Project No.: TCS/00512/09

 

 

 

 

 

 

 

 

 

 

DSD Contract No. DC/2009/13

Construction of Sewage Treatment Works at

 

 

 

 

Yung Shue Wan and Sok Kwu Wan

 

 

 

 

Sok Kwu Wan Portion Area

Monthly Environmental Monitoring and Audit (EM&A) Report (No.23) – June 2012

 

 

 

 

 

Prepared For

Leader Civil Engineering Corporation Limited

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Quality Index

Date

Reference No.

Prepared By

Approved By

13 July 2012

TCS00512/09/600/R0515v2

 

 

Nicola Hon

Environmental Consultant

T.W. Tam

Environmental Team Leader

 

 

Version

Date

Description

1

11 July 2012

First Submission

2

13 July 2012

Amended against IEC’s comments on 12 July 2012

 

 

 


Executive Summary

ES.01.     This is the 23rd monthly Environmental Monitoring and Audit (EM&A) Report for Sok Kwu Wan (hereinafter ‘this Report’) for the designated works under the Environmental Permit [EP-281/2007/A], covering a period from 26 May to 25 June 2012 (hereinafter ‘the Reporting Period’).

 

Environmental Monitoring and Audit Activities

ES.02.     Environmental monitoring activities under the EM&A programme in this Reporting Period are summarized in the following table.

 

Issues

Environmental Monitoring Parameters / Inspection

Occasions

Air Quality

1-hour TSP

54

24-hour TSP

18

Construction Noise

Leq(30min) Daytime

16

Water Quality

Marine Water Sampling

12

Inspection / Audit

ET Regular Environmental Site Inspection

4

 

ES.03.     As informed by the Contractor, the marine work of outfall construction has been commenced on 19 July 2011, therefore, water quality was undertaken in this Reporting Period.

 

Breach of Action and Limit (A/L) Levels

ES.04.     No exceedance of air quality and construction noise monitoring were recorded in this Reporting Period.  The statistics of environmental exceedance, NOE issued and investigation of exceedance are summarized in the following table.

 

Environmental Issues

Monitoring Parameters

Action Level

Limit Level

Event & Action

NOE Issued

Investigation

Corrective Actions

Air Quality

1-hour TSP

0

0

0

--

--

24-hour TSP

0

0

0

--

--

Construction Noise

Leq(30min) Daytime

0

0

0

--

--

Water Quality

DO

0

0

0

--

--

Turbidity

0

0

0

--

--

SS

0

0

0

--

--

Note:   NOE – Notification of Exceedance

 

Environmental Complaint, Notification of Summons and Successful Prosecutions

ES.05.     No written or verbal environmental complaint, summons or successful prosecutions were recorded in this Reporting Period.

 

Reporting Change

ES.06.     No reporting change was made in this Reporting Period.

 

Site Inspection by External Parties

ES.07.     No site inspection was undertaken by external parties i.e. Environmental Protection Department (EPD) or Agriculture, Fisheries and Conservation Department (AFCD) within the Reporting Period.

 

Future Key Issues

ES.08.     During wet season, muddy water and other water quality pollutants via site surface water runoff into the sea body within Fish culture zone at Picnic Bay and the Secondary recreation contact subzone at Mo Tat Wan is the key issue of the Project.  Mitigation measures for water quality should be properly maintained to prevent any muddy or sandy runoff from the loose soil surface overflow on the site boundary.

 

ES.09.     Moreover, special attention should be also paid on the dust mitigation measures to avoid fugitive dust emissions from loose soil surface or haul road.  Mitigation measures implemented for control the surface runoff including wheel wash facilities, covering of the loose soil surface or stockpile with tarpaulin sheet, etc., should fully implement.


 

Table of Contents

 

1            Introduction                                                                                                               1

Project Background                                                                                                 1

Report Structure                                                                                                        2

2            Project Organization and Construction progress                           3

Project Organization and Management Structure                                  3

Construction Progress                                                                                           3

Summary of Environmental Submissions                                                       3

3            Summary of Baseline Monitoring Requirements                                 4

Environmental Aspect                                                                                              4

Monitoring Locations                                                                                              4

Monitoring Frequency and Period                                                                    5

Monitoring Equipment                                                                                             6

Equipment Calibration                                                                                             7

Meteorological Information                                                                              7

Data Management and Data QA/QC Control                                                   7

Reporting                                                                                                                         7

Determination of Action/Limit (A/L) Levels                                                     8

4            Impact Monitoring Results - Air Quality                                                   9

5            Impact Monitoring Results – Construction Noise                               10

6            Impact Monitoring Results – Water Qulaity                                            11

7            Ecology                                                                                                                           13

8            Waste Management                                                                                                  14

9            Site Inspection                                                                                                            15

10          Environmental Complaint and Non-Compliance                                  16

11          Implementation Status of Mitigation Measures                                   17

12          Impact Forecast                                                                                                         23

13          Conclusions and Recommendations                                                            24

Conclusions                                                                                                                  24

Recommendations                                                                                                       24

 

 


List of TABLES

 

Table 2-1        Status of Environmental Licenses and Permits

Table 3-1        Summary of EM&A Requirements

Table 3-2        Location of Air Quality Monitoring Station

Table 3-3        Location of Construction Noise Monitoring Station

Table 3-4        Location of Marine Water Quality Monitoring Station

Table 3-5        Action and Limit Levels for Air Quality

Table 3-6        Action and Limit Levels for Construction Noise

Table 3-7        Action and Limit Levels for Marine Water Quality

Table 4-1        Summary of 24-hour and 1-hour TSP Monitoring Results – AM1

Table 4-2        Summary of 24-hour and 1-hour TSP Monitoring Results – AM2

Table 4-3        Summary of 24-hour and 1-hour TSP Monitoring Results – AM3

Table 5-1        Summarized of Construction Noise Monitoring Results at NM1

Table 5-2        Summarized of Construction Noise Monitoring Results at NM2

Table 5-3        Summarized of Construction Noise Monitoring Results at RNM3

Table 5-4        Summarized of Construction Noise Monitoring Results at NM4

Table 6-1        Summary of Water Quality Results – Mid-ebb Tides (Dissolved Oxygen)

Table 6-2        Summary of Water Quality Results – Mid-ebb Tides (Turbidity & Suspended Solids)

Table 6-3        Summary of Water Quality Results – Mid-flood Tides (Dissolved Oxygen)

Table 6-4        Summary of Water Quality Results – Mid-flood Tides (Turbidity & Suspended Solids)

Table 6-5        Summarized Exceedances of Marine Water Quality

Table 8-1        Summary of Quantities of Inert C&D Materials

Table 8-2        Summary of Quantities of C&D Wastes

Table 9-1        Site Observations

Table 10-1       Statistical Summary of Environmental Complaints

Table 10-2       Statistical Summary of Environmental Summons

Table 10-3       Statistical Summary of Environmental Prosecution

Table 11-1       Environmental Mitigation Measures

 

List of Appendices

 

Appendix A    Site Layout Plan – Sok Kwu Wan Portion Area

Appendix B     Organization Structure and Contact Details of Relevant Parties

Appendix C    A Master and Three Months Rolling Construction Programme

Appendix D     Location of Monitoring Stations (Air Quality / Construction Noise / Water Quality)

Appendix E     Monitoring Equipments Calibration Certificate

Appendix F     Event and Action Plan

Appendix G     Monitoring Data Sheet

Appendix H     Graphical Plots of Monitoring Results

Appendix I      Meteorological Information

Appendix J      Monthly Summary Waste Flow Table

Appendix K     Weekly Site Inspection Checklist

Appendix L     Implementation Schedule of Mitigation Measures

Appendix M    Tree Inspection Report

 

 


1    Introduction

Project Background

1.01          The Leader Civil Engineering Corporation Limited (Leader) has been awarded the Contract DC/2009/13 - Construction of Sewage Treatment Works at Yung Shue Wan and Sok Kwu Wan (the Project) by the Drainage Services Department (DSD) on 4 May 2010.  The Project is part of an overall plan approved under a statutory EIA for Outlying Islands Sewerage Stage 1 Phase 2 Package J – Sok Kwu Wan Sewage Collection and Treatment (Register No. AEIAR-075/2003) and Disposal Facilities and Outlying Islands Sewerage Stage 1 Phase 1 Package C – Yung Shue Wan Sewage Treatment Works and Outfall (Register No. EIA-124/BC).  The Environmental Permit (EP) No. EP-281/2007 and EP-282/2007 for the Project have been obtained by the DSD on 29 June 2007 for the relevant works.  After July 2009, EP-281/2007/A stead EP-281/2007 is EP for Sok Kwu Wan relevant works.

 

1.02          The Project involves construction of sewage treatment works at Sok Kwu Wan and Yung She Wan with a capacity of 1,430m3/day and 2,850m3/day respectively to provide secondary treatment, construction of 2 pumping stations at Sok Kwu Wan and 1 pumping station at Yung Shue Wan, construction of submarine outfall from the coastline and lying of underground sewerage pipeline.  The site layout plan for the captioned work under the Project is showing in Appendix A.

 

1.03          According to the Particular Specification (PS) and Appendix 25 of the Project, Leader should establish an Environmental Team (ET) to implement the environmental monitoring and auditing works to fulfill the requirements as stipulated in the Environmental Monitoring and Audit (EM&A) Manual.  This EM&A Manual is referred to the Appendix B of the Review Report on EIA Study – Sok Kwu Wan (Final) in January 2007 (Agreement No. CE 20/2005(DS)).

 

1.04          Action-United Environmental Services and Consulting (AUES) has been commissioned by Leader as the ET to implement the relevant EM&A programme.  Organization chart of the Environmental Team for the Project is shown in Appendix B.  For ease of reporting, the proposed EM&A programme for baseline and impact monitoring is spilt to following two stand-alone parts:

(a)    Proposed EM&A Programme for Baseline and Impact Monitoring – Sok Kwu Wan (under EP No. 281/2007/A varied on 23 September 2009)

(b)    Proposed EM&A Programme for Baseline and Impact Monitoring – Yung Shue Wan (under EP No. 282/2007)

 

1.05          According to the EM&A Manual of Sok Kwu Wan and Yung Shue Wan, baseline water quality monitoring should be carried out for consecutive six months before the marine work commencement.  Therefore, the baseline reports of Sok Kwu Wan and Yung Shue Wan are divided to two volumes i.e. the Volume 1 for air quality and noise monitoring; and the Volume II for water quality monitoring for separate submission.

 

1.06          There is a concurrent DSD contract “DC/2007/18 Yung Shue Wan and Sok Kwu Wan Village Sewerage, Stage 1 Works undertaking at Sok Kwu Wan since April 2008.

 

1.07          Consider that the construction works of DC/2007/18 and DC/2009/13 at Sok Kwu Wan is under the same Environmental Permit and EM&A Manual, the performance criteria of air quality and construction noise at Sok Kwu Wan under the Project is recommended to adopt the Action/Limit Levels established by contract DC/2007/18.  The Baseline Monitoring Report Volume 1 under the Project for air quality and noise at Sok Kwu Wan was submitted on 9 July 2010 and verified by IEC and for EPD endorsement before the relevant land works commencement on 27 July 2010.

 

1.08          This is the 23rd monthly EM&A Report – Sok Kwu Wan Portion Area presenting the monitoring results and inspection findings for the Reporting Period from 26 May to 25 June 2012.


Report Structure

1.09          The Monthly Environmental Monitoring and Audit (EM&A) Report – Sok Kwu Wan is structured into the following sections:-

Section 1    Introduction

Section 2    Project Organization and Construction Progress

Section 3    Summary of Monitoring Requirements

Section 4    Air Quality Monitoring Results

Section 5    Construction Noise Monitoring Results

Section 6    Water Quality Monitoring Results

Section 7    Waste Management

Section 8    Site Inspections

Section 9    Environmental Complaints and Non-Compliance

Section 10  Implementation Statues of Mitigation Measures

Section 11  Impact Forecast

Section 12  Conclusions and Recommendation

 


2    Project Organization and Construction progress

            Project Organization and Management Structure

2.01            Organization structure and contact details of relevant parties with respect to on-site environmental management are shown in Appendix B.

 

            Construction Progress

2.02            The master and three month rolling construction programme are enclosed in Appendix C and the major construction activities undertaken in this Reporting Period are listed below:-

l             Construction of Pumping Station No. 1& 2

l             Dredging of SKW Submarine Outfall

 

            Summary of Environmental Submissions

2.03            Summary of the relevant permits, licences, and/or notifications on environmental protection for this Project in this Reporting Period is presented in Table 2-1.

 

Table 2-1         Status of Environmental Licenses and Permits

Item

Description

License/Permit Status

1

Air Pollution Control (Construction Dust) Regulation

Notified EPD on 19 May 2010

Ref.: 317486

2

Chemical Waste Producer Registration

Issued on 8/6/2010

WPN 5213-912-L2720-01

3

Water Pollution Control Ordinance

Approved on 29/9/2010

Valid to: 30/09/2015

Licence no.: WT00007567-2010

4

Billing Account for Disposal of Construction Waste

Issued on 26 May 2010

A/C No: 7010815

5

Construction Noise Permit

Permit no. GW-RS0284-12

Valid from: 26 Mar 2012

Until: 25 Sep 2012

 

2.04            The “Baseline/Impact Monitoring Methodology (TCS00512/09/600/R0010Ver.4)” was set out in accordance with the Sok Kwu Wan EM&A Manual’ requirements.  It was approved by the Engineer Representative (ER) and agreed with the Independent Environmental Checker (IEC) and then submitted to the EPD on 8 July 2010.

 

2.05            Baseline Monitoring Report - Volume 1 for Sok Kwu Wan (TCS00512/09/600/R0020Ver.3) was verified by the IEC on 12 July 2010 and submitted to EPD on 12 July 2010.

 

2.06            Baseline Water Quality Monitoring Report - Volume 2 for Sok Kwu Wan (TCS00512/09/600/R0182v7) was revised against EPD comments and re-submitted on 11 October 2011.


3    Summary of Baseline Monitoring Requirements

Environmental Aspect

3.01            The EM&A baseline monitoring programme cover the following environmental issues:

Ÿ     Air quality;

Ÿ     Construction noise; and

Ÿ     Marine water quality

 

3.02            The ET implements the EM&A programme in accordance with the aforementioned requirements.    Detailed air quality, construction noise and water quality of the EM&A programme are presented in the following sub-sections.

 

3.03            A summary monitoring parameters for the air quality, noise and marine water monitoring is presented in Table 3-1:

 

Table 3-1         Summary of EM&A Requirements

Environmental Issue

Parameters

Air Quality

     1-hour TSP Monitoring by Real-Time Portable Dust Meter; and

     24-hour TSP Monitoring by High Volume Air Sampler.

Noise

     Leq (30min) during normal working hours; and

     Leq (15min) during Restricted Hours.

Marine Water Quality

In-situ Measurements

      Dissolved Oxygen Concentration (DO) (mg/L);

      Dissolved Oxygen Saturation (% );

      Turbidity (NTU);

      pH unit;

      Salinity (ppt);

      Water depth (m); and

      Temperature (ºC).

Laboratory Analysis

Ÿ     Suspended Solids (SS) (mg/L)

 

Monitoring Locations

Air Quality

3.04            Three air monitoring stations: AM1, AM2 and AM3 were designated in the EM&A Manual Section 2.5.  The detailed air monitoring stations is described in Table 3-2 and graphical is shown in Appendix D.

 

Table 3-2         Location of Air Quality Monitoring Station

Sensitive Receiver

Location

AM1

Squatter house in Chung Mei Village

AM2

Squatter house in Chung Mei Village

AM3

Football court

 

Construction Noise

3.05            According to EM&A Manual Section 3.4, there were four noise sensitive receivers (NM1-NM4) designated for the construction noise monitoring.  NM1, NM2 and NM4 of the three designated monitoring stations were identified and are monitored by the current DSD contract DC/2007/18. However, the premises monitoring station NM3 was rejected by the owner of 1B Sok Kwu Wan and an alternative noise monitoring station RNM3 replacement was proposed by the contract DC/2007/18 ET and accepted by the IEC and EPD before the baseline monitoring commencement in April 2008.  The location RNM3 is located at Sok Kwu Wan Sitting-out area which just 3m width footpath away from the original location house 1B.  The detailed construction noise monitoring stations to also under the Project is described in Table 3-3 and graphical is shown in Appendix D.

 


Table 3-3         Location of Construction Noise Monitoring Station

Sensitive Receiver

Location

NM1

1, Chung Mei Village

NM2

20, Sok Kwu Wan

RNM3

Sok Kwu Wan Sitting-out Area

NM4

2-storey village house at Ta Shui Wan

 

Water Quality

3.06            Three control stations (C1-C3) and three impact stations (W1-W3) were recommended in the EM&A Manual Section 4.5.  Impact stations W1-W3 identified at the sensitive receivers (FCZ and secondary contact recreation subzone) to monitor the impacts from the construction of the submarine outfall as well as the effluent discharge from the proposed STW on water quality.  Three control stations: C1, C2 & C3 were specified at locations representative of the project site in its undisturbed condition and located at upstream and downstream of the works area.  Detailed and co-ordnance of marine water quality monitoring stations is described in Table 3-4 and the graphical is shown in Appendix D and would be performed for EM&A programme.

 

Table 3-4         Location of Marine Water Quality Monitoring Station

Station

Description

Co-ordnance

Easting

Northing

W1

Secondary recreation contact subzone at Mo Tat Wan

832 968

807 732

W2

Fish culture zone at Picnic Bay

832 670

807 985

W3

Fish culture zone at Picnic Bay

832 045

807 893

C1 (flood)

Control Station

833 703

808 172

C2

Control Station

831 467

807 747

C3 (ebb)

Control Station

832 220

808 862

 

Monitoring Frequency and Period

3.07            The impact monitoring carried out in the EM&A programme is basically in accordance with the requirements in EM&A Manual Sections 2.7, 3.6, 4.7 and 4.8.  The monitoring requirements are listed as follows.

 

Air Quality Monitoring

Parameters:      1-hour TSP and 24-hour TSP.

Frequency:        Once in every six days for 24-hour TSP and three times in every six days for 1-hour TSP.

Duration:           Throughout the construction period.

 

Noise Monitoring

Parameters:      Leq 30min) & Leq(5min), L10 and L90.

Leq(15min) & Leq(5min), L10 and L90 during the construction undertaken during Restricted hours (19:00 to 07:00 hours next of normal working day and full day of public holiday and Sunday)

Frequency:        Once per week during 0700-1900 hours on normal weekdays.  Restricted hour monitoring should depend on conditions stipulated in Construction Noise Permit.

Duration:           Throughout the construction period.

 

Marine Water Quality Monitoring

Parameters:

Duplicate in-situ measurements: water depth, temperature, dissolved oxygen, pH, turbidity and salinity;

HOKLAS-accredited laboratory analysis: suspended solids

 

Frequency:

Three days a week, at mid ebb and mid flood tides.  The interval between 2 sets of monitoring will be more than 36 hours.

Sampling Depth

(i.) Three depths: 1m below water surface, 1m above sea bottom and at mid-depth when the water depth exceeds 6m. 

(ii.)     If the water depth is between 3m and 6m, two depths: 1m below water surface and 1m above sea bottom.

(iii.)    If the water depth is less than 3m, 1 sample at mid-depth is taken

Duration:

During the course of marine works

 

Post-Construction Monitoring – Marine Water

3.08            Upon the marine works (dredging and HDD pipe installation) completion, 4 weeks of post-construction monitoring would be undertaken in accordance with the Section 4.8 of EM&A Manual .  The requirements of post-construction monitoring such as the parameter, frequency, location and sampling depth is same as the impact monitoring.

 

Monitoring Equipment

Air Quality Monitoring

3.09            The 24-hour and 1-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.  If the ET proposes to use a direct reading dust meter to measure 1-hour TSP levels, it shall submit sufficient information to the IEC to approve.  The filter paper of 24-hour TSP measurement shall be determined by HOKLAS accredited laboratory.

 

Noise Monitoring

3.10            Sound level meter in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring.  The sound level meter shall be checked using an acoustic calibrator. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m s-1.

 

Water Quality Monitoring

3.11            Dissolved Oxygen and Temperature Measuring Equipment The instrument should be a portable and weatherproof dissolved oxygen (DO) measuring instrument complete with cable and sensor, and use a DC power source. The equipment should be capable of measuring as included a DO level in the range of 0 – 20mg L-1 and 0 – 200% saturation; and a temperature of 0 – 45 degree Celsius.

 

3.12            pH MeterThe instrument shall consist of a potentiometer, a glass electrode, a reference electrode and a temperature-compensating device.  It shall be readable to 0.1 pH in a range of 0 to 14.

 

3.13            Turbidity (NTU) Measuring EquipmentThe instrument should be a portable and weatherproof turbidity measuring instrument using a DC power source. It should have a photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU.

 

3.14            Water Sampling EquipmentA water sampler should comprise a transparent PVC cylinder, with a capacity of not less than 2 litres, which can be effectively sealed with latex cups at both ends. The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth.

 

3.15            Water Depth DetectorA portable, battery-operated echo sounder should be used for the determination of water depth at each designated monitoring station. This unit can either be hand held or affixed to the bottom of the work boat.

 

3.16            Salinity Measuring EquipmentA portable salinometer capable of measuring salinity in the range of 0 - 40 parts per thousand (ppt) should be provided for measuring salinity of the water at each monitoring location.

 

3.17            Sample Containers and StorageWater samples for suspended solids should be stored in high density polythene bottles with no preservative added, packed in ice (cooled to 4°C without being frozen).

 

3.18            Monitoring Position Equipment - A hand-held or boat-fixed type digital Differential Global Positioning System (DGPS) with way point bearing indication and Radio Technical Commission for maritime (RTCM) Type 16 error message ‘screen pop-up’ facilities (for real-time auto-display of error messages and DGPS corrections from the Hong Kong Hydrographic Office), or other equipment instrument of similar accuracy, should be provided and used during marine water monitoring to ensure the monitoring vessel is at the correct location before taking measurements.

 

3.19            Suspended Solids AnalysisAnalysis of suspended solids shall be carried out in a HOKLAS or other international accredited laboratory.

 

            Equipment Calibration

3.20            Calibration of the HVS is performed upon installation in accordance with the manufacturer’s instruction using the NIST-certified standard calibrator (Tisch Calibration Kit Model TE-5025A).  The calibration data are properly documented and the records are maintained by ET for future reference.

 

3.21            The 1-hour TSP meter was calibrated by the supplier prior to purchase.  Zero response of the equipment was checked before and after each monitoring event. In-house calibration with the High Volume Sampler (HVS) in same condition was undertaken in yearly basis.

 

3.22            The sound level meter and calibrator are calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme at yearly basis.

 

3.23            The Water Quality Monitoring equipments such as DO meter, pH meter, turbidity measuring instrument and salinometer, are calibrated by HOKLAS accredited laboratory of three month intervals.

 

3.24            All updated calibration certificates of the monitoring equipment used for the impact monitoring programme in the Reporting Period would be attached in Appendix E.

 

            Meteorological Information

3.25            The meteorological information during the construction phase is obtained from the Wong Chuk Hang Station of the Hong Kong Observatory (HKO) due to it nearly the Project site.

 

            Data Management and Data QA/QC Control

3.26            The impact monitoring data are handled by the ET’s systematic data recording and management, which complies with in-house Quality Management System. Standard Field Data Sheets (FDS) are used in the impact monitoring programme.

 

3.27            The monitoring data recorded in the equipment e.g. 1-hour TSP meter, sound level meter and Multi-parameter Water Quality Monitoring System, are downloaded directly from the equipments at the end of each monitoring day.  The downloaded monitoring data are input into a computerized database properly maintained by the ET.  The laboratory results are input directly into the computerized database and QA/QC checked by personnel other than those who input the data.  For monitoring activities require laboratory analysis, the local laboratory follows the QA/QC requirements as set out under the HOKLAS scheme for all laboratory testing.

 

            Reporting

3.28            It was agreed among the ER, IEC, Contractor and ET that, in order to streamline the EM&A report submission and to cater for the occasional delay in obtaining laboratory analysis results, the cutoff day for each month is the 25th i.e. the first day of each report is the 26th of the last month and the end day, the 25th of that month.

 

            Determination of Action/Limit (A/L) Levels

3.29            According to the Sok Kwu Wan Environmental Monitoring and Audit Manual, the air quality, construction noise and marine water quality were set up, namely Action and Limit levels are listed in Tables 3-5, 3-6 and 3-7 as below.

Table 3-5           Action and Limit Levels for Air Quality

Monitoring Station

Action Level (mg/m3)

Limit Level (mg/m3)

1-hour

24-hour

1-hour

24-hour

AM1

343

173

500

260

AM2

331

175

500

260

AM3

353

191

500

260

 

Table 3-6           Action and Limit Levels for Construction Noise

Monitoring Location

Action Level

Limit Level

0700-1900 hours on normal weekdays

NM1

NM2

RNM3

NM4

When one or more documented complaints are received

75 dB(A) of Leq(30min) during normal hours from 0700 to 1900 hours on normal weekdays, reduced to 70 dB(A) of Leq(30min) for schools and 65 dB(A) during school examination periods

 

Table 3-7           Action and Limit Levels for Marine Water Quality

Parameter

Performance Criteria

Impact Station

W1

W2

W3

DO Concentration (Surface and Middle)

(mg/L)

Action Level

5.39

4.64

4.71

Limit Level

5.29

4.56

4.54

DO Concentration (Bottom)

(mg/L)

Action Level

N/A

3.60

3.37

Limit Level

N/A

3.06

3.18

Turbidity (Depth-Average)

(NTU)

Action Level

4.39

4.84

6.48

Limit Level

6.06

5.99

6.71

Suspended Solids (Depth-Average)

(mg/L)

Action Level

12.41

9.24

10.79

Limit Level

12.68

11.28

12.25

 

3.30            Should non-compliance of the environmental quality criteria occurs, remedial actions will be triggered according to the Event and Action Plan enclosed in Appendix F.


4    Impact Monitoring Results - Air Quality

4.01            The impact EM&A programme was carried out as compliance with the contract Particular Specification, Sok Kwu Wan EM&A Manual and the EP. 

 

Results of Air Quality Monitoring

4.02            In this Reporting Period, 54 and 18 monitoring events were performed for 1-hour TSP and 24-hour TSP monitoring respectively at the designated locations AM1, AM2 and AM3.  The monitoring results for 24-hour and 1-hour TSP are summarized in Tables 4-1, 4-2 and 4-3.  The detail 24-hour TSP data are shown in Appendix G and the graphical plots of are shown in Appendix H.

 

Table 4-1           Summary of 24-hour and 1-hour TSP Monitoring Results – AM1

Date

24-hour TSP (mg/m3)

1-hour TSP (mg/m3)

Date

Start Time

1st hour measured

2nd hour measured

3rd hour measured

26-May-12

14

28-May-12

9:00

59

57

52

1-Jun-12

36

1-Jun-12

8:00

52

55

60

7-Jun-12

24

7-Jun-12

8:00

59

57

57

13-Jun-12

29

12-Jun-12

8:00

79

77

75

19-Jun-12

30

18-Jun-12

11:00

67

69

62

25-Jun-12

30

22-Jun-12

8:00

64

67

69

Average

(Range)

27

(14 – 36)

Average

(Range)

63

(52 – 79)

 

Table 4-2           Summary of 24-hour and 1-hour TSP Monitoring Results – AM2

Date

24-hour TSP (mg/m3)

1-hour TSP (mg/m3)

Date

Start Time

1st hour measured

2nd hour measured

3rd hour measured

26-May-12

36

28-May-12

11:05

55

53

49

1-Jun-12

55

1-Jun-12

11:05

53

59

55

7-Jun-12

49

7-Jun-12

10:15

61

57

53

13-Jun-12

53

12-Jun-12

10:05

68

73

69

19-Jun-12

69

18-Jun-12

13:05

70

74

68

25-Jun-12

30

22-Jun-12

10:05

63

71

65

Average

(Range)

49

 (30 – 69)

Average

(Range)

61

(49 – 74)

 

Table 4-3           Summary of 24-hour and 1-hour TSP Monitoring Results – AM3

Date

24-hour TSP (mg/m3)

1-hour TSP (mg/m3)

Date

Start Time

1st hour measured

2nd hour measured

3rd hour measured

26-May-12

75

28-May-12

13:30

79

74

72

1-Jun-12

77

1-Jun-12

13:30

80

75

81

7-Jun-12

51

7-Jun-12

12:45

97

101

93

13-Jun-12

86

12-Jun-12

12:30

121

127

124

19-Jun-12

109

18-Jun-12

15:30

151

163

156

25-Jun-12

49

22-Jun-12

12:30

167

174

168

Average

(Range)

75

 (49 – 109)

Average

(Range)

117

(72– 174)

 

4.03            As shown in Tables 4-1, 4-2 and 4-3, 1-hour and 24-hour TSP results fluctuated well below the Action Level during the Reporting Period. 

 

4.04            The meteorological information during the impact monitoring days are summarized in Appendix I.


5    Impact Monitoring Results – Construction Noise

5.01            The noise monitoring results are presented in the following sub-sections.

 

Results of Construction Noise Monitoring

5.02            In this Reporting Period, a total of 16 construction noise monitoring events were undertaken at designated location NM1, NM2, RNM3 and NM4.  The results for Leq30min at NM1, NM2, RNM3 and NM3 are summarized in Tables 5-1, 5-2, 5-3 and 5-4 and graphical plots are shown in Appendix H.

 

Table 5-1           Summarized of Construction Noise Monitoring Results at NM1

Date

Start Time

End time

1st Leq5

2nd Leq5

3rd Leq5

4th Leq5

5th Leq5

6th Leq5

Leq30

28-May-12

11:00

11:30

55.8

51.2

51.2

52.7

49.3

50.0

52.3

7-Jun-12

10:15

10:45

62.3

59.3

59.9

66.4

60.0

60.0

62.2

12-Jun-12

11:00

11:30

58.1

54.4

58.7

54.1

48.1

51.5

55.5

18-Jun-12

14:00

14:30

60.3

56.9

55.4

49.0

48.4

49.6

55.5

Limit Level in dB(A)

-

75

 

Table 5-2           Summarized of Construction Noise Monitoring Results at NM2

Date

Start Time

End time

1st Leq5

2nd Leq5

3rd Leq5

4th Leq5

5th Leq5

6th Leq5

Leq30

28-May-12

13:00

13:30

60.0

59.3

57.8

59.7

57.8

56.9

58.7

7-Jun-12

11:00

11:30

63.8

65.8

63.8

60.8

61.0

63.9

63.5

12-Jun-12

11:39

12:09

63.7

64.8

59.3

60.0

58.3

60.8

61.8

18-Jun-12

14:37

15:07

71.7

63.7

63.6

61.2

62.8

60.6

66.0

Limit Level in dB(A)

-

75

 

Table 5-3           Summarized of Construction Noise Monitoring Results at RNM3

Date

Start Time

End time

1st Leq5

2nd Leq5

3rd Leq5

4th Leq5

5th Leq5

6th Leq5

Leq30

Corrected* Leq30

28-May-12

13:45

14:15

58.3

57.7

57.4

57.4

57.5

58.3

57.8

60.8

7-Jun-12

11:40

12:10

62.4

62.7

62.7

62.3

62.4

62.2

62.5

65.5

12-Jun-12

13:00

13:30

62.7

63.5

65.0

63.2

63.9

65.1

64.0

67.0

18-Jun-12

15:15

15:45

56.8

56.9

62.0

64.3

57.3

55.3

60.1

63.1

Limit Level in dB(A)

-

75

* A façade correction of +3dB(A) has been added according to acoustical principles and EPD guidelines.

 

Table 5-4           Summarized of Construction Noise Monitoring Results at NM4

Date

Start Time

End time

1st Leq5

2nd Leq5

3rd Leq5

4th Leq5

5th Leq5

6th Leq5

Leq30

28-May-12

14:30

15:00

54.2

54.2

54.5

54.1

54.2

54.2

54.2

7-Jun-12

13:00

13:30

58.4

57.1

57.1

51.8

52.2

53.2

55.7

12-Jun-12

13:35

14:05

55.0

57.3

57.9

56.6

62.4

54.5

58.2

18-Jun-12

16:00

16:30

60.0

58.5

64.1

56.5

57.3

58.0

59.9

Limit Level in dB(A)

-

75

 

5.03            It was noted that no noise complaint (which is an Action Level exceedance) was received.  During the noise monitoring, external noise sources from traffic road, animals, human, trolley and ventilation system were observed occasionally.  In view of the results shown in Tables 5-1, 5-2, 5-3 and 5-4 which were all below 75dB(A), no Action or Limit Level exceedance was triggered during this month.


6    Impact Monitoring Results – Water Qulaity

6.01           The construction of marine outfall works was commenced on 19 July 2011 and therefore marine water quality monitoring is required in this Reporting Period.  In this Reporting Period, 12 events of water quality monitoring were carried out at the designated locations.

 

6.02           The monitoring results including in-situ measurements and laboratory testing results are presented in Appendix G.  The graphical plots are shown in Appendix H.

 

6.03           During the Reporting Period, field measurements of both control and impact stations showed that marine water of the depth average of the salinity concentration was within 26.64 to 34.58 ppt, and pH value was within 7.19 to 8.17.

 

6.04           Monitoring results of 3 key parameters: dissolved oxygen (DO), turbidity and suspended solids (SS) in this Reporting Period, are summarized in Tables 6-1, 6-2, 6-3 and 6-4.  A summary of exceedances for the 3 parameters are shown in Table 6-5.

 

Table 6-1           Summary of Water Quality Results – Mid-ebb Tides (Dissolved Oxygen)

Sampling date

Dissolved Oxygen conc. of Depth Ave. of Surf. and Mid Layer (mg/L)

Dissolved Oxygen conc. of Depth Ave. of Bottom Layer (mg/L)

W1

W2

W3

C1

C2

C3

W1

W2

W3

C1

C2

C3

26-May-12

6.07

6.51

6.74

5.77

7.06

5.39

NA

6.32

6.36

5.64

6.98

5.42

28-May-12

6.74

7.39

7.10

6.01

5.49

6.43

NA

6.55

7.56

5.82

5.60

6.42

30-May-12

7.09

6.30

7.17

6.25

7.69

6.98

NA

6.11

6.59

6.25

8.35

6.57

1-Jun-12

7.00

6.83

6.60

6.46

7.22

6.63

NA

6.44

6.24

6.15

6.30

6.35

5-Jun-12

6.98

6.92

8.08

7.76

8.27

8.27

NA

6.64

7.38

7.25

7.21

7.21

7-Jun-12

6.12

6.42

5.96

5.97

6.45

6.45

NA

6.56

5.50

5.46

5.46

5.46

9-Jun-12

5.89

6.70

6.88

6.91

6.85

6.85

NA

6.09

6.70

6.35

5.64

5.64

12-Jun-12

6.23

5.23

5.31

4.86

5.22

5.22

NA

4.27

4.67

4.50

5.32

5.32

14-Jun-12

5.50

5.41

5.44

4.88

4.00

4.00

NA

6.42

4.93

4.87

3.55

3.55

16-Jun-12

6.61

6.36

6.48

5.88

4.29

4.29

NA

7.17

5.56

6.14

5.31

5.31

19-Jun-12

5.64

5.46

7.34

6.17

5.57

5.57

NA

5.61

7.90

5.54

8.69

8.69

21-Jun-12

6.02

5.84

5.93

5.10

5.93

5.93

NA

4.86

4.64

5.20

4.60

4.60

 

Table 6-2           Summary of Water Quality Results – Mid-ebb Tides (Turbidity & Suspended Solids)

Sampling date

Turbidity Depth Ave. (NTU)

Suspended Solids Depth Ave. (mg/L)

W1

W2

W3

C1

C2

C3

W1

W2

W3

C1

C2

C3

26-May-12

0.25

1.37

1.12

1.13

1.40

1.62

0.50

0.83

1.40

0.77

1.17

0.53

28-May-12

1.80

2.70

2.73

2.38

0.77

1.60

1.60

4.00

2.20

2.63

3.00

0.93

30-May-12

1.05

1.25

1.90

1.43

1.33

1.78

3.00

1.20

0.50

0.50

0.93

0.50

1-Jun-12

1.60

2.30

1.72

2.07

2.37

1.82

4.30

1.67

3.87

1.27

3.63

2.17

5-Jun-12

1.50

2.10

4.97

2.57

2.35

3.25

2.20

1.97

1.20

1.85

1.33

1.03

7-Jun-12

1.10

1.08

1.50

2.93

1.50

1.78

2.40

3.10

2.93

2.10

3.43

4.33

9-Jun-12

0.50

2.47

0.87

1.33

1.67

1.57

1.80

1.50

6.23

2.00

1.17

4.73

12-Jun-12

2.65

2.28

3.15

2.77

1.50

4.10

0.80

0.50

0.83

1.97

2.00

1.13

14-Jun-12

0.85

2.75

5.52

1.53

1.00

1.85

5.60

4.87

2.37

3.27

2.03

2.80

16-Jun-12

3.90

4.25

5.40

3.48

4.62

3.42

3.40

1.73

2.87

3.93

3.53

3.20

19-Jun-12

3.50

4.10

3.77

7.10

7.10

6.08

2.60

3.63

2.60

8.37

3.63

3.50

21-Jun-12

1.00

1.30

2.60

1.02

1.47

0.97

3.90

2.67

1.83

1.57

1.83

3.60

 

Table 6-3           Summary of Water Quality Results – Mid-flood Tides (Dissolved Oxygen)

Sampling date

Dissolved Oxygen conc. of Depth Ave. of Surf. and Mid Layer (mg/L)

Dissolved Oxygen conc. of Depth Ave. of Bottom Layer (mg/L)

W1

W2

W3

C1

C2

C3

W1

W2

W3

C1

C2

C3

26-May-12

6.50

6.47

6.29

6.24

5.30

4.99

NA

6.07

5.84

5.83

4.85

4.81

28-May-12

5.81

6.73

6.06

5.63

6.50

5.33

NA

6.01

5.75

5.02

6.63

4.96

30-May-12

6.91

7.03

6.64

7.48

6.66

7.13

NA

6.60

6.97

7.33

6.98

7.12

1-Jun-12

7.33

6.39

6.05

6.51

6.22

5.80

NA

7.31

6.05

6.06

6.19

5.99

5-Jun-12

7.86

6.80

7.48

7.09

6.69

6.95

NA

6.00

6.73

6.69

7.86

6.47

7-Jun-12

5.91

5.94

5.52

6.11

5.08

5.92

NA

5.07

5.65

5.08

6.58

5.42

9-Jun-12

7.47

7.23

6.78

7.11

7.49

6.59

NA

6.92

7.48

7.49

6.43

6.64

12-Jun-12

5.47

5.65

5.46

6.71

6.45

6.53

NA

6.75

5.32

6.45

4.18

5.52

14-Jun-12

5.77

5.04

5.00

5.32

4.50

5.13

NA

4.01

4.37

4.50

3.52

5.22

16-Jun-12

6.18

6.19

6.74

7.30

7.31

6.39

NA

5.44

6.87

7.31

5.89

6.91

19-Jun-12

6.42

7.01

6.75

6.26

7.22

6.53

NA

6.47

6.90

7.22

4.97

5.57

21-Jun-12

6.55

5.70

6.11

6.72

5.43

6.65

NA

4.82

5.46

5.43

5.24

4.17

 

Table 6-4           Summary of Water Quality Results – Mid-flood Tides (Turbidity & Suspended Solids)

Sampling date

Turbidity Depth Ave. (NTU)

Suspended Solids Depth Ave. (mg/L)

W1

W2

W3

C1

C2

C3

W1

W2

W3

C1

C2

C3

26-May-12

1.45

1.07

1.20

0.75

1.38

0.85

1.10

1.17

2.23

1.27

0.63

0.67

28-May-12

1.70

1.13

0.90

1.82

1.55

1.68

0.50

0.73

1.27

1.17

1.70

1.63

30-May-12

0.65

1.67

2.25

1.15

2.85

1.23

0.50

0.50

0.50

0.50

0.50

0.53

1-Jun-12

1.75

2.95

1.78

1.72

1.60

1.93

2.50

2.23

1.30

5.90

2.47

4.40

5-Jun-12

1.65

1.95

2.47

2.42

2.27

1.83

0.90

1.67

4.20

3.07

2.53

1.83

7-Jun-12

0.90

2.68

1.82

1.45

1.58

1.17

1.90

3.03

3.53

4.30

2.57

2.33

9-Jun-12

0.70

1.02

1.42

1.45

0.48

1.05

1.60

4.30

1.80

2.07

2.67

2.97

12-Jun-12

1.90

2.82

4.12

3.13

3.67

3.87

1.10

0.73

7.07

0.90

1.10

0.57

14-Jun-12

1.80

2.83

2.78

2.12

4.68

2.47

3.60

2.37

4.50

4.57

5.10

3.37

16-Jun-12

2.00

3.20

3.80

4.08

4.07

3.62

3.40

3.03

2.40

2.70

3.20

2.47

19-Jun-12

3.05

4.70

6.23

5.78

4.57

6.97

3.90

5.90

5.47

6.57

2.97

6.43

21-Jun-12

1.45

1.30

1.22

1.40

2.10

0.83

4.40

2.97

4.23

3.77

3.60

4.13

 

Table 6-5           Summarized Exceedances of Marine Water Quality

Station

DO

(Ave of Surf. & mid-depth)

DO (Ave. of Bottom Layer)

Turbidity

(Depth Ave.)

SS

(Depth Ave)

Total Exceedance

Action

Limit

Action

Limit

Action

Limit

Action

Limit

Action

Limit

Mid-Ebb

W1

0

0

0

0

0

0

0

0

0

0

W2

0

0

0

0

0

0

0

0

0

0

W3

0

0

0

0

0

0

0

0

0

0

Mid-Flood

W1

0

0

0

0

0

0

0

0

0

0

W2

0

0

0

0

0

0

0

0

0

0

W3

0

0

0

0

0

0

0

0

0

0

No of Exceedance

0

0

0

0

0

0

0

0

0

0

 

6.05           For marine water monitoring, no exceedance of Action/Limit levels was recorded in this Reporting Period.  Therefore, no associated corrective actions were then required.

7    Ecology

7.01           According to Clause 3.7 and Figure 4 in the Environmental Permit No. EP-281/2007/A, a total of 12 numbers Celtis Timorensis (uncommon species) in Chung Mei at Sok Kwu Wan, are identified to require labeling, fencing and protection.  Out of these, four numbers located in the Pumping Station No.1 area are required to be transplanted in advance of pumping station construction and the transplantation proposal has been submitted to EPD previously.

 

7.02           Regular inspection of the transplanted tree was carried out by the landscaping sub-Contractor (Melofield Nursery and Landscape Contractor Limited) on 31 May and 15 June 2012.  As a contingency measure in case that CT7 to CT10 can no longer be recovered, additional 7 no. of Celtis Timorensis (No. CT_1A to CT7A) were planted adjacent to the under-monitoring Celtis Timorensis CT7 to CT10 on 30 April 2011.  The tree inspection report is presented in Appendix M.

 

 

8    Waste Management

8.01            Waste management was carried out by an on-site Environmental Officer or an Environmental Supervisor from time to time.

 

Records of Waste Quantities

8.02            All types of waste arising from the construction work are classified into the following:

l                 Construction & Demolition (C&D) Material;

l                 Chemical Waste;

l                 General Refuse; and

l                 Excavated Soil

 

8.03            The quantities of waste for disposal in this Reporting Period are summarized in Table 8-1 and 8-2 and the Monthly Summary Waste Flow Table is shown in Appendix J.  Whenever possible, materials were reused on-site as far as practicable.

 

Table 8-1        Summary of Quantities of Inert C&D Materials

Type of Waste

Quantity

Disposal Location

C&D Materials (Inert) (‘000m3)

0

-

Reused in the Contract (Inert) (‘000m3)

0

-

Reused in other Projects (Inert) (‘000m3)

0

-

Disposal as Public Fill (Inert) (‘000m3)

0

-

 

Table 8-2         Summary of Quantities of C&D Wastes

Type of Waste

Quantity

Disposal Location

Metal (kg)

0

-

Paper / Cardboard Packing (kg)

0

-

Plastic (kg)

0

-

Chemical Wastes (kg)

0

-

General Refuses (tonne)

6.4

Outlying Islands Transfer Facilities (Sok Kwu Wan)

 

8.04            There was no site effluent discharged but the estimated volume of surface runoff was less than 50m3 in this monthly period.

 


9    Site Inspection

9.01            According to the Environmental Monitoring and Audit Manual, the environmental site inspection should been formulated by ET Leader.  Regular environmental site inspections had been carried out by the ET to confirm the environmental performance.  In this Reporting Period, weekly site inspection by ET was carried out on 29 May, 5, 12 and 19 June 2012 and a joint-site visit by IEC Representative, RE, the Contractor and ET was carried out on 5 June 2012.

 

9.02            The findings/ deficiencies that observed during the weekly site inspection are listed in Table 9-1 and the relevant checklists are attached in Appendix K.

 

Table 9-1         Site Observations

Date

Findings / Deficiencies

Follow-Up Status

29 May 2012

Ÿ                No environmental issue was observed during site inspection.

Ÿ                As a reminder, unused chemical should be stored in proper area with labeling.

Not required for reminder.

5 June 2012

Ÿ                Oil spillage is found from the plant.  The Contractor should remove the contaminated soil to chemical storage area.

Rectified on 12 June 2012.

12 June 2012

Ÿ                No environmental issue was observed during site inspection.

N.A.

19     June 2012

Ÿ                The fencing of transplanted tree area is broken.  The Contractor should rectify and maintain the protection.

Ÿ                As reminded that the sediment tank should be cleaned up regularly to maintain functioning.

Rectified on 21 June 2012.

           


10Environmental Complaint and Non-Compliance

10.01        No environmental complaint, summons and prosecution was received in this Reporting Period.  The statistical summary table of environmental complaint is presented in Tables 10-1, 10-2 and 10-3.

 

Table 10-1       Statistical Summary of Environmental Complaints

Reporting Period

Environmental Complaint Statistics

Frequency

Cumulative

Complaint Nature

27 July 2010 – 31 December 2011

1 (Nov 2011)

1 (Nov 2011)

water quality

January - May 2012

0

1 (Nov 2011)

NA

June 2012

0

1 (Nov 2011)

NA

 

Table 10-2       Statistical Summary of Environmental Summons

Reporting Period

Environmental Summons Statistics

Frequency

Cumulative

Complaint Nature

27 July 2010 – 31 December 2011

0

0

NA

January - May 2012

0

0

NA

June 2012

0

0

NA

 

Table 10-3       Statistical Summary of Environmental Prosecution

Reporting Period

Environmental Prosecution Statistics

Frequency

Cumulative

Complaint Nature

27 July 2010 – 31 December 2011

0

0

NA

January - May 2012

0

0

NA

June 2012

0

0

NA

 

 


11Implementation Status of Mitigation Measures

11.01        The environmental mitigation measures that recommended in the Sok Kwu Wan Environmental Monitoring and Audit covered the issues of dust, noise, water and waste and they are summarized as following:

 

Dust Mitigation Measure

11.02        Installation of 2m high solid fences around the construction site of Pumping Station P2 is recommended.  Implementation of the requirements stipulated in the Air Pollution Control (Construction Dust) Regulation and the following good site practices are recommended to control dust emission from the site:

(a)        Stockpiles of imported material kept on site should be contained within hoardings, dampened and / or covered during dry and windy weather;

(b)        Material stockpiled alongside trenches should be covered with tarpaulins whenever works are close to village houses;

(c)        Water sprays should be used during the delivery and handling of cement, sands, aggregates and the like.

(d)        Any vehicle used for moving sands, aggregates and construction waste shall have properly fitting side and tail boards.  Materials should not be loaded to a level higher than the side and tail boards, and should be covered by a clean tarpaulin.

 

Noise Mitigation Measure

 

11.03        As detailed in the EIA report, concreting work of the Pumping Station P1a and sewer alignment construction activities would likely cause adverse noise impacts on some of the noise sensitive receivers.  Appropriate mitigation measures have therefore been recommended.  The mitigation measures recommended in the EIA report are summarised below:

(a)        Use of quiet equipment for the construction activities of the Pumping Stations and sewer alignment;

(b)        Use of temporary noise barrier around the site boundary of Pumping Station P1a;

(c)        Use of kick ripper (saw and lift) method to replace the breaker for pavement removal during sewer alignment construction;

(d)        Restriction on the number of plant during sewer alignment construction;

(e)        Use of noise screening structures in the form of acoustic shed or movable barrier wherever practicable and feasible in areas with sufficient clearance and headroom during the construction of sewer alignment;

(f) Adoption of manual working method wherever practicable and feasible in areas where the worksites of the proposed sewer alignment are located less than 20m from the residential noise sensitive receivers and less than 30m from the temple and the public library; and

(g)        Implementation of the following good site practices:

Ÿ                 Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction programme.

Ÿ                 Mobile plant, if any, should be sited as far away from NSRs as possible.

Ÿ                 Machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum.

Ÿ                 Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs.

Ÿ                 Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities.

 

Water Quality Mitigation Measure

11.04        No-dig method using Horizontal Directional Drilling (HDD) would be used for the installation of outfall pipe of about 480 m from shore to minimize the potential water quality impacts arising from the dredging works required for the submarine outfall construction.  For the remaining outfall pipe of about 240m and the diffuser section, open trench dredging would still be required.

 

11.05        During the dredging works, the Contractor should be responsible for the design and implementation of the following mitigation measures.

Ÿ     Dredging should be undertaken using closed grab dredgers with a total production rate of 55m3/hr;

Ÿ     Deployment of 2-layer silt curtains with first layer enclosing the grab and the second layer at around 50, from the dredging area while dredging works are in progress;

Ÿ     all vessels should be sized such that adequate clearance (i.e. minimum clearance of 0.6m) is maintained between vessels and the sea bed at all states of the tide to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash;

Ÿ     all pipe leakages should be repaired promptly and plant shall not be operated with leaking pipes;

Ÿ     excess material should be cleaned from the decks and exposed fittings of barges before the vessel is moved;

Ÿ     adequate freeboard (i.e. minimum of 200m) should be maintained on barges to ensure that decks are not washed by wave action;

Ÿ     all barges should be fitted with tight fitting seals to their bottom openings to prevent leakage of material; and

Ÿ     loading of barges and hoppers should be controlled to prevent splashing of dredged material to the surrounding water, and barges and hoppers should not be filled to a level which would cause the overflow of materials or sediment laden water during loading or transportation; and

Ÿ     the decks of all vessels should be kept tidy and free of oil or other substances that might be accidentally or otherwise washed overboard.

           

Construction Run-off and Drainage

11.06        The Contractor should observe and comply with the Water Pollution Control Ordinance and the subsidiary regulations.  The Contractor should follow the practices, and be responsible for the design, construction, operation and maintenance of all the mitigation measures as specified in ProPECC PN 1/94 “Construction Site Drainage”.  The design of the mitigation measures should be submitted by the Contractor to the Engineer for approval.  These mitigation measures should include the following practices to minimise site surface runoff and the chance of erosion, and also to retain and reduce any suspended solids prior to discharge:

Ÿ     Provision of perimeter channels to intercept storm-runoff from outside the site.  These should be constructed in advance of site formation works and earthworks.

Ÿ     Works programmes should be designed to minimize works areas at any one time, thus minimising exposed soil areas and reducing the potential for increased siltation and runoff.

Ÿ     Sand/silt removal facilities such as sand traps, silt traps and sediment basins should be provided to remove the sand/silt particles from run-off.  These facilities should be properly and regularly maintained.  These facilities shall be carefully planned to ensure that they would be installed at appropriate locations to capture all surface water generated on site.

Ÿ     Careful programming of the works to minimise soil excavation works during rainy seasons.

Ÿ     Exposed soil surface should be protected by paving or hydroseeding as soon as possible to reduce the potential of soil erosion.

Ÿ     Trench excavation should be avoided in the wet season, and if necessary, these should be excavated and backfilled in short sections.

Ÿ     Open stockpiles of construction materials on site should be covered with tarpaulin or similar fabric.

 

General Construction Activities

11.07        Debris and rubbish generated on-site should be collected, handled and disposed of properly to avoid entering the nearby coastal waters and stormwater drains.  All fuel tanks and storage areas should be provided with locks and be sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank.  Open drainage channels and culverts near the works areas should be covered to block the entrance of large debris and refuse.

 


Wastewater Arising from Workforce

11.08        Portable toilets shall be provided by the Contractors, where necessary, to handle sewage from the workforce. The Contractor shall also be responsible for waste disposal and maintenance practices

 

Sediment Contamination Mitigation Measure

11.09        The basic requirements and procedures for dredged mud disposal are specified under the WBTC No. 34/2002.  The management of the dredging, use and disposal of marine mud is monitored by the MFC, while the licensing of marine dumping is the responsibility of the Director of Environmental Protection (DEP).

 

11.10        The uncontaminated dredged sediment will be loaded onto barges and transported to the designated marine disposal site. Appropriate dredging methods have been incorporated into the recommended water quality mitigation measures including the use of closed-grab dredgers and silt curtains.  Category L sediment would be suitable for disposal at a gazetted open sea disposal ground.

 

11.11        During transportation and disposal of the dredged marine sediments, the following measures should be taken to minimize potential impacts on water quality:

Ÿ     Bottom opening of barges should be fitted with tight fitting seals to prevent leakage of material. Excess material should be cleaned from the decks and exposed fittings of barges and hopper dredgers before the vessel is moved.

Ÿ     Monitoring of the barge loading should be conducted to ensure that loss of material does not take place during transportation. Transport barges or vessels should be equipped with automatic self-monitoring devices as specified by the DEP.

 

Construction Waste Mitigation Measure

Good Site Practices and Waste Reduction Measures

11.12        It is not anticipated that adverse waste management related impacts would arise, provided that good site practices are strictly followed. Recommendations for good site practices for the construction waste arising include:

Ÿ     Nomination of an approved person, such as a site manager, to be responsible for the implementation of good site practices, arranging for collection and effective disposal to an appropriate facility, of all wastes generated at the site.

Ÿ     Training of site personnel in proper waste management and chemical handling procedures.

Ÿ     Appropriate measures to minimize windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers.

Ÿ     Provision of sufficient waste disposal points and regular collection for disposal.

Ÿ     Separation of chemical wastes for special handling and appropriate treatment at the Chemical Waste Treatment Facility.

Ÿ     Regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors.

Ÿ     Maintain records of the quantities of wastes generated, recycled and disposed.

 

11.13        In order to monitor the disposal of C&D waste at landfills and to control fly tipping, a trip-ticket system should be included as one of the contractual requirements and implemented by an Environmental Team undertaking the Environmental Monitoring and Audit work.  An Independent Environmental Checker should be responsible for auditing the results of the system.

 

11.14        Good management and control can prevent the generation of significant amount of waste.  Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices.  Recommendations to achieve waste reduction include:

Ÿ     segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal;

Ÿ     to encourage collection of aluminium cans by individual collectors, separate labelled bins should be provided to segregate this waste from other general refuse generated by the work force;

Ÿ     any unused chemicals or those with remaining functional capacity should be recycled;

Ÿ     use of reusable non-timber formwork to reduce the amount of C&D material;

Ÿ     prior to disposal of C&D waste, it is recommended that wood, steel and other metals should be separated for re-use and / or recycling to minimise the quantity of waste to be disposed of to landfill;

Ÿ     proper storage and site practices to minimise the potential for damage or contamination of construction materials; and

Ÿ     plan and stock construction materials carefully to minimise amount of waste generated and avoid unnecessary generation of waste.

 

General Site Wastes

11.15        A collection area should be provided where waste can be stored prior to removal from site.  An enclosed and covered area is preferred for the collection of the waste to reduce 'wind blow' of light material.

 

Chemical Wastes

11.16        After use, chemical waste (eg. cleaning fluids, solvents, lubrication oil and fuel) should be handled according to the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.  Any unused chemicals or those with remaining functional capacity should be recycled.  Spent chemicals should be properly stored on site within suitably designed containers, and should be collected by an approved operator for disposal at the Chemical Waste Treatment Facility or other licenced facility in accordance with the Waste Disposal (Chemical Waste) (General) Regulation under the Waste Disposal Ordinance.

 

11.17        Any service shop and minor maintenance facilities should be located on hard standings within a bunded area, and sumps and oil interceptors should be provided.  Maintenance of vehicles and equipment involving activities with potential for leakages and spillage should only be undertaken with the areas appropriately equipped to control these discharges.

 

Construction and Demolition Material

11.18        The C&D material should be separated on-site into three categories: (i) public fill, the inert portion of the C&D material (e.g. concrete and rubble), which should be re-used on-site or disposed of at a public filling area; (ii) C&D waste for re-use and/or recycling, the non-inert portion of the C&D material, (e.g. steel and other metals, wood, glass and plastic); (iii) C&D waste which cannot be re-used and/or recycled.  The waste producers are responsible for its disposal at strategic landfills.

 

11.19        In order to minimise the impact resulting from collection and transportation of material for off-site disposal, it was recommended that inert material should be re-used on-site where possible.  Prior to disposal of C&D material, it was also recommended that steel and other metals should be separated for re-use and/or recycling where practicable to minimise the quantity of waste to be disposed of to landfill.

 

Ecology Mitigation Measure

Terrestrial Ecology

11.20        The uncommon tree species should be labelled and probably fenced to avoid direct or indirect disturbance during construction.  Works areas should avoid woodland habitats, in particular where these trees are located.

 

11.21        Construction and maintenance of site runoff control measures would be required at all work sites during construction. These should include barriers to direct runoff to sand/silt removal facilities (sand/silt/traps and/or sediment basins); minimisation of earthworks during rainy season (May to September); and coverage of sand/fill piles and exposed earth during storms.

11.22        Special attention should be paid during the breeding season of Romer’s Tree Frog (March to September) to ensure their habitat landward to Pumping Station P2 site is well protected from site runoff. Barriers should be deployed completely along the landward side of the pumping station site boundary to prevent any site runoff from entering the tree frog habitat. Intactness of the barriers should be frequently inspected.

 

Intertidal and Subtidal Ecology

11.23        Construction and maintenance of site runoff control measures would be required at all work sites during construction. These should include barriers to direct runoff to sand/silt removal facilities (sand/silt/traps and/or sediment basins); use of silt curtains along coastline; minimisation of earthworks during rainy season (May to September); and coverage of sand/fill piles and exposed earth during storms.

 

11.24        To reduce impacts of sediment resuspension upon nearby habitats and organisms during dredging, all dredging should be done using a closed-grab dredger, and silt curtains should be deployed around the dredger during all dredging activity

 

Fisheries Mitigation Measure

11.25        Closed grab dredger, deployment of silt curtains around the immediate dredging area and low dredging rate have been recommended in Water Quality of the EIA report in order to minimise sediment release into the water column.

 

Landscape & Visual Mitigation Measure

11.26        Mitigation measures recommended in the EIA Report for landscape and visual impacts during the construction stage are summarised below.

Ÿ     Screening of site construction works by use of hoarding that is appropriate to its site context;

Ÿ     Retaining existing trees and minimising damage to vegetation where possible by close co-ordination and on site alignment adjusted of rising main and gravity sewer pipelines.  Tree protective measures should be implemented to ensure trees identified as to be retained are satisfactorily protected during the construction phase;

Ÿ     Careful and efficient transplanting of affected trees (1 no.) to temporary or final transplant location (the proposed tree to be transported is a semi-mature Macaranga tanarius and is located at the proposed Pumping Station P2 location);

Ÿ     Short excavation and immediate backfilling of sections upon completion of works to reduce active site area;

Ÿ     Conservation of top-soil for reuse.

Ÿ     Night-time light source from marine fleets should be directed away from the residential units

 

11.27        The implementation schedule of mitigation measures is presented in Appendix L.

 

11.28        Leader had been implementing the required environmental mitigation measures according to the Sok Kwu Wan Environmental Monitoring and Audit Manual subject to the site condition.  Environmental mitigation measures generally implemented by Leader in this Reporting Period are summarized in Table 11-1.

 

Table 11-1  Environmental Mitigation Measures

Issues

Environmental Mitigation Measures

Water Quality

·     Drainage channels were provided to convey run-off into the treatment facilities; and

·     Drainage systems were regularly and adequately maintained.

Air Quality

·     Cover all excavated or stockpile of dusty material by impervious sheeting or sprayed with water to maintain the entire surface wet;

·     Public roads around the site entrance/exit had been kept clean and free from dust; and

·     Tarpaulin covering of any dusty materials on a vehicle leaving the site.

Noise

·     Good site practices to limit noise emissions at the sources;

·     Use of quite plant and working methods;

·     Use of site hoarding or other mass materials as noise barrier to screen noise at ground level of NSRs; and

·     To minimize plant number use at the worksite.

Waste and Chemical Management

·     Excavated material should be reused on site as far as possible to minimize off-site disposal. Scrap metals or abandoned equipment should be recycled if possible;

·     Waste arising should be kept to a minimum and be handled, transported and disposed of in a suitable manner;

·     The Contractor should adopt a trip ticket system for the disposal of C&D materials to any designed public filling facility and/or landfill; and

·     Chemical waste shall be handled in accordance with the Code of Practice on the Packaging, Handling and Storage of Chemical Wastes.

General

Ÿ    The site was generally kept tidy and clean.

 


12Impact Forecast

12.01Key issues to be considered in the coming month include:

 

Water Quality

·          Erect of sand bag in proper area to avoid any muddy surface runoff from the loose soil surface or haul road during the rainy days; and

·          The accumulated stagnant water should be drained away.

 

Air Quality

·          Vehicles shall be cleaned of mud and debris before leaving the site;

·          Stockpile and loose soil surface shall be covered with tarpaulin sheet or other means to eliminate the fugitive dust;

·          Water spaying on the dry haul road and exit/entrance of the site in regular basis is reminded; and

·          Public roads around the site entrance/exit had been kept clean and free from dust.

 

Noise

·          Works and equipment should be located to minimize noise nuisance from the nearest sensitive receiver; and

·          Idle equipments should be either turned off or throttled down;

 

Waste and Chemical Management

·          Housekeeping on site shall be improved;

·          The Contractor is advised to fence off the construction waste at a designated area in order to maintain the tidiness of the site;

·          Drip tray and proper label should be provided for all chemical containers.

·          C&D waste should be disposed in regular basis.

 

 

 


13Conclusions and Recommendations

Conclusions

13.01        This is the 23rd monthly EM&A Report covering the construction period from 26 May to 25 June 2012.

 

13.02        No 1-hour and 24-hour TSP results were found to be triggered the Action or Limit Level in this Reporting Period. 

 

13.03        No noise complaint (an Action Level exceedance) was received and no construction noise measurement results that exceeded the Limit Level were recorded in this Reporting Period.

 

13.04        The monitoring result demonstrated no exceedance of Action or Limit Level of marine water quality monitoring in this Reporting Period.

 

13.05        No documented complaint, notification of summons or successful prosecution was received.

 

13.06        In this Reporting Period, weekly site inspection by ET was carried out on 29 May, 5, 12 and 19 June 2012 and a joint-site visit by IEC Representative, RE, the Contractor and ET was carried out on 5 June 2012.  All the observation has been rectified during the next week site inspection.  The environmental performance of the Project was therefore considered as satisfactory.

 

13.07        No site inspection was undertaken by external parties i.e. Environmental Protection Department (EPD) or Agriculture, Fisheries and Conservation Department (AFCD) within the Reporting Period.

 

Recommendations

13.08        During wet season, muddy water and other water quality pollutants via site surface water runoff into the sea body within Fish culture zone at Picnic Bay and the Secondary recreation contact subzone at Mo Tat Wan is the key issue of the Project.  Mitigation measures for water quality should be properly maintained to prevent any muddy or sandy runoff from the loose soil surface overflow on the site boundary.

 

13.09        Moreover, special attention should be also paid on the dust mitigation measures to avoid fugitive dust emissions from loose soil surface or haul road.  Mitigation measures implemented for control the surface runoff including wheel wash facilities, covering of the loose soil surface or stockpile with tarpaulin sheet, etc., should fully implement.