Agreement No. CE
63/2016 (EP)
Environmental Monitoring and Audit
for Disposal Facility to the East of Sha Chau (2017-2020) - Investigation
MONTHLY EM&A REPORT FOR September 2017
¡P Dredging operation at ESC CMP Vb;
¡P Disposal of contaminated mud at
ESC CMP Vd; and
¡P Capping operation at SB CMP 2.
Figure 1.1 Works Schedule for ESC CMP V and SB CMPs
¡P
Water Quality Monitoring during
Dredging of ESC CMP Vb was undertaken on 1, 6, 8, 11, 13, 15, 18, 20, 22 and 25 September 2017;
¡P
Water Column Profiling of ESC CMP Vd was
undertaken on 7 September 2017; and
¡P
Pit Specific Sediment Chemistry of ESC CMP Vd was
undertaken on 12 September 2017.
¡P
Water Quality Monitoring During Capping of SB CMPs was undertaken on 29 September 2017.
¡P Laboratory analyses of
sediment samples collected for Pit Specific
Sediment Chemistry of ESC CMP Vd in September 2017;
and
¡P Laboratory analyses of
water samples collected for Water Quality Monitoring During Capping of SB CMPs in September 2017.
¡P
Water Quality Monitoring During
Dredging of ESC CMP Vb in September 2017; and
¡P
Water Column Profiling of ESC CMP Vd in September 2017.
Table 1.1 Details of Exceedances
Recorded at ESC CMP Vb between 1 and 25 September
2017
Date |
Tide |
Parameter |
Station |
Type of Exceedance |
Remarks |
8
September 2017 |
Mid-Ebb |
Turbidity |
DS4 |
Action |
These exceedances were not considered as indicating
any unacceptable impacts from the dredging operations to WSRs outside the
works area due to the following reasons: ¡P
The
exceedance was not considered as indicating any unacceptable impacts from the
dredging operations to Water Sensitive Receivers (WSRs) outside the works
area because Stations DS4 and DS5 are located further away from the works area of CMP
Vd when compared to stations DS1 at which the
levels of Turbidity did not exceed the Action and Limit Levels during the
same tidal period. ¡P
In
addition, levels of SS at all stations complied with the Action and Limit
levels. Therefore, it is considered
that the dredging operations did not cause adverse water quality impact in
terms of SS levels, which are more representative to determine the effects of
dredging operation to nearby sensitive receivers (e.g. fisheries). |
8
September 2017 |
Mid-Ebb |
Turbidity |
DS5 |
Limit |
|
22
September 2017 |
Mid-Ebb |
Turbidity |
DS4 |
Action |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
22
September 2017 |
Mid-Flood |
Turbidity |
DS1 |
Limit |
These exceedances were not considered as indicating any unacceptable
impacts from the dredging operations to WSRs outside the works area due to
the following reasons: ¡P
The
exceedances of Limit Levels were only recorded within a limited range at
Impact stations DS1, DS2 and DS3 which are within ~1 km distance downstream
from the dredging operation during one tidal period and exceedances were not
recorded at any WSR stations. In
addition, the dredging rate was well within the limit as specified under the
EP. As such, there did not appear
to be any evidence of unacceptable water quality impact as a result of the
dredging operations at the CMP Vd. ¡P
In
addition, levels of SS at all stations complied with the Action and Limit
levels. Therefore, it is
considered that the dredging operations did not cause adverse water quality
impact in terms of SS levels, which are more representative to determine the
effects of dredging operation to nearby sensitive receivers (e.g. fisheries).
|
22
September 2017 |
Mid-Flood |
Turbidity |
DS2 |
Limit |
|
22
September 2017 |
Mid-Flood |
Turbidity |
DS3 |
Limit |
|
|
|
|
|
|
In-situ
Measurements
Laboratory Measurements for Suspended Solids (SS)
¡P
Water Quality Monitoring during Capping Operations of SB CMPs
in September 2017.
¡P
Routine Water Quality Monitoring of ESC CMP Vd;
¡P
Water Column Profiling of ESC CMP Vd; and
¡P
Pit Specific Sediment Chemistry of ESC CMP Vd.
([1])
ERM (2013) Final Report. Submitted
under Agreement No. CE 4/2009 (EP) Environmental
Monitoring and Audit for Contaminated Mud Pit at East Sha Chau. For CEDD.
([2]) ERM (2017) Final
Report. Submitted
under Agreement No. CE 23/2012 (EP) Environmental
Monitoring and Audit for Contaminated Mud Pits to the
South of The Brothers and at East Sha Chau
(2012 - 2017). For
CEDD.
([3]) ERM -
Hong Kong, Ltd (2009) Baseline Monitoring Report. For the Civil Engineering &
Development Department, Hong Kong SAR Government.