Agreement No. CE 23/2012 (EP)
Environmental Monitoring and Audit
for Contaminated Mud Pits to the South of The Brothers
and at East Sha Chau (2012-2017) - Investigation
48th MONTHLY PROGRESS REPORT FOR August 2016
1.1.1
Since early 1990s, contaminated sediment ([1])
arising from various construction works (e.g. dredging and reclamation
projects) in Hong Kong has been disposed of at
a series of seabed pits at East of Sha Chau (ESC). In late
2008, a review indicated that the existing and planned facilities at ESC would
not be able to meet the disposal demand after 2012. In order to meet this demand, the Hong Kong
Special Administrative Region Government (HKSARG) decided to implement a new
contained aquatic disposal (CAD) ([2])
facility at the South of The Brothers (SB CMPs) which
had been under consideration for a number of years.
1.1.2
The environmental acceptability of the
construction and operation of the Project had been confirmed by findings of the
associated Environmental Impact Assessment (EIA) study completed in 2005 under Agreement No. CE 12/2002(EP) ([3]). The Director of Environmental Protection
(DEP) approved this EIA report under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO) in September
2005 (EIA
Register No.: AEIAR-089/2005).
1.1.3
In accordance with the EIA
recommendation, prior to commencement of construction works for the SB CMPs, the Civil Engineering and Development Department
(CEDD) undertook a detailed review and update of the EIA findings for the SB
site ([4]). Findings of the EIA review undertaken in
2009/ 2010 confirmed that the construction and operation of the SB site had
been predicted to be environmentally acceptable.
1.1.4
Environmental Permits (EPs) (EP-312/2008/A and EP-427/2011A) were
issued by the Environmental Protection Department (EPD) to the CEDD, the Permit
Holder, on 28 November 2008 for ESC CMP V and on 23 December 2011 for SB CMPs, respectively. Under the requirements of the EPs, an
Environmental Monitoring and Audit (EM&A) programme as set out in the
EM&A Manuals ()
()
is required to be implemented for the CMPs.
1.1.5
The present EM&A programme under Agreement No. CE
23/2012 (EP) covers the dredging, disposal and capping operations of the
SB CMPs as well
as ESC CMPs. Detailed works
schedule for ESC CMPs and SB CMPs
is shown in Figure 1.1. In August
2016, the following works were being undertaken:
· Disposal of contaminated mud at ESC CMP Vd; and
· Capping operation at SB CMP 2.
Figure 1.1 Works
Schedule for ESC CMPs and SB CMPs
1.2
Reporting Period
1.2.1
This 48th Monthly Progress
Report covers the EM&A activities for
the reporting month of August 2016.
1.3
Details of
Sampling and Laboratory Testing Activities
1.3.1
The following monitoring activities have
been undertaken for ESC CMPs in August 2016:
· Benthic Recolonisation Studies of ESC CMP IV was undertaken on 5 August 2016;
· Sediment Chemistry
after a Major Storm of ESC CMPs was undertaken on 5 August 2016;
· Routine Water Quality
Monitoring of ESC CMPs was
undertaken on 8 August 2016;
· Pit Specific Sediment
Chemistry of ESC CMP Vd was
undertaken on 9 August 2016;
· Demersal Trawling of ESC CMPs
was undertaken on 10 and 11 August 2016.
· Water Column Profiling of
ESC CMP Vd was
undertaken on 15 August 2016;
· Cumulative Impact Sediment
Chemistry of ESC CMPs was
undertaken on 16 and 17 August 2016;
· Sediment Toxicity Test of
ESC CMPs was
undertaken on 16 and 17 August 2016; and
1.3.2
The following monitoring activities have
been undertaken for SB CMPs in August 2016:
· Water Quality
Monitoring During Capping of SB CMPs was undertaken on 18 August 2016; and
· Benthic Recolonisation Studies of SB CMP 1 was undertaken on 23 August
2016.
1.4.1
No outstanding sampling remained for August 2016.
1.4.2
A summary of field activities conducted are presented in Annex
A. The following analyses are in progress and will be presented
in the corresponding quarterly report:
·
Species identification of the biota samples collected from Demersal Trawling for ESC CMPs in July and August 2016;
·
Laboratory analyses of sediment samples collected for Benthic Recolonisation Studies of ESC CMPs and SB CMP 1 in August 2016; and
·
Laboratory analyses for Sediment Toxicity Test of ESC CMPs in August 2016.
1.4.3
The following laboratory analyses are in progress during the
preparation of this monthly report and will be presented in the next monthly
report once the data are available:
·
Laboratory analyses of sediment samples collected for Pit
Specific Sediment Chemistry of ESC CMP Vd in August 2016; and
·
Laboratory analyses of sediment samples collected for Cumulative
Impact Sediment Chemistry of ESC CMP Vd in August 2016.
1.5
Brief Discussion
of the Monitoring Results for ESC CMPs
1.5.1
Brief discussion of the monitoring results of
the following activities for ESC CMPs is presented in
this 48th Monthly Progress Report:
· Routine Water Quality
Monitoring of ESC CMPs in
August 2016;
·
Water Column Profiling of ESC CMP Vd in August 2016; and
· Sediment Chemistry
after a Major Storm of ESC CMPs in August 2016.
1.5.2
Routine
Water Quality Monitoring of ESC CMPs – August 2016
1.5.3
Routine
Water Quality Monitoring of ESC CMPs was undertaken on 8 August 2016. The
monitoring results have been assessed for compliance with the Water Quality Objectives (WQOs) set by Environmental Protection Department (EPD).
This consists
of a review of the EPD routine water quality monitoring data for the wet season
period (April to October) of 2005 - 2014 from stations in the Northwestern
Water Control Zone (WCZ), where the ESC CMPs are
located (). For Salinity, the averaged value obtained
from the Reference stations was used for the basis as the WQO. Levels of Dissolved Oxygen (DO) and
Turbidity were also assessed for compliance with the Action and Limit Levels (see Table B1 of Annex B for details). The monitoring results are shown in Tables B2 and B3 of Annex B and Figures
1 - 10 of Annex C.
A total of sixteen (16) monitoring stations were sampled in August 2016 as shown in Figure 1.2.
In-situ Measurements
1.5.4
Graphical presentation of the monitoring results
(Temperature, DO, pH, Salinity and Turbidity) is shown in Figures 1 - 6 of Annex C. Analyses
of results for August 2016 indicated that
the levels of pH and DO complied
with the WQOs at all stations (Impact, Intermediate,
Reference and Ma Wan stations) in August
2016 (Table B2 of Annex B; Figures 1 and 3 of Annex C). Levels of Salinity at most stations complied
with the WQOs, except for Ma Wan station (Table B2 of Annex B; Figure 5 of Annex C). The higher Salinities recorded at Ma Wan
station are likely to be caused by the larger separation distance to Pearl
River mouth, which release a large amount of freshwater runoff in the area
during flooding, when compared to the Reference stations.
1.5.5
The levels of DO and Turbidity complied
with the Action and Limit Levels at all stations (Table B2 of Annex B; Figures 3 and 6 of Annex C).
1.5.6
Overall, in-situ measurement results
of the Routine
Water Quality Monitoring indicated that the disposal operation at ESC
CMP Vd did not appear to cause any unacceptable impacts in water quality in August 2016.
Laboratory Measurements
1.5.7
Laboratory analysis of August 2016
results indicated that concentrations of Cadmium, Lead, Silver and Mercury were
below their limit of reporting at all stations.
Arsenic, Chromium, Nickel, Copper and Zinc were detected in August 2016 samples and the
concentrations of these metals and metalloid were
similar amongst stations (Table B3 of Annex B; Figure 7 of Annex C).
1.5.8
For nutrients, concentrations of Total
Inorganic Nitrogen (TIN) at all stations in August 2016 exceeded the WQO (0.5 mg/L) (Table B3 of Annex B; Figure 8 of Annex C). It should be noted that due to the effect of
Pearl River, the North Western WCZ has historically experienced higher levels
of TIN ([8]). Since TIN concentrations were recorded to be
similar amongst all stations, the exceedances of TIN
WQO at all stations are unlikely to be caused by the disposal operation at ESC
CMP Vd. Concentrations
of Ammonia Nitrogen (NH3-N) were relatively similar amongst all stations (Table B3 of Annex B; Figure 8 of Annex C). Levels of 5-day Biochemical Oxygen Demand
(BOD5) appear to be higher at Ma Wan station in August 2016 (Table B3 of Annex B; Figure 9 of Annex C).
1.5.9
Analyses of results for August 2016 indicated that the SS levels complied with the WQO (11.1 mg/L for wet
season) and the
Action and Limit Levels at all stations (Table B3 of Annex B; Figure 10 of Annex C).
1.5.10
Overall, results of the Routine Water Quality
Monitoring indicated that the disposal operation at ESC CMP Vd did not appear to cause any unacceptable deterioration
in water quality in August 2016. Detailed statistical analysis will be
presented in the Quarterly Report to investigate any spatial and temporal
trends of potential concern.
1.5.11
Water
Column Profiling of ESC CMP Vd
– August 2016
1.5.12
Water
Column Profiling was
undertaken at a total of two sampling stations (Upstream and Downstream
stations) on 15 August
2016. The monitoring results have been
assessed for compliance with the WQOs (see Section 1.5.3 for details). Levels of DO and Turbidity were also assessed
for compliance with the Action and Limit Levels (see Table B1 of Annex B for details).
In-situ Measurements
1.5.13
Analyses of results for August 2016 indicated that levels of Salinity and pH complied with the WQOs at both Downstream and Upstream stations (Table B4 of Annex B).
Levels of DO at Upstream station was lower than
the WQO (4 mg/L for wet season). However, DO and Turbidity at all stations complied
with the Action and Limit Levels (Table
B4 of Annex B).
Laboratory Measurements for Suspended Solids (SS)
1.5.14
Analyses of results for August 2016 indicated that the SS
levels were higher than the WQO at Downstream station. However, both Upstream and Downstream
stations complied with the Action and Limit Levels (Table B4 of Annex B).
1.5.15
Overall, the monitoring results indicated that the mud
disposal operation at ESC CMP Vd did not appear to
cause any deterioration in water quality during this reporting period.
1.5.16
Sediment Chemistry after a
Major Storm of ESC CMPs – August 2016
1.5.17
Sampling
for Sediment Chemistry after a Major Storm Event was conducted at nine (9)
monitoring stations (Figure 1.3) on 5 August 2016 after the visit of
Typhoon Nida, which led to the issue of Gale or Storm
Wind Signal No.8 on 1 August 2016. The
track of Nida is shown in Figure 1.4.
Figure
1.4 Track of Typhoon Nida from 29 July to 3 August 2016 (Source: Hong Kong Observatory)
1.5.18
Analyses of results for the Sediment Chemistry after a Major Storm indicated that the concentrations
of all inorganic contaminants were below the LCEL (Figures 11 and 12 of Annex B).
1.5.19
Overall, there appeared to be no evidence showing the
failure of CMPs in retaining disposed mud or causing
contamination of sediments after the major storm event in August 2016.
1.6.1
Brief discussion of the monitoring results of
the following activities for SB CMPs is presented in
this 48th
Monthly Progress Report:
·
Water Quality Monitoring during Capping Operations of SB CMPs
in August 2016.
1.6.2
Water Quality Monitoring
during Capping of SB CMPs – August 2016
1.6.3
The monitoring results obtained during August 2016 sampling in the wet season have
been assessed for compliance with the WQOs (see Section 1.5.3 for details). Levels
of DO and Turbidity were also assessed for compliance with the Action and Limit
Levels (see Table B5 of Annex B for details).
A total of twenty (20) monitoring stations were sampled in
August 2016 as shown in Figure 1.5.
Graphical presentation of the monitoring results is provided in Annex
C.
In-situ Measurements
1.6.4
Graphical presentation of the monitoring results
(Temperature, DO, pH, Salinity and Turbidity) is shown in Figures 13
- 18 of Annex C.
Levels of pH at all stations in August 2016 complied with the WQO (Table B6 of Annex B; Figure 13 of Annex C).
The levels
of Turbidity at
all stations complied with the Action and Limit levels in August 2016 (Table B6 of Annex B; Figure 14 of Annex C).
DO at all stations also complied with the WQO and the Action and Limit
levels in August 2016 (Table B6 of Annex B;
Figure 16 of Annex
C).
1.6.5
Levels of Salinity at most stations complied with the WQO except at Tai Ho Bay 2 station (Table B6 of Annex
B; Figure 18 of Annex C). The
lower Salinities recorded at Tai Ho Bay 2 are likely due to the close proximity
of the nearby streams, which release large amount of freshwater runoff in the
area during flooding.
Laboratory Measurement
1.6.6
Concentrations of SS were recorded higher
than the WQO (11.1 mg/L for wet season) at
Reference, Intermediate, Ma Wan and Tai Mo To stations in August 2016 (Table B6 of Annex B; Figure 19 of Annex C). However, levels of SS at all stations complied with the Action and Limit Levels
(Table B4 of Annex B).
1.6.7
For nutrients, concentrations of NH3 were relatively similar amongst all stations (Table B6 of Annex
B; Figure 20 of Annex C). TIN at all stations exceeded the WQO of 0.5
mg/L (Table B6 of Annex B; Figure 21 of Annex C). As discussed in Section 1.5.8, the
North Western WCZ has historically experienced higher levels of TIN and
such exceedances of TIN WQO at all stations are
unlikely to be caused by the disposal operation at CMP 2. Levels of BOD5
appeared to be higher at Tai Ho Bay 1 station in August 2016 (Table B6 of Annex B; Figure 22 of Annex C).
1.6.8
Overall, the monitoring results indicated
that the capping operation at CMP 2 did not appear to cause any unacceptable
deterioration in water quality in August
2016. Statistical analysis will be undertaken
and presented in the quarterly report to investigate whether the capping
operations at CMP 2 is causing any unacceptable impacts in water quality of the area.
1.7
Activities
Scheduled for the Next Month
1.7.1
The following monitoring activities will be
conducted in the next monthly period of September 2016 for ESC CMPs:
·
Water Column Profiling of ESC CMP Vd; and
·
Pit Specific Sediment Chemistry of ESC CMP Vd.
1.7.2
No monitoring activities will be
scheduled in the next monthly period of September 2016 for SB CMPs.
1.7.3
The sampling schedule is presented in Annex
A.
1.8.1
A summary of the Study programme is presented in Annex
D.