1.1.1. Bestwise – Sun Fook Kong Joint Venture (the Contractors) appointed 3NV Technology Limited (3NV) to undertake the Landscape and Visual Monitoring for the Operational Phase of the “Enhancement of Deodourisation System at Stonecutters Island Sewage Treatment Works” (hereafter referred to as “the Project”).
1.1.2. The Project is part of the Harbour Area Treatment Scheme (HATS) Stage 2A. According to Environmental Permit No. EP-322/2008/G issued on 9th May 2014 by the Environmental Protection Department (hereinafter called EPD) to the Drainage Services Department (hereinafter called the DSD) as the Permit Holder and the EM&A Manual for the HATS Stage 2A, all landscape and visual mitigation measures shall be monitored monthly on-site during the first year of the Operational Phase at 8 preliminary treatment works (PTW) and the Stonecutters Island Sewage Treatment Works (SCISTW).
1.2.1. The objective is to monitor and audit the contractor’s landscape works, in particular, to ensure the existing trees retained on-site are being well preserved, tree transplanting and felling operations are being undertaken in accordance with the requirements, procedures, and specifications as stipulated in the contract and the approvals granted by concerned authorities, and all the newly planted vegetations are being maintained properly during the establishment period.
Under the EM&A Manual, Landscape and Visual Monitoring audit should be undertaken during the first year of the Operational Phase to ensure and check that the implementation and maintenance of landscape and visual mitigation measures are carried out by a Registered Landscape Architect (RLA).
2.2.1. Site inspections should be undertaken once every month through the first year of the Operational Phase.
2.3.1. Under this Project, there are 8 PTW and SCISTW that should be monitored. The details of the monitoring location are summarized in Table 1.1.
Table 1.1 L&V Monitoring Locations
No. |
Description |
1 |
North Point PTW |
2 |
Wan Chai East PTW |
3 |
Central PTW |
4 |
Sandy Bay PTW |
5 |
Cyberport PTW |
6 |
Wah Fu PTW |
7 |
Aberdeen PTW |
8 |
Ap Lei Chau PTW |
9 |
Stonecutter Island PTW |
2.4.1. A Registered Landscape Architect is employed to monitor and audit the contractor’s landscape works, in particular, to ensure the existing trees retained on-site are being well preserved, tree transplanting and felling operations are being undertaken in accordance with the requirements, procedures, and specifications as stipulated in the contract and the approvals granted by concerned authorities, and all the newly planted vegetations are being maintained properly during the establishment period by complete a checklist.
3.1.1. No visible irregularities were found. The completed checklist is shown in Appendix A.
3.2.1. Generally, all L&V mitigation measures listed in EM&A were applied at 8 PTWs and SCISTW. Table 3.1 summarized the reminders of the 8 PTWs and SCISTW.
Table 3.1 Summary of Reminders for the 8 PTWs and SCISTW
Monitoring Location |
Reminders |
North Point PTW |
1. Carry out proper maintenance to plantings 2. Increase the frequency of watering |
Wan Chai East PTW |
1. Carry out proper maintenance to plantings 2. Provide adequate protection to trees adjacent to works area |
Central PTW |
1. Carry out proper maintenance to plantings |
Sandy Bay PTW |
1. Carry out proper maintenance to plantings 2. Increase the frequency of watering 3. Continuous monitoring of the tree condition (such as trees at inner side with leaves shredded or foliage’s colour turns yellow) |
Cyberport PTW |
1. Carry out proper maintenance to plantings 2. Increase the frequency of watering 3. Increase the maintenance of pot plants |
Wah Fu PTW |
1. Carry out proper maintenance to plantings 2. Increase the frequency of watering |
Aberdeen PTW |
1. Carry out proper maintenance to plantings 2. Increase the frequency of watering 3. Closely monitor the conditions of the pruned trees 4. Review if pruning is required for tree with branches span over driveway by the maintenance party |
Ap Lei Chau PTW |
1. Carry out proper maintenance to plantings 2. Increase the frequency of watering |
Stonecutter Island PTW |
1. Close monitoring or tree risk assessment may be required especially for trees T110 & T109 2. Review the situation and to remove the trees by the maintenance party to reduce the safety risk |