TABLE OF CONTENTS

 

EXECUTIVE SUMMARY

1.            INTRODUCTION

Scope of Report

Project Organization and Contacts of Key Management

Summary of Construction Works

2.            ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS

Monitoring Parameters

Environmental Quality Performance Limits (Action/Limit Levels)

Environmental Mitigation Measures

3.            MONITORING RESULTS

Air Quality

Ecology

Landscape and Visual

Environmental Site Inspection

4.            Advice on Solid and liquid Waste Mangement Status

5.            Summary of Non-Compliance (Exceedances) of environmental qualitY

Summary of Exceedances and Review of the Reasons for non-compliance

6.            Environmental complaints, notification of summons and successful prosecutioN

7.            Comments, Recommendations and Conclusions

Comments on Mitigation Measures

Recommendations on EM&A Programme

Conclusions

 

List of Tables

 

Table 1.1              Contact Information of Key Personnel

Table 3.1              Summary of Number of Exceedances for 1-hr & 24-hr TSP Concentration

Table 3.2              Summary of Number of Exceedances for Daytime Noise

Table 6.1              Summary of Environmental Complaints and Prosecutions

 

List of Figures

 

Figure 1.1         Site Layout Plan

Figure 2.1         Locations of Air Quality and Noise Monitoring Stations

 

 

List of Appendices

 

Appendix A       Project Organization Structure

Appendix B       Construction Programme

Appendix C       Implementation Schedule of Mitigation Measures (EMIS)

Appendix D      Action and Limit Levels for Air Quality        and Noise

Appendix E       Graphical Presentation of Air Quality Monitoring Results

Appendix F       Graphical Presentation of Noise Monitoring Results

Appendix G      Environmental Complaint Log


 


EXECUTIVE SUMMARY

The Project “Landslide Preventive Works at Po Shan, Mid-levels – Design and Construction (Natural Terrain Risk Mitigation Works)” (hereafter called “the Project”) includes the installation of about 700 numbers of soil nails and about 60 numbers of raking drains on the natural terrain within the concerned area.

China State – China Railway Joint Venture (CCJV) was commissioned as the Contractor of the Project. ENSR Asia (HK) Ltd., which was integrated into AECOM Asia Company Limited as of 1 May 2009, was employed by CCJV as the Environmental Team to carry out the EM&A programme.

The impact environmental monitoring and audit for the Project includes the air quality, noise, ecology, landscape and visual monitoring. The construction of the Project and the EM&A programme commenced on 1 April 2008.

This report documented the findings of EM&A works conducted in the period from July 2009 to September 2009. As informed by the Contractor, construction activities carried out in the reporting quarter were:

-       Soil nailing works at Portion B2;

-       Soil nail head construction at Portion B2;

-       Rock slope stabilization works at Portion D; and

-       Slope reinstatement works at Portion A1, A2, B1 and C.

 

Environmental Monitoring Works

 

EM&A Programme

 

A summary of monitoring and audit activities conducted in the reporting quarter is listed below:

 

24-hour TSP monitoring

16

sessions

1-hour TSP monitoring

48

sessions

Daytime Noise monitoring

13

sessions

Ecology monitoring

6

sessions

Landscape and Visual Audit

  6

sessions

Environmental Site Inspection

12

sessions

Breaches of Action and Limit Levels

There was no action / limit level exceedance recorded for 1-hour and 24-hour TSP monitoring.

In the reporting quarter, all noise level recorded complied with the limit level.

Complaint, Notification of Summons and Successful Prosecution

There was no complaint, notification of summons and successful prosecution received in the reporting quarter.

.

 

 


1.    INTRODUCTION

Scope of Report

1.1          This is the sixth Quarterly Environmental Monitoring and Audit (EM&A) Summary Report under the Contract CE 28/2004 (GE) – Landslide Preventive Works at Po Shan Road, Mid-Levels – Design and Construction (Natural Terrain Risk Mitigation Works). This report presented a summary of the environmental monitoring and audit works, and list of activities carried out by the ET for the Project for the period from July 2009 to September 2009.

 

Project Organization and Contacts of Key Management

1.2          The project organization is shown in Appendix A. The key personnel contact names and numbers are summarised in Table 1.1

 

Table 1.1       Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

CEDD

Senior Engineer

H. W. Sun

2762 5375

2714 0247

ER (MGS)

Resident Engineer

Lawrence Shek

3188 0400

3188 0775

Assistant Resident Engineer

S. F. Chau

3188 0400

3188 0775

IEC (ENVIRON)

Independent Environmental Checker

David Yeung

3743 0788

3548 6988

Contractor (CCJV)

Project Manager

C Y Mak

3188 0538

3188 1710

Safety and Environmental Officer

Brian Yam

3188 0538

3188 1710

ET (ENSR)

ET Leader

Edith Ng

3105 8525

2891 0305

 

Summary of Construction Works

1.3          The Contactor has carried out major activities in the reporting quarter. Details of the works undertaken in this reporting period are listed below:

 

-       Soil nailing works at Portion B2;

-       Soil nail head construction at Portion B2;

-       Rock slope stabilization works at Portion D; and

-       Slope reinstatement works at Portion A1, A2, B1 and C.

 

1.4          The general layout plan of the Project site showing the contract area is shown in Figure 1.1.

 

1.5          The construction programme is provided in Appendix B.

 

1.6          The mitigation measures implementation schedule are presented in Appendix C.

 


2.    ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS

Monitoring Parameters

2.1          The EM&A Manual designated two monitoring stations to monitor environmental impacts on air quality and noise due to the Project. The monitoring locations are depicted in Figure 2.1.

 

2.2          The EM&A Manual also required ecology monitoring, bi-weekly landscape and visual audits, and environmental site inspections for air quality, noise, water quality, chemical, waste management, ecology and landscape and visual.

Environmental Quality Performance Limits (Action/Limit Levels)

2.3          The environmental quality performance limits (i.e. Action/Limit Levels) were derived from the baseline air quality monitoring results of Access road to Po Shan Mansions (CA1) and Podium of Hamilton Court (CA2) and / or as defined in the EM&A Manual (CN1 & CN2), and are given in Appendix D.

Environmental Mitigation Measures

2.4          Relevant environmental mitigation measures were stipulated in the Particular Specification and EP (No.: EP-235/2005/B) for the Contractor to adopt. A list of mitigation measures and their implementation statuses are given in Appendix C.

 

 

 


3.     MONITORING RESULTS

Air Quality

3.1          Air quality monitoring, including 1-hr and 24-hr TSP, was conducted at least 3 times every 7 days and at least once every 7 days respectively at the 2 monitoring stations (CA1 and CA2), in accordance with the EM&A Manual. Forty-eight 1-hr TSP and sixteen 24-hr TSP monitoring events were carried out in this reporting quarter.

3.2          The weather was mostly sunny and fine in the reporting quarter. The trend of air quality for the reporting quarter are given in Appendix E. Major dust source of the construction works area included soil nailing works from the Project, construction activities of another project under the same contract (concurrent project) carried out in the vicinity and nearby traffic emissions.

3.3          There was no Action and Limit Level exceedance recorded for both 1-hr and 24-hr TSP in the reporting quarter.

3.4          Table 3.1 presents the number of exceedances recorded in each month of the reporting quarter. The number of monitoring events included regular monitoring events and additional ones, if any.

 

Table 3.1       Summary of Number of Exceedances for 1-hr & 24-hr TSP Concentration

Monitoring Parameter

Location

Level of Exceedance

Month

Jul 09

Aug 09

Sep 09

1-hr TSP

CA1

No. of monitoring events

15

15

18

Action

0

0

0

Limit

0

0

0

CA2

No. of monitoring events

15

15

18

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

24-hr TSP

CA1

No. of monitoring events

5

6

5

Action

0

0

0

Limit

0

0

0

CA2

No. of monitoring events

5

6

5

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

 

Construction Noise

3.5          Noise monitoring was conducted at the 2 monitoring stations (CN1 and CN2) for at least once per week during 0700 – 1900 of the reporting quarter. Thirteen noise monitoring events were conducted in the reporting quarter.

3.6          As no noise complaint was received in the reporting quarter, no Action Level exceedance was recorded. All measured noise levels were below the Limit Level and the graphical plots of trends of the monitoring results are provided in Appendix F.

3.7          Table 3.2 presents the number of exceedances recorded in each month of the reporting quarter. The number of monitoring events included regular monitoring events and additional ones, if any.

 

Table 3.2       Summary of Number of Exceedances for Daytime Noise

Monitoring Parameter

Location

Level of Exceedance

Month

Jul 09

Aug 09

Sep 09

Daytime Noise

CN1

No. of monitoring events

4

4

5

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

CN2

No. of monitoring events

4

4

5

Action

0

0

0

Limit

0

0

0

 

Total

0

0

0

3.8          Major noise sources during the noise monitoring included the construction activities from the Project and another project under the same contract (concurrent project) carried out in the vicinity and nearby traffic noise.

 

Ecology

3.9          Ecological monitoring was carried out twice a month by a suitably qualified local ecologist to check on the health and condition of the plant species of conservation interest. Six ecological monitoring were conducted in the reporting quarter.

3.10        During monitoring visit on 7 July 2009, the previously missing vegetation of conservation interest V 54 were located and tagged.  However, another two individuals V086 and V088 were not properly fenced off.

3.11        A vegetation of conservation V018 located during the May 2009 monitoring visit was still in very poor condition. 

3.12        Soil of natural terrain along an access road (near Row AH) was not well covered.

3.13        General refuse was accumulated within demarcated area with vegetation of conservation interest. The Contractor was reminded to remove the general refuse.

3.14        Sandbags and stones were observed piled against a few trees. The Contractor was requested to keep the sandbags and stones away from the trees.

Landscape and Visual

3.15        Bi-weekly landscape and visual audit was conducted by a Registered Landscape Architect (RLA) to monitor the implementation of landscape and visual mitigation measures. Six landscape and visual audits were conducted in the reporting quarter.

3.16        Protection to the existing tree previously found with its trunk enclosed within the make-shift conveyor system was outstanding.  The Contractor was requested to rectify the edge board to ensure that conveying of materials would not damage the tree trunk.

3.17        It was noted that compensatory planting proposal for the replacement of dead tree T611 was outstanding.  The Contractor was recommended to seek Engineer’s agreement on the replacement planting as soon as possible.

3.18        It was noted that the Contractor’s clarification of the status of existing trees T516, T517, T666, and T698 located immediately outside of the works boundary was outstanding.  The Contractor was reminded to provide necessary information as soon as possible.

3.19        It was found that a couple of rubber air hoses had been rubbed against a tree trunk leaving black marks.  The Contractor was requested to relocate the hoses away from the tree.

3.20        It was observed a side branch of tree T608 overhanging the footpath was structurally cracked.  The Contractor was requested to prune and remove the damaged tree branch for safety and healthy growth of the tree.

3.21        It was noted several trees were broken by recent strong winds and Typhoon Molave.   The Contractor was reminded to report damaged trees to the Engineer for record.

3.22        It was observed sacks of construction waste materials were piled against the base and trunk of existing tree.  The Contractor was requested to clear the materials away from the tree.

3.23        Further rectification of the tree ID numbers on site was carried, with only approximately 85% completed.   The Contractor was reminded to finish the rectification of missing tree ID numbers works for the remaining existing trees as soon as possible.

3.24        As the project is nearing completion, as previously mentioned, for safety consideration when to area is to be re-open for the general public use, it is recommend that the side branch of existing tree T678 overhanging the footpath with its low headroom be pruned back to prevent any possible accidents in future.  Also, the dead tree T612 with half broken branch along the footpath is also recommended to be removed.

Environmental Site Inspection

3.25        There were 12 site inspections conducted in the reporting quarter to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. The major concerns for the Project are air quality, noise, water quality, waste management, ecology and landscape and visual. Observations recorded are described below.

Air Quality

3.26        Some of the temporary exposed slopes at Row R were not properly covered. The Contractor was reminded to properly cover all exposed slopes.

Noise

3.27        No adverse observation was identified in the reporting quarter.

Water Quality

3.28        Loose sediment was observed accumulated on the platform at Row X, Row AF and Row AH. The Contractor was reminded to clear the sediment regularly and as soon as the soil nailing operation finishes.

3.29        Sediment was observed accumulated in the sand trap at Row C. The Contractor was advised to clear the sediment more frequently especially during rainy seasons.

3.30        Sediment, leaves and general refuse were observed in the u-channel at Row A and Row R. The Contractor was reminded to clear them regularly and properly maintain the drainage system.

3.31        Stagnant water was observed accumulated in a soil nail head at Row AA. The Contractor was reminded to clear the stagnant water.

 

Chemical and Waste Management

3.32        A chemical container was observed placed on ground without drip tray at Row X. The Contractor was reminded to provide drip tray to all chemical containers on site.

3.33        A drip tray of a soil nailing controller at Row AA was observed accumulated with oily water. The Contractor was reminded to remove the oily water frequently and treat it as chemical waste.

 

Ecology

3.34        A plant species of conservation interest (V018) was still in very poor condition.

3.35        Two individuals of vegetation of conservation interest V086 and V088 were not fenced off.

3.36        An access road (near Row AH) along natural terrain was not well covered.

3.37        A plant species of conservation interest (V018) was still in very poor condition.

3.38        An access road (near Row AH) along natural terrain was not well covered.

3.39        Sandbags and stones were observed piled against a few trees. The Contractor was requested to keep the sandbags and stones away from the trees.

3.40        General refuse was accumulated within demarcated area with vegetation of conservation interest. The Contractor was reminded to remove the general refuse.

 

Landscape and Visual

3.41        Protection to the existing tree previously found with its trunk enclosed within the make-shift conveyor system was outstanding.  The Contractor was requested to rectify the edge board to ensure that conveying of materials would not damage the tree trunk.

3.42        It was noted that compensatory planting proposal for the replacement of dead tree T611 was outstanding.  The Contractor was recommended to seek Engineer’s agreement on the replacement planting as soon as possible.

3.43        It was noted that the Contractor’s clarification of the status of existing trees T516, T517, T666, and T698 located immediately outside of the works boundary was outstanding.  The Contractor was reminded to provide necessary information as soon as possible.

3.44        It was found that a couple of rubber air hoses had been rubbed against a tree trunk leaving black marks.  The Contractor was requested to relocate the hoses away from the tree.

3.45        It was observed a side branch of tree T608 overhanging the footpath was structurally cracked.  The Contractor was requested to prune and remove the damaged tree branch for safety and healthy growth of the tree.

3.46        It was noted several trees were broken by recent strong winds and Typhoon Molave.   The Contractor was reminded to report damaged trees to the Engineer for record.

3.47        It was observed sacks of construction waste materials were piled against the base and trunk of existing tree.  The Contractor was requested to clear the materials away from the tree.

3.48        Further rectification of the tree ID numbers on site was carried, with only approximately 85% completed.   The Contractor was reminded to finish the rectification of missing tree ID numbers works for the remaining existing trees as soon as possible.

3.49        As the project is nearing completion, as previously mentioned, for safety consideration when to area is to be re-open for the general public use, it is recommend that the side branch of existing tree T678 overhanging the footpath with its low headroom be pruned back to prevent any possible accidents in future.  Also, the dead tree T612 with half broken branch along the footpath is also recommended to be removed.

 

 

4.    Advice on Solid and liquid Waste Mangement Status

 

4.1          The Contractor has registered as a chemical waste producer for this Project. The Chemical Waste Storage Area located at the Contractor’s site office area was properly maintained in the reporting quarter.

4.2          As advised by the Contractor, 45.83 ton of inert C&D waste was disposed offsite to Chai Wan and 26.47 ton of non-inert C&D waste was disposed offsite to SENT landfill in the reporting period. C&D waste generated was reused on site as much as possible.

 

 

5.    Summary of Non-Compliance (Exceedances) of environmental qualitY

Summary of Exceedances and Review of the Reasons for non-compliance

5.1          There was no 1-hr TSP, 24-hr TSP and noise exceedance recorded in the reporting quarter.

 

 

 

6.    Environmental complaints, notification of summons and successful prosecutioN

 

6.1          No complaint, notification of summons and prosecution was received in the reporting quarter. Table 6.1 summarized the complaint, summons and successful prosecution received in the reporting period.

 

    Table 6.1  Summary of Environmental Complaints and Prosecutions

 

July 2009

August 2009

September 2009

Total

Complaint Logged

0

0

0

0

Summons

Served

0

0

0

0

Successful Prosecution

0

0

0

0

Total

0

0

0

0

 

 

 

7.    Comments, Recommendations and Conclusions

Comments on Mitigation Measures

7.1          According to the environmental site inspections performed in the reporting quarter, the following recommendations are provided:

 

Air Quality

-       Soil nail workstations on site should be properly enclosed.

Noise

-       N/A

Water Quality

-       Sedimentation tanks on site should be properly maintained;

-       Site effluent must be collected and treated prior to discharge to public drain;

-       U-channels should be kept clear of mud, debris, leaves, construction waste and materials; and

-       Soil and exposed earth at all working platforms and slopes should be cleaned up.

Chemical and Waste Management

-       Drip trays should be provided to all plants and chemical containers on site;

-       Oils and fuels should be stored in designated area;

-       Empty chemical containers should be disposed of as chemical waste;

-       C&D waste, debris and general refuse on-site should be collected, handled and disposed of properly; and

-       Waste skips should be provided to collect general refuse and construction wastes.

Ecology

-       The Contractor was reminded to take all necessary actions to prevent grout leakage and muddy run-off to the surrounding natural environment;

-       All identified vegetation of conservation interest should be preserved;

-       All site access should be clearly demarcated and no excessive removal of vegetation in natural areas adjacent to the site access should be allowed;

-       All plant species of conservation interest should be fenced off and tagged properly with clear sign, especially for those located near major access road and areas likely to be impacted by construction activities;

-       The Contractor was recommended to take necessary measures to prevent damage to all vegetation within the construction site; and

-       Dust and soil on vegetation should be washed away in a timely manner.

 

Landscape and Visual

-       The Contractor was reminded to provide protection to the existing tree located within the conveyor system to prevent damage to the tree trunk.

-       The Contractor was requested to remove the air hoses away from the tree trunk to prevent abrasion.

-       The Contractor was again reminded to seek Engineer’s agreement on the replacement planting for dead tree.

-       The Contractor was reminded to rectify all remaining ineligible tree ID numbers for all remaining existing trees.

-       The Contractor was reminded to clarify the status of missing trees as soon as possible.

-       The Contractor was recommended to clear all existing sacks of construction waste materials away from the base and trunk of existing tree as soon as possible.

-       The Contractor was recommended to prune all unsafe tree branches and dead trees as soon as possible.

 

 

Recommendations on EM&A Programme

7.2          The impact air quality and noise monitoring programme ensured that any environmental impact to the receivers would be readily detected and timely actions could be taken to rectify any non-compliance.  Assessment and analysis of monitoring results collected demonstrated the environmental acceptability of the Project.  The ecological monitoring, bi-weekly landscape and visual audit and weekly site inspection ensured that all the environmental mitigation measures recommended in the EIA report were effectively implemented.

7.3          The EM&A programme effectively monitored the environmental impacts from the construction activities and no particular recommendation was advised for the improvement of the programme.

Conclusions

7.4          Air quality and noise monitoring, ecological monitoring, bi-weekly landscape and visual audit and weekly site inspection were carried out from July 2009 to September 2009, in accordance with the EM&A Manual.

7.5          No Action and Limit Level exceedance or non-compliance was recorded for the monitoring works in the reporting quarter.

7.6          No environmental complaints, summons or prosecution were made against the Project in the reporting quarter.