tagged.
6.29
Vegetation and plant species
of conservation interest located near soil nailing work areas were densely
covered with soil and dust.
6.29
Hardened grout was found in
the natural habitat near the Project area.?
CV001 to V013 were found to be in good condition
during the monitoring visits, nevertheless, plastic fencings supported by
strong poles were recommended to demarcate plant locations clearly to prevent
tipping and entry of personnel in order to avoid damage to the plants.onstruction materials placed near tree trunks and spillage of concrete
near soil nailing areas were observed.?Some of the plants were not properly protected during soil nailing
works and serious damages to root systems were recorded.?One recently dead tree was
found within the works area.
6.29
Landscape
and Visual
6.29
The
Contractor was advised that retained trees should be properly
protected before installation of scaffolding at PT3. Immediate
action had been undertaken by the Contractor and status / condition was to be
followed up. / sand
bags
5.23
The
Contractor was recommended to apply root protective sealant to the wounded
roots.?The Contractor was recommended to
seek the Engineer’s agreement for excavation works near existing tree roots in
order to minimize damage to the tree root system.?If root pruning is required, prior approval
from Engineer is required.
5.23
The
Contractor was recommended to clean the material fines off the tree trunks and
to provide tree protection in future when carried out drilling works.
Assessment
of Environmental Monitoring Results
6.29
All monitoring results were
audited against the Action / Limit levels and any exceedance would be validated and issued when
necessary.
6.29
The monitoring results in
the reporting period were comparable with the EIA predictions. Detailed
discussions are given in Section 2 and 3.
Advice on
the Solid and Liquid Waste Management Status
6.29
The Contractor is registered as a chemical waste
producer for this Project. The Chemical Waste Storage
Area located at the Contractor’s site office area was
properly maintained in the reporting month.
6.29
4.1815.93No waste disposal was made in the reporting month. Also 20kg of chemical waste was collected by
licenced waste collector in the reporting month. Most of the C&D waste generated was
reused on site.
Environmental
Licenses and Permits
The environmental licenses and permits for this
Project and valid in the reporting month is
summarized in Table 6.1.
Table 6.1 ?Summary of Environmental Licensing and
Permit Status
|
|
|
|
|
|
|
|||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Implementation
Status of Environmental Mitigation Measures
6.29
In
response to the site audit findings, the Contractor carried out corrective
actions.
6.29
A summary
of the Implementation Schedule of Mitigation Measures (EMIS) is
presented in Appendix C. Most of
the necessary mitigation measures were implemented properly.
Summary of
Exceedances of the Environmental Quality Performance Limit
6.29
All 1-hour TSP, 24-hour TSP
and noise monitoring results complied with the Action / Limit levels.
6.29
No exceedance was recorded
in the reporting month.
Summary of
Complaints,
Notification of Summons and Successful Prosecutions
6.29
The
Environmental Complaint Handling Procedure is annexed in Figure 6.1.
6.29
EPD received an enquiry regarding the dust
emission on hillside behind Po Shan Mansions and
conveyed their concerns to ER and Contractor on 22 May 2009. Improved mitigation measures to prevent excessive dust emission, such as enhancement of enclosures and watering
facilities, during
soil nail drilling were taken by the Contractor. EPD had inspected the site on 26 May 2009 and had no adverse comment on the dust control measures currently carried out on site.
6.29
No environmental complaint, notification of summons and
successful prosecutions was received in the reporting month.
Construction
Programme for the Coming Months
7.5
The construction programme
for the Project is provided in Appendix B.
7.5
The major construction works in May 2008 are:
-
Permanent
Nails installation at Portion A1
-
Test Nails
(5 nos.) for Pull Out Test at Portion B2
-
Site
Clearance for soil nails setting out to Portion A2 (i.e. from Row Q to Row AE)
Permanent Nails
installation at Portion B2
Key Issues
for Coming Month
7.5
Key issues to be considered
in the coming month included:
-
Properly store and label oils and chemicals on siteSufficient dust suppression
measuresmaintained;
-
Collection of construction
waste should be carried out
regularly;
-
Site runoff should be
properly collected and treated prior to discharge;
-
Construction activities
should avoid causing damage to the trees and to plants species of conservation interest;
-
Quieter
powered mechanical equipment should be used.
7.5
The following mitigation
measures are required:
Air Quality Impact
-
Regular
watering should be used during soil nailing;
-
Dusty
material stockpiled should be completely covered;
-
Dusty
activities should be re-scheduled if high-wind conditions encountered;
-
Open
burning should be strictly prohibited;
-
All dusty
vehicle loads transporting to, from and between site locations should be
covered with tarpaulin;
-
Vehicle
wheel and body washing facilities should be used at all exit points of the
site;
-
Wind
shield, dust extraction units or water spraying should be used at the loading
points.
Construction Noise Impact
-
Quieter
powered mechanical equipment should be used;
-
Insulating
fabric should be used for drill rigs during drilling process;
-
Noise
generating construction works should be carried out during daytime only;
-
Noise
barriers or other measures should be used to minimize disturbance to the bat
roost;
-
Plant on
site should be properly maintained and serviced regularly;
-
Mobile
plants should be sited as far from NSRs as possible;
-
Machines
and plant in intermittent use should be throttled down;
-
Strong
noise emitting plants, wherever possible, should be oriented so that
noise is directed away from the nearby NSRs;
-
Material stockpiles,
wherever possible, should be effectively utilized to screen noise from
construction activities;
-
Movable noise barrier with
surface mass in excess of 7kg/m2 should be
used for PME wherever possible;
-
Noise
insulating fabric should be adopted for drill rig operating in Works Area E.
Water Quality Impact
-
Prevent
runoff water from entering the nearby water-bodies;
-
Silt traps
and oil / grease separators should be regularly cleaned and maintained;
-
Outlet
pipe extending above the slope surface should be installed;
-
Air should be used as the
flushing medium of the drilling equipment;
-
Earth bunds or sand bag
barriers should be provided on-site to direct storm water to silt removal
facilities;
-
Exposed slope / soil surface
and opened stockpile of more than 50m3 should be
covered with tarpaulin;
-
Oils and
fuels should be used and stored in designated area.
Chemical and Waste
Management
-
Debris and
rubbish on-site should be collected, handled and disposed of properly;
-
Waste
skips should be provided to collect general refuse and construction wastes;
-
Soil
contamination with fuel leaked from construction plants
should be removed off-site;
-
Sufficient
waste disposal points with regular collection should be provided;
-
Appropriate
measures should be provided to minimize windblown litter and dust during transportation
of waste;
-
Different
containers should be used to segregate and store different
types of waste;
-
Encourage collection of aluminum cans, PET
bottles and paper by providing separate bins;
-
Unused chemicals should be
recycles wherever possible;
-
Proper storage and site
practices should be adopted to minimize the potential for damage and
contamination of construction materials;
-
Oils and fuels should be
stored in designated area;
-
Plan and stock construction
materials carefully to minimize waste generation.
Ecological
Impact
-
Soil nail
installation should avoid / minimize damage of root system to the existing
plants;
-
Fences
should be erected along the boundary of the works area
-
Disturbance
to the natural woodland and shrubland habitats should be minimized by
preventing tipping, vehicle movements and encroachment of personnel onto the
adjacent area;
-
Permanent
casing should be provided to the drillhole of soil nail;
-
Placement
of equipment or stockpile should be located in designated areas to minimize
disturbance to natural or
moderate-high ecological value habitats;
-
Construction
activities should be restricted to works areas;
-
Disturbance
to existing vegetation should
be minimized wherever possible.
Landscape and Visual Impact
-
Designation of “no-intrusion
zones?and record any trespass and damage to existing vegetation;
-
Soil nails on site should
avoid tree trunks and tree roots;
-
Dust and erosion control
should be provided for exposed soil;
-
For tree planting
operations, method statement should be checked against specification
requirements;
-
All retained trees within
the working boundary should be checked regularly;
-
Control over appearance
of hoarding, construction
plants / machines;
-
Security floodlights should
be carefully selected to avoid light pollution.
Monitoring Schedule for the Coming Months
7.5
The
tentative schedule for environmental monitoring in May 2008 is
provided in Appendix L.
Conclusions
8.8
The
construction phase of the project commenced in April 2008.
8.8
1-hour TSP and 24-hour
TSP monitoring was carried out in the reporting month. All monitoring results
complied with the action / limit level. No exceedance was recorded.
8.8
All impact
daytime noise monitoring results complied with the limit level in the reporting
month.
8.8
Environmental site
inspections were carried out 5 times in April 2008. Recommendations
on remedial actions were given
to the Contractor for the deficiencies identified during
the site audit.
Two landscape
and visual audits were carried out in the reporting month. keep all C&D materials / equipments / sand bags away from the
trees. The Contractor was also recommended to apply root
protective sealant to the wounded root and the Engineer’s agreement should be
sought for excavation works near existing tree roots in order to minimize
damage to the tree root system.?If root
pruning is required, prior approval from Engineer is required.
One tree was found
damaged and proper protection to the tree barks was
recommended.
The Contractor was reminded
to properly tag all the vegetation of
conservation interest and aConstruction materials
placed near tree trunks and spillage of concrete near soil nailing areas were
observed.?Some of the plants were not
properly protected during soil nailing works and serious damages to root
systems were recorded.?One recently dead
tree was found within the works area.V001 to
V013 were found to be in good condition during the monitoring visits,
nevertheless, plastic fencings supported by strong poles were recommended to
demarcate plant locations
clearly to prevent tipping and entry of personnel in order to avoid damage to
the plants.
8.8
While one enquiry
regarding dust emission was received, Nno
environmental complaint, notification of summons and prosecution was received in the
reporting month.
6.18.8Baseline
air quality monitoring was carried out between 14 and 31 January 2008 at 2
monitoring locations. Action / limit levels for air quality at each location
were derived from the baseline monitoring results. The weather during the
baseline monitoring period was generally fine with occasions of rainfalls.
6.28.8Baseline
noise levels were obtained from the impact noise monitoring programme from the
adjacent construction works. The Action level of construction noise is based on
documented complaints received, while the Limit Level is the level at a
specific limit according to EIAO-TM.
6.38.8For
the vegetation survey, a total of 12 species of 129 individuals of floral
species of conservation importance were identified
and tagged during the detailed vegetation survey.?Besides the mitigation measures recommended
in the Project EM&A Manual, works should aim to avoid and minimise any
damage caused to the existing trees and vegetation.
6.48.8The landscape and visual baseline review was
conducted in November 2007. Based on the walk-over survey, it is considered
that the baseline landscape resources, landscape character areas and visually
sensitive receivers originally identified with the EIA study area are generally
unchanged and remain valid. The addition to VSR R1E of the Future Residents of
No. 55 Conduit Road will not substantially affect the visual baseline, as views
of the site area are likely to be largely or entirely blocked by the
intervening Po Shan Mansion buildings. Changes to the landscape and visual
baseline are thus judged to be insignificant.
Recommendations
8.8
According to the
environmental site inspections performed in the reporting month, the following
recommendations were provided:
Air Quality Impact
-
Nil
Construction Noise Impact
-
Nil
Water Quality Impact
-
Nil
Chemical and Waste Management
-
Oils and fuels should be
stored in designated area;
-
Debris and rubbish on-site
should be collected, handled and disposed of properly;
-
Waste skips should be
provided to collect general refuse and construction wastes.
Ecological Impact
-
The Contractor was reminded
to take all necessary actions to prevent grout leakage and
muddy run-off to the surrounding natural environment;
-
All identified vegetation of
conservation
interest should be preserved;
-
All site access should be
clearly demarcated and no excessive removal of vegetation in natural areas
adjacent to the site access should be allowed;
-
All plant species of
conservation interest should be fenced off and tagged properly with clear sign, especially for those
located near major access road and areas likely to be impacted by
construction activities;
-
The Contractor was recommended to take necessary
measures to prevent damage to all vegetation within
the construction site; and
Dust and soil on vegetation
should be washed away in a timely manner.Ecological Impact
Soil nail
installation should avoid / minimize damage of root system to the existing plants.
-
Landscape
and Visual Impact
;;;;; andSoil nails on site should avoid tree trunks and
tree roots.