Contract No: HK/2009/05 Wanchai Development Phase II and Central Wanchai
Bypass Sampling, Field Measurement
and Testing Work (Stage 1) Environmental Permit
no. EP-364/2009/A, Further Evironmental
permit nos. fep-01/364/2009, fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A,
FEP-05/364/2009/A
and FEp-06/364/2009/a Monthly Environmental Monitoring & Audit Report - December 2010 - |
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
Certified
by: |
|
|
Raymond Dai Environmental Team Leader |
DATE: |
|
4 January 2011 |
Table of contents
2.2 Scope of the Project and Site
Description
2.3 Division of the Project
Responsibility
2.4 Project Organization and
Contact Personnel
3. status of regulatory compliance
3.1 Status of Environmental
Licensing and Permitting under the Project
5.2 Real Time Noise Monitoring
Results
6.2 Real Time Noise Monitoring
6.4 Review of the Reasons for and
the Implications of Non-compliance
6.5 Summary of action taken in the
event of and follow-up on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST
OF TABLES
Table 2.1 Schedule 2 Designated Projects under this
Project
Table 2.2 Details of Individual Contracts under the
Project
Table 2.3 Contact Details of Key Personnel
Table 3.2 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/17
Table 3.3 Summary of submission status under
FEP-03/364/2009 Condition
Table 3.4 Cumulative Summary of Valid Licences and
Permits under Contract no. 04/HY/2006
Table 3.5 Summary of submission status under
FEP-04/364/2009/A Condition
Table 3.6 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/01
Table 3.7 Summary of submission status under
FEP-02/364/2009 Condition
Table 3.8 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/02
Table 3.9 Summary of submission status under
FEP-01/364/2009 Condition
Table
3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/18
Table
3.11 Summary
of submission status under FEP-05/364/2009/A Condition
Table
3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Table
3.13 Summary
of submission status under FEP-06/364/2009/A Condition
Table 4.1 Noise Monitoring Station
Table 4.2 Real Time Noise Monitoring Station
Table 4.3 Air Monitoring Station
Table 5.1 Noise Monitoring Stations for Contract
no. HY/2009/17
Table 5.2 Noise Monitoring Stations for Contract
no. 04/HY/2006 and HY/2009/18
Table 5.3 Noise Monitoring Station for Contract nos.
HK/2009/01 and HK/2009/02
Table 5.4 Noise Monitoring Station for Contract nos.
HY/2009/15
Table 5.5 Real Time Noise Monitoring Station for
Contract no. HY/2009/17
Table 5.6 Air Monitoring Stations for Contract no.
HY/2009/17
Table 5.7 Air Monitoring Stations for Contract no.
04/HY/2006 and HY/2009/18
Table 5.8 Air Monitoring Stations for Contract no.
HK/2009/01
Table 5.9 Air Monitoring Station for Contract no.
HK/2009/02
Table
5.10 Air
Monitoring Station for Contract no. HY/2009/15
Table
5.11 Details
of Waste Disposal for Contract no. HY/2009/17
Table
5.12 Details
of Waste Disposal for Contract no. 04/HY/2006
Table
5.13 Details
of Waste Disposal for Contract no. HK/2009/01
Table
5.14 Details
of Waste Disposal for Contract no. HK/2009/02
Table
5.15 Details
of Waste Disposal for Contract no. HY/2009/18
Table
5.16 Details
of Waste Disposal for Contract no. HY/2009/15
Table 8.1 Summary of Environmental Inspections for
Contract no. HY/2009/17
Table 8.2 Summary of Environmental Inspections for
Contract no. 04/HY/2006
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful
Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project
Organization Chart
Figure
4.1 Locations of
Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation
Schedule
Appendix 4.1 Action and Limit Level
Appendix
4.2 Copies of
Calibration Certificates
Appendix
5.1 Monitoring Schedule
for Reporting Month and Coming month
Appendix
5.2 Noise Monitoring
Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and
Graphical Presentations
Appendix
5.4 Real-time Noise
Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix
9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract
no. HY/2009/17
- Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under
FEP-03/364/2009
·
Piling
Works.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
·
No
major construction activity was undertaken in reporting month. Only preparation
works was commenced in the reporting month.
·
Initial
record survey
·
Condition
survey
·
Tree
survey
·
Cable
detection
Contract
no. 04/HY/2006 – Reconstruction of Bus Terminus near
Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
·
Modification
of bus bays at the bus terminus
·
Modification
of traffic island at Man Yiu Street
·
Resurfacing
Works at Man Kwong Street
Contract no. HK/2009/01 - Wan Chai Development Phase II -
Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre -
Tunnel Works under FEP-02/364/2009
·
No
major construction activity was undertaken in reporting month.
Contract no. HK/2009/02 - Wan Chai Development Phase II -
Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
No
major construction activity was undertaken in reporting month.
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
·
No
major construction activity was undertaken in reporting month.
Noise Monitoring
Air Monitoring
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Contract no.
HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works under FEP-03/364/2009
·
Piling
Works
Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
No
major construction activity was undertaken in next reporting month. Only
preparation works was commenced.
·
Hoarding
and project signboard erection
·
Cable
detection and excavation of trial pit
·
Preparation
works for tree transplanting
·
Condition
survey
·
Preparation
works for erection of CLC
·
Provision
of site welfare facilities
Contract
no. 04/HY/2006 – Reconstruction of Bus Terminus near
Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
·
Resurfacing
Works at Man Yiu Street
·
Construction
of Planting Area at Man Kwong Street
Contract no. HK/2009/01 - Wan Chai Development Phase II -
Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre -
Tunnel Works under FEP-02/364/2009
·
No
major construction activities are anticipated in coming reporting month.
Contract no. HK/2009/02 - Wan Chai Development Phase II -
Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
No
major construction activities are anticipated in coming reporting month.
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
·
No
major construction activity was undertaken in reporting month.
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009A and Further Environmental
permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009,
FEP-04/364/2009/A, FEP-05/364/2009/A and FEP-06/364/2009/A to implement the
Environmental Monitoring and Audit (EM&A) programme as stipulated in the
EM&A Manual of the approved Environmental Impact Assessment (EIA) Report
for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular
Specification Section 27.
1.1.3.
This
report documents the finding of EM&A works for Environmental Permit (EP)
no. EP-364/2009/A, Further Environmental Permit (FEP) nos. FEP-01-364/2009,
FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A and
FEP-06/364/2009/A during the period 28th October to 27th
November 2010. The cut-off date of reporting is at 27th of each
reporting month.
Section 1 Introduction – details the scope and structure of
the report.
Section 2 Project Background – summarizes background and scope of
the project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Status of Regulatory Compliance – summarizes the status of valid
Environmental Permits / Licenses during the reporting period.
Section 4 Monitoring Requirements – summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section 5 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 6 Compliance Audit – summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section 7 Cumulative Construction Impact due to
the Concurrent Projects – summarizes the relevant cumulative construction impact due
to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection – summarizes the findings of weekly site
inspections undertaken within the reporting period, with a
review of any
relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of summons and
Prosecution –
summarizes the cumulative statistics on complaints, notification of summons and
prosecution
Section 10 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern
Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved
on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested east-west Connaught Road Central/Harcourt Road / Gloucester Road
Corridor (the Corridor) which is currently operating beyond its capacity. The
CWB will provide relief to the existing congestion along the Corridor and cater
for the anticipated growth of traffic on Hong Kong Island. Without the CWB and
its access roads, there will not be sufficient capacity to serve the heavy
traffic demands at both strategic and local levels.
2.2
Scope of the Project and Site Description
2.2.1.
Design
and Construction of Central – Wan Chai Bypass and Island Eastern Corridor Link
under the Project involves the construction and operation of a trunk road and
its road tunnel more than 800m in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope
of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL)
includes:
· A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
·
Tunnel
control buildings and ventilation buildings;
·
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
Causeway Bay area;
·
Associated
road lighting, road signing, traffic control and surveillance system; and
·
Other
associated works.
2.2.3. The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads |
Schedule
2, Part I, A.1 and A.7 |
Trunk road
and road tunnel more than 800 m in length |
DP2 |
Road P2
and other roads which are classified as primary/district distributor roads |
Schedule
2, Part I, A.1 |
Primary /
district distributor roads |
DP3 |
Reclamation
works including associated dredging works |
Schedule
2, Part I, C.1 and C.12 |
Reclamation
more than 5 ha in size and a dredging operation less than 100 m from a
seawater intake point |
DP5 |
Wan Chai
East Sewage Outfall |
Schedule 2,
Part I, F.5 and F.6 |
Submarine
sewage pipelines with a total diameter more than 1,200 mm and include a
submarine sewage outfall |
DP6 |
Dredging
for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui |
Schedule
2, Part I, C.12 |
A dredging
operation less than 100 m from a seawater intake point |
2.3
Division of the Project Responsibility
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be commenced. Contractors of individual contracts will be
required by the EP holder to apply Further Environmental Permits such that the
impact monitoring stations are sub-divided accordingly to facilitate the
implementation of EM&A programme and to streamline the EM&A reporting
for individual FEP holders correspondingly.
2.3.2.
In
the reporting month, advance piling work at FEHD Whitfield Depot under Contract
no. HY/2009/17 was commenced on 5 October 2010. The details of individual
contracts are summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central -
Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works. |
DP1 |
5
October 2010 |
HY/2009/18 |
Central -
Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
Anticipated
to be commenced in January 2011 |
04/HY/2006 |
Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works |
DP1, DP2 |
Pending |
HK/2009/02 |
Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)
(CWB Tunnel) |
DP1 |
Pending |
HY/2009/15 |
Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1 |
Pending |
2.4
Project Organization and Contact Personnel
2.4.1.
Civil
Engineering and Development Department and Highways Department are the overall
project controllers for the Wan Chai Development Phase II and Central-Wan Chai
Bypass respectively. For the construction phase of the Project, Project
Engineer, Contractor(s), Environmental Team and Independent Environmental
Checker are appointed to manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer
for WDII |
Principle
Resident Engineer |
Mr.
Frankie Fan |
2587 1778 |
2587 1877 |
Engineer
for CWB |
Principle
Resident Engineer |
Mr. Peter
Poon |
3916 1818 |
3529 2829 |
|
Lam Woo & CO., LTD. |
Contractor
under Contract no. HY/2009/17 |
Project
Manager |
Mr. K. S.
Law |
9090 1378 |
2566 7522 |
Construction
Manager / Sub Agent |
Mr. Joe
Tsang |
9725-5874 |
|||
Site Agent |
Mr.
Daniel Chan |
9372 0495 |
|||
Environmental
Officer |
Mr. Andy
Mak |
6461 3065 |
|||
Chiu Hing
Construction & Transportation Co. Ltd. |
Contractor
under Contract no. 04/HY/2006 |
Contract
Manager |
Mr.
Frederick Tsui |
2967
6363 |
2967
6366 |
Senior
Site Agent |
Mr.
Alvin Ma |
2967
6363 |
2967
6366 |
||
Environmental
Consultant |
Mr.
Jimmy Cheng |
2965
0898 |
2556
9172 |
||
Chun Wo –
Leader Joint Venture |
Contractor
under Contract no. HK/2009/01 |
Site
Agent |
Mr. Paul
Yu |
9456 9819 |
2634 1626 |
Operation
Manager |
Mr. Ho
Wing Tai |
9306 1356 |
|||
Construction
Manager |
Mr. David
Wong |
9653 8635 |
|||
Construction
Manager |
Mr. Wilson
Lau |
5183 1270 |
|||
Construction
Manager |
Mr. Alex
Tsang |
9194 9383 |
|||
Environmental
Officer (Compliance Manager) |
Mr.Ho
Wing Tai |
9306 1356 |
|||
Environmental
Engineer |
Mr. Ken
Yang |
9262 6791 |
|||
Chun Wo –
CRGL Joint Venture |
Contractor
under Contract no. HK/2009/02 |
Project
Manager |
Mr. Chan
Sing Cho |
3658 3002 |
2827 9996 |
Site
Agent |
Mr. Eric
Lam |
3658-3048 |
|||
Deputy
Site Agent |
Mr.
Anthony Wu |
3658-3004 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Barry
Leung |
3658 3031 |
|||
Environmental
Engineer |
Ms. Flora
Ng |
3658-3064 |
|||
Leighton
Contractors (Asia) Limited |
Contractor
under Contract no. HY/2009/18 |
Site
Agent |
Mr. Brian
Gillon |
2214 7700 |
2140 6799 |
Deputy
Site Agent |
Mr.
Desmond Sze |
2214 7703 |
|||
Quality
& Env. Manager |
Mr.
Stephen Moc |
2214 7720 |
|||
Environmental
Officer |
Mr.
Anfernee Chow |
2214 7721 |
|||
Environmental
Supervisor |
Mr.
Kelven Yip |
2214 7722 |
|||
China
State Construction Engineering (HK) Ltd. |
Contractor
under Contract no. HY/2009/15 |
Project
Manager |
Mr. M Y
Wong |
2823 7879 |
2566 2192 |
Site
Agent |
Mr. Leung
Kwok Yiu |
9026 8808 |
|||
Head of
construction |
Mr. Simon
Tang |
9022 6060 |
|||
Construction
Manager |
Mr. C K
Kwok |
9779 2162 |
|||
Assistant
Construction Manager (East) |
Mr. Gene
Cheung |
6105 4880 |
|||
Assistant
Construction Manager (West) |
Mr. Tony
Chiu |
9090 0606 |
|||
Section
Agent (East) |
Mr. Jason
Chan |
9254 1635 |
|||
Section
Agent (West) |
Mr. Tang
Ka Tung |
9473 4771 |
|||
Environmental
Manager |
Ms. Anna
Yu |
9473 1945 |
|||
ENVIRON
Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David
Yeung |
3743 0788 |
3548 6988 |
Lam
Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr.
Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
In
the reporting month, the principal work activities of individual contracts are
included as follows:
Contract no.
04/HY/2006 – Reconstruction of Bus
Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
·
Modification
of bus bays at the bus terminus
·
Modification
of traffic island at Man Yiu Street
·
Resurfacing
Works at Man Kwong Street
Contract no.
HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works under FEP-03/364/2009
·
Piling
Works
Contract no. HY/2009/18 - Central -
Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
·
No
major construction activity was undertaken in reporting month. Only preparation
works was commenced in the reporting month.
·
Initial
record survey
·
Condition
survey
·
Tree
survey
·
Cable
detection
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
No
major construction activity was undertaken in reporting month.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
·
No
major construction activity was undertaken in reporting month.
Contract no. HY/2009/15 -
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
·
No
major construction activity was undertaken in reporting month.
2.4.4.
In
coming reporting month, the principal work activities of individual contracts
are anticipated as follows:
Contract
no. 04/HY/2006 – Reconstruction of Bus Terminus near
Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
·
Resurfacing
Works at Man Yiu Street
·
Construction
of Planting Area at Man Kwong Street
Contract
no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
·
Piling Works.
Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
No
major construction activity was undertaken in next reporting month. Only
preparation works was commenced.
·
Hoarding
and project signboard erection
·
Cable
detection and excavation of trial pit
·
Preparation
works for tree transplanting
·
Condition
survey
·
Preparation
works for erection of CLC
·
Provision
of site welfare facilities
Contract no. HK/2009/01 - Wan Chai Development Phase II -
Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre -
Tunnel Works under FEP-02/364/2009
·
No major construction
activity is anticipated in coming reporting month.
Contract no. HK/2009/02 - Wan Chai Development Phase II -
Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
No major construction
activity is anticipated in coming reporting month.
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
·
No major construction
activity was undertaken in reporting month.
3.1
Status of Environmental Licensing and Permitting under the
Project
3.1.1. A summary of the current status on licences
and/or permits on environmental protection pertinent to the Project is shown in
Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov
2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18
Feb 2010 |
Valid |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21
Apr 2010 |
Valid |
|
Further Environmental Permit |
12
July 2010 |
Valid |
|
Further Environmental Permit |
14
Oct 2010 |
Valid |
|
Further Environmental Permit |
15
Nov 2010 |
Valid |
|
Further Environmental Permit |
22
Nov 2010 |
Valid |
3.1.2. Due to the multi-contract nature of the
Project, the status of permits and/or licences under the individual contract(s)
are presented as below:
Contract no. HY/2009/17 - Central - Wan Chai
Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under
FEP-03/364/2009
3.1.3. Summary of the current status on licences
and/or permits on environmental protection pertinent and submission under
FEP-03/364/2009 for contract no. HY/2009/17 are shown in Table 3.2 and Table
3.3.
Table
3.2 Cumulative Summary of Valid
Licences and Permits under Contract no.
HY/2009/17
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/364/2009 |
12 Jul
2010 |
N/A |
Valid |
Notification
of Works Under APCO |
319348 |
13 Jul
2010 |
N/A |
Valid |
Discharge
Licence |
WT00007212-2010 |
5 Aug
2010 |
5 Aug
2010 – 31 Aug 2015 |
Valid |
Registration
as a Waste Producer |
5213-151-L2608-05 |
13 May
2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7010400 |
16 Mar
2010 |
N/A |
Valid |
Table 3.3 Summary of submission status under FEP-03/364/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction
Companies |
18 September 2010 |
Conditions 2.7 and 2.8 |
Submission of
works schedule and location plan |
1 September 2010 |
Condition 2.9 |
Noise Management Plan |
1 September 2010 |
Contract
no. 04/HY/2006 – Reconstruction of Bus Terminus near Man
Yiu Street and Man Kwong Street under FEP-04/364/2009/A
3.1.4. Summary of the current status on licences
and/or permits on environmental protection pertinent and submission under
FEP-04/364/2009/A for contract no. 04/HY/2006 are shown in Table 3.4 and Table
3.5.
Table 3.4 Cumulative Summary of Valid Licences and
Permits under Contract no. 04/HY/2006
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
N/A |
Valid |
Notification of Works Under APCO |
322225 |
7 Oct 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7005123 |
9 Mar 2007 |
N/A |
Valid |
Table 3.5 Summary of submission status under FEP-04/364/2009/A Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
11 June 2010 |
Conditions 2.7 and 2.8 |
Submission of works schedule and location plan |
11 June 2010 and 5 August 2010 |
Condition 2.9 |
Noise Management Plan |
19 October 2010 |
Condition 2.10 |
Landscape Plan |
26 Nov 10 |
Contract no. HK/2009/01 -
Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
3.1.5. Summary of the current status on licences
and/or permits on environmental protection pertinent and submission under
FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.6 and
Table 3.7
Table 3.6 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
N/A |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313088 |
6 Jan
2010 |
N/A |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
Billing Account under Waste
Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a
Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table 3.7 Summary of submission status under FEP-02/364/2009 Condition
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
Contract no. HK/2009/02 -
Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
3.1.6. Summary of the current status on licences
and/or permits on environmental protection pertinent and submission under
FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.8 and
Table 3.9.
Table 3.8 Cumulative Summary of Valid Licences and
Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Valid |
|
WT00006757-2010 |
28 May 2010 |
31
May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
Billing Account under Waste Disposal
Ordinance |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table 3.9 Summary of submission status under FEP-01/364/2009
Condition
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
3.1.7. Summary of the current status on licences
and/or permits on environmental protection pertinent and submission under FEP-05/364/2009A
for contract no. HY/2009/18 are shown in Table 3.10 and Table 3.11.
Table 3.10 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2009/18
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
N/A |
Valid |
Notification of Works Under APCO |
322293 |
07 Oct 2010 |
N/A |
Valid |
Discharge Licence |
H2540/19.09/DS/KPC/kpc/00121 |
N/A |
N/A |
Application under preparation |
Billing Account under Waste Disposal
Ordinance |
7011587 |
11-Oct-10 |
N/A |
Valid |
Registration as a Waste Producer |
WPN: 8335-121-L1048-04 |
17 Dec
2010 |
N/A |
Valid |
Table 3.11 Summary of submission status under
FEP-05/364/2009/A Condition
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
3.1.8. Summary of the current status on licences
and/or permits on environmental protection pertinent and submission under
FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.12 and
Table 3.13
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
22 Nov 2010 |
N/A |
Valid |
|
22 Nov 2010 |
N/A |
Valid |
||
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Table 3.13 Summary of submission status under
FEP-06/364/2009/A Condition
EP Condition |
Submission |
Date of Submission |
NIL |
NIL |
NIL |
3.1.9. Implementation status of the recommended
mitigation measures during this reporting period is presented in Appendix 3.1.
Noise Monitoring Stations
4.1.1. The noise monitoring stations for the Project
are listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
Real time Noise Monitoring Stations
4.1.2. The noise monitoring stations for the Project
are listed and shown in Table 4.2 and Figure 4.1.. Appendix 4.1 shows the
established Action/Limit Levels for the monitoring works.
Table 4.2 Real Time Noise
Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong
Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil Street
Community
Liaison Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.3.
The construction noise level shall be measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq
(30 minutes) shall be used as the monitoring parameter for the time
period between 0700 and 1900 hours on normal weekdays. For all other time
periods, Leq (5 minutes) shall be employed for comparison with the
Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
4.1.4.
Noise monitoring shall be
carried out at all the designated monitoring stations. The monitoring frequency
shall depend on the scale of the construction activities. The following is an
initial guide on the regular monitoring frequency for each station on a weekly
basis when noise generating activities are underway:
·
One set of measurements
between 0700 and 1900 hours on normal weekdays.
4.1.5.
Real time noise shall be
carried out at the designated monitoring stations. The following is an initial
guide on the regular monitoring frequency for each station on a 24 hours daily
basis when noise generating activities are underway:
·
One set of measurements
between 0700 and 1900 hours on normal weekdays.
·
One set of measurements
between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on
public holidays.
·
One set of measurements
between 2300 and 0700 hours on next day on everyday.
4.1.6.
If construction works are
extended to include works during the hours of 1900 – 0700 as well as public
holidays and Sundays, additional weekly impact monitoring shall be carried out
during respective restricted hours periods. Applicable permits under NCO shall
be obtained by the Contractor.
Monitoring Equipment
4.1.7.
As referred to in the
Technical Memorandum ™ issued under the NCO, sound level meters in compliance
with the International Electrotechnical Commission Publications 651: 1979 (Type
1) and 804: 1985 (Type 1) specifications shall be used for carrying out the
noise monitoring. Immediately prior to and following each noise measurement the
accuracy of the sound level meter shall be checked using an acoustic calibrator
generating a known sound pressure level at a known frequency. Measurements may
be accepted as valid only if the calibration level from before and after the
noise measurement agree to within 1.0 dB.
4.1.8.
Noise measurements shall not
be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with
gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind
speed meter capable of measuring the wind speed in m/s.
4.1.9.
The sound level meter shall
be checked using an acoustic calibrator generating a known sound pressure level
at a known frequency before deployment to the site and during each site visit.
Measurements may be accepted as valid only if the calibration level from before
and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
4.2.1.
The air monitoring stations
for the Project are listed and shown in Table 4.3 and Figure 4.1..
Appendix 4.1 shows the
established Action/Limit Levels for the monitoring works.
Table 4.3 Air Monitoring Station
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North Point |
CMA2a |
Causeway Bay Community Centre |
Causeway Bay |
CMA3a |
Future CWB site office at Wanchai Waterfront Promenade |
Causeway Bay |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (western End of Podium) |
Central |
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP
levels should be measured to indicate the impacts of construction dust on air
quality. The 24-hour TSP levels shall be measured by following the standard
high volume sampling method as set out in the Title 40 of the Code of Federal
Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including
temperature, pressure, weather conditions, elapsed-time meter reading for the
start and stop of the sampler, identification and weight of the filter paper,
and any other local atmospheric factors affecting or affected by site
conditions, etc., shall be recorded down in detail.
4.2.4.
For regular impact
monitoring, the sampling frequency of at least once in every six-days, shall be
strictly observed at all the monitoring stations for 24-hour TSP monitoring.
For 1-hour TSP monitoring, the sampling frequency of at least three times in
every six-days should be undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs)
in compliance with the following specifications shall be used for carrying out
the 1-hour and 24-hour TSP monitoring:
·
0.6 - 1.7 m3 per minute
adjustable flow range;
·
Equipped with a timing /
control device with +/- 5 minutes accuracy for 24 hours operation;
·
Installed with elapsed-time
meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable of providing a
minimum exposed area of 406 cm2;
·
Flow control accuracy: +/-
2.5% deviation over 24-hour sampling period;
·
Equipped with a shelter to
protect the filter and sampler;
·
Incorporated with an
electronic mass flow rate controller or other equivalent devices;
·
Equipped with a flow
recorder for continuous monitoring;
·
Provided with a peaked roof
inlet;
·
Incorporated with a
manometer;
·
Able to hold and seal the
filter paper to the sampler housing at horizontal position;
·
Easily changeable filter;
and
·
Capable of operating
continuously for a 24-hour period.
4.2.6. Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7.
A clean laboratory with
constant temperature and humidity control, and equipped with necessary
measuring and conditioning instruments to handle the dust samples collected,
shall be available for sample analysis, and equipment calibration and
maintenance. The laboratory should be HOKLAS accredited.
4.2.8.
Filter paper of size 8"
x 10" shall be labeled before sampling. It shall be a clean filter paper
with no pinholes, and shall be conditioned in a humidity-controlled chamber for
over 24-hours and be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter
paper loaded with dust shall be kept in a clean and tightly sealed plastic bag.
The filter paper shall then be returned to the laboratory for reconditioning in
the humidity controlled chamber followed by accurate weighing by an electronic
balance with readout down to 0.1 mg. The balance shall be regularly calibrated
against a traceable standard.
4.2.10.
All the collected samples
shall be kept in a good condition for 6 months before disposal.
4.2.11.
Current calibration
certificates of equipments are presented in Appendix
4.2.
5.0.1.
The environmental monitoring
will be implemented based on the division of works areas of each designed
project managed under different contracts with separate FEP applied by
individual contractors. Overall layout
showing work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring results
are presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the
concurrent contracts are as follows:
Contract
no. 04/HY/2006 –Reconstruction of Bus Terminus near Man Yiu Street and Man
Kwong Street under FEP-04/364/2009/A.
Contract
no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
5.0.3.
The environment monitoring
schedules for reporting month and coming month are presented in Appendix
5.1.
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
5.1.1. The
proposed division of noise monitoring stations for Contract no. HY/2009/17 are
summarized in Table 5.1 below:
Table
5.1 Noise Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria
Centre |
5.1.2.
No action and limit
exceedance was recorded during day time and restricted hour period in the
reporting month. Noise monitoring results measured in this reporting period are
reviewed and summarized. Details of
noise monitoring results and graphical presentation can be referred in Appendix 5.2.
Contract no. 04/HY/2006 – Reconstruction of
Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange
under FEP-05/364/2009/A
5.1.3. The
proposed division of noise monitoring stations for Contract no. 04/HY/2006 and
Contract no. HY/2009/18 are summarized in Table 5.2 below:
Table
5.2 Noise Monitoring Stations for Contract no. 04/HY/2006 and HY/2009/18
Station |
Description |
M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
5.1.4.
No exceedance was recorded
in the reporting month. Noise monitoring results measured in this reporting
period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix
5.2.
5.1.5.
The commencement of major
construction works for Contract no. HY/2009/18 under FEP-05/364/2009A is
pending. Only preparation works was commenced in the
reporting month.
Contract
no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
and Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.6. The
commencement of construction works for Contract no. HK/2009/01 and HK/2009/02
under FEP-02/364/2009 and FEP-01/364/2009 respectively are pending. The
proposed division of noise monitoring stations are summarized in Table
5.3 below.
Table
5.3 Noise Monitoring Station for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour
Road Sports Centre |
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
5.1.7.
The commencement of construction works for
Contract no. under FEP-06/364/2009/A is pending. The proposed division of noise
monitoring stations are summarized in Table 5.3 below.
Table
5.4 Noise Monitoring Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun
Area |
M3a |
Tung Lo
Wan Fire Station |
5.2
Real Time Noise Monitoring Results
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
5.2.1. The
proposed division of noise monitoring stations are summarized in Table
5.5 below. Real time noise monitoring for the piling works under
contract no. HY/2009/17 was commenced on 5 October 2010
Table
5.5 Real Time Noise
Monitoring Station for Contract no. HY/2009/17
District |
Description |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
5.2.2. No
exceedance was recorded between 0700 and 1900 hours. In contrast, one major
exceedance was recorded between 1900 and 2300 hours 21 December 2010 and
between 2300 and 0700 on the next day on 23 December 2010. Details of real time
noise monitoring results and graphical presentation can be referred to Appendix 5.4
.
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
5.3.1. The
proposed division of air monitoring stations are summarized in Table
5.6 below. Air monitoring for the piling works under contract no.
HY/2009/17 was commenced on 8 October 2010.
Table
5.6 Air
Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
CMA2a |
Causeway
Bay Community Centre |
5.3.2.
No exceedance was recorded
in the reporting month. Air quality monitoring results measured in this
reporting period are reviewed and summarized.
Details of air monitoring results and graphical presentation can be
referred in Appendix
5.3.
Contract no. 04/HY/2006 – Reconstruction of
Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
and Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
5.3.3. The
proposed division of air monitoring stations are summarized in Table
5.7 below.
Table
5.7 Air
Monitoring Stations for Contract no. 04/HY/2006 and HY/2009/18
Station |
Description |
MA1e |
International
Finance Centre (Eastern End of Podium) |
MA1w |
International
Finance Centre (Western End of Podium) |
5.3.4.
No exceedance was recorded
in the reporting month. Air quality monitoring results measured in this
reporting period are reviewed and summarized.
Details of air monitoring results and graphical presentation can be
referred in Appendix
5.3.
5.3.5.
The commencement of major
construction works for Contract no. HY/2009/18 under FEP-05/364/2009A is
pending. Only preparation works was commenced in the
reporting month.
Contract
no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
5.3.6. Air
quality monitoring will be commenced depending on the commencement of work for
Contract no. HK/2009/01 under FEP-02/364/2009. The proposed division of air
monitoring stations are summarized in Table 5.8 below.
Table
5.8 Air
Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children
Playgrounds opposite to Pedestrian Plaza |
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.3.7. Air
quality monitoring will be commenced depending on the commencement of work for
Contract no. HK/2009/02 under FEP-01/364/2009. The proposed division of air
monitoring stations are summarized in Table 5.9 below.
Table
5.9 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society
for the Prevention of Cruelty to Animals |
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
5.3.8.
Air quality monitoring will
be commenced depending on the commencement of work for Contract no. HY/2009/15
under FEP-06/364/2009/A. The proposed division of air monitoring stations are
summarized in Table 5.10 below.
Table
5.10 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site
office at Wanchai Waterfront Promenade |
Contract no. HY/2009/17 –Central - Wan Chai
Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under
FEP-03/364/2009
5.4.1.
Inert C&D waste was
recycled in the reporting month. Details of the waste flow table are summarized
in Table
5.11
Table 5.11 Details of Waste Disposal for Contract no.
HY/2009/17
Waste Type |
Quantity this
month, m3 |
Cumulative
Quantity-to-Date, m3 |
Disposal / Dumping
Grounds |
Inert C&D materials
disposed |
NIL |
NIL |
N/A |
Inert C&D materials
recycled |
303.78 |
1037.02 |
N/A |
Non-inert C&D materials
disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials
recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street under FEP-04/364/2009/A
5.4.2.
Inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.12.
Table 5.12 Details of Waste Disposal for Contract no. 04/HY/2006
Inert C&D materials
disposed |
152.6 |
1288.5 |
Chai Wan and T.K.O. 137 |
Inert C&D materials
recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials
disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials
recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract
nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
5.4.3.
No inert and non-inert
C&D waste was disposed of in this reporting month. Details of the waste
flow table are summarized in Table 5.13.
Table
5.13 Details of Waste Disposal for Contract no. HK/2009/01
Inert C&D materials
disposed |
NIL |
NIL |
N/A |
Inert C&D materials
recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials
disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials
recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract
no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai East (CWB Tunnel) under FEP-01/364/2009
5.4.4.
No inert and no-inert
C&D waste was disposed of in this reporting month. Details of the waste
flow table are summarized in Table 5.14.
Table
5.14 Details of Waste Disposal for Contract no. HK/2009/02
Inert C&D materials
disposed |
NIL |
NIL |
N/A |
Inert C&D materials
recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials
disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials
recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
5.4.5.
No inert and no-inert
C&D waste was disposed of in this reporting month. Details of the waste
flow table are summarized in Table 5.15.
Table 5.15 Details of Waste Disposal for Contract no. HY/2009/18
Inert C&D materials
disposed |
0 |
0 |
N/A |
Inert C&D materials
recycled |
0 |
0 |
N/A |
Non-inert C&D materials
disposed |
0 |
0* |
N/A |
Non-inert C&D materials
recycled |
0 |
0 |
N/A |
Chemical waste disposed |
0 |
0 |
N/A |
*Contractor clarified
that no Non-inert C&D waste materials disposed at November 2010 on 24
December 2010.
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
5.4.6.
No inert and no-inert C&D
waste was disposed of in this reporting month. Details of the waste flow table
are summarized in Table 5.16.
Table 5.16 Details of Waste Disposal for Contract no. HY/2009/15
Inert C&D materials
disposed |
NIL |
NIL |
N/A |
Inert C&D materials
recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials
disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials
recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
6.0.1.
The Event Action Plan for
construction noise, air qualities are presented in Appendix 6.1.
Contract
no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under
FEP-03/364/2009
6.1.1. No exceednace was recorded in the reporting
month.
Contract
no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
6.1.2. No
exceedance was recorded in the reporting month.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
6.1.3. No noise monitoring was undertaken in the
reporting month.
Contract
nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre - Tunnel Works and HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel)
6.1.4. No noise monitoring was undertaken in the
reporting month.
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
6.1.5. No noise monitoring was undertaken in the
reporting month.
6.2
Real Time Noise Monitoring
Contract no. HY/2009/17 –
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
6.2.1. No exceedance was recorded between 0700 and 1900 hours. In contrast, one major exceedance was recorded between 1900 and 2300 hours 21 December 2010 and between 2300 and 0700 on the next day on 23 December 2010. No construction activity was conducted during such Time periods. As there is no construction work near the monitoring station, estimating the noise contributed from Island Eastern Corridor. It is concluded that the exceedances were non-project related.
Contract
no. HY/2009/17 – Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under
FEP-03/364/2009
6.3.1. No exceedance was recorded in the reporting
month.
Contract
no. 04/HY/2006 –
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
6.3.2. No
exceedance was recorded in the reporting month.
Contract
no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
6.3.3. No air quality monitoring was undertaken in
the reporting month.
Contract
nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre - Tunnel Works and HK/2009/02 - Wan Chai Development Phase II -
Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)
6.3.4.
No
air quality monitoring was undertaken in the reporting month.
Contract
no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) FEP-06/364/2009/A
6.3.5.
No
air quality monitoring was undertaken in the reporting month.
6.4
Review of the Reasons for and the Implications of
Non-compliance
6.3.1.
There was no non-compliance
from the site audits in the reporting period. The observations and
recommendations made in each individual site audit session were presented in
Section 8.
6.3.2.
No project-related
non-compliance from monitoring was recorded in the reporting month.
6.5
Summary of action taken in the event of and follow-up on
non-compliance
6.4.1.
There was no particular
action taken since no project-related non-compliance was recorded from the site
audits and environmental monitoring in the reporting period.
7.0.1.
According to Condition 3.4
of the EP-364/2009/A, this section addresses the relevant cumulative
construction impact due to the concurrent activities of the current projects
including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase
II (WWDII), Central-WanChai Bypass (CWB) and Island Eastern Corridor Link
projects (IECL).
7.0.2.
From the Monthly EM&A
report (December 2010) of Central Reclamation Phase III the key works in
December 2010 are as follows:
·
Type
A filling in FRAW and FRAE above +2.5mPD
·
General
filling works above +2.5mPD in IRAE
·
Surcharging
in FRAW and FRAE
·
Construction
of cantilever slab at caisson
·
Base
slab, wall and roof construction at Culvert F
·
Construction
of storm and foul drainage and gullies in hinterlands for Road P2, Road D7, and
Road D9
·
Construction
of GPO boundary wall
·
Construction
of PLA boundary wall
·
Road
P2 Underpass ramp structures
·
Precasting
for retaining wall (offsite)
·
Installation
of cooling mains discharge pipes in FRAE and FRAW
·
Bulk
excavation to formation level at CWB works
·
Construction
of CWB structure
·
Disposal
of material off-site to Government fill banks
7.0.3.
According to the
construction programme of Wan Chai Development Phase II, Central-Wan Chai
Bypass and Island Eastern Corridor Link projects, the major construction
activity under Wan Chai Development Phase II was the filling works at North
Point Reclamation Stage 1(NPR1), dredging works at Wan Chai Reclamation Stage
1(WCR1), Advanced
piling works at FEHD Whitfield Depot and
cross-harbour water mains in the reporting month. The major environmental
impact was water quality impact at North Point and Wan Chai. Land-based
construction activity was only the modification works of bus terminus near Man
Yiu Street and Man Kwong Street under CWB and advance piling works at FEHD
Whitfield Depot in the reporting month.
7.0.4.
The major environmental
impacts generated from the Central Reclamation Phase III were located along the
coastline of Central and Admiralty while modification works of bus terminus
near Man Yiu Street and Man
Kwong Street under CWB and advanced piling works
at FEHD Whitfield
Depot were undertaken in the reporting month. No
significant air, noise impact were anticipated in the reporting month. Besides,
no environmental monitoring exceedance was recorded from the Project in the
reporting month. Thus, it is evaluated
that the cumulative construction impact from the concurrent projects including
Wan Chai Development Phase II and Central Reclamation Phase III was
insignificant.
.
8.0.1.
During this reporting month,
weekly environmental site audits were conducted for Contracts no. HY/2009/17
and 04/HY/2006. No non-conformance was identified during the site audits.
8.0.2.
Four site
inspections for Contract no. HY/2009/17 were carried out during this reporting
period. The results of these inspections and outcomes are summarized in Table
8.1.
Table
8.1 Summary of Environmental Inspections for Contract no. HY/2009/17
Item |
Date |
Observations |
Action
taken by Contractor |
Outcome |
101130_01 |
30-Nov-10 |
The
contractor is recommended to improve the filter for silty discharge at
breakwater accidentally. By lending geotextile from HEC and surrounding the exiting
of pipe as a temporary mitigating measure. As a prolong measure, the
contractor is recommended to increase the no. of sedimentation tank. |
Improve
the filtration facilities. |
Completion
as observed on 7-Dec-10 |
101207_01 |
07-Dec-10 |
The
contractor was reminded to conduct water spraying at the haul road. |
Conduct
water spraying at the haul road. |
Completion
as observed on 15-12-10 |
101207_02 |
07-Dec-10 |
Drip
tray shall be provided underneath the air compressor. |
Provide
drip tray underneath the air compressor. |
Completion
as observed on 15-12-10 |
101215_01 |
15-Dec-10 |
Design
and quantity of sedimentation tank at site should be reviewed and enhanced. |
Increase
the number of sedimentation tank. |
Completion
as observed on 21-12-10 |
101215_02 |
15-Dec-10 |
Discarded
cement bags and chemical containers should be covered with tarpaulin sheet
and placed on the drip tray respectively. |
Covered
Discarded cement bags and chemical containers with tarpaulin sheet and placed
on the drip tray respectively. |
Completion
as observed on 21-12-10 |
8.0.3.
Four site inspections
for Contract no. 04/HY/2006 were carried out during this reporting period. The results of these inspections and outcomes
are summarized in Table 8.2.
Table 8.2
Summary of Environmental Inspections for Contract no. 04/HY/2006
Item |
Date |
Observations |
Action
taken by Contractor |
Outcome |
101129_01 |
29-Nov-10 |
Improve
house keeping, include refuse collection, shall be conducted. |
Improve
house keeping. |
Completion
as observed on 6-Dec-10 |
101206_01 |
06-Dec-10 |
Stockpile
shall be covered by tarpaulin. |
Cover
stockpile by tarpaulin. |
Completion
as observed on 20-Dec-10 |
101206_02 |
06-Dec-10 |
Water
spraying shall be conducted during breaking. |
Conduct
water spraying during breaking. |
Completion
as observed on 13-Dec-10 |
101213_01 |
13-Dec-10 |
All
stockpiles shall be covered well. |
Cover
all stockpiles well. |
Completion
as observed on 20 Dec-10 |
101213_02 |
13-Dec-10 |
An
idle compressor was found oil leakage. The contractor was reminded to
maintain before use. |
Ensure
maintenance was conducted before use. |
Completion
as observed on 20 Dec-10 |
101220_01 |
20-Dec-10 |
Oil
leakages of oil dumps were found near the track exit. The contractor was
reminded to provide drip tray. |
Provide
drip tray for chemical storage. |
Completion
as observed on 03-Jan-11 |
101220_02 |
20-Dec-10 |
Water
spraying to prevent dust generate, reasonably practicable, during material
handling. |
Conduct
water spraying during material handling. |
Completion
as observed on 30 Dec-10 |
101220_03 |
20-Dec-10 |
Check
and conduct maintenance of the protective barriers of trees. |
Maintenance
the protective barrier for trees. |
Completion
as observed on 03-Jan-11 |
9.0.1.
No
complaint, notification of summons and prosecution was received in the
reporting month. The details of cumulative complaint
log and updated summary of complaints are presented in Appendix
9.1.
9.0.2.
Cumulative statistic on
complaints and successful prosecutions are summarized in Table 9.1 and Table
9.2 respectively.
Table 9.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
December 2010 |
0 |
Project-to-Date |
0 |
Table 9.2 Cumulative Statistics on Successful
Prosecutions
Environmental
Parameters |
Cumulative No.
Brought Forward |
No. of Successful
Prosecutions this month (Offence Date) |
Cumulative No.
Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1.
The EM&A programme was
carried out in accordance with the EM&A Manual requirements, minor
alterations to the programme proposed were made in response to changing
circumstances.
10.0.2.
The scheduled construction
activities and the recommended mitigation measures for the coming month are
listed in Table 10.1. The construction programmes of individual contracts
are provided in Appendix 10.1.
Table
10.1 Summary of Key
Construction Activities of Individual Contract(s) to be commenced in Coming
Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HY/2009/17 |
·
Drilling,
installation steel H-Pile & grouting |
·
Noise barrier
shall be implemented; ·
Watering any
dust generating activities; and Improvement of wheel washing facilities Improvement and increasing the number of sedimentation tanks. |
04/HY/2006 |
·
Modification
of bus bays at the bus terminus |
·
Noise barrier shall be implemented; ·
Watering any dust generating activities ·
Check and maintain protective barrier for
trees |