Table
of Contents
1.1 Background
1.2 Scope of Report
1.3 Organization Structure
1.4 Summary of Construction Works
2.1 Air quality
2.2 Noise Monitoring
2.3 Water Quality Monitoring
2.4 Dolphin monitoring
2.5 Coral Monitoring
2.6 EM&A Site inspection
2.7 Waste Management Status
2.8 Environmental Licenses and
Permits
2.9 Implementation Status of
Environmental Mitigation Measures
2.10 Summary of Exceedances of the
Environmental Quality Performance Limit
2.11 Summary of Complaints,
Notification of Summons and Successful Prosecutions
3.1 Construction Programme for
the Coming Months
3.2 Key Issues for the Coming
Month
3.3 Monitoring Schedule for the
Coming Month
4 Conclusions
and recommendations
4.1 Conclusions
List
of Tables
Table 1.1 |
|
Table 2.1 |
|
Table
2.2 |
|
Table
2.3 |
Summary
of 1-hour TSP Monitoring Results in the Reporting Period |
Table
2.4 |
Summary
of 24-hour TSP Monitoring Results in the Reporting Period |
Table
2.5 |
|
Table 2.6 |
|
Table
2.7 |
Summary
of Construction Noise Monitoring Results in the Reporting Period |
Table 2.8 |
Locations
of Impact Water Quality Monitoring Stations and its Corresponding Monitoring Requirements |
Table 2.9 |
|
Table
2.10 |
|
Table
2.11 |
|
Table
2.12 |
|
Table
2.13 |
|
Table
2.14 |
Specific
Observations Identified during the Weekly Site Inspections in this Reporting
Month |
Table
2.15 |
Quantities
of Different Waste Generated in the Reporting Period |
Table
2.16 |
List
of Figures
Figure 1.1 |
|
Figure 1.2 |
General Layout Plan of
Contract No. HY/2012/07 - Viaducts A, B, C, D, E & F |
Figure 1.3 |
|
Figure 1.4 |
|
Figure 2.1 |
|
Figure 2.2 |
|
Figure 2.3 |
|
Figure 2.4 |
|
Figure 2.5 |
Locations of Dolphin Sightings
during Impact Dolphin Monitoring Survey |
Figure 2.6 |
List of Appendices
Appendix A |
|
Appendix B |
|
Appendix C |
Implementation Schedule
of Environmental Mitigation Measures (EMIS) |
Appendix D |
|
Appendix E |
|
Appendix F |
|
Appendix G |
Impact Air Quality
Monitoring Results and Graphical Presentation |
Appendix H |
|
Appendix I |
|
Appendix J |
Impact Water Quality
Monitoring Results and Graphical Presentation |
Appendix K |
|
Appendix L |
|
Appendix M |
|
Appendix N |
Under Contract No. HY/2012/07,
Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the
Southern Connection Viaduct Section of the Tuen Mun ¡V Chek Lap Kok Link Project (TM-CLK Link Project) while AECOM
Asia Company Limited was appointed by HyD as the
Supervising Officer. For
implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM)
has been appointed as the Environmental Team (ET). ENVIRON Hong Kong Ltd. was employed by
the HyD as the Independent Environmental Checker
(IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A. Another application
for variation of environmental permit (VEP) (EP-354/2009/B) was granted on 28 January 2014.
The
construction phase of the Contract commenced on 31 October 2013 and will
tentatively be completed by 2018.
The impact monitoring of the EM&A programme,
including air quality, noise, water quality and marine ecological monitoring as
well as environmental site inspections, commenced on 31 October 2013.
This
is the Tenth Monthly EM&A report presenting the EM&A works carried out
during the period from 1 to 31 August 2014 for the Southern
Connection Viaduct Section in accordance with the Updated EM&A Manual of the
TM-CLK Link Project. As informed by the Contractor, major
activities in the reporting period included:
Marine-based Works
¡P Construction
of Pile caps at Viaduct B;
¡P Marine
piling platform installation;
¡P Marine
Piling at Viaducts B, D & E;
¡P Construction
of rockfill platform at Viaduct D landing; and
¡P Additional
marine ground investigation (GI) and laboratory testing.
Land-based
Works
¡P Construction
of pile cap superstructure of Viaduct B;
¡P Fence
installation and relocation of Area 2, Viaducts A, B, C & D;
¡P Land
Piling at Viaduct B;
¡P Piling
platform installation for Viaducts B, C, D and E;
¡P Additional
land GI, trial pits & lab testing;
¡P Utility
surveys; and
¡P Slope
work of Slope 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.
A summary of
monitoring and audit activities conducted in the reporting period is listed
below:
24-hour TSP
monitoring 5
sessions
1-hour TSP
monitoring 5
sessions
Noise
monitoring 5
sessions
Impact Water
Quality Monitoring 13
sessions
Impact Dolphin
Monitoring 2
sessions
Joint
Environmental site inspection 4
sessions
Breaches of Action and Limit Levels for Air Quality
No exceedance
of Action and Limit Levels was recorded for construction air monitoring in the
reporting month.
Breaches of Action and Limit Levels for Noise
No exceedance
of Action and Limit Levels was recorded for construction noise monitoring in
the reporting month.
Breaches of Action and Limit Levels for Water Quality
No exceedance
of Action and Limit Levels was recorded for impact water quality monitoring in
the reporting month.
Impact Dolphin Monitoring
Whilst
two (2) Action Level exceedances and no Limit Level exceedance were observed
for the quarterly dolphin monitoring data between June and August 2014, no
unacceptable impact from the construction activities of the TM-CLKL Southern Connection
Viaduct Section on Chinese White Dolphins was noticeable from general
observations. Due to monthly
variation in dolphin occurrence within the study area, it would be more
appropriate to draw conclusion on whether any impacts on dolphins have been
detected related to the construction activities of the TM-CLKL Southern
Connection Viaduct Section in the quarterly EM&A reports, where comparison
on distribution, group size and encounter rates of dolphins between the
quarterly impact monitoring period and baseline monitoring period will be made.
Daily
marine mammal exclusion zone monitoring was undertaken. No sighting of the Indo-Pacific humpback
dolphin Sousa chinensis
(i.e. Chinese White Dolphin) was recorded in August 2014 during the exclusion
zone monitoring.
Coral Monitoring
No
Post-Translocation Coral Monitoring was conducted in the reporting month.
Environmental
Complaints, Non-compliance & Summons
No
environmental complaint, notification of summons and successful prosecution was
received in the reporting month.
Reporting Change
There was no
reporting change required in the reporting period.
Upcoming Works for the Next Reporting Period
Works to be
undertaken in the next monitoring period of September 2014 include the
following:
Marine
Works
¡P Construction
of Pile caps at Viaduct B;
¡P Marine
piling platform installation;
¡P Marine
Piling at Viaducts B & E;
¡P Marine
piling platform installation for Viaduct D; and
¡P Additional
marine ground investigation (GI) and laboratory testing.
Land-based
Works
¡P Construction
of pile cap superstructure of Viaduct B;
¡P Fence
installation and relocation of Works Area 2, Viaducts A, B, C & D;
¡P Land
Piling at Viaduct B and Viaduct C;
¡P Piling
platform installation for Viaducts B, C, D and E;
¡P Additional
land GI, trial pits & lab testing;
¡P Utility
surveys; and
¡P Slope
work of Slope 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.
Future Key Issues
Potential
environmental impacts arising from the above upcoming construction activities
in the next reporting month of September 2014 are mainly associated with dust,
noise, marine water quality, marine ecology and waste management issues.
According to
the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure
Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau
Link and North Lantau Highway would be operating beyond capacity after
2016. This forecast has been based
on the estimated increase in cross boundary traffic, developments in the
Northwest New Territories (NWNT), and possible developments in North Lantau,
including the Airport developments, the Lantau Logistics Park (LLP) and the
Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB).
In order to cope with the anticipated traffic demand, two new road
sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.
An
Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in
accordance with the EIA Study Brief (No. ESB-175/2007) and
the Technical Memorandum of the
Environmental Impact Assessment Process (EIAO-TM). The
EIA Report was submitted under the Environmental Impact Assessment Ordinance
(EIAO) in August 2009. Subsequent
to the approval of the EIA Report (EIAO Register Number AEIAR-146/2009), an
Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of
Environmental Protection (DEP) on 4 November 2009, and EP variation
(EP-354/2009A) was issued on 8 December 2010.
Under
Contract No. HY/2012/07,
Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the
Southern Connection Viaduct Section of TM-CLKL (¡§the Contract¡¨) while AECOM
Asia Company Limited was appointed by HyD as the
Supervising Officer. For
implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM)
has been appointed as the Environmental Team (ET). ENVIRON Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A. Another application for variation of
environmental permit (VEP) (EP-354/2009/B)
was granted on 28 January 2014.
The
organization structure of the Contract is shown in Appendix A. The key personnel contact names and
contact details are summarized in Table
1.1 below.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
HyD
(Highways Department) |
Project
Coordinator |
Stanley Chan |
2762 3406 |
3188 6614 |
|
Senior
Engineer |
Steven Shum |
2762 4133 |
3188 6614 |
SOR (AECOM Asia
Company Limited) |
Chief
Resident Engineer |
Daniel Ip |
3553 3800 |
2492 2057 |
|
Resident
Engineer |
Kingman Chan |
3691 3950 |
3691 2899 |
ENPO / IEC (ENVIRON
Hong Kong Ltd.) |
ENPO Leader |
Y.H. Hui |
3465 2888 |
3465 2899 |
IEC |
Dr. F.C.
Tsang |
3465 2828 |
3465 2899 |
|
Contractor (Gammon
Construction Limited) |
Environmental
Manager |
Brian Kam |
3520 0387 |
3520 0486 |
Environmental
Officer |
Roy Leung |
3520 0387 |
3520 0486 |
|
|
24-hour
Complaint Hotline |
|
9738 4332 |
|
ET (ERM-HK) |
ET Leader |
Jovy
Tam |
2271 3113 |
2723 5660 |
Marine-based
Works
¡P Construction
of Pile caps at Viaduct B;
¡P Marine
piling platform installation;
¡P Marine
Piling at Viaducts B, D & E;
¡P Construction
of rockfill platform at Viaduct D landing; and,
¡P Additional
marine ground investigation (GI) and laboratory testing.
Land-based
Works
¡P Construction
of pile cap superstructure of Viaduct B;
¡P Fence
installation and relocation of Area 2, Viaducts A, B, C & D;
¡P Land
Piling at Viaduct B;
¡P Piling
platform installation for Viaducts B, C, D and E;
¡P Additional
land GI, trial pits & lab testing;
¡P Utility
surveys; and
¡P Slope
work of Slope 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.
The
locations of the construction activities are shown in Figure 1.3. The Environmental Sensitive Receivers in
the vicinity of the Project are shown in Figure 1.4.
Figure 1.3 Locations
of Construction Activities in the Reporting Month
The
EM&A programme required environmental monitoring
for air quality, noise, water quality and marine ecology as well as environmental
site inspections for air quality, noise, water quality, waste management,
marine ecology and landscape and visual impacts. The EM&A requirements and related
findings for each component are summarized in the following sections.
Table 2.1 Locations
of Impact Air Quality Monitoring Stations
Monitoring Station |
Location |
Description |
Monitoring Dates |
ASR 8 |
Pak Mong Village Watch Tower |
Rooftop of
the premise |
4, 8, 14, 20
and 26 August 2014 |
ASR 8A |
Area 4 |
On ground at
the Area 4 |
Table 2.2 Air
Quality Monitoring Equipment
Equipment |
Brand and Model |
High Volume Sampler |
Tisch Environmental Mass Flow
Controlled Total Suspended Particulate (TSP) High
Volume Sampler (Model No. TE-5170) |
Wind Sensor |
Global Water (Wind
Speed Sensor: WE550; Wind Direction Sensor: WE570) |
Wind Anemometer for
calibration |
Lutron (Model No.
AM-4201) |
Table 2.3 Summary
of 1-hour TSP Monitoring Results in the Reporting Period
|
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
ASR
8A |
69 |
43
- 113 |
394 |
500 |
ASR
8 |
67 |
43
- 116 |
393 |
500 |
Table 2.4 Summary
of 24-hour TSP Monitoring Results in the Reporting Period
|
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
ASR
8A |
41 |
40
- 43 |
178 |
260 |
ASR
8 |
43 |
41
- 45 |
178 |
260 |
All
1-hour and 24-hour TSP results were below the Action and Limit levels at all
monitoring locations in the reporting period. No action is thus required to be
undertaken in accordance with the Event Action Plan presented in Appendix L.
Noise
monitoring was performed on 4, 8, 14, 20 and 26 August
2014 using sound level meter at the designated monitoring station NSR 1 (Figure 2.2; Table 2.5) in accordance with the
requirements stipulated in the Updated EM&A Manual. Acoustic calibrator was deployed to
check the sound level meters at a known sound pressure level. Details of the equipment deployed are
provided in Table 2.6. Copies of the calibration certificates
for the equipment are presented in Appendix E.
Table 2.5 Location
of Impact Noise Monitoring Station
Monitoring Station |
Location |
Description |
Parameter |
Frequency and Duration |
Monitoring Dates |
NSR 1 |
Pak Mong Village Watch Tower |
Rooftop of
the premise |
30-minute
measurement at each monitoring station between 0700 and 1900 on normal weekdays
(Monday to Saturday). Leq, L10 and
L90 would be recorded. |
At least
once per week |
4, 8, 14, 20
and 26 August 2014 |
Table 2.6 Noise
Monitoring Equipment
Equipment |
Brand and Model |
Integrated Sound
Level Meter |
Rion
NL-31 |
Acoustic
Calibrator |
Rion
NC-73 |
Table 2.7 Summary
of Construction Noise Monitoring Results in the Reporting Period
|
Average , dB(A), Leq
(30mins) |
Range, dB(A), Leq (30mins) |
Limit Level, dB(A), Leq
(30mins) |
NSR
1 |
56 |
54
- 57 |
75 |
Table 2.8 Locations
of Impact Water Quality Monitoring Stations and its Corresponding Monitoring
Requirements
Station ID |
Type |
Coordinates |
*Parameters, unit |
Frequency |
Depth |
|
|
|
Easting |
Northing |
|
|
|
IS(Mf)9 |
Impact
Station (Close to HKBCF construction site) |
813273 |
818850 |
Temperature(¢XC)
pH (pH unit)
Turbidity (NTU)
Water depth (m)
Salinity (ppt)
DO (mg/L and % of saturation) ¡P
SS (mg/L) |
Impact monitoring: 3 days per week, at mid-flood
and mid-ebb tides during the construction period of the Contract |
3 water depths: 1m below sea surface, mid-depth and 1m above sea bed. If the water depth is less than 3m,
mid-depth sampling only. If water
depth less than 6m, mid-depth may be omitted |
IS(Mf)16 |
Impact Station
(Close to HKBCF construction site) |
814328 |
819497 |
|||
IS8 |
Impact Station(Close
to HKBCF construction site) |
814251 |
818412 |
|||
SR4 |
Sensitive receiver
(Tai Ho Inlet) |
814760 |
817867 |
|||
SR4a |
Sensitive receiver |
815247 |
818067 |
|||
CS(Mf)3 |
Control
Station |
809989 |
821117 |
|||
CS(Mf)5 |
Control
Station |
817990 |
821129 |
|||
*Notes: |
Table
2.9 Water
Quality Monitoring Equipment
Equipment |
Brand and Model |
DO and Salinity |
YSI Pro2030 |
Turbidity meter |
HACH Model 2100Q |
pH meter |
HANNA HI8314 |
Positioning
Equipment |
Koden913MK2 with KBG-3 DGPS antenna |
Water Depth Detector |
Speedtech Instrument SM-5 |
Water Sampler |
Kemmerer 1520 (1520-C25) 2.2L with messenger |
No Action and
Limit levels exceedances was recorded at all monitoring stations for impact
water quality monitoring in the reporting month. No action is thus required to be
undertaken in accordance with the Event Action Plan presented in Appendix L.
Table
2.10 Dolphin Monitoring Equipment
Equipment |
Model |
|
Global Positioning System
(GPS) Camera Laser Binoculars Marine Binocular Vessel for Monitoring |
Garmin 18X-PC Geo One Phottix Nikon D90 300m 2.8D fixed focus Nikon D90 20-300m zoom lens Infinitor LRF 1000 Bushell 7 x 50 marine binocular with compass and
reticules 65 foot single engine motor vessel with viewing platform 4.5m above
water level |
|
Table
2.11 Impact Dolphin Monitoring Line Transect
Co-ordinates
Line No. |
Easting |
Northing |
|
Line No. |
Easting |
Northing |
||
1 |
Start Point |
804671 |
814577 |
|
13 |
Start Point |
816506 |
819480 |
1 |
End Point |
804671 |
831404 |
|
13 |
End Point |
816506 |
824859 |
2 |
Start Point |
805475 |
815457 |
|
14 |
Start Point |
817537 |
820220 |
2 |
End Point |
805477 |
826654 |
|
14 |
End Point |
817537 |
824613 |
3 |
Start Point |
806464 |
819435 |
|
15 |
Start Point |
818568 |
820735 |
3 |
End Point |
806464 |
822911 |
|
15 |
End Point |
818568 |
824433 |
4 |
Start Point |
807518 |
819771 |
|
16 |
Start Point |
819532 |
821420 |
4 |
End Point |
807518 |
829230 |
|
16 |
End Point |
819532 |
824209 |
5 |
Start Point |
808504 |
820220 |
|
17 |
Start Point |
820451 |
822125 |
5 |
End Point |
808504 |
828602 |
|
17 |
End Point |
820451 |
823671 |
6 |
Start Point |
809490 |
820466 |
|
18 |
Start Point |
821504 |
822371 |
6 |
End Point |
809490 |
825352 |
|
18 |
End Point |
821504 |
823761 |
7 |
Start Point |
810499 |
820690 |
|
19 |
Start Point |
822513 |
823268 |
7 |
End Point |
810499 |
824613 |
|
19 |
End Point |
822513 |
824321 |
8 |
Start Point |
811508 |
820847 |
|
20 |
Start Point |
823477 |
823402 |
8 |
End Point |
811508 |
824254 |
|
20 |
End Point |
823477 |
824613 |
9 |
Start Point |
812516 |
820892 |
|
21 |
Start Point |
805476 |
827081 |
9 |
End Point |
812516 |
824254 |
|
21 |
End Point |
805476 |
830562 |
10 |
Start Point |
813525 |
820872 |
|
22 |
Start Point |
806464 |
824033 |
10 |
End Point |
813525 |
824657 |
|
22 |
End Point |
806464 |
829598 |
11 |
Start Point |
814556 |
818449 |
|
23 |
Start Point |
814559 |
821739 |
11 |
End Point |
814556 |
820992 |
|
23 |
End Point |
814559 |
824768 |
12 |
Start Point |
815542 |
818807 |
|
|
|
|
|
12 |
End Point |
815542 |
824882 |
|
|
|
|
|
The Action and
Limit levels of dolphin impact monitoring are shown in Appendix D. The Event and Action plan is presented
in Appendix L.
A
total of thirteen (13) groups of forty-eight (48) Chinese White Dolphins were
sighted during the two sets of monitoring surveys in August 2014. All sightings were made in NWL during
the two sets of surveys in August, while no dolphin was sighted at all in
NEL. All except three (3) sightings
were made on primary lines during on-effort search, and none of the dolphin
groups was associated with operating fishing vessel. The distribution of dolphin sightings
during the reporting month is shown in Figure 2.5.
Encounter rates of Chinese White Dolphins are deduced
from the survey effort and on-effort sighting data made under favourable conditions (Beaufort 3 or below) in August 2014
are shown in Tables 2.12 and 2.13.
Table 2.12 Individual
Survey Event Encounter Rates
|
|
Encounter rate (STG) (no. of
on-effort dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI)
(no. of dolphins from all on-effort sightings per 100 km of survey
effort) |
Primary
Lines Only |
Primary
Lines Only |
||
NEL |
Set 1: Aug 5th/6th |
0.0 |
0.0 |
|
Set 2: Aug 15th/19th |
0.0 |
0.0 |
NWL |
Set 1: Aug 5th/6th |
5.6 |
22.5 |
|
Set 2: Aug 15th/19th |
9.7 |
40.4 |
Note: Dolphin Encounter Rates are deduced
from the two sets of surveys ( two surveys in each set) in August 2014 in
Northeast (NEL) and Northwest Lantau (NWL) |
Table 2.13 Monthly
Average Encounter Rates
|
Encounter
rate (STG) (no.
of on-effort dolphin sightings per 100 km of survey effort) |
Encounter
rate (ANI)
(no. of dolphins from all
on-effort sightings per 100 km of survey effort) |
||
Primary Lines Only |
Both
Primary and Secondary Lines |
Primary Lines Only |
Both
Primary and Secondary Lines |
|
Northeast
Lantau |
0.0 |
0.0 |
0.0 |
0.0 |
Northwest
Lantau |
7.5 |
7.9 |
30.8 |
29.1 |
Note:
Overall dolphin encounter rates (sightings per 100km of survey effort)
from all four surveys are conducted in August 2014 on primary lines only as
well as both primary lines and secondary lines in Northeast and Northwest
Lantau
Daily 250 m marine
mammal exclusion zone monitoring was undertaken during the period of marine
works activities being undertaken. No sighting of Indo-Pacific
humpback dolphin Sousa chinensis (i.e. Chinese White Dolphin) were recorded in
August 2014 during the exclusion zone monitoring.
Table 2.14 Specific
Observations Identified during the Weekly Site Inspections in this Reporting
Month
Inspection Date |
Environmental Observations |
Recommendations/ Remarks |
6 August
2014 |
Site Access
9A ¡P
Chemical containers were not placed in drip tray. ¡P
A drip tray was found unplugged. Slope next
to NL1 ¡P
Drainage was filled with trash. Site Access
9B ¡P
Chemical containers were not placed in drip tray. Slope BC8 ¡P
Tarpaulin sheet for soil nail on unpaved slope was
not cover properly. |
Site Access
9A ¡P
Chemical Containers should be placed in drip tray. ¡P
The contractor should provide stopper to the drip
tray. Slope next
to NL1 |
|
¡P
The contractor was reminded to clean up the drainage
regularly. Site Access
9B ¡P
Chemical Containers should be placed in drip tray. Slope BC8 ¡P
Soil nail on unpaved slope should be well covered. |
|
14 August
2014 |
Pier B1 |
Pier B1 |
|
¡P
A drip tray was found unplugged. ¡P
Stagnant water was found in a drip tray. Pier
A,C&D1 ¡P
A drip tray of generator could not be covered well
by screen. ¡P
Stagnant water was found in a drip tray. ¡P
A drip tray was found unplugged. |
¡P
The drip tray should be plugged. ¡P
Stagnant water in drip tray should be cleared. Pier
A,C&D1 ¡P
The screen was improved immediately and able to
cover the drip tray of generator properly. ¡P
Stagnant water in drip tray should be cleared. ¡P
The drip tray should be plugged. |
|
Pier E4 |
Pier E4 |
|
¡P
Muddy water was accumulated on the platform. ¡P
A label of waste category label was missing. |
¡P
Muddy water should be cleared. ¡P
Waste category label should be labelled properly. |
21 August
2014 |
Pier B1 |
Pier B1 |
|
¡P
Stagnant water was accumulated in a drip tray. Pier E10 ¡P
Chemical containers were not labelled properly. ¡P
Soil and sand were accumulated on the platform Slope BC9 ¡P
Soil and mud was observed accumulating in drainage. |
¡P
Stagnant water in a drip tray should be cleared. Pier E10 ¡P
Chemical containers should be labelled properly. ¡P
Soil and sand on the platform were cleaned up
immediately. Slope BC9 ¡P
Soil and mud in drainage should be cleared
regularly. |
27 August
2014 |
Slope BC9 |
Slope BC9 |
|
¡P
A chemical container was not placed in drip tray. ¡P
An unpaved slope was not covered. ¡P
Refuse was observed on the slope. ¡P
A part of bund was missing at the path on slope. Pier B15 ¡P
A drip tray was found unplugged. |
¡P
The chemical container was removed intermediately. ¡P
The unpaved slope should be covered by tarpaulin
sheet. ¡P
Refuse on the slope should be removed. ¡P
The Contractor was reminded to implement
precautionary measures for preventing soil and sand runoff from the slope. Pier B15 ¡P
The drip tray should be plugged. |
The
Contractor has rectified all of the observations identified during
environmental site inspections in the reporting month.
The Contractor
had submitted application form for registration as chemical waste producer
under the Contract. Sufficient
numbers of receptacles were available for general refuse collection and
sorting.
Wastes
generated during this reporting period include mainly construction wastes
(inert and non-inert), imported fill, recyclable materials and marine
sediment. Reference has been made
to the waste flow table prepared by the Contractor (Appendix M). The quantities of different types of
wastes are summarized in Table 2.15.
Table 2.15 Quantities
of Different Waste Generated in the Reporting Period
Month/Year |
Inert C&D Materials (a)
(m3) |
Imported Fill (m3) |
Inert Construction Waste
Re-used (m3) |
Non-inert Construction Waste (b)
(kg) |
Recyclable Materials (c) (kg) |
Chemical Wastes (kg) |
Marine Sediment (m3) |
|
Category L |
Category M (Mp
& Mf) |
|||||||
August 2014 |
6,580 |
288 |
1,412 |
98,220 |
22,281 |
0 |
0 |
164 |
Notes: |
||||||||
(a) Inert
construction wastes include hard rock and large broken concrete, and
materials disposed as public fill. (b) Non-inert
construction wastes include general refuse disposed at landfill. (c) Recyclable
materials include metals, paper, cardboard, plastics, timber, felled trees
and others. |
The Contractor
was advised to properly maintain on site C&D materials and waste collection,
sorting and recording system, dispose of C&D materials and wastes at
designated ground and maximize reuse/ recycle of C&D materials and
wastes. The Contractor was also
reminded to properly maintain the site tidiness and dispose of the wastes accumulated
on site regularly and properly.
For chemical
waste containers, the Contractor was reminded to treat properly and store
temporarily in designated chemical waste storage area on site in accordance
with the Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes.
The status of
environmental licensing and permit is summarized in Table 2.16 below.
Table 2.16 Summary
of Environmental Licensing and Permit Status
License/
Permit |
License
or Permit No. |
Date of Issue |
Date of Expiry |
License/
Permit Holder |
Remarks |
Environmental Permit |
EP-354/2009/B |
28 Jan 2014 |
N/A |
HyD |
Tuen Mun- Chek Lap Kok Link |
Construction Dust Notification |
361571 |
5 Jul 2013 |
N/A |
GCL |
|
Construction Dust Notification |
362093 |
17 Jul 2013 |
N/A |
GCL |
For Area 23 |
Billing Account for Disposal |
7017735 |
10 Jul 2013 |
End of Project |
GCL |
- |
Chemical Waste Registration |
5213-961-G2380-13 |
10 Oct 2013 |
N/A |
GCL |
Chemical waste produced in Contract HY/2012/07 (Area 1 adjacent to Cheng Tung Road, Siu Ho Wan) |
Chemical Waste Registration |
5213-961-G2380-14 |
10 Oct 2013 |
N/A |
GCL |
Chemical waste produced in Contract HY/2012/07 (Area 2 adjacent to Cheung Tung Road, Pak Mong
Village) |
Chemical Waste Registration |
5213-974-G2588-03 |
4 Nov 2013 |
N/A |
GCL |
Chemical waste produced in Contract HY/2012/07 (WA5 adjacent to Cheung Tung Road, Yam O) |
Construction Waste Disposal Account |
7017735 |
10 Jul 2013 |
N/A |
GCL |
Waste disposal in Contract HY/2012/07 |
Waste Water Discharge License |
WT00019017-2014 |
13 May 2014 |
31 May 2019 |
GCL |
Discharge for marine portion |
Waste Water Discharge License |
WT00019018-2014 |
13 May 2014 |
31 May 2019 |
GCL |
Discharge for land portion |
Construction Noise Permit |
Nil |
Application in process |
N/A |
GCL |
For Piling Works |
Construction Noise Permit |
GW-RS0419-14 |
15 May 2014 |
13 Nov 2014 |
GCL |
For loading & unloading on NLH near Viaducts A & B |
Construction Noise Permit |
GW-RS0226-14 |
30 Mar 2014 |
29 Sep 2014 |
GCL |
For loading & unloading on NLH near Viaduct D |
Construction Noise Permit |
GW-RS0792-14 |
31 Jul 2014 |
24 Dec 2014 |
GCL |
Broad Permit for Works at Seafront & Marine Piers & Pier B9 |
Construction Noise Permit |
GW-RS0700-14 |
21 Jul 2014 |
31 Dec 2014 |
GCL |
For loading & unloading on NLH near Viaduct A & B |
Construction Noise Permit |
GW-RW0123-14 |
27 Feb 2014 |
27 Aug 2014 |
GCL |
For night works and works in general holiday at WA5 |
Dumping Permit/ Loading Permit (Type 1 ¡V Open Sea Disposal) |
(4) in EP/MD/14-075 |
25 Sep 2013 |
N/A |
GCL |
- |
Chemical Waste Registration |
5213-951-G2380-17 |
12 Jun 2014 |
N/A |
GCL |
Viaducts A, B, C, D & E |
Construction Noise Permit for night works and works in general
holidays |
GW-RS0646-14 |
27 Jun 2014 |
26 Oct 2014 |
GCL |
Broad Permit for Works at Seafront & Marine Piers & Pier B9 |
Construction Noise Permit for night works and works in general
holidays |
GW-RS0647-14 |
28 Jun 2014 |
26 Oct 2014 |
GCL |
Pier C7 & D8 at CEDD Access Road |
Construction Waste Disposal Account |
7017735 |
10 Jul 2013 |
N/A |
GCL |
- |
Construction Noise Permit |
GW-RW0640-14 |
28 Aug 2014 |
27 Feb 2015 |
GCL |
General works at WA5 |
Marine Dumping Permit |
EP/MD/15-066 |
28 Jul 2014 |
27 Jan 2015 |
GCL |
For dumping Type I sediment |
Marine Dumping Permit |
EP/MD/15-065 |
1 Aug 2014 |
31 Aug 2014 |
GCL |
For dumping Type I (Dedicated Site) and Type II sediment |
No complaint,
notification of summons and prosecution was received in the reporting period.
Statistics on
complaints, notifications of summons, successful prosecutions are summarized in
Appendix N.
Marine
Works
¡P Construction
of Pile caps at Viaduct B;
¡P Marine
piling platform installation;
¡P Marine Piling at Viaducts
B & E;
¡P Marine piling platform
installation for Viaduct D; and
¡P Additional
marine ground investigation (GI) and laboratory testing.
Land-based
Works
¡P Construction
of pile cap superstructure of Viaduct B;
¡P Fence
installation and relocation of Works Area 2, Viaducts A, B, C & D;
¡P Land
Piling at Viaduct B and Viaduct C;
¡P Piling
platform installation for Viaducts B, C, D and E;
¡P Additional
land GI, trial pits & lab testing;
¡P Utility
surveys; and
¡P Slope
work of Slope 9SE-B/C8, 9SE-B/C9 & 9SE-B/F9.
Potential
environmental impacts arising from the above upcoming construction activities
in the next reporting month of September 2014 are mainly associated with dust,
noise, marine water quality, marine ecology and waste management issues.
This Tenth
Monthly EM&A Report presents the findings of the EM&A activities
undertaken during the period from 1 to 31 August 2014, in accordance with the
Updated EM&A Manual and the requirements of EP-354/2009/B.
A total of thirteen (13) groups of forty-eight (48) Chinese White
Dolphins were sighted during the two sets of monitoring surveys in August
2014. All sightings were made in
NWL during the two sets of surveys in August, while no dolphin was sighted at
all in NEL. All except three (3)
sightings were made on primary lines during on-effort search, and none of the
dolphin groups was associated with operating fishing vessel. Whilst two
Action Level exceedances and no Limit Level exceedances were observed for the
quarterly dolphin monitoring data between June and August 2014, no unacceptable impact from the construction
activities of the TM-CLKL Southern Connection Viaduct Section on Chinese White
Dolphins was noticeable from general observations during the dolphin
monitoring in this reporting month.
The ET will
keep track on the construction works to confirm compliance of environmental
requirements and the proper implementation of all necessary mitigation measures.
[JY1]Appendix I1- 20 Aug, weather condition, typo ¡§Cloudy¡¨