1.1 Background
1.2 Scope of Report
1.3 Organization Structure
1.4 Summary of Construction Works
2.1 Air quality
2.2 Noise Monitoring
2.3 Water Quality MOnitoring
2.4 Dolphin monitoring
2.5 EM&A Site inspection
2.6 Waste Management Status
2.7 Environmental Licenses and
Permits
2.8 Implementation Status of
Environmental Mitigation Measures
2.9 Summary of Exceedances of the
Environmental Quality Performance Limit
2.10 Summary of Complaints,
Notification of Summons and Successful Prosecutions
3.1 Construction Programme for
the Coming Months
3.2 Key Issues for the Coming
Month
3.3 Monitoring Schedule for the
Coming Month
4 Conclusions and recommendations
4.1 Conclusions
4.2 Recommendations
List of Tables
Table 1.1 |
|
Table 2.1 |
|
Table
2.2 |
|
Table
2.3 |
Summary
of 1-hour TSP Monitoring Results in the Reporting Period |
Table
2.4 |
Summary
of 24-hour TSP Monitoring Results in the Reporting Period |
Table
2.5 |
|
Table 2.6 |
|
Table
2.7 |
Summary
of Construction Noise Monitoring Results in the Reporting Period |
Table 2.8 |
Locations
of Impact Water Quality Monitoring Stations and its Corresponding Monitoring Requirements |
Table 2.9 |
|
Table
2.10 |
|
Table
2.11 |
|
Table
2.12 |
|
Table
2.13 |
|
Table
2.14 |
|
Table
2.15 |
|
Table
2.16 |
List of Figures
Figure 1.1 |
|
Figure 1.2 |
|
Figure 1.3 |
|
Figure 1.4 |
|
Figure 1.5 |
|
Figure 1.6 |
|
Figure 1.7 |
|
Figure 1.8 |
|
Figure 1.9 |
|
Figure 1.10 |
|
Figure 1.11 |
|
Figure 1.12 |
|
Figure 2.1 |
|
Figure 2.2 |
|
Figure 2.3 |
|
Figure 2.4 |
|
Figure 2.5 |
Locations of Dolphin
Sightings during Impact Dolphin Monitoring Survey |
Figure 2.6 |
List of Appendices
Appendix A |
|
Appendix B |
|
Appendix C |
Implementation Schedule
of Environmental Mitigation Measures (EMIS) |
Appendix D |
|
Appendix E |
|
Appendix F |
|
Appendix G |
Impact Air Quality
Monitoring Results and Graphical Presentation |
Appendix H |
|
Appendix I |
|
Appendix J |
Impact Water Quality
Monitoring Results and Graphical Presentation |
Appendix K |
|
Appendix L |
|
Appendix M |
|
Appendix N |
Under Contract No. HY/2012/07,
Gammon Construction Limited (GCL) is commissioned by the Highways Department
(HyD) to undertake the design and construction of the Southern Connection Viaduct
Section of the Tuen Mun ¡V Chek Lap Kok Link Project (TM-CLK Link Project) while
AECOM Asia Company Limited was appointed by HyD as the Supervising
Officer. For implementation of the
environmental monitoring and audit (EM&A) programme under the Contract,
ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET). ENVIRON Hong Kong Ltd. was employed by
the HyD as the Independent Environmental Checker (IEC) and Environmental
Project Office (ENPO) in accordance with Environmental
Permit No. EP-354/2009/A.
The
construction phase of the Contract commenced on 31 October 2013 and will be
tentatively be completed by 2018.
The impact monitoring of the EM&A programme, including air quality,
noise, water quality and marine ecological monitoring as well as environmental
site inspections, commenced on 31 October 2013.
This
is the second monthly EM&A report presenting the EM&A works carried out
during the period from 1 to 31 December 2013 for the Southern
Connection Viaduct Section in accordance with the Updated EM&A Manual of the
TM-CLK Link Project. As informed by the Contractor, major
activities in the reporting period included:
Marine-based Works
¡P
Survey tower erection;
¡P
Marine piling platform
installation;
¡P
Construction of rockfill
platform at Viaduct D landing; and
¡P
Additional marine ground
investigation (GI) and laboratory testing.
Land-based
Works
¡P
SOR¡¦s and Contractor¡¦s
site offices erection at Area 5;
¡P
Satellite container
offices erection along seawall;
¡P
Tree felling at Pak Mong
area;
¡P
Fence relocation for
Viaducts A, C & D;
¡P
Additional land GI, trial
pits and laboratory testing; and
¡P
Utility surveys.
A summary of
monitoring and audit activities conducted in the reporting period is listed
below:
24-hour TSP
monitoring 6
sessions
1-hour TSP
monitoring 6
sessions
Noise
monitoring 6
sessions
Impact Water
Quality Monitoring 13
sessions
Impact dolphin
monitoring 2
sessions
Joint
Environmental site inspection 4
sessions
Breaches of Action and Limit Levels for Air Quality
Two (2)
exceedances of Action Level in 24-hr TSP monitoring were recorded at both ASR8A
and ASR8 in the reporting month. No
exceedance of Action and Limit Levels was recorded for 1-hour monitoring in the
reporting month. The exceedance was
considered not related to the construction works of this Contract upon further
investigation.
Breaches of Action and Limit Levels for Noise
No exceedance
of Action and Limit Levels was recorded for construction noise monitoring in
the reporting month.
Breaches of Action and Limit Levels for Water Quality
No exceedance
of Action and Limit Levels was recorded for impact water quality monitoring in
the reporting month.
Impact Dolphin Monitoring
During this
month of dolphin monitoring, no unacceptable impact from the construction activities
of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins
was noticeable from general observations.
Due to monthly
variation in dolphin occurrence within the study area, it would be more
appropriate to draw conclusion on whether any impacts on dolphins have been
detected related to the construction activities of the TM-CLKL Southern
Connection Viaduct Section in the quarterly EM&A reports, where comparison
on distribution, group size and encounter rates of dolphins between the
quarterly impact monitoring period and baseline monitoring period will be made.
Daily
marine mammal exclusion zone monitoring was undertaken. No sighting of the Indo-Pacific humpback
dolphin Sousa chinensis was recorded
in December 2013 during the exclusion zone monitoring.
Environmental Complaints, Non-compliance & Summons
No complaint,
notification of summons and successful prosecution was received in the
reporting month.
Reporting Change
There was no
reporting change required in the reporting period.
Upcoming Works for the Next Reporting Period
Works to be
undertaken in the next monitoring period of January 2014 include the following:
Marine
Works
¡P
Erect temporary working platforms;
¡P
GI and trial pit works for marine foundation at
Viaduct B; and
¡P
Marine foundation at Viaduct B, E2, E5-8 and E13.
Land-based
Works
¡P
Site set-up for Area 2 and works area along Cheung
Tung Road for Viaduct B;
¡P
Set up container site offices along CEDD access road;
and
¡P
Construct temporary road at CEDD track for piling.
Future Key Issues
Potential
environmental impacts arising from the above upcoming construction activities
in the next reporting month of January 2014 are mainly associated with dust, noise,
marine water quality, marine ecology and waste management issues.
According to
the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure
Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge,
Lantau Link and North Lantau Highway would be operating beyond capacity after
2016. This forecast has been based
on the estimated increase in cross boundary traffic, developments in the
Northwest New Territories (NWNT), and possible developments in North Lantau,
including the Airport developments, the Lantau Logistics Park (LLP) and the
Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB).
In order to cope with the anticipated traffic demand, two new road
sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL)
and Tuen Mun Western Bypass (TMWB) are proposed.
An
Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in
accordance with the EIA Study Brief (No. ESB-175/2007) and
the Technical Memorandum of the
Environmental Impact Assessment Process (EIAO-TM). The
EIA Report was submitted under the Environmental Impact Assessment Ordinance
(EIAO) in August 2009. Subsequent
to the approval of the EIA Report (EIAO Register Number AEIAR-145/2009), an
Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of
Environmental Protection (DEP) on 4 November 2009, and EP variation (EP-354/2009A)
was issued on 8 December 2010.
Under
Contract No. HY/2012/07,
Gammon Construction Limited (GCL) is commissioned by the Highways Department
(HyD) to undertake the design and construction of the Southern Connection
Viaduct Section of TM-CLKL (¡§the Contract¡¨) while AECOM Asia
Company Limited was appointed by HyD as the Supervising Officer. For implementation of the environmental
monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong,
Limited (ERM) has been appointed as the Environmental Team (ET). ENVIRON Hong Kong Ltd. was employed by
HyD as the Independent Environmental Checker (IEC) and Environmental Project
Office (ENPO) in accordance with Environmental
Permit No. EP-354/2009/A.
The
organization structure of the Contract is shown in Appendix A.
The key personnel contact names and
contact details are summarized in Table
1.1 below.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
SOR (AECOM Asia
Company Limited) |
Chief
Resident Engineer |
Daniel Ip |
3553 3800 |
2492 2057 |
ENPO / IEC (ENVIRON
Hong Kong Ltd.) |
ENPO Leader |
Y.H. Hui |
3465 2888 |
3465 2899 |
IEC |
Tony Cheng |
3465 2888 |
3465 2899 |
|
Contractor (Gammon
Construction Limited) |
Environmental
Manager |
Brian Kam |
3520 0381 |
3520 0486 |
Environmental
Officer |
Roy Leung |
3520 0387 |
3520 0486 |
|
|
24-hour
Complaint Hotline |
|
9738 4332 |
|
ET (ERM-HK) |
ET Leader |
Jovy Tam |
2271 3113 |
2723 5660 |
Marine-based
Works
¡P
Survey tower erection;
¡P
Marine piling platform
installation;
¡P
Construction of rockfill
platform at Viaduct D landing; and
¡P
Additional marine ground
investigation (GI) and laboratory testing.
Land-based
Works
¡P
SOR¡¦s and Contractor¡¦s
site offices erection at Area 5;
¡P
Satellite container
offices erection along seawall (ie CEDD Access Road);
¡P
Tree felling at Pak Mong
area;
¡P
Fence relocation for
Viaducts A, C & D;
¡P
Additional land GI, trial
pits & lab testing; and
¡P
Utility surveys.
The EM&A
programme required environmental monitoring for air quality, noise, water
quality and marine ecology as well as environmental site inspections for air
quality, noise, water quality, waste management, marine ecology and landscape
and visual impacts. The EM&A
requirements and related findings for each component are summarized in the
following sections.
Air quality monitoring stations ASR9A and ASR9C in
Siu Ho Wan MTRC Depot were the proposed locations in accordance with the
Updated EM&A Manual. However,
authorization of getting access into Siu Ho Wan MTRC Depot is still being
sought for the impact monitoring of the EM&A programme for the captioned
Contract. Thus, a proposal for
setting up alternative air quality monitoring stations at ASR8A (Area 4) and
ASR8 (Rooftop of Pak Mong Village Watch Tower) was submitted on 13 November
2013 which was subsequently approved.
Table 2.1 Locations
of Impact Air Quality Monitoring Stations
Monitoring Dates |
Monitoring Station |
Location |
Description |
3, 9, 13,
19, 24, 30 December 2013 |
ASR 8 (1) |
Pak Mong
Village Watch Tower |
Rooftop of
the premise |
ASR 8A (1) |
Area 4 |
On ground at
the Area 4 |
|
Note: (1)
Air Quality Monitoring Stations ASR9A and ASR9C (Siu Ho Wan MTRC Depot)
proposed in accordance with the Updated EM&A were temporarily relocated
to ASR8A and ASR8, respectively. |
Table 2.2 Air Quality Monitoring Equipment
Equipment |
Brand and Model |
High Volume Sampler |
Tisch Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High Volume Sampler (Model No. TE-5170) |
Wind Sensor |
Global Water WE550 |
Table 2.3 Summary
of 1-hour TSP Monitoring Results in the Reporting Period
|
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
ASR
8A |
145 |
42
- 275 |
394 |
500 |
ASR
8 |
157 |
63
- 319 |
393 |
500 |
Table 2.4 Summary
of 24-hour TSP Monitoring Results in the Reporting Period
|
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
ASR
8A |
136 |
80
- 210 |
178 |
260 |
ASR
8 |
131 |
83
- 205 |
178 |
260 |
All
1-hour TSP results were below the Action and Limit level at all monitoring
locations in the reporting period. However,
two (2) exceedances of Action Level in 24-hr TSP were detected on 13 December
2013 at both ASR8A and ASR8. Upon
further investigation, the exceedances were considered not related to the
construction works of this Contract.
The Contractor was reminded to keep track of the construction activities
in compliance with the environmental requirements and implement all necessary
mitigation measure properly. Cumulative
statistics of exceedances is presented in Appendix N
Noise
monitoring was performed using sound level meter at the designated monitoring
station NSR 1 (Figure 2.2; Table 2.5) in
accordance with the requirements stipulated in the Updated EM&A Manual. Acoustic calibrator was deployed to
check the sound level meters at a known sound pressure level. Details of the equipment deployed are provided
in Table 2.6. Copies of the calibration certificates
for the equipment are presented in Appendix E.
Table 2.5 Location
of Impact Noise Monitoring Station
Monitoring Station |
Location |
Description |
Parameter |
Frequency and Duration |
NSR 1 |
Pak Mong
Village Watch Tower |
Rooftop of
the premise |
30-mins
measurement at each monitoring station between 0700 and 1900 on normal
weekdays (Monday to Saturday). Leq, L10
and L90 would be recorded. |
At least
once per week |
Table 2.6 Noise
Monitoring Equipment
Equipment |
Brand and Model |
Integrated
Sound Level Meter |
Rion
NL-31 |
Acoustic
Calibrator |
Rion
NC-73 |
Table 2.7 Summary
of Construction Noise Monitoring Results in the Reporting Period
|
Average , dB(A), Leq
(30mins) |
Range, dB(A), Leq (30mins) |
Limit Level, dB(A), Leq
(30mins) |
NSR
1 |
58 |
56
- 59 |
75 |
Station ID |
Type |
Coordinates |
*Parameters, unit |
Frequency |
Depth |
|
|
|
Easting |
Northing |
|
|
|
IS(Mf)9 |
Impact
Station (Close to HKBCF construction site) |
813273 |
818850 |
Temperature(¢XC)
pH(pH unit)
Turbidity (NTU)
Water depth (m)
Salinity (ppt)
DO (mg/L and % of saturation) SS (mg/L) |
Impact monitoring: 3 days per week, at mid-flood
and mid-ebb tides during the construction period of the Contract |
3 water depths: 1m below sea surface, mid-depth and 1m above sea bed. If the water depth is less than 3m,
mid-depth sampling only. If water
depth less than 6m, mid-depth may be omitted |
IS(Mf)16 |
Impact Station
(Close to HKBCF construction site) |
814328 |
819497 |
|||
IS8 |
Impact Station(Close
to HKBCF construction site) |
814251 |
818412 |
|||
SR4 |
Sensitive receiver
(Tai Ho Inlet) |
814760 |
817867 |
|||
SR4a |
Sensitive receiver |
815247 |
818067 |
|||
CS(Mf)3 |
Control
Station |
809989 |
821117 |
|||
CS(Mf)5 |
Control
Station |
817990 |
821129 |
|||
*Notes: |
Table
2.9 Water
Quality Monitoring Equipment
Equipment |
Brand and Model |
DO, Temperature meter and Salinity |
YSI Pro2030 |
Turbidimeter |
HACH Model 2100Q |
pH meter |
HANNA HI8314 |
Positioning
Equipment |
Koden913MK2 with KBG-3 DGPS antenna |
Water Depth Detector |
Speedtech Instrument SM-5 |
Water Sampler |
Kemmerer 1520 (1520-C25) 2.2L with messenger |
No
Action and Limit level exceedance was recorded at all monitoring stations for
impact water quality monitoring in the reporting month. No action is thus required to be
undertaken in accordance with the Event Action Plan presented in Appendix L.
Table
2.10 Dolphin Monitoring Equipment
Equipment |
Model |
|
Global Positioning
System (GPS) Camera Laser Binoculars Marine Binocular Vessel for Monitoring |
Garmin 18X-PC Geo One Phottix Nikon D90 300m 2.8D fixed focus Nikon D90 20-300m zoom lens Infinitor LRF 1000 Bushell 7 x 50 marine binocular with compass and
reticules 65 foot single engine motor vessel with viewing platform 4.5m above
water level |
|
Table
2.11 Impact Dolphin Monitoring Line Transect
Co-ordinates
Line No. |
Easting |
Northing |
|
Line No. |
Easting |
Northing |
||
1 |
Start Point |
804671 |
814577 |
|
13 |
Start Point |
816506 |
819480 |
1 |
End Point |
804671 |
831404 |
|
13 |
End Point |
816506 |
824859 |
2 |
Start Point |
805475 |
815457 |
|
14 |
Start Point |
817537 |
820220 |
2 |
End Point |
805477 |
826654 |
|
14 |
End Point |
817537 |
824613 |
3 |
Start Point |
806464 |
819435 |
|
15 |
Start Point |
818568 |
820735 |
3 |
End Point |
806464 |
822911 |
|
15 |
End Point |
818568 |
824433 |
4 |
Start Point |
807518 |
819771 |
|
16 |
Start Point |
819532 |
821420 |
4 |
End Point |
807518 |
829230 |
|
16 |
End Point |
819532 |
824209 |
5 |
Start Point |
808504 |
820220 |
|
17 |
Start Point |
820451 |
822125 |
5 |
End Point |
808504 |
828602 |
|
17 |
End Point |
820451 |
823671 |
6 |
Start Point |
809490 |
820466 |
|
18 |
Start Point |
821504 |
822371 |
6 |
End Point |
809490 |
825352 |
|
18 |
End Point |
821504 |
823761 |
7 |
Start Point |
810499 |
820690 |
|
19 |
Start Point |
822513 |
823268 |
7 |
End Point |
810499 |
824613 |
|
19 |
End Point |
822513 |
824321 |
8 |
Start Point |
811508 |
820847 |
|
20 |
Start Point |
823477 |
823402 |
8 |
End Point |
811508 |
824254 |
|
20 |
End Point |
823477 |
824613 |
9 |
Start Point |
812516 |
820892 |
|
21 |
Start Point |
805476 |
827081 |
9 |
End Point |
812516 |
824254 |
|
21 |
End Point |
805476 |
830562 |
10 |
Start Point |
813525 |
820872 |
|
22 |
Start Point |
806464 |
824033 |
10 |
End Point |
813525 |
824657 |
|
22 |
End Point |
806464 |
829598 |
11 |
Start Point |
814556 |
818449 |
|
23 |
Start Point |
814559 |
821739 |
11 |
End Point |
814556 |
820992 |
|
23 |
End Point |
814559 |
824768 |
12 |
Start Point |
815542 |
818807 |
|
|
|
|
|
12 |
End Point |
815542 |
824882 |
|
|
|
|
|
The action and
limit levels of dolphin impact monitoring are shown in Tables 2.12 & 2.13.
The Event and Action plan is presented in Appendix K.
Table 2.12 Action Level and
Limit Level for Dolphin Impact Monitoring
|
North Lantau Social Cluster |
|
|
NEL |
NWL |
Action Level |
STG
< 70% of baseline & |
STG
< 70% of baseline & |
Limit Level |
[STG < 40% of baseline & ANI
< 40% of baseline] and STG < 40% of baseline & ANI
< 40% of baseline |
|
Notes: 1.
STG
means quarterly encounter rate of number of dolphin sightings, which is 6.00
in NEL and 9.85 in NWL during the baseline monitoring period 2.
ANI
means quarterly encounter rate of total number of dolphins, which is 22.19
in NEL and 44.66 in NWL during the baseline monitoring period 3.
For
North Lantau Social Cluster, AL will be trigger if NEL or NWL fall below the
criteria; LL will be triggered if both NEL and NWL fall below the criteria. |
Table 2.13 Derived Value of
Action Level (AL) and Limit Level (LL)
|
North
Lantau Social Cluster |
|
|
NEL |
NWL |
Action
Level |
STG
< 4.2 & ANI< 15.5 |
STG
< 6.9 & ANI < 31.3 |
Limit
Level |
[STG < 2.4 & ANI <8.9] and [STG < 3.9 & ANI <17.9] |
A
total of eight groups
of thirty-three dolphins sightings were recorded
during the two sets
of surveys. All
except one sighting were made in NWL during the two sets of surveys in December,
with another group being sighted in NEL.
None
of the 33
sightings was made in the proximity of this Project. The distribution of dolphin sightings
during the reporting month is shown in Figure 2.5.
Encounter
rates of Chinese White Dolphins are deduced from the survey effort and
on-effort sighting data made under favourable conditions (Beaufort 3 or below with
good visibility) in December 2013 with the results presented in Tables 2.14 and 2.15.
Table 2.14 Individual Survey
Event Encounter Rates
|
|
Encounter rate (STG) (no. of
on-effort dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI)
(no. of dolphins from all on-effort sightings per 100 km of survey
effort) |
|
|
Primary Lines Only |
Primary Lines Only |
NEL |
Set 1: Dec
5th/ 9th |
2.68 |
8.05 |
|
Set 2: Dec
13th/ 19th |
0.0 |
0.0 |
NWL |
Set 1:
Dec 5th/ 9th |
6.95 |
30.57 |
|
Set 2:
Dec 13th/19th |
6.82 |
27.27 |
Table 2.15 Monthly Average
Encounter Rates
|
Encounter rate (STG)
(no. of on-effort dolphin sightings per 100 km of
survey effort) |
Encounter rate (ANI)
(no. of dolphins from all on-effort sightings per
100 km of survey effort) |
||
Primary Lines Only |
Both Primary and Secondary
Lines |
Primary Lines Only |
Both Primary and Secondary
Lines |
|
Northeast Lantau |
1.4 |
1.0 |
4.1 |
3.1 |
Northwest Lantau |
6.9 |
5.3 |
29.6 |
22.6 |
Note: Overall dolphin encounter rates (sightings per
100km of survey effort) from all four surveys are conducted in December 2013 on
primary lines only as well as both primary lines and secondary lines in
Northeast and Northwest Lantau
The
impact phase marine bored piling monitoring has not been carried out in the
reporting month since no bored piling works were scheduled to be undertaken.
Daily 250 m marine
mammal exclusion zone monitoring was undertaken during the period of dredging
activities being undertaken. No sighting of the Indo-Pacific
humpback dolphin Sousa chinensis were recorded in December 2013
during the exclusion zone monitoring.
Air Quality
Noise
Water Quality
Chemical and Waste Management
Floating
debris and trash were observed within the silt curtain.
Stagnant
water was found accumulating in drip tray.
Stockpiles
were not covered properly by tarpaulin sheet.
Landscape and Visual Impact
Miscellaneous
The
Environmental Permit was displayed at the site entrance.
The
Contractor has rectified all observations identified during environmental site
inspection in the reporting month.
Follow-up inspections on the status on provision of mitigation measures
will be conducted to ensure all identified items are mitigated properly.
The status of
environmental licensing and permit is summarized in Table 2.16 below.
Table 2.16 Summary of Environmental Licensing and
Permit Status
Statutory Reference |
License/
Permit |
License
or Permit No. |
Date
of Issue |
Date
of Expiry |
License/ Permit Holder |
Remarks |
EIAO |
Environmental Permit |
EP-354/2009/A |
8 Dec 2010 |
NA |
HyD |
Tuen Mun- Chek Lap Kok Link |
NCO |
Construction Dust Notification |
361571 |
5 Jul 2013 |
NA |
GCL |
- |
NCO |
Construction Dust Notification |
362093 |
17 Jul 2013 |
NA |
GCL |
Areas 2 and 3 |
WDO |
Billing Account for Disposal |
7017735 |
10 Jul 2013 |
End of Project |
GCL |
- |
WDO |
Chemical Waste Registration |
5213-961-G2380-13 |
10 Oct 2013 |
NA |
GCL |
Chemical waste produced in Contract HY/2012/07 |
WDO |
Chemical Waste Registration |
5213-961-G2380-14 |
10 Oct 2013 |
NA |
GCL |
Chemical waste produced in Contract HY/2012/07 |
WDO |
Chemical Waste Registration |
5213-974-G2588-03 |
4 Nov 2013 |
NA |
GCL |
Chemical waste produced in Contract HY/2012/07 |
WDO |
Construction Waste Disposal Account |
7017735 |
10 Jul 2013 |
NA |
GCL |
Waste disposal in Contract HY/2012/07 |
WPCO |
Waste Water Discharge License |
Nil |
Application Ref. 368337 |
NA |
GCL |
Discharge for discharge points for Viaduct A & B |
NCO |
Construction Noise Permit |
Nil |
Application in process |
NA |
GCL |
For Piling Works |
NCO |
Construction Noise Permit |
GW-RW0660-13 |
27 Sep 2013 |
02 Feb 2014 |
GCL |
For night works and works in general
holidays |
NCO |
Construction Noise Permit |
GW-RS1129-13 |
31 Oct 2013 |
30 Apr 2014 |
GCL |
For night works and works in general
holidays |
NCO |
Construction Noise Permit |
GW-RS1186-13 |
23 Oct 2013 |
24 Dec 2013 |
GCL |
For night works and works in general
holidays |
NCO |
Construction Noise Permit |
GW-RS1187-13 |
24 Oct 2013 |
28 Feb 2014 |
GCL |
For night |
NCO |
Construction Noise Permit |
GW-RW0925-13 |
11 Dec 2013 |
17 Apr 2014 |
GCL |
Renewal of Area 5 site office erection |
NCO |
Construction Noise Permit |
GW-RS1423-13 |
11 Dec 2013 |
30 Apr 2014 |
GCL |
Renewal for marine portion |
NCO |
Construction Noise Permit |
GW-RS1413-13 |
18 Dec 2013 |
26 Mar 2014 |
GCL |
For loading and unloading on NLH near viaduct A & B |
DASO |
Dumping Permit/ Loading Permit (Type 1 ¡V Open Sea Disposal) |
(4) in EP/MD/14-075 |
25 Sep 2013 |
NA |
GCL |
- |
Marine
Works
¡P
Erect temporary working platforms;
¡P
GI and trial pit works for marine foundation at
Viaduct B; and
¡P
Marine foundation at Viaduct B, E2, E5-8 and E13.
Land-based Works
¡P
Site set-up for Area 2 and works area along Cheung
Tung Road for Viaduct B;
¡P
Set up container site offices along CEDD access road;
and
¡P
Construct temporary road at CEDD track for piling.
Potential
environmental impacts arising from the above upcoming construction activities
in the next reporting month of January 2014 are mainly associated with dust, noise,
marine water quality, marine ecology and waste management issues.
This second
Monthly EM&A Report presents the findings of the EM&A activities
undertaken during the period from 1 to 31 December 2013, in accordance with the
Updated EM&A Manual and the requirements of EP-354/2009/A.
A total of eight (8) groups
of thirty-three
(33) dolphins sighting were recorded during the two sets of
surveys. All except one
sighting were made in NWL during the two sets of surveys with one sighting made
in NEL in December 2013. None of
the 33 sightings
was made in the proximity of the TM-CLKL Southern Connection Viaduct
Section. During this reporting
period of dolphin monitoring, no unacceptable impact from the construction activities
of the TM-CLKL Southern Connection Viaduct Section on Chinese
White Dolphins was noticeable from general observations.
Air Quality
Impact
¡P All
working plants and vessels on site should be regularly inspected and properly
maintained by the Contractor to avoid dark smoke emission.
¡P Open
stockpiles should be properly covered by the Contractor.
¡P The
Contractor should provide water spraying to suppress fugitive dust for any
dusty construction activity.
Construction
Noise Impact
¡P Vessels
and equipment operating should be checked regularly and properly maintained by
the Contractor.
Water Quality
Impact
¡P The
Contractor should regularly review and maintain drainage systems to make sure
they are functioning effectively.
¡P Proper
drainage channels, bunds and set-up should be provided by the Contractor at the
site to collect/ intercept the surface run-off or waste water generated from
works area to ensure no direct discharge from site to surrounding water bodies.
Chemical and
Waste Management
¡P All
types of wastes should be collected and sorted accordingly and removed timely
by the Contractor. They should be
properly stored in designated areas within the works areas temporarily.
¡P All
plants and vehicles on site should be properly maintained by the Contractor and
drip trays should be provided where appropriate to prevent oil leakage.
¡P All
drain holes of the drip trays within the works areas should be properly plugged
by the Contractor to avoid any oil and chemical waste leakage.
¡P Oil
stains on soil surface should be cleared and disposed of as chemical waste by
the Contractor.
¡P Floating
debris and trash observed within the silt curtain and around the working barge
should be collected as far as possible to maintain the cleanliness of the
surrounding sea.