Contents
1.1 Purpose of the Report
2.1 Project Area
2.2 Environmental Sensitive Receivers
2.3 Major Construction Activities
2.4 Monitoring Schedule of The Reporting Month
2.5 Status of Environmental Approval Documents
2.6 Community Liaison Group Meeting
2.7 Summary of Non-Compliance With The Environmental
Quality Performance Limits
2.8 Summary of Environmental Complaints
2.9 Summary of Environmental Summons
3 Environmental Issues and Actions
3.1 Previous Environmental Deficiencies and Follow-up
Actions
3.2 Implementation Status on Environmental Protection
Requirements
4.1 Air and Noise
4.2 Water Quality
4.3 POPs Monitoring
4.4 Waste Management
4.5 Cultural Heritage
4.6 Landscape and Visual
4.7 Land Contamination, Hazard to Life and Fuel Spill
Risk
4.8 Ecology
4.9 EM&A Manual
4.10 Baseline Water Quality Monitoring
5.1 Key Issues for the Next Month
5.2 Impact Prediction for the Next Month
5.3 Works and Monitoring Schedule for the Next Month
LIST OF TABLES & FIGURES
Table 2.1 Summary
of Works Undertaken During the Reporting Period
Table 2.2 Period and Cumulative Quantity of
Excavated Marine Sediments
Table 2.3 Summary of Environmental
Licensing, Notification and Permit Status
LIST OF ANNEXES
Annex A Project Location
Annex B Water Quality and Ecological
Sensitive Receivers
Annex C Cumulative Complaints Statistics
Annex D Implementation Programme of
Mitigation Measures
Annex E Landscape and Visual Audit – Site
Inspection Checklist and Photographs
EXECUTIVE
SUMMARY
The construction
works for the Permanent Aviation Fuel Facility resumed on 9 July 2007 and Phase
1a was completed on 20 March 2010.
Construction works for Phase 1b are anticipated to be completed in
August 2010. This forty-fifth monthly Environmental Monitoring and Audit (EM&A)
report presents the EM&A work carried out during the period from 1 July to 31 July 2010 in accordance with the EM&A Manual.
Breaches of all Action and Limit Levels
Dredging work was
completed in December 2009 and there have been no dredging operations
subsequently. Therefore no water quality
monitoring was conducted during the reporting period that required comparison
against Action and Limit Levels.
Complaint Log
No environmental
complaints were received during the reporting period.
Notifications of any Summons
and Successful Prosecutions
No environmental summons or prosecutions were received in this reporting
period.
Reporting Changes
There were no reporting changes in the reporting period.
Future Key Issues
·
Dust
release and suppression; and
·
Water
discharge.
Leighton
Contractors (
The construction works for PAFF commenced in November 2005 based upon
the previous EIA (EIAO Register Number
AEIAR-062-2002) conducted and the Environmental Permit EP-139/2002 granted on the 28th August 2002. Due to minor changes to the detailed layout
of the site and the site boundary, application for Variation to the
Environmental Permit (VEP) (VEP-133/2004)
was submitted to the Director of Environmental Protection (DEP) for
approval. The variation to the EP (EP-139/2002/A) was granted by the EPD in
February 2004.
The decision by
the EPD to grant the above Environmental Permit was, however, subject to a
Judicial Review. The Judicial Review
sided in the favour of the DEP, as did the subsequent Judgement from the Court
of Appeal from the High Court for Judicial Review in March 2005. However, the DEP’s decision to grant the EP
was quashed by the Judgement of the Court of Final Appeal of July 2006.
The construction
works were stopped following the Judgement of the Court of Final Appeal of July
2006. As such, in order to continue with
the construction of the project, the project went through the statutory
procedures under the EIAO again with a new design in order to obtain an
environmental permit. The revised EIA
was submitted in 2007 and the environmental permit (EP-262/2007) was granted in May 2007. EP-262/2007
has been amended to EP-262/2007/A and
issued by the EPD on 30 November 2007. A
further Variation to the Environmental Permit was approved to allow dredging
works to continue until March 2008. As
such, EP-262/2007/A has been amended
to EP-262/2007/B and issued by the
EPD on 27 February 2008.
The construction
works and EM&A requirements were resumed on 9 July 2007 following the
latest requirements of the EP-262/2007/B
and EM&A Manual. Construction of Phase 1a of PAFF was completed
on 20 March 2010 and operations began on 30 March 2010. Construction of Phase 1b of PAFF is
anticipated to be completed in August 2010.
Details regarding the EM&A requirements and changes should refer to
the updated EM&A Manual. For the marine works, all piling activities
were completed before the previous suspension of construction works in 2006.
This is the forty-fifth EM&A Report which
summarizes the monitoring results and audit findings for the EM&A programme
during the reporting period from 1 July to
31 July 2010.
The project area
is in Area 38 of Tuen Mun and the pipelines are located in
2.2
Environmental
Sensitive Receivers
No air and noise
sensitive receivers were identified close to the project area. However, water sensitive receivers and
ecological sensitive receivers were identified in the EIA study, and are shown
in Annex B.
2.3
Major
Construction Activities
A summary of the major
works undertaken in this reporting period is shown in Table 2.1. Initial marine dredging operations were
completed on 23 January 2009 and resumed on 13 November 2009 for pipeline
repair works that were completed on 11 December 2009. No dredging operations were carried out
during the reporting period. Table
2.2 presents the cumulative quantity of excavated materials from
December 2007 up to 31 July 2010. Daily
and cumulative dredging production rates from December 2007 to 31 July 2010 are
illustrated in Figure 2.1.
Table 2.1 Summary
of Works Undertaken During the Reporting Period
Area |
Works
undertaken |
Tuen Mun Area 38 |
·
Tank Farm (Phase 1b) ·
Emergency Vehicle Access (EVA) Road
Construction for Phase 1b |
Table 2.2 Period
and Cumulative Quantity of Excavated Marine Sediments
Type of Excavated
Materials |
Period Bulk Volume (m3) |
Cumulative Bulk Volume (m3)
(from 17 December 2007 to that date) |
From 17
December 2007 to 31 March 2008 |
||
Contaminated
Mud |
71,564 |
71,564 |
Uncontaminated
Mud |
123,953 |
123,953 |
From 1
September 2008 to 23 January 2009 |
||
Contaminated
Mud |
0 |
71,564 |
Uncontaminated
Mud |
149,147 |
273,100 |
From 13
November 2009 to 13 December 2009 |
||
Contaminated
Mud |
7,399 |
78,963 |
Uncontaminated
Mud |
18,561 |
291,661 |
From 14
December 2009 to 31 July 2010 |
||
Contaminated
Mud |
0 |
78,963 |
Uncontaminated
Mud |
0 |
291,661 |
2.4
Monitoring
Schedule of The Reporting Month
No water quality monitoring or other monitoring was
conducted during the reporting period; hence presentation of a monitoring
schedule is not applicable.
2.5
Status of
Environmental Approval Documents
A summary of the relevant permits, licences, and/or
notifications on environmental protection for this Project since July 2007 is
presented in Table 2.3.
Table 2.3 Summary
of Environmental Licensing, Notification and Permit Status
Permit/ Licenses/ Notification |
Reference |
Validity
Period |
Remarks |
Environmental
Permit |
EP-262/2007/B |
Throughout
Project |
Issued
on 27 February 2008 (EP-262/2007/A on
30 November 2007, EP-262/2007
issued on 31 May 2007, EP-139/2002
originally granted on 28 August 2002 and EP-139/2002/A
granted on 24 February 2004 were superseded) |
Chemical
Waste Producer Registration |
WPN 5111-421-L2174-25 |
Throughout
Project |
Issued
on 10 November 2005 |
Notification
of Construction Works under Air Pollution Control (Construction Dust)
Regulation |
H2104/U1D/5542/DG/DH/PL |
Throughout
Project |
Notification
on 6 July 2007 |
Construction
Noise Permit |
GW-RW0676-07 |
21
December 2007 to 19 June 2008 |
For
land-based works including air compressors, breakers, excavators, wheeled
loaders, mobile cranes, concrete lorry mixers, hand-held pokers, bar
benders/cutters, wood saws, grinders, submarine water pump, lorries with crane,
dump trucks, rollers, ventilation fans and generators |
GW-RW0677-07 |
21
December 2007 to 29 February 2008 |
For
marine dredging operation including grab dredger, tug boat, split hopper
barge and motor sampan |
|
GW-RW0678-07 |
21
December 2007 to 18 June 2008 |
For
marine jetty works including concrete pump derrick barges, hand-held
grinders, generators, air compressors, boring machines, water pumps, tug
boat, grout mixers and grout pumps |
|
GW-RW0094-08 |
1
March to 31 March 2008 |
For
marine dredging operation including grab dredger, tug boat, split hopper
barge and motor sampan |
|
GW-RW0312-08 |
04
July 2008 to 22 December 2008 |
For
marine jetty works including concrete pump derrick barges, hand-held grinders,
generators, air compressors, boring machines, water pumps, tug boat, grout
mixers and grout pumps |
|
GW-RW0313-08 |
04
July 2008 to 19 December 2008 |
For
land-based works including air compressors, breakers, excavators, wheeled
loaders, mobile cranes, concrete lorry mixers, hand-held pokers, bar
benders/cutters, wood saws, grinders, submarine water pump, lorries with
crane, dump trucks, rollers, ventilation fans and generators |
|
GW-RW0373-08 |
1
August 2008 to 20 January 2009 |
For
land-based works including air compressors, breakers, excavators, wheeled
loaders, mobile cranes, concrete lorry mixers, hand-held pokers, bar
benders/cutters, wood saws, grinders, submarine water pump, lorries with
crane, dump trucks, rollers, ventilation fans, generators, stirrer, jet
chisel, water jet machine and dehumidifier |
|
|
GW-RW0368-08 |
1
September to 30 November 2008 |
For
marine dredging operation including grab dredger, tug boat, split hopper
barge and motor sampan |
GW-RW0054-09 |
16
February 2009 to 5 August 2009 |
For
land-based and marine works including passenger launch, winch, welding
machine, grinder, generator, power pack, tug boat, crane, air compressor,
roller, hoist and derrick barge |
|
GW-RW0261-09 |
3
July 2009 to 3 November 2009 |
For
land-based and marine works including derrick barge, grinder, crane, tug
boat, drill, welding machine, hopper barge, motor sampan, air compressor |
|
GW-RW0299-09 |
21
July 2009 to 20 January 2010 |
For
land-based works including air compressors, breakers, excavators, wheeled
loaders, mobile cranes, concrete lorry mixers, hand-held pokers, bar
benders/cutters, wood saws, grinders, submarine water pump, lorries with
crane, dump trucks, rollers, ventilation fans, generators, stirrer, jet
chisel, water jet machine and dehumidifier etc |
|
|
GW-RW0459-09 |
26
October 2009 to 28 February 2010 |
For
marine dredging operation including air compressors, derrick barge, tug boat,
mobile crane, hand-held grinder, generator, hand-held drill, winch, welding
machine, motor sampan, grab dredger hopper barge etc |
|
GW-RW0008-10 |
21
January 2010 to 20 July 2010 |
For
the use of powered mechanical equipment for the purpose of carrying out
construction work other than percussive piling and/or the carrying out of
prescribed construction work. For
on-site powered mechanical equipment. |
|
GW-RW0092-10 |
1
March 2010 to 30 April 2010 |
For
the use of powered mechanical equipment for the purpose of carrying out
construction work other than percussive piling and/or the carrying out of
prescribed construction work.
Specifically for Grab dredger, Derrick barge, Tug boat, Motor sampan
and Hopper barge. |
Marine
Dumping Permit |
EP/MD/08-064 |
13
December 2007 to 29 February 2008 |
For
Type 1 – Open Sea Disposal |
EP/MD/08-065 |
13
December 2007 to 12 January 2008 |
For
Type 1d & Type 2 marine disposal |
|
EP/MD/08-071 |
13
January 2008 to 12 February 2008 |
For
Type 1d & Type 2 marine disposal |
|
EP/MD/08-090 |
3
March to 31 March 2008 |
For
Type 1d & Type 2 marine disposal |
|
EP/MD/08-091 |
3
March to 31 March 2008 |
For
Type 1 – Open Sea Disposal |
|
EP/MD/09-018 |
1
September to 30 September 2008 |
For
Type 1d & Type 2 marine disposal |
|
EP/MD/09-032 |
1
October to 31 October 2008 |
For
Type 1d & Type 2 marine disposal |
|
EP/MD/09-017 |
1
September to 30 November 2008 |
For
Type 1 – Open Sea Disposal |
|
EP/MD/09-039 |
1
December 2008 to 31 January 2009 |
For
Type 1 – Open Sea Disposal |
|
|
EP/MD/10-041 |
11
November 2009 to 31 December 2009 |
For
Type 1 – Open Sea Disposal |
EP/MD/10-042 |
11
November 2009 to 10 December 2009 |
For
Type 1 – Open Sea Disposal (Dedicated Site) & Type 2 – Confined Marine
Disposal |
|
Wastewater
Discharge License |
EP760/421/011399/l |
15 March 2006 to 31 March 2011 |
Issued
on 15 March 2006 |
2.6
Community Liaison
Group Meeting
According to the EP requirements, a Community Liaison
Group (CLG) was established within three months of commencement of construction
of the Project. The major duty of the
CLG is to advise on and monitor the proper design, construction and operation
of the Project. The CLG comprises
representatives from Airport Authority, members of Tuen Mun community and
academics. During
the reporting period no meetings were organised by the CLG. The details of the CLG (including Membership and its Terms of
Reference) and the minutes of previous meetings can be found on the Project
website (http://www.paffhk.com).
2.7
Summary of
Non-Compliance With The Environmental Quality Performance Limits
No environmental
non-compliance was found during the reporting period.
2.8
Summary of
Environmental Complaints
No environmental
complaints were received during the reporting period. A summary of environmental complaints since
project commencement is presented in Annex C.
2.9
Summary of
Environmental Summons
No summons was
received in this reporting period. A
summary of legal proceeding since project commencement is presented in Annex C.
3.1
Previous
Environmental Deficiencies and Follow-up Actions
As no environmental
complaints were received over the last reporting period, no follow-up actions
were required.
Site inspections
were carried out by the ET on 7, 13, 20 and 30 July 2010. Overall, the site was in good orderly
manner. Environmental deficiencies and
follow-up actions/mitigation measures were identified during the inspections,
as follows:
Air Quality
·
On 7, 13 and 20 July 2010, the Contractor was reminded to cover or water
the stockpile of sand near the workshop area (Tank 9 area) and ensure all stockpiles
of material and unpaved areas were watered regularly to prevent dust
generation.
Water Quality
·
On 7 and 13 July 2010, a water hose on the EVA road was found to be
leaking. The Contractor was advised to
fix it or turn off the water supply to it.
·
On 13 July 2010, water was found in the drip trays of an air compressor
on the EVA road. The Contractor was
advised to clear the water as soon as practicable.
·
On 13 July 2010, water was found dripping from Fire Services Part No
71289 on the EVA road. The Contractor
was advised to check situation with the Fire Services personnel.
·
On 20 July 2010, the Contractor was requested to provide a drip tray for
a hose pipe near the chemical waste storage facility.
Waste/Chemical Management
·
On 7 and 13 July 2010, general refuse was observed around the Tank Farm
area and outside the bund wall. The
Contractor was reminded to keep site in good condition and dispose of refuse
appropriately.
·
On 7 July 2010, the Contractor was unable to open the locks on the two
chemical waste storage facilities and on 13 July 2010, on one of the
facilities. The Contractor was advised
to replace the broken locks as soon as possible.
·
On 20 and 30 July 2010, chemicals near Tank 12 had no drip
trays/secondary containment measure. The
Contractor was advised to provide drip trays or tarpaulin for all chemicals on
site, to avoid oil leakage.
·
On 30 July 2010, chemical waste was observed near the old site
office. The Contractor was advised to
place the chemical waste in the designated chemical waste storage facility.
General Housekeeping
·
On 13 July 2010, mud from lorry wheels was found on the road by vehicle
entrance to Phase 1a. The Contractor was
advised to clear this as soon as possible.
With the exception of the above observations, the site was in an orderly
manner. The ET will keep track on the
EM&A programme to ensure compliance of environmental requirements and the
proper implementation of all necessary mitigation measures.
3.2
Implementation
Status on Environmental Protection Requirements
The
implementation status of environmental mitigation measures and requirements as
stated in the EIA Report, Environmental Permits and EM&A Manual during the reporting
period is summarized in Annex
D.
Air and Noise monitoring
is not required for the project.
No dredging activities were undertaken during the reporting
period. Water quality monitoring was
therefore not required for the reporting month.
Persistent
organic pollutants (POPs) monitoring was not required since there was no
dredging operation during the reporting month.
According
to EP Condition 3.3, the Contractor’s
Waste Management Plan (Revision 5) (WMP), which has been certified by the ET
and IEC, was submitted to the EPD on 5 November 2008. A further revision (Revision 6) of WMP has
been submitted to ET and is currently under review.
The
Watching Brief Report, verified by the
Independent Environmental Checker, was submitted to the EPD and AMO on 9 May
2008.
The project
construction works began at the end of 2005 and the landscape works began in
mid-2006. In accordance with the Condition 3.8 of Environmental Permit (EP
139/2002/A granted in February 2004),
the Contractor employed Toyo Greenland Co. Ltd (Toyo) to create a detailed landscape plan and this was submitted to
the Director of EPD on 8 February 2006.
This original landscape plan was certified by IEC and ET, and approved
by the Leisure and Cultural Services Department on 6 April 2006 and the
District Lands Office,
Although
construction work was suspended between July 2006 and July 2007, the berm/landscaping
bund was originally populated by vegetation grown during this project
suspension period.
To address Condition 3.4 of the updated
Environmental Permit (EP 262/2007/B) based on
an updated EIA report (Register No.
AEIAR-107/2007), the
Contractor submitted the Landscape Plan, which was certified by ET and IEC, to
the EPD in December 2009. The EPD
provided comments on 4 February 2010.
Following revisions, the Contractor submitted an updated landscaping
proposal for the PAFF project to the Lands Department (who are responsible for
circulating it to other government departments including EPD) in April
2010. The Lands Department then required that the
submission be in compliance with the latest technical circular, so a
resubmission was made, which was verbally approved by the Lands Department at
the end of July 2010.
Planting works
were carried out by Toyo on the berm/landscaping bund with over 1,100 trees
planted by the end of the reporting period([1]). A
tree survey was also conducted in April 2010 and revealed a 100% tree survival rate of the newly
planted trees. Landscaping works were
completed in July 2010 and ECO are now undertaking the landscape maintenance at
PAFF.
According to the EIA report and EM&A Manual, mitigation measures and site inspections are
required during the landscaping/planting works and the weekly site inspections
include general audits on landscape and visual issues to ensure that the site
is in an orderly and acceptable manner.
Operations of
PAFF Phase 1a started on 30 March 2010 and in accordance with the EM&A Manual , Landscape and Visual
(LV) audits of the site will be undertaken once every two months for one year
following this date. According
to the EM&A Manual, the
Bi-monthly Landscape and Visual Audits
During the reporting period, a
All landscape and visual mitigation
measures have been implemented with the exception of:
Full
details of the findings and observations of the
4.7
Land
Contamination, Hazard to Life and Fuel Spill Risk
According to the EIA report and EM&A Manual, mitigation measures and design phase audit are
required to minimise the risk of fuel spill and hazards. In 2007, the
Contractor submitted an updated design audit plan according to the EP
requirements. These were certified and
verified by the ET and IEC respectively and submitted to the EPD on 7 November
2007.
Pursuant to Condition 3.5 of the EP, the Contractor
submitted design drawings and supporting information according to the EP
requirements. The ET and IEC certified
the documents and submitted to the EPD on 7 December 2009. The documents were placed under the EIAO
register on 14 December 2009.
Weekly site
inspections covered the waste management aspects which included measures to
prevent land contamination by chemical waste.
Marine Mammal Monitoring
In accordance to EM&A Manual, following the
completion of PAFF Phase 1a construction activities on 20 March 2010, six days of
post-construction marine mammal monitoring were undertaken. Details of the monitoring methodology and
results are presented and detailed in the Post-Construction
Marine Mammal Monitoring Report, which was certified by the IEC and
submitted to the EPD on 15 April 2010.
The EM&A Manual for the Project was
updated by the ET to include the detailed arrangements of setting up a CLG,
carrying out design audit, and monitoring of Persistent Organic Pollutants during
the dredging phase of construction of the Project. The revised EM&A Manual, which was verified by the IEC, was submitted to
the EPD on 1 April 2009.
4.10
Baseline Water
Quality Monitoring
The Final Baseline Monitoring Report was submitted to the EPD on 20
February 2008 and placed under the EIAO register.
5.1
Key Issues for
the Next Month
Key issues to be
considered in the next month will be:
·
Dust
release and suppression; and
·
Water
discharge.
5.2
Impact Prediction for the
Next Month
Provided that
environmental mitigation measures including good on-site practises are properly
implemented, it is not expected that unacceptable adverse impacts will arise.
5.3
Works and
Monitoring Schedule for the Next Month
Work programme
for the next month includes:
·
Site
works at Phase 1b (construction works for tank farm, drainages, emergency
vehicle access road etc).
Weekly site
inspections of Phase 1b construction site will be undertaken in accordance with
the EM&A Manual and are expected
to no longer be required after August 2010, when Phase 1b is anticipated to get
its Operations Permit.