TABLE OF CONTENTS


EXECUTIVE SUMMARY

1.            Introduction

Scope of Report

Project Organization and Contacts of Key Management

Summary of Construction Works

2.            Environmental Monitoring And Audit Requirements

Monitoring Parameters

Environmental Quality Performance Limits (Action/Limit Levels)

Environmental Mitigation Measures

3.            Air Quality Monitoring Results

Monitoring Requirements

Monitoring Equipment

Monitoring Parameters, Frequency and Duration

Monitoring Locations

Monitoring Methodology

Monitoring Result

4.            Construction Noise Monitoring Results

Monitoring Requirements

Monitoring Equipment

Monitoring Locations

Monitoring Parameters

Monitoring Methodology

Monitoring Results

5.            Ecology Monitoring Results

Monitoring Requirement

Monitoring Location

Monitoring Methodology

Monitoring Results

6.            Landscape and Visual Audit Results

Monitoring Requirement

Monitoring Results

7.            Environmental Site Inspection

8.            Advice on Solid and liquid Waste Mangement Status

9.            Summary of Non-Compliance (Exceedances) of Environmental Quality

10.          Environmental Complaints, Notification of Summons and Successful Prosecution

11.          Comparison of EM&A Data with EIA Prediction

12.          Review of Effectiveness and Efficiency of the Monitoring Methodology and Mitigation Measures

13.          Recommendations on the EM&A Programme

14.          Conclusions

 

 

 

List of Tables

 

Table 1.1              Contact Information of Key Personnel

Table 2.1              Air Quality Monitoring Equipment

Table 2.2              Air Quality Monitoring Parameters, Frequency and Duration

Table 2.3              Locations of Air Quality Monitoring Stations

Table 3.1              Noise Monitoring Equipment

Table 3.2              Locations of Noise Monitoring Stations

 

 

List of Figures

 

Figure 1.1         Site Layout Plan

Figure 2.1         Locations of Air Quality and Noise Monitoring Stations

 

 

 

List of Appendices

 

Appendix A       Project Organization Structure

Appendix B       Construction Programme

Appendix C       Implementation Schedule of Mitigation Measures (EMIS)

Appendix D      Action and Limit Levels for Air Quality        and Noise

Appendix E       Graphical Presentation of Air Quality Monitoring Results

Appendix F       Graphical Presentation of Noise Monitoring Results

Appendix G      Statistics of Complaints, Notification of summons and Successful Prosecutions

 

 

 


EXECUTIVE SUMMARY

The Project “Landslide Preventive Works at Po Shan, Mid-levels – Design and Construction (Natural Terrain Risk Mitigation Works)” (hereafter called “the Project”) includes the installation of about 700 numbers of soil nails and about 60 numbers of raking drains on the natural terrain within the concerned area.

China State – China Railway Joint Venture (CCJV) was commissioned as the Contractor of the Project. ENSR Asia (HK) Ltd., which was integrated into AECOM Asia Company Limited as of 1 May 2009, was employed by CCJV as the Environmental Team to carry out the EM&A programme.

The impact environmental monitoring and audit for the Project includes the air quality, noise, ecology, landscape and visual monitoring. The construction of the Project and the EM&A programme commenced on 1 April 2008.

The termination of the construction phase EM&A programme of the Project was approved by EPD on 31 December 2009.

This Final EM&A Review Report summarizes the findings of EM&A works conducted in the construction period from April 2008 to December 2009. The construction activities carried out in the reporting period were:

-       Test nails for pull out test;

-       Permanent nails installation;

-       Site clearance for soil nail setting;

-       Setting out of locations of soil nail;

-       Soil Nail Installation;

-       Erection of scaffolded and working platform;

-       Soil nail head preparatory works;

-       Soil nail construction;

-       Soil nail head construction;

-       Rock slope stabilization works;

-       Slope reinstatement works;

-       Removal of winch system;

-       Laying of corrosion mat and wire mesh to soil profile at soil nailing area;

-       Hydroseeding; and

-       Compensatory planting to soiling nailing area.

 

Environmental Monitoring Works

 

EM&A Programme

 

A summary of monitoring and audit activities conducted in the reporting period is listed below:

 

24-hour TSP monitoring

108(CA1)/110(CA2)

sessions

1-hour TSP monitoring

111

sessions

Daytime Noise monitoring

92

sessions

Ecology monitoring

42

sessions

Landscape and Visual Audit

  46

sessions

Environmental Site Inspection

91

sessions

Breaches of Action and Limit Levels

There was no Action / Limit level exceedance recorded for 1-hour and 24-hour TSP monitoring throughout the construction period of the Project.

All noise level recorded complied with the Limit level throughout the construction period of the Project. No noise related complaint was received in the reporting period, hence no Action Level exceedance was recorded.

Complaint, Notification of Summons and Successful Prosecution

There were two (2) environmental complaints received in the reporting period.

EPD referred two complaints from residents nearby Po Shan Mansions, regarding construction dust emission

from the slope work at Po Shan Road in May 2009. Through on-site investigation, construction dust could potentially be generated from soil nail drilling works of the Project. Although all the 1-hr and 24-hr TSP monitoring results in May 2009 did not exceed the Action levels, the Contractor was recommended to improve mitigation measures to prevent dust emission as far as possible. EPD had inspected the site on 22 May 2009

and had no adverse comment on the dust control measures carried out on site. During follow-up site inspections

by ET, enhanced mitigation measures were taken by the Contractor and no significant construction or fugitive

dust was observed.

There was no notification of summons and successful prosecution received in the reporting period.

 

 


1.    Introduction

Scope of Report

1.1          This is the Final EM&A Review Report under the Contract CE 28/2004 (GE) – Landslide Preventive Works at Po Shan Road, Mid-Levels – Design and Construction (Natural Terrain Risk Mitigation Works). This report presented a summary of the environmental monitoring and audit works, and list of activities carried out by the ET for the Project for the period from April 2008 to December 2009.

 

Project Organization and Contacts of Key Management

1.2          The project organization is shown in Appendix A. The key personnel contact names and numbers are summarised in Table 1.1

 

Table 1.1       Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

CEDD

Senior Engineer

H. W. Sun

2762 5375

2714 0247

ER (MGS)

Resident Engineer

Lawrence Shek

3188 0400

3188 0775

Assistant Resident Engineer

S. F. Chau

3188 0400

3188 0775

IEC (ENVIRON)

Independent Environmental Checker

David Yeung

3743 0788

3548 6988

Contractor (CCJV)

Project Manager

C. Y. Mak

3188 0538

3188 1710

Safety and Environmental Officer

Yue Kin Fung

3188 0538

3188 1710

ET (AECOM)

ET Leader

Edith Ng

3105 8525

2891 0305

 

Summary of Construction Works

1.3          Construction works undertaken by the Contractor during the construction period of the Project are listed below:

 

-       Test nails for pull out test;

-       Permanent nails installation;

-       Site clearance for soil nail setting;

-       Setting out of locations of soil nail;

-       Soil Nail Installation;

-       Erection of scaffolded and working platform;

-       Soil nail head preparatory works;

-       Soil nail construction;

-       Soil nail head construction;

-       Rock slope stabilization works;

-       Slope reinstatement works;

-       Removal of winch system;

-       Laying of corrosion mat and wire mesh to soil profile at soil nailing area;

-       Hydroseeding; and

-       Compensatory planting to soiling nailing area.

 

1.4          The general layout plan of the Project site showing the contract area is shown in Figure 1.1.

 

1.5          The construction programme is provided in Appendix B.

 

1.6          The mitigation measures implementation schedule are presented in Appendix C.

 

 

 

2.    Environmental Monitoring And Audit Requirements

Monitoring Parameters

2.1          The EM&A Manual designated two monitoring stations to monitor environmental impacts on air quality and noise due to the Project. The monitoring locations are depicted in Figure 2.1.

 

2.2          The EM&A Manual also required ecology monitoring, bi-weekly landscape and visual audits, and environmental site inspections for air quality, noise, water quality, chemical, waste management, ecology and landscape and visual.

Environmental Quality Performance Limits (Action/Limit Levels)

2.3          The environmental quality performance limits (i.e. Action/Limit levels) were derived from the baseline air quality monitoring results of Access road to Po Shan Mansions (CA1) and Podium of Hamilton Court (CA2) and / or as defined in the EM&A Manual (CN1 & CN2), and are given in Appendix D.

Environmental Mitigation Measures

2.4          Relevant environmental mitigation measures were stipulated in the Particular Specification and EP (No.: EP-235/2005/B) for the Contractor to adopt. A list of mitigation measures and their implementation statuses are given in Appendix C.

 

 

 


3.     Air Quality Monitoring Results

 

Monitoring Requirements

3.1          In accordance with the EM&A Manual, 1-hour and 24-hour TSP levels at 2 air quality monitoring stations were established. Impact 1-hour and 24-hour TSP monitoring was conducted for at least once every 7 days during the construction phase of the Project. The Action and Limit level of the air quality monitoring is provided in Appendix D.

Monitoring Equipment

3.2          24-hour TSP air quality monitoring was performed using High Volume Sampler (HVS) located at each designated monitoring station. The HVS meets all the requirements of the EM&A Manual. Portable direct reading dust meters were used to carry out the 1-hour TSP monitoring. Table 2.1 summarises the equipment used.

 

Table 2.1       Air Quality Monitoring Equipment

Equipment

Model

High Volume Sampler

GS 2310 Accu-vol system

Calibrator

GMW 25

1-hour TSP Dust Meter

Laser Dust Monitor – Model LD-3

 

Monitoring Parameters, Frequency and Duration

3.3          Table 2.2 summarizes the monitoring parameters, frequency and duration of impact TSP monitoring.

 

Table 2.2       Air Quality Monitoring Parameters, Frequency and Duration

Monitoring Station

Parameter

Frequency and Duration

CA1 & CA2

24-hour TSP

At least once every 7 days

1-hour TSP

At least 3 times every 7 days

Monitoring Locations

3.4          Both monitoring stations were set up at the proposed locations in accordance with EM&A Manual. Table 2.3 describes details of the two monitoring stations. The monitoring locations are shown in Figure 2.1.

 

Table 2.3       Locations of Air Quality Monitoring Stations

Monitoring Station

Identity / Description

CA1

Access road to Po Shan Mansions

CA2

Podium of Hamilton Court

 

 

 

Monitoring Methodology

24-hour TSP Monitoring

 

Installation

 

3.5          The HVS was installed in the vicinity of the air sensitive receivers.  The following criteria were considered in the installation of the HVS.

·         A horizontal platform with appropriate support to secure the sampler against gusty wind was provided.

·         The distance between the HVS and any obstacles, such as buildings, was at least twice the height that the obstacle protrudes above the HVS.

·         A minimum of 2 meters separation from walls, parapets and penthouse was required for rooftop sampler.

·         No furnace or incinerator flues were nearby.

·         Airflow around the sampler was unrestricted.

·         Permission was obtained to set up the samplers and to obtain access to the monitoring stations.

·         A secured supply of electricity is needed to operate the samplers.

 

Preparation of Filter Papers

 

·         Glass fibre filters, G810 were labeled and sufficient filters that were clean and without pinholes were selected.

·         All filters were equilibrated in the conditioning environment for 24 hours before weighing.  The conditioning environment temperature was around 25 °C and not variable by more than ±3 °C; the relative humidity (RH) was < 50% and not variable by more than ±5%.  A convenient working RH was 40%.

·         ALS Technichem (HK) Pty Ltd. has comprehensive quality assurance and quality control programmes.

 

Field Monitoring

 

·         The power supply was checked to ensure the HVS works properly.

·         The filter holder and the area surrounding the filter were cleaned.

·         The filter holder was removed by loosening the four bolts and a new filter, with stamped number upward, on a supporting screen was aligned carefully.

·         The filter was properly aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.

·         The swing bolts were fastened to hold the filter holder down to the frame.  The pressure applied should be sufficient to avoid air leakage at the edges.

·         Then the shelter lid was closed and was secured with the aluminum strip.

·         The HVS was warmed-up for about 5 minutes to establish run-temperature conditions.

·         A new flowrate record sheet was set into the flow recorder.

·         The range specified in the EM&A Manual was between 0.6-1.7 m3/min.

·         The programmable timer was set for a sampling period of 24 hrs + 1 hr, and the starting time, weather condition and the filter number were recorded.

·         The initial elapsed time was recorded.

·         At the end of sampling, the sampled filter was removed carefully and folded in half length so that only surfaces with collected particulate matter were in contact.

·         It was then placed in a clean plastic envelope and sealed.

·         All monitoring information was recorded on a standard data sheet.

·         Filters were sent to ALS Technichem (HK) Pty Ltd.  for analysis.

 

Maintenance and Calibration

 

·         The HVS and its accessories are maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.

·         HVSs are calibrated using GMW-25 Calibration Kit prior to the commencement of baseline air quality monitoring, and will be calibrated at bi-monthly intervals throughout all stages of the impact monitoring.

 

1-hour TSP Monitoring

 

Measuring Procedures

 

3.6          The measuring procedures of the 1-hour dust meter are in accordance with the Manufacturer’s Instruction Manual as follows:

·         Set POWER to “ON”, push BATTERY button, make sure that the meter’s indicator is in the range with a red line and allow the instrument to stand for about 3 minutes (Then, the air sampling inlet has been capped).

·         Push the knob at MEASURE position.

·         Push “O-ADJ” button. (Then meter’s indication is 0).

·         Push the knob at SENSI ADJ position and set the meter’s indication to S value described on the Test Report using the trimmer for SENSI ADJ.

·         Pull out the knob and return it to MEASURE position.

·         Push “START” button.

 

Maintenance and Calibration

 

3.7          The 1-hour TSP meter would be checked at 3-month intervals and calibrated at 1-year intervals throughout all stages of the air quality monitoring.

Monitoring Result

3.8          One hundred and eleven (111) 1-hr TSP monitoring events were carried out in the reporting period. For 24-hour TSP monitoring, one hundred and eight (108) monitoring events were conducted for CA1, while one hundred and ten (110) monitoring events were carried out for CA2 in the reporting period.

3.9          The weather during the monitoring sessions was mostly fine and sunny. The trend of air quality for the reporting period are given in Appendix E. Major dust source of the construction works area included soil nail installation activities from the Project, construction activities of another project under the same contract (concurrent project) carried out in the vicinity and nearby traffic emissions.

3.10        There was no Action and Limit level exceedance recorded for both 1-hr and 24-hr TSP during the course of the construction period of the Project.

 

 

4.    Construction Noise Monitoring Results

Monitoring Requirements

4.1          In accordance with the EM&A Manual, impact noise levels should be obtained at 2 noise monitoring stations. Impact noise monitoring was conducted for at least once per week during the construction phase of the Project. The Action and Limit level of the noise monitoring is provided in Appendix D.

Monitoring Equipment

4.2          Integrating Sound Level Meter was employed for noise monitoring.  They were Type 1 sound level meters capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx). They comply with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1).  Portable electronic wind speed indicator capable of measuring wind speed in m/s was employed to check the wind speed.  Table 3.1 details the noise monitoring equipment used.

 

Table 3.1       Noise Monitoring Equipment

Equipment

Model

Integrating Sound Level Meter

Rion NL-31

Calibrator

Rion NC73

Monitoring Locations

4.3          Two monitoring stations were set up in accordance with EM&A Manual. Table 3.2 describes details of the two monitoring stations. The monitoring locations are shown in Figure 2.1.

 

Table 3.2       Locations of Noise Monitoring Stations

Monitoring Station

Identity / Description

CN1

Block A, Po Shan Mansions

CN2

Block A, Po Shan Mansions

Monitoring Parameters

4.4          One set of 30-mins measurement at each monitoring station between 0700 and 1900 on normal weekdays at a frequency of once per week was required to determine the impact noise level. Leq, L10 and L90 would be recorded.

Monitoring Methodology

Monitoring Procedures

·         The Sound Level Meter was set on a tripod at a height of 1.2 m above the ground.

·         Façade measurements were made at all three monitoring locations.

·         The battery condition was checked to ensure the correct functioning of the meter.

·         Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:

-         frequency weighting: A

-         time weighting: Fast

-         time measurement: Leq(30 minutes) during non-restricted hours i.e. between 07:00 and 19:00 on normal weekdays

·         Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94 dB at 1000 Hz.  If the difference in the calibration level before and after measurement was more than 1 dB(A), the measurement would be considered invalid and repeat of noise measurement would be required after re-calibration or repair of the equipment.

·         The wind speed was frequently checked with a portable wind meter.

·         During the monitoring period, the Leq , L10 and L90 were recorded.  In addition, site conditions and noise sources were recorded on a standard record sheet.

·         Noise measurement was paused during periods of high intrusive noise (e.g. dog barking, helicopter noise) if possible. Observations were recorded when intrusive noise was unavoidable.

·         Noise monitoring was cancelled in the presence of fog, rain, wind with a steady speed exceeding 5 m/s, or wind with gusts exceeding 10 m/s.

Maintenance and Calibration

·         The microphone head of the sound level meter and calibrator is cleaned with soft cloth at quarterly intervals.

·         The meter should be checked and calibrated at yearly intervals.

Monitoring Results

4.5          Ninety-two (92) noise monitoring events were conducted in the reporting period.

4.6          No noise related complaint was received in the reporting period, hence no Action Level exceedance was recorded.

4.7          All measured noise levels were below the Limit level and the graphical plots of trends of the monitoring results are provided in Appendix F.

4.8          Major noise sources during the noise monitoring included the construction activities from the Project, from another project under the same contract (concurrent project) carried out in the vicinity and nearby traffic noise.

 

 

5.    Ecology Monitoring Results

Monitoring Requirement

5.1          As required under Environmental Permit No. EP-235/2005/B, the Permit Holder is required to carry out monitoring of the plant species of conservation interest to check on the health and condition of the plants twice a month during the construction period of the Project.

5.2          It is required to undertake the ecological tasks to fulfill the requirements of the Environmental Permit (EP).  As required by Conditions 2.11 and 3.5 of the EP, a suitably qualified ecologist with 7 or more years of relevant experience shall be employed to conduct the ecological monitoring.

Monitoring Location

5.3          The ecological monitoring was carried out for plant individuals of conservation interest identified within the proposed works area.

Monitoring Methodology

5.4          The ecological monitoring was conducted twice monthly by a suitably qualified local ecologist to check on the health and condition of the plant species of conservation interest. Forty-two (42) ecological monitoring was conducted in the reporting period.

5.5          The plants of conservation interest, which were tagged during the baseline survey, were checked during each monitoring.

Monitoring Results

5.6          A total of 13 plant species of conservation interest (i.e. V001 to V013) were identified within the area during an earlier Detailed Vegetation Survey conducted under this Project.  V001 to V013 were found to be in good condition during the monitoring visits in the reporting period, nevertheless, plastic fencings supported by strong poles were recommended to demarcate plant locations clearly to prevent tipping and entry of personnel in order to avoid damage to the plants. Fencings had been set up in the area during the monitoring visits in May 2008.

5.7          The bark of two individuals of vegetation located adjacent to the temporary conveyor belt was found to be slightly damaged. It was recommended that hessian sacking should be wrapped around the trunk of vegetation to prevent damage during the transportation of construction materials.  The concerned trunks were found to be wrapped during the second visit in May 2008.

5.8          Construction materials such as planks, sand bags and metal rods were found to be placed over or near the lower trunks of some trees.  It was recommended that these materials should be kept in proper place to avoid damage to vegetation within works area.

5.9          Concrete was found spilled over from the soil nailing works zones onto nearby areas.  It was recommended that the concrete should be removed from the soil surface.  The Contractor advised that the concrete will be removed and measures will be implemented to avoid any further spillage.

5.10        The leaves, branches and trunk of a tree (Machilus sp.) located in Row O was found to be covered with sand and mud probably generated from nearby soil nailing works.

5.11        Two trees, Celtis sinensis and Machilus sp., located near the conveyor belt and above Row Q were found to be dead and in very poor condition respectively.  A dead tree (tree tag number T238) was collapsed within works area.  It was recommended that all dead trees found within the construction site should be recorded and reported to relevant departments without delay.

5.12        Two main roots of a big tree (Acacia confusa of tree tag number T247) were cut due to the construction of soil nail number I6.

5.13        The trunk of a tree (tree tag number T344) located next to a soil nailing area in Row O was covered with concrete.

5.14        The lower trunk of Tree No. T5955 adjacent to soil nailing position on Row AF was covered with grout.

5.15        One of the main branches of a plant (Glochidion wrightii) on Soil Nailing Row X was cut to give way to machinery.  The Contractor was advised that trimming of plant within works area is not allowed.

5.16        A proper handrail for site access to the south of Row AF should be set up instead of tying ropes on trees as support.

5.17        Tree No. T611 (Schefflera heptaphylla) on Row R was found to be in very poor condition.  A recently dead tree on Row AF was tipped to one side.

5.18        Vegetation located between Row AO to AU was excessively removed during site clearance.  The plant debris was dumped in the adjacent woodland habitat outside the works area.

5.19        The unpaved area adjacent to the footpath at Row R was utilized as a main site access, soil on this area was found to be heavily eroded to expose the root system of nearby vegetation.  The unpaved area was subsequently covered with sand bags.

5.20        A large number of metal rods were placed outside the soil nailing area.  Some of them were merely supported by shrubs.

5.21        The leaves of vegetation located near the operation of soil nailing were covered with dust.

5.22        A heavy cable of the soil nailing machine was found hanging on tree trunk and branch T6788 and T9795.

5.23        Trunks of trees located above Row AR were not covered with warping for protection while site clearance and scaffolding works were underway.

5.24        Signs of grout leakage on a natural drainage path were recorded.  The hardened grout covered the drainage path between Row AB to Row AQ, and a large amount of the tagged vegetation of conservation interest (Cibotium barometz) was affected.  As most of the tags of the affected individuals were disappeared and leaves were also seriously damaged, it was therefore not able to identify the exact number of affected individuals on site.  However, judging from the extent of the grout leakage, it is believed that vegetation tagged as V022, V023, V024, V025, V026, V027, V028, V029, V030, V031, V032, V033, V034, V035, V036, V037 and V038 were affected.  At the time of monitoring visit, the Contractor was recommended to remove all hardened grout from the vegetation as well as the soil surface immediately.  To prevent further damage to the tagged vegetation, the Contractor was advised to fenced off the vegetation properly and restrict any unauthorized access of site workers to the area.

5.25        The leaves of vegetation located near the operation area of soil nailing works were covered heavily with dust and were subsequently washed by soil nail contractor upon request.  Some of the fabric shields next to the soil nailing machine were found to be worn out.

5.26        A major site access near Row AF was not clearly demarcated and vegetation was removed to give way to the access.

5.27        Most of the harden grout from the previous leakage incident in December 2008 covering on the vegetation and soil surface had been removed by the Contractor. Four individuals vegetation of conservation interest tagged as V015, V016, V017 and V018 were missing. It was believed that they were covered by the leaked grout and removed during the cleaning process. To prevent further damage to the tagged vegetation, the Contractor was advised to fenced off the vegetation properly and restrict any unauthorized access of site workers to the area.

5.28        The leaves of vegetation located near the operation area of soil nailing works were covered heavily with dust and were subsequently washed by the Contractor upon request.

5.29        A large area of leaked grout and muddy run-off was found in most soil nailing works areas.  The plant species of conservation interest (such as V022 to V035) located within these areas were almost wiped out and cannot be located on site during the monitoring visits.

5.30        The leaves of vegetation located near the operation area of soil nailing works were covered heavily with dust and were subsequently washed by the Contractor upon request.

5.31        Fencing of a vegetation of conservation interest (V059) was worn out.  A lower branch of the tagged vegetation was carelessly pressed down by scaffolding materials near an assess road.  Damage of the tagged vegetation was sighted.  The Contractor was advised to fenced off the vegetation properly with a clear signage notable to all the construction workers and restrict any unauthorized access to the area.

5.32        Electric cable wires were found hanging on tress or being tied to small branches of vegetation/tree within the construction site.  The Contractor was recommended to hang the cable wires on or along the engineering scaffold instead of on the body part vegetation/tree to prevent mechanical damage to the vegetation/tree.

5.33        Three individuals of vegetation of conservation interest in Group V015, V016 and V017 had been identified and tags tied back during the 28 April 2009 visit.  The Contractor agreed to fence off two of the individuals which were located outside the existing fence-off area.  The Contractor was also advise to erect a clear sign notable to all the construction workers and restrict any unauthorized entry to the area.

5.34        Another two vegetation of conservation V018 and V035 could not be located during the monitoring visits, The Contractor advised the concerned vegetation were probably covered up under the temporary storage platform and scaffolding, the Contractor agreed to identify the missing individual once the platform has been removed from the site. 

5.35        Hardened grout was found in the natural habitat near the Project area.  To prevent the plant from being affected by grout leakage and muddy site run-off, the Contractor was reminded to remove any grout from the natural habitat as soon as possible and add sand bags around the hardened grout.

5.36        Sign of oil / lubricant spillage was observed from soil nailing machine on the nearby vegetation.  The Contractor was recommended to remove any soil nailing machine from the vegetation.

5.37        Part of the plant species of conservation interest were not properly fenced off or tagged, particularly in works area above Row AD.  The Contractor was advised to fence off and label the vegetation properly with a clear sign notable to all the construction workers and restrict any unauthorized access to the area.

5.38        During monitoring visit on 2 June 2009, a number of vegetation of conservation interest were missing from site, including V057, V058, V063, V056, V054, V055, V052, and V042.  And some others were not fenced off, including V065, V051, V053, V048, V049, V050, V043, V044, V045, V046, and V047.  The missing vegetation were subsequently found and tagged in 23 June 2009 visit apart from V054.  The eleven unprotected were also fenced off.

5.39        A vegetation of conservation V018 was found to be in very poor condition.  

5.40        Soil of natural terrain along an access road (near Row AH) was not well covered.

5.41        During monitoring visit on 7 July 2009, the previously missing vegetation of conservation interest V054 were located and tagged.  However, another two individuals V086 and V088 were not properly fenced off.

5.42        A vegetation of conservation V018 located during the May 2009 monitoring visit was still in very poor condition. 

5.43        Soil of natural terrain along an access road (near Row AH) was not well covered.

5.44        General refuse was accumulated within demarcated area with vegetation of conservation interest. The Contractor was reminded to remove the general refuse.

5.45        Sandbags and stones were observed piled against a few trees. The Contractor was requested to keep the sandbags and stones away from the trees.

5.46        During the inspections in December 2009, it was observed that shrubs had been planted within the within the impacted areas under this Project to compensate for the loss of understorey vegetation of the woodland habitat due to the construction of landslide preventive works.

 

 

 

6.    Landscape and Visual Audit Results

Monitoring Requirement

6.1          During the construction phase of the Project, landscape and visual monitoring was carried out bi-weekly by a Registered Landscape Architect (RLA) to check if the design, implementation and maintenance of the landscape and visual mitigation measures are fully realized.

6.2          Bi-weekly landscape and visual audit was conducted by a Registered Landscape Architect (RLA) to monitor the implementation of landscape and visual mitigation measures. Forty-six (46) landscape and visual audits were conducted in the reporting period.

Monitoring Results

6.3          The bark of existing tree T254 was damaged by the works as no tree protection was provided.  The Contractor was requested to carry out tree protection works for the tree as soon as possible.

6.4          The tree bark of one existing was damaged by the erection of the temporary conveyor / pulley system on the slope just immediately outside of the site boundary of Landslide Preventive Works.  The Engineer was requested to clarify if it is considered part of the soil nail works.

6.5          An existing dead tree was partially uprooted and fallen over.  The Contractor was requested to clear the dead tree for safety consideration.

 

6.6          One of the temporary shelter areas was installed against some branches of an existing tree.  The Contractor was requested to re-adjust the temporary shelter to clear of the tree branches so as not to cause damage to the tree.

6.7          The wrapping of hessian for the tree protection of some of the trees had been wrapped with two tree trunks together.  The Contractor was reminded to individually wrap the trees and not to force the tree trunks together.

6.8          Overhead plastic sheets for rain shelter were tied to existing tree branches.  The Contractor was reminded that the trees should not be used for temporary anchoring of works and to untie from tree branches as soon as possible.

6.9          The construction of some of the soil nail drilling platforms surrounds existing trees, which was protected with only hessian clothes.  The Contractor was requested to provide more protection to these trees by the use of wooden slats strapping around the trunks to prevent accidental damage to tree barks by heavy equipment / tools during the drilling works.

6.10        Minor damage to the tree bark at the base of one tree on slope was observed.  The Contractor was reminded to be more carefully when carry out works near existing trees.

6.11        Construction equipments, metal pipes / steel bars were observed stockpiled against the tree trunks of existing trees at several locations on site.  The Contractor was requested to clear the equipment and construction materials and not to place them against trees in future in order to prevent damage to the trees.

6.12        Soil bags, construction waste and materials were observed placed on slopes and rested at the base of the tree trunks.  The Contractor was requested to clear the soil bags away from the base of the tree as soon as possible.

6.13        Sealing of the root wounds for tree T247 was still outstanding.  The Contractor was reminded to apply protective sealant to prevent the roots from rotting as soon as possible.

6.14        A number of minor tree branches were observed damaged by typhoon. The Contractor was requested to prune the broken tree branches back to living tissues as soon as possible.

6.15        A couple of dead trees, including a tree with rotten trunk at the base were observed near existing tree T534. The Contractor was recommended to remove all the dead and dying trees away from the footpath area for the safety of workers.

6.16        Many of the trees numbers were obscured by recently wrapped hessian tree protection.  The Contractor was requested to re-instate the tree numbers on existing trees for ease of identification.

6.17        The leaves of existing tree T611 were wilted due to dry soil condition.  The Contractor was recommended to water the tree on a daily basis and to monitor the condition of the tree.

6.18        It was still observed that the Contractor had not removed the dead trees, including a tree with rotten trunk at the base located near existing tree T534.  The Contractor was recommended to remove all the dead and rotten trees away from the footpath area for safety.

6.19        The leaves of previously wilted tree T611 had dried out and was dead eventually. The Contractor was recommended to seek Engineer’s agreement on the replacement planting.

6.20        It was observed that the Contractor had tied the toe board onto the existing tree trunk.  The Contractor was requested to remove it as soon as possible.

6.21        Rectification of many of the tree identification numbers for the existing retained trees was outstanding.  The Contractor was reminded to re-instate the tree numbers on existing trees for ease of reference as soon as possible.

6.22        Existing trees T516, T517, T666, and T698 immediate outside of works area boundary were missing and clarification of the status of existing trees T516, T517, T666, and T698 was outstanding.  The Contractor was requested to clarify the status of the missing trees for information and record.

6.23        Several undersized existing trees were broken.  The Contractor was reminded to be more careful in order to minimize damage on trees in future.

6.24        The Contractor had pruned some of the existing tree branches to facilitate soil nailing works.  However, as required under the contract Particular Specification, the Contractor shall seek the Engineer’s agreement prior to carry out any tree pruning works.  Therefore, the Contractor was reminded to seek Engineer’s agreement for pruning of existing trees in future.

6.25        Some excavated rocks for soil nail heads were piled against the based of an existing tree. The Contractor was reminded to clear the rocks away from the tree as soon as possible.

6.26        A tree was observed with its branch hacked off and left with scars.  The Contractor was reminded that pruning of tree branch requires permission from the Engineer and that pruning of tree branch shall be carried out by approved landscape contractor.

6.27        The Contractor had used an existing tree as support to tie the large hose.  The Contractor was requested to remove the hose from the tree as soon as possible.

6.28        The tree bark of an existing tree with protective hessian wrappings was damaged by scrapings from the moving of pipe sleeves for stock piling nearby. The Contractor was requested to provide better tree protection and to ensure moving of equipments and materials do not damage existing trees.

6.29        It was observed that some excavation for soil nail heads concreting area was larger than necessary, causing unnecessary damage to the existing tree roots.  The Contractor was reminded that the excavation of soil nail areas should be kept to the minimum to minimize damage to the existing trees.

6.30        It was found that a termite tube had infected the dead tree T511 at the corner of footpath stair.  The Contractor was request to urgently remove the infected dead tree for consideration of safety of the workers and the public in future.

6.31        It was observed that electrical cables were strung overhead and hanged from tree branches.  The Contractor was requested to remove the electrical cables away from the trees as soon as possible.

6.32        It was observed that the Contractor had tied safety ropes around the base of several existing trees for the works.  The Contractor was reminded that the practice was not acceptable and was requested to remove the ropes as soon as possible.

6.33        It was observed that soil was compacted against the base of a small existing tree on the upper slope side and used as passage area.  The Contractor was reminded the practice was unacceptable and the compacted soil is to be removed and constructed with proper passage without affecting the existing tree if required.

6.34        It was observed that the Contractor had tied ropes to the base of existing tree T668 for support of the large air hose.  The Contractor was requested to remove the rope from the base of the tree.

6.35        It was observed that an existing tree on the slope which had partially grown above an existing boulder was undermined by the recent removal of the boulder due to engineering safety considerations.  The tree root system was partially undermined and exposed, which would lead to dry-out and possible collapse during strong winds and typhoons.  The Contractor was recommended to back-filled the pit and compact the slope surface area to stabilize the tree.

6.36        It was observed that the make-shift materials conveyor system had its edge board encircled an existing tree, with the tree trunk being easily damaged by the conveyor ‘boat’.  The Contractor was requested to rectify the edge board to ensure that conveying of materials would not damage the tree trunk.

6.37        It was found that a couple of rubber air hoses had been rubbed against a tree trunk leaving black marks.  The Contractor was requested to relocate the hoses away from the tree.

6.38        It was observed a side branch of tree T608 overhanging the footpath was structurally cracked.  The Contractor was requested to prune and remove the damaged tree branch for safety and healthy growth of the tree.

6.39        It was noted several trees were broken by recent strong winds and Typhoon Molave.   The Contractor was reminded to report damaged trees to the Engineer for record

6.40        Nearing completion of the construction of the Project, for safety consideration when to area is to be re-open for the general public use, it is recommend that the side branch of existing tree T678 overhanging the footpath with its low headroom be pruned back to prevent any possible accidents in future.  Also, the dead tree T612 with half broken branch along the footpath is also recommended to be removed.

 

 

7.    Environmental Site Inspection

7.1          Ninety-one (91) site inspections were conducted in the reporting period to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. The major concerns for the Project are air quality, noise, water quality, waste management, ecology and landscape and visual. Observations recorded are summarized below. All the observations were rectified by the Contractor within the agreed time frame.

Air Quality

7.2          The soil nail workstation at Row O was not fully enclosed. Although immediate action had been taken to provide tarpaulin sheet for covering the soil nail extraction outlet, the Contractor was still reminded to fully enclose the workstation.

Noise

7.3          No adverse observation was identified during the course of the construction period of the Project.

Water Quality

7.4          Construction waste, deposited silt, debris, leaves were accumulated inside the u-channels. The Contractor was reminded to remove the waste, silt, debris and leaves regularly and properly maintain the drainage system.

7.5          Exposed earth surface was observed on the slope above Row H. The Contractor was reminded to cover the slope and provide bunding along the edge of the u-channel under the slope to prevent muddy runoff prior to clearing the mud.

7.6          Minor muddy water was observed running down the u-channel near Row K and Row M. The Contractor was reminded to clear the exposed earth at all working platforms and properly maintain the desilting tank next to Row D. The Contractor was also reminded not to spray water directly on exposed earth and make sure the effluent would be treated before discharged to public drain.

7.7          Exposed earth was observed around the area of soil nail installation and on the slope of the site area. The Contractor was advised to clean up the earth as soon as the soil nail operation was completed.

7.8          Some sand bags were found damaged. The Contractor was advised to replace the sand bags.

7.9          Exposed slope was observed below Row R. The Contractor was advised to compact the loose sediment on the slope and/or to cover the slope with tarpaulin sheets.

7.10        Loose sediment was observed accumulated on the slope above Row AI, and on the platform at Row X, Row AF and Row AH. The Contractor was reminded to clear the sediment regularly and as soon as the soil nailing operation finishes.

7.11        Sediment was observed accumulated in the sand trap at Row C. The Contractor was advised to clear the sediment more frequently especially during rainy seasons.

7.12        Stagnant water was observed accumulated in a soil nail head at Row AA. The Contractor was reminded to clear the stagnant water.

 

Chemical and Waste Management

7.13        Oil stain was found on ground under drill rig. The Contractor was reminded to clear the oil stain, provide a drip tray, and properly maintain the plants on site to prevent leakage

7.14        Chemical containers and oil containers were placed on ground without drip tray. The Contractor was reminded to provide drip tray to all chemicals on site.

7.15        Stockpile of C&D waste and C&D materials were found at working platforms and scattered on the slope. The Contractor was reminded to clear the C&D waste off-site regularly and to collect and recycle the useful materials.

7.16        Soil nail installation controllers were found without drip trays. The Contractor was reminded to provide drip trays to the plants on site.

 

7.17        Small amount of cement slurry was found run off into the u-channel at Row R. The Contractor was reminded to clean up the slurry inside the u-channel and prevent further runoff.

7.18        Some cement slurry was observed on the platform of Pullout 16 and observed dripping to the slope below. The Contractor was requested to properly clean up the slurry.

7.19        Stagnant water was observed inside uncovered chemical containers. The Contractor was advised to pour off the stagnant water and dispose of as chemical waste, and properly cover all chemical containers on site.

7.20        Cement powder was observed scattered on working platform. While immediate action by Contractor to clear the cement powder into sand bags, the Contractor was still reminded to properly handle all chemicals on site.

7.21        A hole was found on a drip tray and oily water was running out. The Contractor was requested to fix the drip tray as soon as possible.

7.22        A drip tray of a soil nailing controller was observed accumulated with oily water. The Contractor was reminded to remove the oily water frequently and treat it as chemical waste.

 

Ecology

7.23        Refer to Section 5.

 

Landscape and Visual

7.24        Refer to Section 6.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

8.    Advice on Solid and liquid Waste Mangement Status

 

8.1          The Contractor was registered as a chemical waste producer for this Project. The Chemical Waste Storage Area located at the Contractor’s site office area was properly maintained in the reporting period.

8.2          As advised by the Contractor, 40.5 ton and 400.82 ton of inert C&D waste were disposed offsite to Public Filling Barging Point at Quarry Bay and Chai Wan respectively, while 197.98 ton of non-inert C&D waste was disposed offsite to SENT landfill in the reporting period. Also 20kg of chemical waste was collected by licenced waste collector. C&D waste generated was reused on site as much as possible.

 

9.    Summary of Non-Compliance (Exceedances) of Environmental Quality

 

9.1          There was no 1-hr TSP, 24-hr TSP and noise monitoring exceedance recorded during the course of the construction period of the Project.

9.2          No noise related complaint was received in the reporting period, hence no Action Level exceedance of noise was recorded.

 

 

 

10. Environmental Complaints, Notification of Summons and Successful Prosecution

 

10.1        EPD referred two (2) complaints, one on 15 May 2009 and one on 19 May 2009, from residents nearby Po Shan Mansions, regarding construction dust emission from the slope work at Po Shan Road. Through on-site investigation on 19 May 2008, construction dust could potentially be generated from soil nail drilling works of the Project. Although all the 1-hr and 24-hr TSP monitoring results in May 2009 did not exceed the Action levels, the Contractor was recommended to improve mitigation measures to prevent dust emission as far as possible, such as enhancement of tarpaulin enclosures and watering facilities, during soil nail drilling works. EPD had inspected the site on 22 May 2009 and had no adverse comment on the dust control measures carried out on site. During follow-up site inspections by ET on 26 May 2009, enhanced mitigation measures were taken by the Contractor and no significant construction or fugitive dust was observed.

10.2        No notification of summons and prosecution was received during the course of the construction period of the Project.

10.3        A summary record of the complaints, notification of summons and successful prosecutions is annexed in Appendix G

 

      

11. Comparison of EM&A Data with EIA Prediction

 

11.1        The environmental monitoring data collected during the construction period were generally well below the Action and Limit levels, so the monitoring results were within acceptable levels which is consistent with the EIA prediction.

 

 

 

12. Review of Effectiveness and Efficiency of the Monitoring Methodology and Mitigation Measures

 

12.1        The environmental monitoring results indicated that the construction activities were in compliance with the relevant environmental requirements and were environmentally acceptable. The effectiveness and efficiency of the monitoring methodology and mitigation measures were considered high as evidenced by a small number of complaints and no monitoring exceedances.

 

 

13. Recommendations on the EM&A Programme

 

13.1        The impact air quality and noise monitoring programme ensured that any environmental impact to the receivers would be readily detected and timely actions could be taken to rectify any non-compliance.    The ecological monitoring, bi-weekly landscape and visual audit and weekly site inspection ensured that all the environmental mitigation measures recommended in the EIA report were effectively implemented.

13.2        The EM&A programme effectively monitored the environmental impacts from the construction activities and no particular recommendation was advised for the improvement of the programme.

 

 

 

 

14. Conclusions

 

14.1        The construction of the Project and the EM&A programme commenced on 1 April 2008. The termination of the construction phase EM&A programme of the Project was approved by EPD on 31 December 2009.

14.2        Air quality and noise monitoring, ecological monitoring, bi-weekly landscape and visual audit and weekly site inspection were carried out from April 2008 to December 2009, in accordance with the EM&A Manual.

14.3        No Action and Limit level exceedance or non-compliance was recorded for the monitoring works during the course of the construction period of the Project.

14.4        Two (2) environmental complaints, but no summons or prosecution were made against the Project during the course of the construction stage.

14.5        Weekly site inspections and monthly site audits were carried out by ET and Independent Environmental Checker (IEC), respectively, to ensure proper implementation of environmental mitigation measures specified in the EM&A Manual and compliance with environmental legislation. The ecological monitoring and bi-weekly landscape and visual audit ensured that all the environmental mitigation measures recommended in the EIA report were effectively implemented.

14.6        Mitigation measures were implemented by the Contractor to minimize the environmental impacts due to construction activities. Site inspections carried out by ET showed that the Contractor rectified the problems observed and no major environmental deficiency was induced. The environmental performance of the Contractor during the construction period was considered satisfactory.

14.7        The monitoring results and statistics of non-compliance indicated that the EIA process with its recommended mitigation and EM&A programme were effective for minimizing the environmental impacts posed by the Project.

14.8        While the environmental impact of the construction work was minimal as shown through the monitoring and audit programme, the environmental conditions of the Project area had returned to ambient conditions as compared to the baseline conditions, upon the completion of construction of the Project.