MTR Corporation Limited
Monthly EM&A Report No. 41
December 2014
Certified by: Environmental Team Leader
(please
refer to submitted true copy)
Verified by: Independent Environmental Checker
(please
refer to submitted true copy)
EXECUTIVE SUMMARY
With the main civil works contracts of the
South Island Line (East) (SIL(E)) Project awarded in May 2011, the commencement
date of construction of the Project was on 25 June 2011. The Environmental
Monitoring and Audit (EM&A) programme of the Project also commenced on 25
June 2011. This is the forty-first Monthly EM&A Report for SIL(E) Project.
The Report presents the results of EM&A works undertaken during the period
of 1 to 30 November 2014. The major construction activities in the reporting
period included piling, excavation, slope stabilization works, shaft excavations,
tunnel excavation as well as construction of stations and depot. Operation of magazine at Chung Hom Shan has been
terminated in October 2014.
Impact monitoring for air quality, noise and
water quality were conducted in the reporting period. No exceedance was found and there was no
breach of Action / Limit Levels for air quality and noise monitoring.
No complaint referred
by EPD was received in the reporting month.
No notification of summon or prosecution
related to the environmental issue was received in the reporting period.
Regular site inspections were conducted by
the Environmental Team (ET) to check the implementation of environmental
mitigation measures. No non-conformance to the environmental requirements was
identified in the reporting period.
Future key issues envisaged in the coming
month include noise and dust emission from site works. The ET will continue the
implementation of the EM&A programme in accordance to the EM&A Manual.
TABLE OF CONTENTS
2.1 Project
Organization and Management Structure
2.2 Construction
Activities in the Reporting Month
2.3 Construction
Activities for the Coming Month
2.4 Project Areas
and Environmental Monitoring Locations
2.5 Summary of
EM&A Requirements
3.4 Action taken in
Event of Exceedance
7. RECORD OF
ENVIRONMENTAL COMPLAINTS
9. RECORD OF
NOTIFICATIONS OF SUMMONS AND PROSECUTIONS
10. STATUS OF
STATUTORY SUBMISSIONS
10.1 Submissions
required under Environmental Permit
10.2 Statutory
Permits and Licenses
11.1 Implementation
of Environmental Mitigation Measures
11.3 Solid and
Liquid Waste Management Status
List of Tables
Table 1 Summary of impact dust
and noise monitoring stations
Table 2 Summary of impact
water quality monitoring stations
List of Figures
Figures 1 to 2
Works Areas of the Project
Figures 3 to 6
Location of Construction Air Quality
Monitoring Stations
Figures 7 to 8
Location of Construction Noise Monitoring
Stations
Figures 9
Air Quality and Noise Monitoring
Locations for Telegraph Bay Barging Point
Figures 10
Water Quality Monitoring Locations for Telegraph
Bay Barging Point
Appendix A1 Project Organization
Appendix A2 Contact
List of Key Personnel of the Project
Appendix B1 Action
and Limit Levels for Construction Noise and Air Quality
Appendix B2 Action
and Limit Levels for Water Quality
Appendix C Calibration
Details
Appendix E Review
of Exceedance in Environmental Monitoring
Appendix F Implementation
of Environmental Mitigation Measures
The South
Island Line (East) (SIL(E)) of 7.0km approximately is a new medium capacity
railway with stations at South Horizons (SOH), Lei Tung (LET), Wong Chuk Hang
(WCH), Ocean Park (OCP) and Admiralty (ADM), comprising underground and
elevated structures. A depot is required at Wong Chuk Hang to provide
maintenance support for the SIL(E).
Main civil
works contracts of the SIL(E) were awarded in May 2011. The commencement date
of construction of the Project was on 25 June 2011. The construction of the
Project is expected to complete in 2016.
The Environmental
Monitoring and Audit (EM&A) programme of the Project commenced on 25 June
2011. This is the forty-first Monthly Environmental Monitoring and Audit
(EM&A) Report for the Project. The Report presents the results of EM&A undertaken
during the period of 1 to 30 November 2014.
2.1 Project Organization and Management Structure
The project
organization is shown in Appendix A1. Contacts of key
personnel of the Project are shown in Appendix A2.
2.2 Construction Activities in the Reporting Month
Major
construction activities carried out by the respective SIL(E) civil works contractors
during the reporting period include:
Site |
Construction
Activities |
Harcourt |
-
Excavation,
blasting works at cavern, tunnels and station box -
Construction
works at station box, cavern and tunnels -
Underpinning
works at station box -
Re-setup
of skip hoist -
ABWF
works at station box -
Vent
shaft modification work -
A&A
works at Admiralty Station |
Contract No. 902
Site |
Construction
Activities |
Hong Kong |
-
Construction of shaft |
Nam Fung Portal |
-
Construction for transition box -
Tunnel excavation by drill
and blast -
Construction of ventilation
building |
Chung Hom
Shan Magazine |
-
Reinstatement works |
Telegraph
|
-
Reinstatement
works |
Site |
Construction Activities |
Zone
B (Ex-Canadian Site to OCP Station) |
-
Reinstatement works in Zone B
(B2-B6) -
Noise Barrier Installation in Zone B (B4) |
OCP
Station |
-
Louvers Installation -
Glazed panels of the glass façade -
Door flame installation -
Ceiling Installation -
Mosaic tiles on wall and
columns -
Installation of glass
balustrade -
Dismantling of tower crane |
Zone C (OCP Station to WCH Station) |
-
PSR and HYR East Road and
Drainage works |
WCH Station |
-
Installation of Glass
balustrade -
Construction of openable
window at concourse level -
Entrance A-ABWF works -
Entrance B Footbridge
construction -
Erection of Vehicular Portal
for Wong Chuk Hang Footbridge across Wong Chuk Hang Road -
Removal of Vehicular Portal
Frame for Wong Chuk Hang Footbridge across Heung Yip Road |
Zone
D (WCH Station to WCH nullah) and External Works |
-
Pedestrian
Link Bridge Installation (D17 and Kun Hoi Path) -
HYR/NLS Road and Drainage
works -
Reinstatement Works |
Zone E (ACB) |
-
Remaining works of Pavement |
Site |
Construction
Activities |
Ex-Harbour |
-
Backfilling -
Tunnel box construction |
Lee Wing Street |
-
Construction of main tunnel -
Construction of ventilation
building |
LET Station Entrance A |
-
Construction of adit -
Construction of station |
LET Station Entrance B |
-
Shaft and adit excavation and
construction |
South Horizons |
-
Station structure construction |
South |
-
Slope protection -
Plant building
structure construction |
Project site office at
Ap Lei Chau Bridge Playground |
-
Handover
to LCSD completed |
Lee Wing Street Barging Point |
-
Reinstatement works |
Site |
Construction Activities |
WCH Depot |
-
Architectural
builders works and finishes -
Road
Works |
2.3 Construction Activities for the Coming Month
The
scheduled major construction activities in the next reporting month are as
follows:
Site |
Construction
Activities |
Harcourt |
-
Excavation,
blasting works at cavern, tunnels and station box -
Construction
works at station box, cavern and tunnels -
Underpinning
works at station box -
Re-setup
of skip hoist -
ABWF
works at station box -
Vent
shaft modification work -
A&A
works at Admiralty Station |
Site |
Construction
Activities |
Hong Kong |
-
Construction of shaft |
Nam Fung
Portal |
-
Construction for transition box -
Tunnel excavation by drill
and blast -
Construction of ventilation
building |
Chung Hom Shan Magazine |
-
Reinstatement works |
Telegraph |
-
Reinstatement
works |
Site |
Construction Activities |
Zone
B (Ex-Canadian Site to OCP Station) |
-
Reinstatement works in Zone B
(B2-B6) -
Remaining works of Noise
Barrier Installation |
OCP Station |
-
Glazed panels of the glass
façade -
Door flame installation -
Ceiling Installation -
Mosaic tiles on wall and
columns -
Construction of
footbridge to Ocean Park |
Zone C (OCP Station to WCH Station) |
-
PSR and HYR East Road and
Drainage works |
WCH Station |
-
Ceiling Installation -
Steel work & glazed
panel for external façade -
Door flame installation -
Entrance A-ABWF works -
Entrance B Footbridge
construction -
Removal of Vehicular Portal
for Wong Chuk Hang Footbridge across Wong Chuk Hang Road |
Zone D (WCH Station to WCH nullah) and Exteranl Works |
-
Pedestrian
Link Bridge Installation (D17 and Kun Hoi Path) -
HYR/NLS Road and Drainage
works -
Noise Barrier Installation -
Reinstatement Works |
Zone E (ACB) |
-
Remaining works of Pavement |
Site |
Construction
Activities |
Ex-Harbour
|
-
Backfilling -
Tunnel box construction -
Retaining wall construction |
Lee Wing Street |
-
Construction of main tunnel -
Construction of ventilation
building |
LET Station Entrance A |
-
Construction of adit -
Construction of station |
LET Station Entrance B |
-
Shaft and adit excavation and
construction |
South Horizons |
-
Station structure construction -
Landscape works at EPIW Footbridge
to Ap Lei Chau Esate |
South |
-
Slope protection -
Plant building
structure construction |
Lee Wing
Street Barging Point |
-
Reinstatement works |
Site |
Construction
Activities |
WCH Depot |
-
Architectural
builders works and finishes -
Road
Works |
2.4 Project Areas and Environmental Monitoring Locations
The works
areas of the Project are shown in Figures 1 and 2. Impact dust and
noise monitoring has been conducted at designated monitoring locations during
operation of the Telegraph Bay barging point in accordance with the
Construction and Demolitions Materials Management Plan (C&DMMP) approved
under EP. Operation of barging point has been terminated by 30 September
2014. Reinstatement of barging
point commenced in October 2014 while marine-based demolition works started on
14 November 2014. The impact dust
and noise monitoring during the restatement works at the barging point at
Telegraph Bay will be carried out in accordance with the environmental review
report submitted for variation to SIL(E) Environmental Permit EP-407/2010 in
November 2011. Regular site audits
will continue to be carried out in parallel to ensure that the recommended
mitigation measures are properly implemented. Marine water quality monitoring has been
conducted during the period of marine-based demolition in accordance with Silt
Curtain Plan for Marine-based Decommissioning of Temporary Pier at Telegraph
Bay submitted under the EP.
The
locations of environmental monitoring stations are shown in Figures 3 to 10. Tables 1 and 2 below
shows the details of the active monitoring stations as reported in Sections 3.1
to 3.3 below.
Table 1 Summary of impact dust and noise monitoring
stations
ID |
Monitoring Station |
Dust |
|
CD1 |
Wong
Chuk Hang San Wai |
CD2 |
|
CD3 |
San Wui
Commercial Society of HK |
CD4 |
Shan On
House |
CD5* |
South
Horizons Phase IV ¡V Block 25 |
DTB1 |
Site boundary of |
Noise |
|
CN1 |
San Wui
Commercial Society of HK |
CN2 |
Holy
Spirit Seminary (Education Institution) |
CN3* |
Shun |
CN4* |
South
Horizons Phase IV ¡V Block 25 |
CN5* |
TWGHs
Jockey Club Rehabilitation Complex Block A (Convalescent Home) |
NTB1 |
Outside
Aegean Terrace |
* Location updated due to site access problem, or as per the agreement
with the premises landlord, and agreed with EPD
Table 2 Summary
of impact marine water quality monitoring stations
Monitoring
Stations |
Coordinates |
|
Easting |
Northing |
|
Control Stations |
|
|
CE
(Ebb) |
830026 |
814956 |
CF
(Flood) |
831778 |
812420 |
Impact Stations |
|
|
I1 |
831088 |
813654 |
I2 |
831105 |
813582 |
Intake
A |
831610 |
812931 |
Intake
B |
830606 |
814583 |
2.5 Summary of EM&A Requirements
The EM&A programme as specified in the
EM&A Manual has been implemented during the construction stage.
In the reporting period, impact monitoring
of LAeq, 30min noise levels was carried out at the monitoring locations as
shown in Table 1 once a week. Also, 24-hour TSP monitoring was conducted at the
monitoring locations as shown in Table 1 once a week. Impact water quality monitoring
at Telegraph Bay was also undertaken at the monitoring locations as shown in
Table 2 three working days per week at mid-ebb and mid-flood tides.
Action and Limit Levels for construction
noise and air quality as well as water quality are shown in Appendices B1 and B2 respectively. Should non-compliance of
the criteria occurs, action in accordance with the respective Event and Action
Plans for construction noise, air quality and water quality in the EM&A
Manual / Updated EM&A Manual / Silt Curtain Plan should be carried out.
Monthly monitoring of the ardeid night
roost location beside Wong Chuk Hang Nullah by qualified ecologist was also
conducted.
In addition, regular site inspection to
active works areas was carried out. The areas of inspection included the
pollution control and mitigation measures within the site. Waste management and
landscape and visual aspects were covered.
24-hour TSP samples were collected by High
Volume Sampler (Graseby-Andersen) following United Sates Environmental
Protection Agency regulations.
The sampling procedure follows to that
described in the App. B of Pt 50 in 40CFR Ch.1 (U.S. Environmental Protection
Agency). TSP is sampled by drawing air through a conditioned, pre‑weighed
filter paper inside the high volume sampler at a controlled rate. After 24‑hour
sampling, the filter paper with retained particles is collected and returned to
the laboratory for drying in a desiccators followed by weighing. TSP levels are
calculated from the ratio of the mass of particulate retained on the filter
paper to the total volume of air sampled.
The samplers have been properly
maintained. Prior to dust monitoring commencing, appropriate checks have been
made to ensure that all equipment and necessary power supply are in good
working condition.
The flow rate of the high volume sampler
with mass flow controller is calibrated using an orifice calibrator. Initial
calibration (five points) is conducted upon installation and prior to
commissioning. Calibration will be carried out every six months. The calibration
records are shown in Appendix C.
To examine the construction dust levels,
24-hour TSP monitoring was undertaken at the monitoring locations as shown in
Table 1 according to the EM&A Manual.
Monitoring results are presented
in the following table (see Appendix D for graphical plots).
The 24-hour TSP levels were within the Action Level. No exceedance was found.
This indicates that the construction activities did not have a noticeable
adverse effect on the general air quality of the project areas. However, excavation and reinstatement works
by other Project were observed in the vicinity of monitoring station DTB1 at
Telegraph Bay barging point during the reporting month, which have generated
fugitive dust emitting to the local environment. The dust suppression measures,
such as water spraying on the haul road and tipping hall, for the barging point
operation were ongoing.
Date |
TSP (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
Compliance |
Weather
Condition |
(Yes/No) |
|||||
CD1
Wong Chuk Hang San Wai |
|||||
6-Novt |
120.1 |
173 |
260 |
Yes |
Cloudy |
13-Nov |
134.0 |
173 |
260 |
Yes |
Fine |
20-Nov |
89.1 |
173 |
260 |
Yes |
Fine |
27-Nov |
78.5 |
173 |
260 |
Yes |
Fine |
CD2
Police College ¡V Police Quarters
|
|||||
3-Nov |
94.9 |
184 |
260 |
Yes |
Cloudy |
10-Nov |
122.7 |
184 |
260 |
Yes |
Cloudy |
17-Nov |
130.5 |
184 |
260 |
Yes |
Fine |
24-Nov |
75.7 |
184 |
260 |
Yes |
Fine |
CD3
San Wui Commercial Society of HK Chan Pak Sha School |
|||||
3-Nov |
84.6 |
169 |
260 |
Yes |
Cloudy |
10-Nov |
59.4 |
169 |
260 |
Yes |
Cloudy |
17-Nov |
82.9 |
169 |
260 |
Yes |
Fine |
24-Nov |
44.1 |
169 |
260 |
Yes |
Fine |
CD4
Shan On House |
|||||
7-Nov |
41.0 |
176 |
260 |
Yes |
Fine |
13-Nov |
55.2 |
176 |
260 |
Yes |
Cloudy |
20-Nov |
54.9 |
176 |
260 |
Yes |
Fine |
27-Nov |
64.5 |
176 |
260 |
Yes |
Cloudy |
CD5 South
Horizons Phase IV ¡V Block 25 |
|||||
7-Nov |
44.5 |
169 |
260 |
Yes |
Fine |
13-Nov |
69.2 |
169 |
260 |
Yes |
Cloudy |
20-Nov |
66.2 |
169 |
260 |
Yes |
Fine |
27-Nov |
63.3 |
169 |
260 |
Yes |
Cloudy |
DTB1 Site boundary of
Telegraph Bay barging point |
|||||
7-Nov |
47.2 |
156 |
260 |
Yes |
Fine |
13-Nov |
76.8 |
156 |
260 |
Yes |
Cloudy |
20-Nov |
61.7 |
156 |
260 |
Yes |
Fine |
27-Nov |
79.7 |
156 |
260 |
Yes |
Cloudy |
Note: Please refer to Figures 3 to 6 and 9 for the location of construction air quality monitoring stations
Monitoring was conducted using B&K
sound analysis equipment ¡V B&K SLM 2250. Microphone was extended 1 meter from
building facades and oriented towards the works area.
B&K 2250 sound level meters and
B&K 4231 calibrators which complied with the International Electrotechnical
Commission Publication 651:1979 (Type 1) and 804:1985 (Type 1), specification
as referred to in the Technical Memoranda to the NCO were used for the impact
monitoring. The sound level meters and calibrators are verified by the
certified laboratory or manufacturer once every two years to ensure they
perform to the same level of accuracy as stated in the manufacturer¡¦s
specifications. The calibration records are shown in Appendix C.
Immediately prior to and following each
set of measurements at any NSR, the accuracy of the sound level meter was
checked using an acoustic calibrator generating a known sound pressure level at
a known frequency. If the
calibration levels before and after the measurement differs by more than 1.0dB,
the measurement shall be repeated to obtain a reliable result (note: maximum
deviation during this initial baseline monitoring period was 0.3dB). Periods of
prolonged or repeated overloading of the sound level meter detector were
avoided by setting the meter with adequate headroom prior to commencing
measurements. Measurements were
recorded to the nearest 0.1 dB, with values of 0.05 being rounded up.
Impact monitoring of LAeq, 30min noise
levels was undertaken to measure construction noise levels in accordance with
the Updated EM&A Manual at the monitoring locations as shown in Table 1. The
monitoring was conducted during the course of construction works, please refer
to S2.2 for major construction activities of the respective SIL(E) civil works contracts
in the
reporting month. Weather conditions throughout the monitoring period were mild
with light wind of not exceeding 2-3m/s on average.
Noise monitoring results are presented in the following
table and graphical plot for are presented in Appendix D.
Date |
Time |
LAeq (dBA) |
Limit Level (dBA) |
Compliance (Yes/No) |
Weather Condition |
|
CN1 San Wui Commercial Society of HK Chan Pak
Sha School |
||||||
5-Nov |
15:30 |
65.2 |
70# |
Yes |
Fine, wind <5m/s |
|
11-Nov |
15:25 |
66.1 |
70# |
Yes |
Fine, wind <5m/s |
|
18-Nov |
14:45 |
68.0 |
70# |
Yes |
Fine, wind <5m/s |
|
25-Nov |
14:55 |
67.6 |
70# |
Yes |
Fine, wind <5m/s |
|
CN2 Holy Spirit Seminary
|
||||||
4-Nov |
16:01 |
64.1 |
70# |
Yes |
Cloudy, wind <5m/s |
|
11-Nov |
16:05 |
65.5 |
70# |
Yes |
Fine, wind <5m/s |
|
18-Nov |
16:15 |
63.1 |
70# |
Yes |
Fine, wind <5m/s |
|
25-Nov |
16:03 |
64.2 |
70# |
Yes |
Fine, wind <5m/s |
|
CN3 Shun Fung Building
|
||||||
7-Nov |
09:30 |
68.1 |
75# |
Yes |
Fine, wind <5m/s |
|
13-Nov |
10:40 |
70.2 |
75# |
Yes |
Cloudy, wind <5m/s |
|
20-Nov |
10:50 |
69.1 |
75# |
Yes |
Fine, wind <5m/s |
|
27-Nov |
10:45 |
67.6 |
75# |
Yes |
Cloudy, wind <5m/s |
|
CN4 South Horizons Phase IV ¡V Block 25 Dover
Court |
||||||
7-Nov |
11:00 |
69.5 |
75# |
Yes |
Fine, wind <5m/s |
|
13-Nov |
11:15 |
68 |
75# |
Yes |
Cloudy, wind
<5m/s |
|
20-Nov |
11:10 |
67.5 |
75# |
Yes |
Fine, wind <5m/s |
|
27-Nov |
10:50 |
68.6 |
75# |
Yes |
Cloudy, wind
<5m/s |
|
CN5 TWGHs Jockey Club Rehabilitation Complex
Block A |
||||||
4-Nov |
15:10 |
64.2 |
75 |
Yes |
Cloudy, wind <5m/s |
|
11-Nov |
15:20 |
63.1 |
75 |
Yes |
Fine, wind <5m/s |
|
18-Nov |
15:25 |
64.5 |
75 |
Yes |
Fine, wind <5m/s |
|
25-Nov |
15:05 |
63.2 |
75 |
Yes |
Fine, wind <5m/s |
|
NTB1 Outside Aegean Terrace
|
||||||
7-Nov |
10:15 |
61.3 |
75 |
Yes |
Fine, wind <5m/s |
|
13-Nov |
10:00 |
59.6 |
75 |
Yes |
Cloudy, wind <5m/s |
|
20-Nov |
10:05 |
60.5 |
75 |
Yes |
Fine, wind <5m/s |
|
27-Nov |
10:00 |
59.6 |
75 |
Yes |
Cloudy, wind <5m/s |
|
(#) Or updated prediction of noise levels as contained in
Construction Noise Mitigation Measures Plan
In accordance with the Silt Curtain Plan
for Marine-based Decommissioning of Temporary Pier at Telegraph Bay submitted
under EP condition 2.16(a), water quality monitoring will be carried out during
the marine-based demolition works at the Telegraph Bay barging point. The
baseline water quality monitoring at Telegraph Bay was scheduled and completed in
August 2014. The Water Quality Baseline Monitoring Report for Marine-based
Demolition work of the temporary pier at Telegraph Bay was submitted to EPD on 26
November 2014 and deposited at the EIAO Register OFfice on 4 December 2014.
Monitoring Methodology
Water quality was
monitored in terms of the following parameters: Dissolved Oxygen (DO, mg/L) and
Dissolved Oxygen Saturation (DO %), temperature (oC), pH, turbidity
(NTU), salinity (ppt), suspended solids (mg/L) and water depth (m) in
accordance with the EM&A Manual of the HKWDT project. All parameters were
measured in-situ whereas SS shall be determined by the laboratory.
Water samples were
taken with a water sampler, consisting of a transparent PVC cylinder of 2
litres that can be effectively sealed with cups at both ends. The water sampler
has a positive latch system to keep it open and prevent premature closure until
released by a messenger when the sampler arrives is at the pre-determined
depth.
Measurement was
taken at 3 water depths, namely, 1m below water surface, mid-depth and 1m above
sea bed, except where the water depth less that 6m, the mid-depth station may
be omitted. Should the water depth be less than 3m, only the mid-depth station
was monitored.
Duplicate in-situ
measurements and samples were collected and analyzed to ensure a robust
statistically interpretable dataset. Where the difference in value between the
first and second measurement of DO or turbidity parameters is more than 25% of
the value of the first reading, the reading was discarded and further readings
were taken.
Water samples were
stored in high-density polythene bottles, packed in ice and delivered to the
laboratory of ALS Technichem (HK) Ltd., a HOKLAS accredited laboratory. The SS
analyses followed the standard method APHA 2540D with a detection limit of
1mg/L.
A digital depth
detector was employed to determine the water depth at selected stations when
flows permit.
Calibration Requirements
On-site monitoring
equipment namely the salinity meter, pH meter, turbidity meter, dissolved
oxygen meter and temperature meter were calibrated before use. The
methodologies for the calibration are referred to the instruction manual
provided by the manufactures respectively.
The calibration records are shown in Appendix
C. Response of
sensors and electrodes was checked with certified standard solutions before
each use.
Monitoring Results
Impact water
quality monitoring was undertaken in accordance with the Silt Curtain Plan at
the respective designated monitoring locations at Telegraph Bay as shown in
Table 2 during the reporting period. Monitoring results and graphical plots are
presented in Appendix D.
3.4 Action taken in Event of Exceedance
There was no exceedance in air quality, noise and water
quality monitoring parameters recorded in the reporting period, therefore no
action was taken.
The landscape and visual mitigation
measures undertaken by the contractors during the construction phase have been
audited on a regular basis according to the EM&A Manual.
Regular inspections and audits were conducted
by the Certified Arborist as required by the EP and it was found that the
transplanting works and the tree protection works being carried out by the
civil works and transplantation contractors were in accordance with the EP/ EIA.
Necessary tree removal or protection works were being carried out in accordance
with the EP/ EIA or approved Tree Removal Application. No non-compliance was identified in the
reporting period.
No immediate hazards were noted for any of
the OVTs during reporting period.
Health conditions of the two retained and
pruned trees, Ficus elastica, located
at Wong Chuk Hang San Wai have been monitored. The contractor had enhanced the
tree protection zone and was reminded to properly maintain the protection zone.
Total of 464 trees of the SIL(E) had been
transplanted as of the reporting month. They were mostly transplanted to the
holding nursery at Chung Hom Shan and Kellett Bay, permanent receptor sites
such as Lok Ma Chau, Telegraph Bay or in-situ under project areas.
Auditing of the ecological mitigation
measures during the construction phase have been carried out on a regular basis
according
to the EM&A Manual.
Regular inspections to the works areas
around the ardeid night roost have been conducted by the ecologist to check the
ecological mitigation measures with regard to the ardeids at Wong Chuk Hang
Nullah. Inspections of the ardeid night roost have been made for any active
ardeid nests. Whilst ardeids have never been recorded nesting at this site,
precautionary checks for active nests or signs of breeding have been made.
Monthly monitoring of the ardeid night
roost location was also conducted by the ecologist from a vantage point, at Ap
Lei Chau Bridge (on the Wong Chuk Hang side), with an unobstructed view over
the area. According to the EM&A Manual, the surveys will commence
approximately one hour before sunset and continue for 20 minutes after sunset,
or until nightfall, which comes sooner. Any aggregation of night roosting
ardeid in the degraded woodland or adjacent area have been located and counted.
During the reporting month, the monthly
night ardeid survey was conducted on 21st
November 2014 commenced at 1635hr.
No ardeids was observed roosted at this location.
Nevertheless, the roosting site at Wong
Chuk Hang shall be maintained in good condition, and proper mitigation measures
will be kept for the tree protection within the site. Proper tree protection
measures have been implemented as far as practicable by the contractor to the
current and potential roost trees retained on site.
Plant Species of Conservation Interest
Detailed field survey led by the ecologist
was undertaken in March and early May 2011 to ascertain the presence of any
rare or protected flora species to be affected. The surveys covered all above
ground works areas of the project and the survey results were presented in the Detailed
Transplanting Baseline Survey Report submitted under the Environmental Permit.
As in the Detailed Transplantating
Baseline Survey Report, two plant species of conservation interest recorded in
the degraded woodland to the south of Wong Chuk Hang Nullah, namely herb Houttuynia cordata and tree Aquilaria sinensis (including
seedlings), and planted young tree Ailanthus
fordii (including seedlings) recorded in a plantation area near Hong Kong
Park will be influenced by the project works. Other plant species of
conservation interest identified will be protected on-site and appropriate tree
protection measures would be established if needed. Health condition of the
most plant species protected in-situ generally remained unchanged as in the
Detailed Transplanting Baseline Survey Report. However, it is noted that health
condition of Ailanthus fordii (tree
no. OCP-T2231), which is outside the active works area at Wong Chuk Hang San
Wai, was found to remain in generally fair physiologically condition. Two Aquilaria sinensis, which are located
outside the active works area to the north of Nam Fung Road, were found in very
poor health condition and suspected to be dead specimens. The two transplanted Aquilaria sinensis have been removed in Nov 2013.
Regular monitoring on the transplanted A. fordii within the works area has been
conducted. The transplanted A. fordii
were in fair health condition and protection fences have been maintained around
the receptor sites. Condition of one transplanted young seedling A.
fordii has grown
satisfactorily with new
leaves developed from the apical bud. while
the retained tree T3 has
remained in satisfactory condition.
According to the Transplanting Proposal
for H. cordata submitted in Sep 2011,
post transplantation maintenance period were undertaken throughout the 12-month
and have been completed.
Mitigation measures on waste management
have been implemented in accordance with the site waste management plans for
the respective civil works contracts. The C&D materials have been disposed
of at the public fill reception facilities while C&D wastes have been
disposed of at the landfills. Operation of the barging point at Telegraph Bay
has been terminated by September 2014. Quantities of wastes disposed in the reporting
period are summarized in the following table:
Contract No |
Inert C&D Materials Disposed at Public Fill (m3) |
Inert C&D Materials Reused (m3) |
Non-inert Waste Disposed at Landfill (m3) |
Chemical Waste to Designated Treatment Facility (litre/ kg) |
Reporting Period: November 2014 |
||||
Contract 901 |
11,674 |
3,040 |
90 |
0 |
Contract 902 |
3,197 |
4,338 |
624 |
404 |
Contract 903 |
1,631 |
14 |
90 |
500 |
Contract 904 |
284 |
0 |
122 |
0 |
Contract 908 |
98 |
0 |
516 |
0 |
7. RECORD OF ENVIRONMENTAL COMPLAINTS
There was no environmental
complaint referred by EPD in the reporting period.
There was no
non-compliance identified in the reporting period.
9.
RECORD OF NOTIFICATIONS OF SUMMONS AND
PROSECUTIONS
No summon or
prosecution related to environmental issue was received or made against the
Project in the reporting period.
10. STATUS OF STATUTORY SUBMISSIONS
10.1 Submissions required under Environmental Permit
A summary of the status of submissions
required under the SIL(E) Environmental Permit as of 30 November 2014 is shown
below:
EP Clause No. |
Description of Submission |
Status |
1.11 |
Commencement date of construction |
Submitted on 25 May 2011 |
1.14 |
Commencement date of operation |
To be submitted no later than 2
months prior to commencement of operation of the Project |
2.1
& 2.2 |
Employment of IEC & ET |
Submitted on 6 Apr 2011 |
2.3 |
Employment of Qualified Ecologist |
Submitted on 6 Apr 2011 |
2.4 |
Employment of Certified Arborist |
Updated Certified Arborist
submitted on 19 Aug 2013 |
2.5 |
Management organization of main construction
companies |
Updated main construction
companies submitted on 15 Jun 2012 |
2.6 |
Construction programme & EP submission
schedule |
Submitted on 10 Jun 2011 |
2.7 |
Set up of Community Liaison Group |
Submitted on 20 Apr 2011 |
2.8 |
Updated EM&A Manual |
EP Condition fulfilled dated 13
February 2012 |
2.9 |
Construction Noise Mitigation Measures Plan |
Updated Construction Noise
Mitigation Measures Plan submitted on 11 May 2012 and EP Condition fulfilled
date 22 May 2012 |
2.11 |
Construction & demolition materials
management plan for barging points |
Revised Construction &
Demolition Materials Management Plan re-submitted on 7 January 2014. |
2.13
(a ) |
Ecological planting & landscape plan |
Revised plan submitted on 22 May 2014 , EP Condition fulfilled dated 27 Jun 2014 |
2.13
(b ) |
As built drawings of ecological planting &
landscape works |
To be submitted no later than 1
month after completion of planting works (at Wong Chuk Hang nullah) |
2.13
(c ) |
Final monitoring report of ecological planting
& landscape works |
To be submitted no later than 1
month after completion of the 3-year post planting care and maintenance
period |
2.14
(a ) |
Detailed transplanting baseline survey report
for plant species of conservation interest |
Resubmitted on 8 Sep 2011 and
no further comment received |
2.14
(b ) |
Transplantation proposal for plant species of
conservation interest |
H. cordata: EP Condition fulfilled dated 15
Sep 2011 Aq. sinensis: EP Condition fulfilled dated 21
Feb 2012 Ai. fordii: EP Condition fulfilled dated 18
Oct 2011 |
2.14
(c ) |
As built drawings of transplanting works for
plant species of conservation interest |
H. cordata: EP Condition fulfilled dated 15
Sep 2011 Aq. sinensis: EP Condition fulfilled dated 2
May 2012 Ai. fordii: EP Condition fulfilled dated 22
Dec 2011 |
2.15 |
Tree protection plan |
Updated Tree protection plan
submitted on 4 May 2012 and EP Condition fulfilled dated 30 May 2012 |
2.16(a
) |
Silt curtain plan |
For EP Condition fulfilled dated 12
Aug 2011 For EP Condition fulfilled dated 14
Dec 2011 Water Quality Baseline
Monitoring Report for Marine-based Demolition work of the temporary pier at
Telegraph Bay was submitted to EPD on 26 Nov 2014 and deposited in EIAO
Registered Office on 4 Dec 2014 |
2.17(b) |
Sample test results for
on-site re-use of marine sediment |
EP Condition fulfilled dated 26
Apr 2013 |
2.17(c) |
Sediment Sampling Report |
EP Condition fulfilled dated 11
Jun 2014 |
2.25 |
Operational groundborne noise review plan |
Resubmitted on 2 Jul 2014 and EP
Condition fulfilled dated 22 Jul 2014 |
2.26 |
Operational groundborne noise mitigation
measures plan |
Resubmitted on 2 Jul 2014 and
EP Condition fulfilled dated 22 Jul 2014 |
2.27 |
As built drawings for operational groundborne
noise mitigation measures |
To be submitted no later than 1
month after completion of tracks installation |
2.29 |
As built drawings for operational airborne noise
mitigation measures on viaduct section |
To be submitted no later than 1
month after completion of noise mitigation measures installation on viaduct
section |
2.30 |
Noise performance test report |
To be submitted no later than 1
month prior to commencement of operation of the Project |
2.31 |
Fixed plant noise audit report |
To be submitted no later than 1
month prior to commencement of operation of the Project |
2.32 |
Visual & landscape plan |
Part1-Site No.6 Nam Fung
Portal: EP Condition fulfilled dated 25
Jun 2013 Part2- Chung Hom Shan Magazine
Site: EP Condition fulfilled dated 13
Oct 2014 Part3- EPIW Footbridge to Ap
Lei Chau Esate: Submitted on 28 Nov 2014 |
3.1 |
Environmental Monitoring
and Audit Requirements |
Termination of water quality monitoring
at Aberdeen Channel approved on 23 Dec 2013 Requirements of noise and air
quality impact monitoring at Telegraph Bay as recommended in the C&DMMP
was fulfilled on 6 Nov 2014. |
3.3 |
Baseline monitoring report |
EP Condition fulfilled dated 21
Feb 2012 |
3.4 |
Monthly EM&A reports |
Submit within 2 weeks after the
end of the reporting month |
4.2 |
Internet address of EM&A and project data |
Submitted on 25 Jul 2011 |
10.2 Statutory Permits and Licenses
A summary of the status of all relevant
environmental permit and licenses as of 30 November 2014 is shown below:
Description |
Effective Date |
Expiry Date |
|
Environmental Permit for South Island Line (East) |
EP-407/2010/E |
29/8/2014 |
N/A |
|
|
|
|
Contract 901 |
|
|
|
Chemical Waste Producer Licence |
5213-124-K3004-01 |
23/5/2011 |
N/A |
Waste Disposal (Trucks) |
7012859 |
1/6/2011 |
N/A |
Water Discharge Licence |
WT00015547-2013 |
26/3/2013 |
31/7/2016 |
CNP for SEE Shaft and
Stationbox |
GW-RS0873-14 |
1/9/2014 |
28/2/2015 |
CNP for Large Plants Delivery |
GW-RS0864-14 |
11/9/2014 |
9/3/2015 |
CNP for Ventilation Shaft
Dismantling |
GW-RS0560-14 |
27/6/2014 |
25/12/2014 |
CNP for Ventilation Shaft
Dismantling (Renewal) |
submitted on 19 Nov 2014 |
|
|
CNP for A&A works at
Admiralty Station |
GW-RS0497-14 |
10/6/2014 |
8/12/2014 |
CNP for A&A works at
Admiralty Station (Renewal) |
GW-RS1337-14 |
9/12/2014 |
19/5/2015 |
CNP for crane operation for
ventilation fan |
GW-RS1308-14 |
23/11/2014 |
30/11/2014 |
|
|
|
|
Contract 902 |
|
|
|
Chemical Waste Producer Licence (Nam Fung) |
5213-175-N2206-12 |
24/6/2011 |
N/A |
Chemical Waste Producer Licence (HK Park) |
5213-124-N2345-02 |
28/10/2011 |
N/A |
Chemical Waste Producer Licence (Telegraph Bay) |
5213-171-N2206-24 |
17/4/2012 |
N/A |
Waste Disposal (Trucks) |
7012912
|
26/5/2011 |
N/A |
Waste Disposal (Vessels) |
7015920 |
14/5/2014 |
2/9/2014 |
Water Discharge Licence for HK Park |
WT00009688-2011 |
22/7/2011 |
31/7/2016 |
Water Discharge Licence for Nam Fung Path |
WT00009749-2011 |
22/7/2011 |
31/7/2016 |
Water Discharge Licence for CHS Magazine |
WT00009842-2011 |
11/8/2011 |
31/8/2016 |
Water Discharge Licence for Telegraph Bay Barging Point |
WT00010649-2011 |
27/10/2011 |
31/10/2016 |
CNP for Nam Fung 24-hour Tunnel Excavation (Drop
Gate at CH1200) |
GW-RS1233-14 |
3/11/2014 |
2/5/2015 |
CNP for HK Park 24-hour Shaft Excavation |
GW-RS1240-14 |
13/11/2014 |
12/2/2015 |
CNP for Telegraph Bay reinstatement |
GW-RS1134-14 |
15/10/2014 |
14/4/2015 |
CNP for Chung Hom Shan Magazine site reinstatement |
GW-RS1085-14 |
6/10/2014 |
5/01/2015 |
|
|
|
|
Contract 903 |
|
|
|
Chemical Waste Producer Licence (Ocean Park Station) |
5213-175-L2174-31 |
14/6/2011 |
N/A |
Chemical Waste Producer Licence
(Ap Lei Bridge) |
5213-175-L2174-32 |
30/6/2011 |
N/A |
Chemical Waste Producer Licence
(Zone D) |
5213-175-L2174-33 |
30/6/2011 |
N/A |
Chemical Waste Producer Licence
(Nam Long Shan Sitting
Out Area) |
5213-175-L2174-34 |
30/6/2011 |
N/A |
Chemical Waste Producer Licence
(Wong Chuk Hang Station) |
5213-175-L2174-35 |
30/6/2011 |
N/A |
Waste Disposal |
7012721 |
12/5/2011 |
N/A |
Water Discharge Licence for Ap
Lei Chau Bridge |
WT00009838-2011 |
5/8/2011 |
31/8/2016 |
Water Discharge Licence for for
all pier areas Zone B |
WT00009931-2011 |
16/8/2011 |
31/8/2016 |
Water Discharge Licence for OCP
station |
WT00010501-2011 |
3/10/2011 |
31/10/2016 |
Water Discharge Licence for
Zone D |
WT00010319-2011 |
3/10/2011 |
31/10/2016 |
Water Discharge Licence for
Zone C |
WT00010648-2011 |
24/10/2011 |
31/10/2016 |
Water Discharge Licence for WCH
Station |
WT00014046-2012 |
24/9/2012 |
31/8/2016 |
Water Discharge Licence for Utilities
Work Area Along Heung Yip Road |
WT00014047-2012 |
25/9/2012 |
30/9/2017 |
Water Discharge Licence for
Kwun Hoi Path |
WT00015968-2013 |
2/5/2013 |
31/5/2018 |
Water
Discharge Licence for Nam Long Shan Road Sitting out area |
WT00018070-2013 |
2/1/2014 |
31/1/2019 |
Water
Discharge Licence for Yip Kan Street |
WT00018301-2014 |
18/2/2014 |
28/2/2019 |
CNP for ABWF in WCH Station Renewal of GW-RS1453-13 |
GW-RS0588-14 |
27/06/2014 |
26/12/2014 |
CNP for
Noise Barrier Installation in Zone E Viaduct (E3-E4) |
GW-RS0824-14 |
05/08/2014 |
31/12/2014 |
CNP for
Noise Barrier Installation in Zone C Viaduct (C9-C16) (Renewal of
GW-RS0118-14) |
GW-RS0829-14 |
11/08/2014 |
31/12/2014 |
CNP for
Noise Barrier Installation in Zone D Viaduct (D0-D4) (Renewal of GW-RS0134-14) |
GW-RS0845-14 |
12/08/2014 |
31/12/2014 |
CNP for
WCH Footbridge Construction |
GW-RS0793-14 |
31/07/2014 |
31/12/2014 |
CNP for
Noise Barrier Installation in Zone B |
GW-RS0993-14 |
12/09/2014 |
11/03/2015 |
CNP for ABWF works in OCP Station (Renewal of GW-RS0119-14) |
GW-RS0878-14 |
20/08/2014 |
18/02/2015 |
CNP for
Noise Barrier Installation in Zone D Viaduct (D8-D12) (Renewal of
GW-RS0332-14) |
GW-RS1137-14 |
19/10/2014 |
12/04/2015 |
CNP for Zone D
(Water pump for D13 Stoplog) (Renewal of GW-RS0354-14) |
GW-RS1186-14 |
29/10/2014 |
28/04/2015 |
CNP for
Noise Barrier Installation in Zone B (B4) |
GW-RS1180-14 |
29/10/2014 |
31/12/2014 |
|
|
|
|
Contract 904 |
|
|
|
Chemical Waste
Producer License for ALC Bridge Rd near Sham Wan Towers |
5111-174-L2758-04 |
4/8/2011 |
N/A |
Chemical Waste
Producer License for ALC Bridge Rd near Harbour Mission School |
5111-174-L2758-03 |
4/8/2011 |
N/A |
Chemical Waste
Producer License for ALC Main Street near Sunny Court |
5111-174-L2758-05 |
4/8/2011 |
N/A |
Chemical Waste
Producer License for Lei Tung Estate Rd near Kaifong Primary School |
5111-174-L2758-02 |
4/8/2011 |
N/A |
Chemical Waste
Producer License for Lee Nam Rd Sitting Out Area |
5111-174-L2758-01 |
4/8/2011 |
N/A |
Chemical Waste
Producer License for Lee Nam Rd Sitting Out Area No. 2 |
5111-174-L2758-07 |
4/8/2011 |
N/A |
Chemical Waste
Producer License for Yi Nam Rd intersect with Lee Nam Rd & SOH Drive |
5111-174-L2758-06 |
4/8/2011 |
N/A |
Waste Disposal (Trucks) |
7012979 |
25/6/2011 |
N/A |
Waste Disposal (Vessels) |
7015570 |
23/7/2012 |
N/A |
Water Discharge
License for ALC Bridge Rd near Sham Wan Towers |
WT00009781-2011 |
5/8/2011 |
31/8/2016 |
Water Discharge
License for ALC Bridge Rd near Harbour Mission School |
WT00009778-2011 |
5/8/2011 |
31/8/2016 |
Water Discharge
License for ALC Main Street near Sunny Court |
WT00009777-2011 |
5/8/2011 |
31/8/2016 |
Water Discharge
License for Lei Tung Estate Rd near Kaifong Primary School |
WT00009780-2011 |
5/8/2011 |
31/8/2016 |
Water Discharge
License for Lee Nam Rd Sitting Out Area |
WT00009779-2011 |
5/8/2011 |
31/8/2016 |
Water Discharge
License for Lee Nam Rd Sitting Out Area No. 2 |
WT00009783-2011 |
5/8/2011 |
31/8/2016 |
Water Discharge
License for Yi Nam Rd intersect with Lee Nam Rd & SOH Drive |
WT00009775-2011 |
5/8/2011 |
31/8/2016 |
Water Discharge
License for Barging Point at Lee Nam Road J/O Lee King Street |
WT00014348-2012 |
5/11/2012 |
30/11/2017 |
CNP for LET Ent B Structure Works |
GW-RS0833-14 |
8/8/2014 |
7/11/2014 |
CNP for
SOH Package 2 and 3 Pumping Test and grouting station near HK Electric |
GW-RS0690-14 |
20/7/2014 |
19/1/2015 |
CNP for
LWB Tunnel and associated tunnel work ¡V tunnel breakthrough |
GW-RS0844-14 |
16/8/2014 |
15/11/2014 |
CNP for Anti-skid work at Lei Tung Estate Road |
GW-RS1059-14 |
6/10/2014 |
14/11/2014 |
CNP for drainage work at Lee Wing Street |
GW-RS1057-14 |
6/10/2014 |
31/12/2014 |
CNP for 24hr PCW at Lei Tung Station
(Concourse Level), Adit B and Lei Tung Entrance Shaft |
GW-RS1155-14 |
21/10/2014 |
16/4/2015 |
|
|
|
|
Contract 908 |
|
|
|
Waste Disposal |
7014839 |
20/3/2012 |
N/A |
Chemical Waste Producer Licence |
5211-175-H2913-42 |
11/4/2012 |
N/A |
Water Discharge Licence |
WT000013232-2012 |
29/6/2012 |
31/5/2017 |
CNP for water pumping, water jetting unit, water treatment
plant, Grout mixer, Grout pump, Hand drill and mobile platform |
GW-RS0463-14 |
10/5/2014 |
9/11/2014 |
CNP for water pumping, water jetting unit, water treatment plant,
Grout mixer, Grout pump, Hand drill and mobile platform (Renewal) |
GW-RS1255-14 |
10/11/2014 |
9/5/2015 |
11.1
Implementation of Environmental Mitigation
Measures
Regular site inspections were undertaken
by the ET in accordance with the EM&A Manual to check the implementation of
environmental mitigation measures in the EIA. The contractors' performance on
environmental matters was assessed. The environmental mitigation measures are
being implemented by the civil works contractors where appropriate. A schedule
of the implementation of mitigation measures identified in the SIL(E) EIA is
given in Appendix F.
The findings from the site inspections and
the associated recommendations on improvement to the environmental protection
and pollution control works were raised to the contractors for reference and/
or action. Observations against the implementation of the mitigation measures
recommended in the EP/ EIA are summarized as follows:
Item |
Description |
Follow up Status |
|
Contract 901 |
|
1 |
The contractor was reminded to provide drip trays for
chemicals and clear the content in drip trays as chemical waste. |
On-going |
2 |
The contractor was reminded to repair the pH
neutralization unit of wastewater treatment system and improve the effluent
quality. |
On-going |
3 |
The contractor was reminded to keep machineries away
from Tree Protection Zone to avoid damages to trees.. |
Improved and standard to be
maintained |
4 |
The contractor was reminded to cover the stock of
over 20 bags cement entirely by impervious sheeting. |
Improved and standard to be
maintained |
5 |
The contractor was reminded to clear refuse and silt
deposited in drainage. |
On-going |
|
Contract 902 |
|
1 |
The contractor was
reminded to properly maintain the site drainage system and provide adequate
silt removal facilities. |
Improved
and standard to be maintained |
2 |
The contractor was reminded to maintain dust
suppression measures. |
Improved
and standard to be maintained |
3 |
The contractor was reminded to properly maintain the
dust and noise control measures at barging point |
Improved and standard to be maintained |
4 |
The contractor was reminded to maintain proper tree
protection works |
On-going |
|
Contract 903 |
|
1 |
The contractor was reminded to maintain proper
mitigation measures in the nullah for the effluent control. |
On-going |
2 |
The contractor was reminded to maintain dust
suppression measures. |
On-going |
3 |
The contractor was reminded to maintain the access
and egress free from dust and keep good housekeeping. |
On-going |
4 |
The contractor was reminded to handle the chemical wasteon
site properly |
On-going |
5 |
The contractor was reminded to maintain tree
protection works. |
On-going |
|
Contract 904 |
|
1 |
The contractor have
provided the noise mitigation measures for the noisy works and was reminded
to properly maintain the noise mitigation measures. |
Improved and standard
to be maintained |
2 |
The contractor was
reminded to provide drip tray to chemicals being used on site. |
Improved and standard
to be maintained |
3 |
The contractor
was reminded to maintain good housekeeping. |
Improved and standard
to be maintained |
4 |
The contractor was
reminded to provide adequate silt removal facilities, as well as properly
maintain the site drainage system and discharge. |
Improved and standard
to be maintained |
5 |
The contractor was
reminded to cover the stockpile and provide frequent watering. |
Improved and standard
to be maintained |
6 |
The contractor was reminded to maintain proper tree
protection and maintenance works. |
Improved and standard to be maintained |
|
Contract 908 |
|
1 |
The contractor was reminded that the stockpiles
should be covered entirely by impervious sheetings. |
On-going |
2 |
The contractor was reminded to remove C&D
wastes in a timely manner |
On-going |
11.3
Solid and Liquid Waste Management Status
Base on the findings of the site
inspections, the Contractors¡¦ performance in solid and liquid waste management
were acceptable and compliance with the EIA requirements were demonstrated. The
current management standard should be maintained.
The IEC conducted site inspections for respective
works areas on 12, 25 and 27 November 2014. Minor irregularities including
provision of movable noise barriers as necessary and enhancing site drainage
system and dust suppression measures were observed during the site inspections.
Follow up actions had been taken by the respective civil works contractors.
Future key issues envisaged in the coming
month include noise, dust and wastewater from site works, disposal of C&D
wastes arising as well as tree protection on site. The ET will continue the
implementation of the EM&A programme in accordance to the EM&A
Manual.
It is concluded from the environmental
monitoring and audit works for the SIL(E) Project that the construction works
were undertaken in an appropriately environmentally sensitive manner in the
reporting period. The environmental protection and pollution control measures
provided by the respective civil works contractors were generally acceptable
apart from some minor irregularities which were rectified timely by the
contractors.
The ET will continue the implementation of
the EM&A programme in accordance to the EM&A Manual and to a level
consistent with MTRCL's Corporate Sustainability Policy.