Executive Summary
The Hong Kong-Zhuhai-Macao Bridge (HZMB) Hong Kong Link Road (HKLR)
serves to connect the HZMB Main Bridge at the Hong Kong Special Administrative
Region (HKSAR) Boundary and the HZMB Hong Kong Boundary Crossing Facilities
(HKBCF) located at the north eastern waters of the Hong Kong International
Airport (HKIA).
The HKLR project has been
separated into two contracts. They are Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between
Scenic Hill and Hong Kong Boundary Crossing Facilities (hereafter referred to
as the Contract) and Contract No. HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between
HKSAR Boundary and Scenic Hill.
China State Construction
Engineering (Hong Kong) Ltd. was awarded by Highways Department as the
Contractor to undertake the construction works of Contract No. HY/2011/03. The
main works of the Contract include land tunnel at Scenic Hill, tunnel
underneath Airport Road and Airport Express Line, reclamation and tunnel to the
east coast of the Airport Island, at-grade road connecting to the HKBCF and
highway works of the HKBCF within the Airport Island and in the vicinity of the
HKLR reclamation. The Contract is
part of the HKLR Project and HKBCF Project, these
projects are considered to be ˇ§Designated Projectsˇ¨, under Schedule 2 of the
Environmental Impact Assessment (EIA) Ordinance (Cap 499) and Environmental
Impact Assessment (EIA) Reports (Register No. AEIAR-144/2009 and AEIAR-145/2009)
were prepared for the Project. The
current Environmental Permit (EP) EP-352/2009/D for HKLR and EP-353/2009/H for
HKBCF were issued on 22 December 2014 and 19 January 2015, respectively. These
documents are available through the EIA Ordinance Register. The construction
phase of
Contract was commenced on 17 October 2012.
BMT Asia Pacific Limited
has been appointed by the Contractor to implement the Environmental Monitoring
& Audit (EM&A) programme for the Contract in accordance with the
Updated EM&A Manual for HKLR (Version 1.0) and will be providing
environmental team services to the Contract.
This is the thirty-third Monthly EM&A report for the Contract which summaries the monitoring
results and audit findings of the EM&A programme during the reporting
period from 1 to 30 June 2015.
Environmental
Monitoring and Audit Progress
The monthly EM&A
programme was undertaken in accordance with the Updated EM&A Manual for
HKLR (Version 1.0). A summary of
the monitoring activities in this reporting month is listed below:
1-hr TSP Monitoring
|
2, 8, 12, 18, 24 and 29 June 2015
|
24-hr TSP Monitoring
|
1, 5, 11, 17, 23 and 26 June 2015
|
Noise Monitoring
|
2, 8, 18, 24 and 29 June 2015
|
Water Quality Monitoring
|
1, 3, 5, 8, 10, 12, 15, 17, 19, 22, 24, 26 and 29 June 2015
|
Chinese White Dolphin
Monitoring
|
2, 10, 24 and 26 June 2015
|
Mudflat Monitoring
(Ecology)
|
6, 14,15, 16, 17 and 20 June 2015
|
Mudflat Monitoring
(Sedimentation Rate)
|
14 June 2015
|
Site Inspection
|
3, 10, 17 and 26 June
2015
|
Due
to the change of tide pattern and weather condition, mudflat monitoring
(ecology) was rescheduled from 13 to 15 June 2015 and from 21 to 17 June 2015.
Due
to the boat availability issue, the dolphins monitoring was rescheduled from 16
June to 24 June 2015 and from 23 June 2015 to 26 June 2015.
Breaches of Action and Limit Levels
A summary of environmental exceedances for this reporting month is as follows:
Environmental
Monitoring
|
Parameters
|
Action
Level (AL)
|
Limit
Level (LL)
|
Air Quality
|
1-hr TSP
|
0
|
0
|
24-hr TSP
|
0
|
0
|
Noise
|
Leq (30 min)
|
0
|
0
|
Water Quality
|
Suspended solids level (SS)
|
0
|
0
|
Turbidity level
|
0
|
0
|
Dissolved oxygen level (DO)
|
0
|
0
|
Complaint Log
There were no complaints
received in relation to the environmental impacts during the reporting period.
Notifications
of Summons and Prosecutions
There were no notifications of summons or
prosecutions received during this reporting month.
Reporting
Changes
This report has been
developed in compliance with the reporting requirements for the subsequent
EM&A reports as required by the Updated EM&A Manual for HKLR (Version
1.0).
The proposal for the change
of Action Level and Limit Level for suspended solid and turbidity was approved
by EPD on 25 March 2013.
The revised Event and
Action Plan for dolphin Monitoring was approved by EPD on 6 May
2013.
The original monitoring station
at IS(Mf)9 (Coordinate- East:813273, North 818850) was observed inside the
perimeter silt curtain of Contract HY/2010/02 on 1 July 2013, as such the
original impact water quality monitoring location at IS(Mf)9 was temporarily
shifted outside the silt curtain. As
advised by the Contractor of HY/2010/02 in August 2013, the perimeter silt
curtain was shifted to facilitate safe anchorage zone of construction
barges/vessels until end of 2013 subject to construction progress. Therefore, water quality monitoring
station IS(Mf)9 was shifted to 813226E and 818708N
since 1 July 2013. According to the
water quality monitoring teamˇ¦s observation on 24 March 2014, the original
monitoring location of IS(Mf)9 was no longer enclosed
by the perimeter silt curtain of Contract HY/2010/02. Thus, the impact water
quality monitoring works at the original monitoring location of IS(Mf)9 has been resumed since 24 March 2014.
Future Key
Issues
The future key issues
include potential noise, air quality, water quality and ecological impacts and
waste management arising from the following construction activities to be
undertaken in the upcoming month:
ˇP
Dismantling/trimming of Temporary 40mm Stone Platform for Construction of
Seawall at Portion X;
ˇP
Filling Works behind Stone Platform at Portion X;
ˇP
Construction of Seawall at Portion X;
ˇP
Loading and Unloading Filling Material at Portion X;
ˇP
Temporary Stone Platform Construction at Portion X;
ˇP
Pipe Piling at Portion X;
ˇP
Excavation and Lateral Support Works at Scenic Hill Tunnel (Cut & Cover
Tunnel) at Portion X;
ˇP
Laying blinding layer for tunnel box structure at Scenic Hill Tunnel (Cut
& Cover Tunnel) at Portion X;
ˇP
Construction of tunnel box structure at Scenic Hill Tunnel (Cut &
Cover Tunnel) at Portion X.
ˇP
Socket H-Piling work at Scenic Hill Tunnel (Cut & Cover Tunnel) at
Portion X;
ˇP
Excavation Works for HKBCF to Airport Tunnel at Portion X;
ˇP
Socket H-Piling work for HKBCF to Airport Tunnel East (Cut &Cover
Tunnel) at Portion X;
ˇP
Pipe Piling works for HKBCF to Airport Tunnel East (Cut &Cover Tunnel)
at Portion X;
ˇP
Works for Diversion of Airport Road;
ˇP
Utilities Detection at Airport Road / Airport Express Line/ East Coast
Road;
ˇP
Establishment of Site Access at Airport Road / Airport Express Line/East
Coast Road;
ˇP
Canopy Pipe Drilling underneath Airport Express Line;
ˇP
Excavation and Lateral Support Works at shaft 3 extension north shaft
& south shaft at Kwo Lo Wan Road;
ˇP
Excavation and Lateral Support Works for HKBCF to Airport Tunnel West (Cut
& Cover Tunnel) at Airport Road;
ˇP
Utility Culvert Excavation at Portion Y;
ˇP
Highway Operation and Maintenance Area Building Foundation Works at
Portion Y;
ˇP
Excavation for Scenic Hill Tunnel at West Portal; and
ˇP
Ventilation Building Foundation Works at West Portal.
1.1.1
The Hong Kong-Zhuhai-Macao Bridge (HZMB) Hong Kong Link Road (HKLR) serves to connect
the HZMB Main Bridge at the Hong Kong Special Administrative Region (HKSAR)
Boundary and the HZMB Hong Kong Boundary Crossing Facilities (HKBCF) located at
the north eastern waters of the Hong Kong International Airport (HKIA).
1.1.2 The HKLR project has been separated into two contracts. They are Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between
Scenic Hill and Hong Kong Boundary Crossing Facilities (hereafter referred to
as the Contract) and Contract No. HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between
HKSAR Boundary and Scenic Hill.
1.1.3
China State Construction
Engineering (Hong Kong) Ltd. was awarded by Highways Department (HyD) as the Contractor to undertake the construction works
of Contract No. HY/2011/03. The Contract is part of the HKLR Project and HKBCF Project,
these projects are considered to be ˇ§Designated Projectsˇ¨, under Schedule 2 of
the Environmental Impact Assessment (EIA) Ordinance (Cap 499) and Environmental
Impact Assessment (EIA) Reports (Register No. AEIAR-144/2009 and
AEIAR-145/2009) were prepared for the Project. The current Environmental Permit (EP)
EP-352/2009/D for HKLR and EP-353/2009/H for HKBCF were issued on 22 December
2014 and 19 January 2015, respectively. These documents are available through
the EIA Ordinance Register. The construction phase of Contract
was commenced on 17 October 2012. Figure
1.1 shows the project site
boundary. The works areas are shown in Appendix O.
1.1.4
The Contract
includes the following key aspects:
ˇP
New reclamation
along the east coast of the approximately 23 hectares.
ˇP
Tunnel of Scenic
Hill (Tunnel SHT) from Scenic Hill to the new reclamation, of approximately 1km
in length with three (3) lanes for the east bound carriageway heading to the
HKBCF and four (4) lanes for the westbound carriageway heading to the HZMB Main
Bridge.
ˇP
An abutment of the
viaduct portion of the HKLR at the west portal of Tunnel SHT and associated
road works at the west portal of Tunnel SHT.
ˇP
An at grade road on
the new reclamation along the east coast of the HKIA to connect with the HKBCF,
of approximately 1.6 km along dual 3-lane carriageway with hard shoulder for
each bound.
ˇP
Road links between
the HKBCF and the HKIA including new roads and the modification of existing
roads at the HKIA, involving viaducts, at grade roads and a Tunnel HAT.
ˇP
A highway operation
and maintenance area (HMA) located on the new reclamation, south of the Dragonair Headquarters Building, including the construction
of buildings, connection roads and other associated facilities.
ˇP
Associated civil,
structural, building, geotechnical, marine, environmental protection,
landscaping, drainage and sewerage, tunnel and highway electrical and
mechanical works, together with the installation of street lightings, traffic
aids and sign gantries, water mains and fire hydrants, provision of facilities
for installation of traffic control and surveillance system (TCSS), reprovisioning works of affected existing facilities,
implementation of transplanting, compensatory planting and protection of
existing trees, and implementation of an environmental monitoring and audit
(EM&A) program.
1.1.5 This is the thirty-third Monthly EM&A report for the
Contract which summarizes the monitoring results and audit findings of the
EM&A programme during the reporting period from 1
to 30 June 2015.
1.1.6
BMT Asia Pacific Limited has been appointed by the Contractor to
implement the EM&A programme for the Contract in
accordance with the Updated EM&A Manual for HKLR (Version 1.0) for HKLR and
will be providing environmental team services to the Contract. Ramboll Environ Hong Kong Ltd. was employed by HyD as the Independent
Environmental Checker (IEC) and Environmental Project Office (ENPO) for the
Project. The project organization with regard to the
environmental works is as follows.
1.2.1 The project organization structure and lines of
communication with respect to the on-site environmental management structure is
shown in Appendix A. The key personnel contact names and
numbers are summarized in Table 1.1.
Table 1.1 Contact
Information of Key Personnel
Party
|
Position
|
Name
|
Telephone
|
Fax
|
Supervising Officerˇ¦s Representative
(Ove Arup & Partners Hong Kong Limited)
|
(Chief Resident Engineer,
CRE)
|
Robert Antony Evans
|
3968 0801
|
2109 1882
|
Environmental Project Office / Independent
Environmental Checker
(Ramboll Environ Hong Kong Limited)
|
Environmental Project Office Leader
|
Y. H. Hui
|
3465 2888
|
3465 2899
|
Independent Environmental Checker
|
Antony Wong
|
3465 2888
|
3465 2899
|
Contractor
(China State Construction Engineering (Hong Kong) Ltd)
|
Project Manager
|
S. Y. Tse
|
3968 7002
|
2109 2588
|
Environmental Officer
|
Federick Wong
|
3968 7117
|
2109 2588
|
Environmental Team
(BMT Asia Pacific)
|
Environmental Team Leader
|
Claudine Lee
|
2241 9847
|
2815 3377
|
24 hours complaint
hotline
|
---
|
---
|
5699 5730
|
---
|
1.3
Construction
Programme
1.3.1 A
copy of the Contractorˇ¦s construction programme is
provided in Appendix
B.
1.4
Construction Works Undertaken During the
Reporting Month
1.4.1 A summary
of the construction activities undertaken during this reporting month is shown
in Table 1.2.
Table 1.2 Construction
Activities During Reporting Month
Description
of Activities
|
Site Area
|
Dismantling/trimming of
temporary 40mm stone platform for construction of seawall
|
Portion X
|
Filling works behind stone
platform
|
Portion X
|
Construction of seawall
|
Portion X
|
Loading and unloading of
filling materials
|
Portion X
|
Temporary stone platform
construction
|
Portion X
|
Excavation and lateral support
works for Scenic Hill Tunnel (Cut
& Cover Tunnel)
|
Portion X
|
Socket H-Piling work for Scenic
Hill Tunnel (Cut & Cover Tunnel)
|
Portion X
|
Laying blinding layer for
tunnel box structure at Scenic Hill Tunnel (Cut & Cover Tunnel)
|
Portion X
|
Construction of tunnel box
structure at Scenic Hill Tunnel (Cut & Cover Tunnel) at Portion X
|
Portion X
|
Excavation for HKBCF to Airport
Tunnel
|
Portion X
|
Excavation for Scenic Hill
Tunnel
|
West Portal
|
Ventilation
building foundation works
|
West Portal
|
Works for diversion of Airport
Road
|
Airport Road
|
Utilities detection
|
Airport Road/ Airport Express Line/ East Coast Road
|
Establishment of Site Access
|
Airport Road/ Airport Express Line/ East Coast Road
|
Canopy pipe drilling underneath
Airport Express Line
|
Airport Express Line
|
Excavation and lateral support
works at shaft 3 extension north shaft & south shaft
|
Kwo Lo Wan
Road
|
Excavation
and Lateral Support Works for HKBCF to Airport Tunnel West (Cut & Cover
Tunnel)
|
Airport Road
|
Utility culvert excavation
|
Portion Y
|
Highway
Operation and Maintenance Area Building
Foundation Works
|
Portion Y
|
2.1
Monitoring
Requirements
2.1.1 In accordance with
the Contract Specific EM&A Manual, baseline 1-hour and 24-hour TSP levels
at two air quality monitoring stations were established. Impact 1-hour TSP monitoring was
conducted for at least three times every 6 days, while impact 24-hour TSP
monitoring was carried out for at least once every 6 days. The Action and Limit
Level for 1-hr TSP and 24-hr TSP are provided in Table 2.1 and Table 2.2,
respectively.
Table 2.1 Action
and Limit Levels for 1-hour TSP
Monitoring Station
|
Action Level, µg/m3
|
Limit Level, µg/m3
|
AMS 5 ˇV Ma Wan Chung Village (Tung Chung)
|
352
|
500
|
AMS 6 ˇV Dragonair / CNAC (Group) Building
(HKIA)
|
360
|
Table 2.2 Action
and Limit Levels for 24-hour TSP
Monitoring Station
|
Action Level, µg/m3
|
Limit Level, µg/m3
|
AMS 5 ˇV Ma Wan Chung Village (Tung Chung)
|
164
|
260
|
AMS 6 ˇV Dragonair / CNAC (Group) Building
(HKIA)
|
173
|
260
|
2.2.1
24-hour TSP air quality monitoring was performed using
High Volume Sampler (HVS) located at each designated monitoring station. The HVS
meets all the requirements of the Contract Specific EM&A Manual. Portable
direct reading dust meters were used to carry out the 1-hour TSP
monitoring. Brand and model of the
equipment is given in Table 2.3.
Table 2.3
Air Quality Monitoring Equipment
Equipment
|
Brand and Model
|
Portable direct reading dust meter (1-hour
TSP)
|
Sibata Digital Dust Monitor (Model No. LD-3B)
|
High Volume Sampler
(24-hour TSP)
|
Tisch Environmental Mass Flow Controlled Total
Suspended Particulate (TSP) High Volume Air Sampler (Model No. TE-5170)
|
2.3.1
Monitoring locations AMS5
and AMS6 were set up at the proposed locations in accordance
with Contract Specific EM&A Manual.
2.3.2
Figure 2.1 shows the locations
of monitoring stations. Table 2.4
describes the details of the monitoring stations.
Table
2.4 Locations
of Impact Air Quality Monitoring Stations
Monitoring
Station
|
Location
|
AMS5
|
Ma Wan Chung Village (Tung Chung)
|
AMS6
|
Dragonair / CNAC (Group) Building (HKIA)
|
2.4.1
Table 2.5 summarizes the monitoring parameters, frequency and
duration of impact TSP monitoring.
Table 2.5 Air
Quality Monitoring Parameters, Frequency and Duration
Parameter
|
Frequency
and Duration
|
1-hour TSP
|
Three times every 6 days while the highest
dust impact was expected
|
24-hour TSP
|
Once every 6 days
|
2.5.1 24-hour TSP
Monitoring
(a) The HVS was installed in the vicinity of the air sensitive receivers.
The following criteria were considered in the installation of the HVS.
(i) A horizontal platform with appropriate support to secure the sampler
against gusty wind was provided.
(ii) The distance between the HVS and any obstacles, such as buildings, was
at least twice the height that the obstacle protrudes above the HVS.
(iii) A minimum of 2 meters separation from walls, parapets and penthouse for
rooftop sampler was provided.
(iv) No furnace or incinerator flues are nearby.
(v) Airflow around the sampler was unrestricted.
(vi) Permission was obtained to set up the samplers and access to the monitoring
stations.
(vii) A secured supply of electricity was obtained to operate the samplers.
(viii) The sampler was located more than 20 meters from any dripline.
(ix) Any wire fence and gate, required to protect the sampler, did not
obstruct the monitoring process.
(x) Flow control accuracy was kept within ˇÓ2.5% deviation over 24-hour
sampling period.
(b) Preparation of Filter Papers
(i) Glass fibre filters, G810 were labelled and sufficient filters that were
clean and without pinholes were selected.
(ii)
All filters were equilibrated in the conditioning environment for 24
hours before weighing. The conditioning environment temperature was around 25 ˘XC and not variable by more than ˇÓ3 ˘XC; the relative humidity (RH) was < 50%
and not variable by more than ˇÓ5%.
A convenient working RH was 40%.
(iii)
All filter papers were prepared and analysed by ALS Technichem
(HK) Pty Ltd., which is a HOKLAS accredited laboratory and has comprehensive
quality assurance and quality control programmes.
(c) Field Monitoring
(i) The power supply was checked to ensure the HVS works properly.
(ii) The filter holder and the area surrounding the filter were cleaned.
(iii) The filter holder was removed by loosening the four bolts and a new
filter, with stamped number upward, on a supporting screen was aligned
carefully.
(iv) The filter was properly aligned on the screen so that the gasket formed an
airtight seal on the outer edges of the filter.
(v)
The swing bolts were fastened to hold the filter holder down to the
frame. The pressure applied was
sufficient to avoid air leakage at the edges.
(vi) Then the shelter lid was closed and was secured with the aluminium strip.
(vii) The HVS was warmed-up for about 5 minutes to establish run-temperature
conditions.
(viii) A new flow rate record sheet was set into the flow recorder.
(ix)
On site temperature and atmospheric pressure readings were taken and the
flow rate of the HVS was checked and adjusted at around 1.1 m3/min,
and complied with the range specified in the Updated EM&A Manual for HKLR
(Version 1.0) (i.e. 0.6-1.7 m3/min).
(x) The programmable digital timer was set for a sampling period of 24
hours, and the starting time, weather condition and the filter number were
recorded.
(xi) The initial elapsed time was recorded.
(xii) At the end of sampling, on site temperature and atmospheric pressure
readings were taken and the final flow rate of the HVS was checked and
recorded.
(xiii)
The final elapsed time was recorded.
(xiv)
The sampled filter was removed carefully and folded in half length so
that only surfaces with collected particulate matter were in contact.
(xv)
It was then placed in a clean plastic envelope and sealed.
(xvi) All monitoring information was recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK)
Pty Ltd. for analysis.
(d) Maintenance and Calibration
(i) The HVS and its accessories were maintained in good working condition,
such as replacing motor brushes routinely and checking electrical wiring to
ensure a continuous power supply.
(ii) 5-point calibration of the HVS was conducted using TE-5025A Calibration Kit prior to the
commencement of baseline monitoring. Bi-monthly 5-point calibration of the HVS
will be carried out during impact monitoring.
(iii) Calibration certificate of the HVSs are provided in Appendix C.
2.5.2 1-hour TSP
Monitoring
(a) Measuring Procedures
The measuring procedures of
the 1-hour dust meter were in accordance with the Manufacturerˇ¦s Instruction
Manual as follows:-
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the ˇ§TIME SETTINGˇ¨ switch to [BG].
(iv) Push
ˇ§START/STOPˇ¨ switch to perform background measurement for 6 seconds.
(v)
Turn the knob at SENSI ADJ position to insert the light scattering
plate.
(vi) Leave the
equipment for 1 minute upon ˇ§SPAN CHECKˇ¨ is indicated in the display.
(vii)
Push ˇ§START/STOPˇ¨ switch to perform automatic sensitivity adjustment.
This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE position.
(ix)
Push the ˇ§TIME SETTINGˇ¨ switch the time set in the display to 3 hours.
(x)
Lower down the air collection opening cover.
(xi)
Push ˇ§START/STOPˇ¨ switch to start measurement.
(b) Maintenance and Calibration
(i) The
1-hour TSP meter was calibrated at 1-year intervals against a Tisch Environmental Mass Flow Controlled Total Suspended
Particulate (TSP) High Volume Air Sampler. Calibration certificates of the
Laser Dust Monitors are provided in Appendix C.
2.6.1 The schedule for air
quality monitoring June 2015 is provided in Appendix D.
2.7.1
The monitoring results for 1-hour TSP and 24-hour TSP
are summarized in Tables 2.6 and 2.7 respectively. Detailed impact air
quality monitoring results and relevant graphical plots are presented in Appendix E.
Table 2.6 Summary
of 1-hour TSP Monitoring Results During the Reporting
Month
Monitoring Station
|
Average (mg/m3)
|
Range (mg/m3)
|
Action Level (mg/m3)
|
Limit Level (mg/m3)
|
AMS5
|
66
|
55 - 92
|
352
|
500
|
AMS6
|
65
|
55 - 76
|
360
|
500
|
Table 2.7 Summary
of 24-hour
TSP Monitoring Results During the Reporting Month
Monitoring Station
|
Average (mg/m3)
|
Range (mg/m3)
|
Action Level (mg/m3)
|
Limit Level (mg/m3)
|
AMS5
|
18
|
13 - 23
|
164
|
260
|
AMS6
|
37
|
26 - 46
|
173
|
260
|
2.7.2
No Action and Limit Level exceedances of 1-hour TSP and 24-hour TSP were
recorded at AMS5 and AMS6 during the reporting month.
2.7.3
The event action plan is annexed in Appendix F.
2.7.4
The wind data obtained from the on-site weather station during the reporting month is shown in Appendix G.
3.1.1
In accordance with the Contract Specific EM&A
Manual, impact noise monitoring was conducted for at least once per week during
the construction phase of the Project. The Action and Limit level of the noise
monitoring is provided in Table 3.1.
Table
3.1 Action
and Limit Levels for Noise during Construction Period
Monitoring Station
|
Time Period
|
Action Level
|
Limit Level
|
NMS5 ˇV Ma Wan Chung
Village (Ma Wan Chung Resident Association) (Tung Chung)
|
0700-1900 hours on normal
weekdays
|
When one documented
complaint is received
|
75 dB(A)
|
3.2.1
Noise monitoring was performed using sound level
meters at each designated monitoring station. The sound level meters deployed comply
with the International Electrotechnical Commission
Publications (IEC) 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Acoustic calibrator was deployed to
check the sound level meters at a known sound pressure level. Brand and model of the equipment are
given in Table 3.2.
Table
3.2 Noise
Monitoring Equipment
Equipment
|
Brand and Model
|
Integrated Sound Level
Meter
|
B&K 2238
|
Acoustic Calibrator
|
B&K 4231
|
3.3.1
Monitoring location NMS5 was set up at the
proposed locations in accordance with Contract Specific EM&A Manual.
3.3.2
Figure
2.1 shows the locations
of monitoring stations. Table 3.3 describes the details of the monitoring
stations.
Table
3.3 Locations
of Impact Noise Monitoring Stations
Monitoring Station
|
Location
|
NMS5
|
Ma Wan Chung Village (Ma
Wan Chung Resident Association) (Tung Chung)
|
3.4.1
Table 3.4 summarizes the monitoring
parameters, frequency and duration of impact noise monitoring.
Table
3.4 Noise
Monitoring Parameters, Frequency and Duration
Parameter
|
Frequency and Duration
|
30-mins measurement at each
monitoring station between 0700 and 1900 on normal weekdays (Monday to
Saturday). Leq, L10 and L90
would be recorded.
|
At least once per week
|
3.5.1
Monitoring Procedure
(a) The sound level meter was
set on a tripod at a height of 1.2 m
above the podium for free-field
measurements at NMS5. A correction of +3 dB(A)
shall be made to the free field measurements.
(b)
The battery condition was
checked to ensure the correct functioning of the meter.
(c)
Parameters such as
frequency weighting, the time weighting and the measurement time were set as
follows:-
(i) frequency weighting: A
(ii) time weighting: Fast
(iii) time measurement: Leq(30-minutes) during non-restricted
hours i.e. 07:00 ˇV 1900 on normal weekdays
(e)
Prior to and after each
noise measurement, the meter was calibrated using the acoustic calibrator for
94.0 dB(A) at 1000 Hz. If the difference in the calibration
level before and after measurement was more than 1.0 dB(A),
the measurement would be considered invalid and repeat of noise measurement
would be required after re-calibration or repair of the equipment.
(f)
During the monitoring
period, the Leq, L10 and L90
were recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
(g)
Noise measurement was
paused during periods of high intrusive noise (e.g. dog barking, helicopter
noise) if possible. Observations were recorded when intrusive noise was
unavoidable.
(h)
Noise monitoring was
cancelled in the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind with gusts exceeding 10m/s. The wind speed shall be checked with a portable wind
speed meter capable of measuring the wind speed in m/s.
3.5.2
Maintenance and Calibration
(a) The microphone head of the sound
level meter was cleaned with soft cloth at regular intervals.
(b) The meter and calibrator
were sent to the supplier or HOKLAS laboratory to check and calibrate at yearly
intervals.
(c) Calibration certificates
of the sound level meters and acoustic calibrators are provided in Appendix C.
3.6.1
The schedule for construction noise monitoring in June
2015 is provided in Appendix D.
3.7.1
The monitoring results for construction noise are
summarized in Table 3.5 and the
monitoring results and relevant graphical plots are provided in Appendix E.
Table 3.5 Summary
of Construction Noise Monitoring Results During the Reporting Month
Monitoring Station
|
Average Leq (30 mins), dB(A)
|
Range of Leq (30 mins), dB(A)
|
Limit Level Leq (30 mins), dB(A)
|
NMS5
|
68
|
64 ˇV 70
|
75
|
*A correction factor of +3dB(A) from free
field to facade measurement was included.
3.7.2
There were no Action and Limit Level exceedances
for noise during daytime on normal weekdays of the reporting month.
3.7.3
Major noise sources during the noise monitoring
included construction activities of the Contract, nearby traffic and insect noise.
3.7.4
The event action plan is annexed in Appendix F.
4
Water Quality Monitoring
4.1.1
Impact water quality monitoring was carried out to
ensure that any deterioration of water quality was detected, and that timely
action was taken to rectify the situation.
For impact water quality monitoring, measurements were taken in
accordance with the Contract Specific EM&A Manual. Table 4.1 shows the established Action/Limit Levels for the
environmental monitoring works. The ET proposed to amend the Acton Level
and Limit Level for turbidity and suspended solid and EPD approved ETˇ¦s
proposal on 25 March 2013.
Therefore, Action Level and Limit Level for the Contract have been
changed since 25 March 2013.
4.1.2
The original and revised Action Level and
Limit Level for turbidity and suspended solid are shown in Table 4.1.
Table
4.1 Action
and Limit Levels for Water Quality
Parameter (unit)
|
Water Depth
|
Action Level
|
Limit Level
|
Dissolved Oxygen (mg/L)
(surface, middle and bottom)
|
Surface and Middle
|
5.0
|
4.2 except 5 for Fish
Culture Zone
|
Bottom
|
4.7
|
3.6
|
Turbidity (NTU)
|
Depth average
|
27.5 or 120% of upstream
control stationˇ¦s turbidity at the same tide of the same day;
The action level has been
amended to ˇ§27.5 and 120% of upstream control stationˇ¦s turbidity at the same
tide of the same dayˇ¨ since 25 March 2013.
|
47.0 or 130% of turbidity
at the upstream control station at the same tide of same day;
The limit level has been
amended to ˇ§47.0 and 130% of turbidity at the upstream control station at the
same tide of same dayˇ¨ since 25 March 2013.
|
Suspended Solid (SS)
(mg/L)
|
Depth average
|
23.5 or 120% of upstream
control stationˇ¦s SS at the same tide of the same day;
The action level has been
amended to ˇ§23.5 and 120% of upstream control stationˇ¦s SS at the same tide of
the same dayˇ¨ since 25 March 2013.
|
34.4 or 130% of SS at the
upstream control station at the same tide of same day and 10mg/L for Water
Services Department Seawater Intakes;
The limit level has been
amended to ˇ§34.4 and 130% of SS at the upstream control station at the same
tide of same day and 10mg/L for Water Services Department Seawater Intakesˇ¨
since 25 March 2013
|
Notes:
(1) Depth-averaged
is calculated by taking the arithmetic means of reading of all three depths.
(2) For DO,
non-compliance of the water quality limit occurs when monitoring result is
lower that the limit.
(3) For SS
& turbidity non-compliance of the water quality limits occur when
monitoring result is higher than the limits.
(4) The change
to the Action and limit Levels for Water Quality Monitoring for the EM&A
works was approved by EPD on 25 March 2013.
4.2.1
Table 4.2 summarises the
equipment used in the impact water quality monitoring programme.
Table
4.2 Water
Quality Monitoring Equipment
Equipment
|
Brand and Model
|
DO and Temperature Meter,
Salinity Meter, Turbidimeter and pH Meter
|
YSI Model 6820 V2-M, 650
|
Positioning Equipment
|
DGPS ˇV KODEN :
KGP913MkII, KBG3
|
Water Depth Detector
|
Layin Associates: SM-5 & SM5A
|
Water Sampler
|
Wildlife Supply Company :
5487-10
|
4.3.1
Table 4.3 summarises the monitoring parameters, frequency and
monitoring depths of impact water quality monitoring as required in the
Contract Specific EM&A Manual.
Table
4.3 Impact
Water Quality Monitoring Parameters and Frequency
Monitoring Stations
|
Parameter, unit
|
Frequency
|
No. of depth
|
Impact Stations:
IS5, IS(Mf)6, IS7, IS8, IS(Mf)9 & IS10,
Control/Far Field
Stations:
CS2 & CS(Mf)5,
Sensitive Receiver
Stations:
SR3, SR4, SR5, SR10A & SR10B
|
ˇP
Depth, m
ˇP
Temperature, oC
ˇP
Salinity, ppt
ˇP
Dissolved Oxygen
(DO), mg/L
ˇP
DO Saturation, %
ˇP
Turbidity, NTU
ˇP
pH
ˇP Suspended Solids (SS), mg/L
|
Three times per week during
mid-ebb and mid-flood tides (within ˇÓ 1.75 hour of the predicted time)
|
3
(1 m below water surface,
mid-depth and 1 m above sea bed, except where the water depth is less than 6
m, in which case the mid-depth station may be omitted. Should the water
depth be less than 3 m, only the mid-depth station will be monitored).
|
4.4.1
In accordance with the Contract Specific EM&A
Manual, thirteen stations (6 Impact Stations, 5 Sensitive Receiver
Stations and 2 Control Stations) were designated for impact
water quality monitoring. The six Impact Stations
(IS) were chosen on the basis of their proximity to the reclamation and thus
the greatest potential for water quality impacts, the five Sensitive Receiver
Stations (SR) were chosen as they are close to the key sensitive receives and
the two Control Stations (CS) were chosen to facilitate comparison of the water
quality of the IS stations with less influence by the Project/ ambient water
quality conditions.
4.4.2
The locations of these monitoring stations are
summarized in Table 4.4 and shown in
Figure 2.1.
Table
4.4 Impact
Water Quality Monitoring Stations
Monitoring Stations
|
Description
|
Coordinates
|
Easting
|
Northing
|
IS5
|
Impact Station (Close to
HKLR construction site)
|
811579
|
817106
|
IS(Mf)6
|
Impact Station (Close to
HKLR construction site)
|
812101
|
817873
|
IS7
|
Impact Station (Close to
HKBCF construction site)
|
812244
|
818777
|
IS8
|
Impact Station (Close to
HKBCF construction site)
|
814251
|
818412
|
IS(Mf)9
|
Impact Station (Close to
HKBCF construction site)
|
813273
|
818850
|
IS10
|
Impact Station (Close to
HKBCF construction site)
|
812577
|
820670
|
SR3
|
Sensitive receivers (San
Tau SSSI)
|
810525
|
816456
|
SR4
|
Sensitive receivers (Tai
Ho Inlet)
|
814760
|
817867
|
SR5
|
Sensitive receivers
(Artificial Reef In NE Airport)
|
811489
|
820455
|
SR10A
|
Sensitive receivers (Ma
Wan Fish Culture Zone)
|
823741
|
823495
|
SR10B
|
Sensitive receivers (Ma
Wan Fish Culture Zone)
|
823686
|
823213
|
CS2
|
Control Station (Mid-Ebb)
|
805849
|
818780
|
CS(Mf)5
|
Control Station
(Mid-Flood)
|
817990
|
821129
|
4.5
Monitoring
Methodology
4.5.1
Instrumentation
(a) The
in-situ water quality parameters including dissolved oxygen, temperature, salinity
and turbidity, pH were measured by multi-parameter meters.
4.5.2
Operating/Analytical Procedures
(a) Digital Differential Global Positioning Systems
(DGPS) were used to ensure that the correct location was selected prior to
sample collection.
(b) Portable, battery-operated echo sounders were used
for the determination of water depth at each designated monitoring station.
(c) All in-situ measurements were taken at 3 water
depths, 1 m below water surface, mid-depth and 1 m above sea bed, except where
the water depth was less than 6 m, in which case the mid-depth station was
omitted. Should the water depth be less than 3 m, only the mid-depth station
was monitored.
(d) At each measurement/sampling depth, two consecutive
in-situ monitoring (DO concentration and saturation, temperature, turbidity,
pH, salinity) and water sample for SS. The probes were retrieved out of the
water after the first measurement and then re-deployed for the second
measurement. Where the difference in the value between the first and second
readings of DO or turbidity parameters was more than 25% of the value of the
first reading, the reading was discarded and further readings were taken.
(e) Duplicate samples from each independent sampling
event were collected for SS measurement. Water samples were collected using the
water samplers and the samples were stored in high-density polythene bottles.
Water samples collected were well-mixed in the water sampler prior to
pre-rinsing and transferring to sample bottles. Sample bottles were pre-rinsed
with the same water samples. The sample bottles were then be packed in
cool-boxes (cooled at 4oC without being frozen), and delivered to
ALS Technichem (HK) Pty Ltd. for the analysis of
suspended solids concentrations. The laboratory determination work would be
started within 24 hours after collection of the water samples. ALS Technichem (HK) Pty Ltd. is a HOKLAS accredited laboratory
and has comprehensive quality assurance and quality control programmes.
(f) The analysis method and detection limit for SS is
shown in Table 4.5.
Table 4.5 Laboratory
Analysis for Suspended Solids
Parameters
|
Instrumentation
|
Analytical Method
|
Detection Limit
|
Suspended Solid (SS)
|
Weighting
|
APHA 2540-D
|
0.5mg/L
|
(g) Other relevant data were recorded, including
monitoring location / position, time, water depth, tidal stages, weather
conditions and any special phenomena or work underway at the construction site
in the field log sheet for information.
4.5.3
Maintenance and Calibrations
(a) All in situ monitoring
instruments would be calibrated by ALS Technichem
(HK) Pty Ltd. before use and at 3-monthly intervals throughout all stages of
the water quality monitoring programme. The
procedures of performance check of sonde and testing
results are provided in Appendix C.
4.6.1
The schedule for impact water quality monitoring in
June 2015 is provided in Appendix D.
4.7.1
Impact water quality monitoring was conducted at all designated
monitoring stations during the reporting month. Impact water quality monitoring
results and relevant graphical plots are provided in Appendix E.
4.7.2
For marine water quality
monitoring, no Action Level and Limit Level exceedance
of turbidity level, dissolved
oxygen level and suspended solid level were recorded during the reporting month.
4.7.1
Water
quality impact sources during the water quality monitoring were the
construction activities of the Contract, nearby construction activities by other parties and
nearby operating vessels by other parties.
4.7.2
The
event action plan is annexed in Appendix
F.
5.1.1
Impact dolphin monitoring is required to be conducted by a qualified dolphin specialist team to
evaluate whether there have
been any effects on the
dolphins.
5.1.2 The Action
Level and Limit Level for dolphin monitoring are shown in Table 5.1.
Table 5.1 Action
and Limit Levels for Dolphin Monitoring
|
North Lantau
Social Cluster
|
NEL
|
NWL
|
Action
Level
|
STG < 4.2 & ANI < 15.5
|
STG < 6.9 & ANI <
31.3
|
Limit Level
|
(STG < 2.4 & ANI
< 8.9) and (STG < 3.9 & ANI < 17.9)
|
Remarks:
1. STG means quarterly encounter rate of number of dolphin sightings.
2. ANI means quarterly encounter rate of total number of dolphins.
3. For North Lantau Social Cluster, AL will be
trigger if either NEL or NWL fall
below the criteria; LL will be triggered if both NEL and NWL fall below the criteria.
5.1.3
The revised Event and Action
Plan for dolphin Monitoring was approved by EPD in 6 May 2013. The revised
Event and Action Plan is annexed in Appendix F.
Vessel-based Line-transect Survey
5.2.1
According to the requirements of the Updated EM&A Manual for HKLR
(Version 1.0), dolphin monitoring programme should
cover all transect lines in NEL and NWL survey areas (see Figure 1 of Appendix H) twice per month. The co-ordinates of all
transect lines are shown in Table 5.2.
Table 5.2 Co-ordinates
of Transect Lines
Line No.
|
Easting
|
Northing
|
|
Line No.
|
Easting
|
Northing
|
1
|
Start Point
|
804671
|
814577
|
|
13
|
Start Point
|
816506
|
819480
|
1
|
End Point
|
804671
|
831404
|
|
13
|
End Point
|
816506
|
824859
|
2
|
Start Point
|
805475
|
815457
|
|
14
|
Start Point
|
817537
|
820220
|
2
|
End Point
|
805477
|
826654
|
|
14
|
End Point
|
817537
|
824613
|
3
|
Start Point
|
806464
|
819435
|
|
15
|
Start Point
|
818568
|
820735
|
3
|
End Point
|
806464
|
822911
|
|
15
|
End Point
|
818568
|
824433
|
4
|
Start Point
|
807518
|
819771
|
|
16
|
Start Point
|
819532
|
821420
|
4
|
End Point
|
807518
|
829230
|
|
16
|
End Point
|
819532
|
824209
|
5
|
Start Point
|
808504
|
820220
|
|
17
|
Start Point
|
820451
|
822125
|
5
|
End Point
|
808504
|
828602
|
|
17
|
End Point
|
820451
|
823671
|
6
|
Start Point
|
809490
|
820466
|
|
18
|
Start Point
|
821504
|
822371
|
6
|
End Point
|
809490
|
825352
|
|
18
|
End Point
|
821504
|
823761
|
7
|
Start Point
|
810499
|
820690
|
|
19
|
Start Point
|
822513
|
823268
|
7
|
End Point
|
810499
|
824613
|
|
19
|
End Point
|
822513
|
824321
|
8
|
Start Point
|
811508
|
820847
|
|
20
|
Start Point
|
823477
|
823402
|
8
|
End Point
|
811508
|
824254
|
|
20
|
End Point
|
823477
|
824613
|
9
|
Start Point
|
812516
|
820892
|
|
21
|
Start Point
|
805476
|
827081
|
9
|
End Point
|
812516
|
824254
|
|
21
|
End Point
|
805476
|
830562
|
10
|
Start Point
|
813525
|
820872
|
|
22
|
Start Point
|
806464
|
824033
|
10
|
End Point
|
813525
|
824657
|
|
22
|
End Point
|
806464
|
829598
|
11
|
Start Point
|
814556
|
818449
|
|
23
|
Start Point
|
814559
|
821739
|
11
|
End Point
|
814556
|
820992
|
|
23
|
End Point
|
814559
|
824768
|
12
|
Start Point
|
815542
|
818807
|
|
|
|
|
|
12
|
End Point
|
815542
|
824882
|
|
|
|
|
|
5.2.2
The survey team used standard line-transect methods (Buckland et al.
2001) to conduct the systematic vessel surveys, and followed the same technique
of data collection that has been adopted over the last 16 years of marine
mammal monitoring surveys in Hong Kong developed by HKCRP (see Hung 2012,
2013). For each monitoring vessel
survey, a 15-m inboard vessel with an open upper deck (about 4.5 m above water
surface) was used to make observations from the flying bridge area.
5.2.3
Two experienced observers (a data recorder and a primary observer) made
up the on-effort survey team, and the survey vessel transited different
transect lines at a constant speed of 13-15 km per hour. The data recorder searched with unaided
eyes and filled out the datasheets, while the primary observer searched for
dolphins and porpoises continuously through 7 x 50 Fujinon
marine binoculars. Both observers
searched the sea ahead of the vessel, between 270o and 90o
(in relation to the bow, which is defined as 0o). One to two additional experienced
observers were available on the boat to work in shift (i.e. rotate every 30
minutes) in order to minimize fatigue of the survey team members. All observers were experienced in small
cetacean survey techniques and identifying local cetacean species.
5.2.4
During on-effort survey periods, the survey
team recorded effort data including time, position (latitude and longitude),
weather conditions (Beaufort sea state and visibility), and distance travelled
in each series (a continuous period of search effort) with the assistance of a
handheld GPS (Garmin eTrex
Legend).
5.2.5
Data including time, position and vessel speed were also automatically
and continuously logged by handheld GPS throughout the entire survey for
subsequent review.
5.2.6
When dolphins were sighted, the survey team would end the survey effort,
and immediately record the initial sighting distance and angle of the dolphin
group from the survey vessel, as well as the sighting time and position. Then the research vessel was diverted
from its course to approach the animals for species identification, group size
estimation, assessment of group composition, and behavioural
observations. The perpendicular
distance (PSD) of the dolphin group to the transect line was later calculated
from the initial sighting distance and angle.
5.2.7
Survey effort being conducted along the parallel transect lines that
were perpendicular to the coastlines (as indicated in Figure 1 of Appendix H) was labeled as ˇ§primaryˇ¨ survey effort,
while the survey effort conducted along the connecting lines between parallel
lines was labeled as ˇ§secondaryˇ¨ survey effort. According to HKCRP long-term dolphin
monitoring data, encounter rates of Chinese white dolphins deduced from effort
and sighting data collected along primary and secondary lines were similar in
NEL and NWL survey areas.
Therefore, both primary and secondary survey effort were presented as
on-effort survey effort in this report.
5.2.8
Encounter rates of Chinese White Dolphins (number of on-effort sightings
per 100 km of survey effort and number of dolphins from all on-effort sightings
per 100 km of survey effort) were calculated in NEL and NWL survey areas in
relation to the amount of survey effort conducted during each month of
monitoring survey. Only data
collected under Beaufort 3 or below condition would be used for encounter rate
analysis. Dolphin encounter rates
were calculated using primary survey effort alone, as well as the combined
survey effort from both primary and secondary lines.
Photo-identification Work
5.2.9
When a group of Chinese White Dolphins were sighted during the
line-transect survey, the survey team would end effort and approach the group
slowly from the side and behind to take photographs of them. Every attempt was made to photograph
every dolphin in the group, and even photograph both sides of the dolphins,
since the colouration and markings on both sides may
not be symmetrical.
5.2.10
A professional digital cameras (Canon EOS 7D and 60D models), equipped
with long telephoto lenses (100-400 mm zoom), were available on board for
researchers to take sharp, close-up photographs of dolphins as they
surfaced. The images were shot at
the highest available resolution and stored on Compact Flash memory cards for
downloading onto a computer.
5.2.11
All digital images taken in the field were first examined, and those
containing potentially identifiable individuals were sorted out. These photographs would then be examined
in greater detail, and were carefully compared to the existing Chinese White
Dolphin photo-identification catalogue maintained by HKCRP since 1995.
5.2.12
Chinese White Dolphins can be identified by their natural markings, such
as nicks, cuts, scars and deformities on their dorsal fin and body, and their
unique spotting patterns were also used as secondary identifying features
(Jefferson 2000).
5.2.13
All photographs of each individual were then compiled and arranged in
chronological order, with data including the date and location first identified
(initial sighting), re-sightings, associated dolphins, distinctive features,
and age classes entered into a computer database. Detailed information on all identified
individuals will be further presented as an appendix in quarterly EM&A
reports.
Vessel-based Line-transect Survey
5.3.1
During the month of June 2015, two sets of
systematic line-transect vessel surveys were conducted on 2nd,
10th, 24th and 26th to cover all
transect lines in NWL and NEL survey areas twice. The survey routes of each
survey day are presented in Figures 2 to
5
of Appendix H.
5.3.2
From these surveys, a total
of 301.30
km of survey effort was
collected, with 91.6%
of the total survey effort
being conducted under favourable weather conditions (i.e. Beaufort Sea State 3
or below with good visibility) (Annex I of Appendix H).
Among the two areas, 115.90
km and 185.40
km of survey effort were
collected from NEL and NWL survey areas respectively. Moreover, the total survey effort
conducted on primary lines was 220.07
km, while the effort on
secondary lines was 81.23
km.
5.3.3
During the two sets of monitoring surveys
in June 2015,
three groups
of 15
Chinese White Dolphins were sighted. (Annex II of Appendix H).
Two sightings were made in NWL, while one
sighting of a lone dolphin was made in NEL. In fact, this lone dolphin was the only
one sighted in NEL waters since July 2014.
5.3.4
During Juneˇ¦s surveys, all
three dolphin sightings
were made on primary lines during
on-effort search, and none of
the dolphin groups was associated with operating fishing
vessel.
5.3.5
Distribution of these dolphin sightings made
in June 2015 is
shown in Figure 6 of Appendix H. Both
sightings made in NWL were located near Lung Kwu
Chau, while the lone dolphin sighted in NEL was found to the east of Siu Mo To (Figure 6 of Appendix H).
5.3.6
Notably, none of the three sightings was
made in the proximity of the HKLR03 and HKBCF reclamation sites, as well as the
HKLR09 and TMCLKL alignments (Figure 6 of Appendix H).
5.3.7
During Juneˇ¦s surveys, encounter rates of Chinese White Dolphins deduced
from the survey effort and on-effort sighting data made under favourable conditions (Beaufort 3 or below) are shown in Table 5.3
and Table 5.4.
5.3.8
The average group size of Chinese White
Dolphins in June 2015 was 5.00 individuals per group. This average was higher
than previous months of dolphin monitoring, which was mainly attributed by the
large group of 10 dolphins sighted during the first monitoring survey in June
near Lung Kwu Chau.
Table 5.3 Individual Survey Event Encounter Rates
|
Encounter
rate (STG)
(no. of on-effort dolphin sightings per 100
km of survey effort)
|
Encounter
rate (ANI)
(no. of dolphins from all on-effort
sightings per 100 km of survey
effort)
|
Primary Lines Only
|
Primary Lines Only
|
NEL
|
Set 1: June 2nd / 10th
|
0.0
|
0.0
|
Set 2: June 24th / 26th
|
2.6
|
2.6
|
NWL
|
Set 1: June 2nd / 10th
|
1.5
|
15.2
|
Set 2: June 24th / 26th
|
0.0
|
0.0
|
Remarks:
1. Dolphin Encounter Rates Deduced from the Two
Sets of Surveys (Two Surveys in Each Set) in June 2015 in Northeast (NEL) and Northwest Lantau (NWL).
Table 5.4 Monthly
Average Encounter Rates
|
Encounter
rate (STG)
(no. of on-effort dolphin sightings per 100
km of survey effort)
|
Encounter rate (ANI)
(no.
of dolphins from all on-effort sightings per 100 km of survey effort)
|
Primary Lines Only
|
Both Primary and Secondary Lines
|
Primary Lines Only
|
Both Primary and Secondary Lines
|
Northeast
Lantau
|
1.3
|
0.9
|
1.3
|
0.9
|
Northwest
Lantau
|
0.8
|
0.6
|
7.8
|
6.2
|
Remarks:
1.
Monthly Average Dolphin Encounter Rates (Sightings Per 100 km of Survey
Effort) from All Four Surveys Conducted in June 2015 on Primary Lines only as well as Both
Primary Lines and Secondary Lines in Northeast (NEL) and Northwest Lantau (NWL).
Photo-identification Work
5.3.9
Eleven individual dolphins were sighted 13
times during Juneˇ¦s surveys. Almost
all of them were sighted only once, except two individuals (NL202 and NL286)
that were sighted twice during the monitoring month (Annex III and IV of Appendix H).
5.3.10
Notably, two of the 11 individual dolphins
(NL104 and NL202) were accompanied with their calves during their
re-sightings. These mother-calf
pairs have been sighted repeatedly throughout the HKLR03 construction period.
Conclusion
5.3.11
During this month of dolphin
monitoring, no adverse impact from the activities of this construction project
on Chinese White Dolphins was noticeable from general observations.
5.3.12
Due to monthly variation in
dolphin occurrence within the study area, it would be more appropriate to draw conclusion
on whether any impacts on dolphins have been detected related to the
construction activities of this project in the quarterly EM&A report, where
comparison on distribution, group size and encounter rates of dolphins between
the quarterly impact monitoring period (June ˇV August
2015) and baseline monitoring period (3-month period) will be made.
5.4.1
Buckland, S. T., Anderson, D. R., Burnham,
K. P., Laake, J. L., Borchers,
D. L., and Thomas, L. 2001. Introduction to distance sampling: estimating
abundance of biological populations.
Oxford University Press, London.
5.4.2
Hung, S. K. 2012. Monitoring of Marine Mammals in Hong
Kong waters: final report (2011-12).
An unpublished report submitted to the Agriculture, Fisheries and
Conservation Department, 171 pp.
5.4.3
Hung, S. K. 2013. Monitoring of Marine Mammals in Hong Kong waters: final report (2012-13). An unpublished report submitted to the
Agriculture, Fisheries and Conservation Department, 168 pp.
5.4.4
Jefferson, T. A. 2000. Population biology of the Indo-Pacific
hump-backed dolphin in Hong Kong waters.
Wildlife Monographs 144:1-65.
Methodology
6.1.1
To avoid disturbance to the mudflat and nuisance to
navigation, no fixed marker/monitoring rod was installed at the monitoring
stations. A high precision Global Navigation Satellite System (GNSS) real time
location fixing system (or equivalent technology) was used to locate the
station in the precision of 1mm, which is reasonable under flat mudflat
topography with uneven mudflat surface only at micro level. This method has been used on
Agricultural Fisheries and Conservation Departmentˇ¦s (AFCD) project, namely
Baseline Ecological Monitoring Programme for the Mai Po Inner Deep Bay Ramsar Site for measurement of seabed levels.
6.1.2
Measurements were taken directly on the mudflat
surface. The Real Time Kinematic
GNSS (RTK GNSS) surveying technology was used to measure mudflat surface levels
and 3D coordinates of a survey point.
The RTK GNSS survey was calibrated against a reference station in the
field before and after each survey.
The reference station is a survey control point established by the Lands
Department of the HKSAR Government or traditional land surveying methods using
professional surveying instruments such as total station, level and/or geodetic
GNSS. The coordinates system was in
HK1980 GRID system. For this
contract, the reference control station was surveyed and established by
traditional land surveying methods using professional surveying instruments
such as total station, level and RTK GNSS.
The accuracy was down to mm level so that the reference control station
has relatively higher accuracy. As
the reference control station has higher accuracy, it was set as true
evaluation relative to the RTK GNSS measurement. All position and height correction were
adjusted and corrected to the reference control station. Reference station survey result and
professional land surveying calibration is shown as Table 6.1:
Table 6.1 Reference
Station Survey result and GNSS RTK calibration result of Round 1
Reference
Station
|
Easting (m)
|
Northing
(m)
|
Baseline
reference elevation (mPD) (A)
|
Round 1
Survey (mPD) (B)
|
Calibration
Adjustment (B-A)
|
T1
|
811248.660mE
|
816393.173mN
|
3.840
|
3.817
|
-0.023
|
T2
|
810806.297mE
|
815691.822mN
|
4.625
|
4.653
|
+0.028
|
T3
|
810778.098mE
|
815689.918mN
|
4.651
|
4.660
|
+0.009
|
T4
|
810274.783mE
|
816689.068mN
|
2.637
|
2.709
|
+0.072
|
6.1.3
The precision of the measured mudflat surface level
reading (vertical precision setting) was within 10 mm (standard deviation)
after averaging the valid survey records of the XYZ HK1980 GRID
coordinates. Each survey record at
each station was computed by averaging at least three measurements that are
within the above specified precision setting. Both digital data logging and
written records were collected in the field. Field data on station fixing and mudflat
surface measurement were recorded.
Monitoring Locations
6.1.4
Four monitoring stations were established based on the
site conditions for the sedimentation monitoring and are shown in Figure
6.1.
Monitoring Results
6.1.5
The baseline sedimentation rate monitoring was in
September 2012 and impact sedimentation rate monitoring was undertaken on 14
June 2015. The mudflat surface levels at the four established
monitoring stations and the corresponding XYZ HK1980 GRID coordinates are
presented in Table 6.2 and Table 6.3.
Table 6.2 Measured
Mudflat Surface Level Results
|
Baseline
Monitoring (September 2012)
|
Impact
Monitoring (June 2015)
|
Monitoring Station
|
Easting (m)
|
Northing (m)
|
Surface Level
(mPD)
|
Easting (m)
|
Northing (m)
|
Surface Level
(mPD)
|
S1
|
810291.160
|
816678.727
|
0.950
|
810291.164
|
816678.734
|
1.033
|
S2
|
810958.272
|
815831.531
|
0.864
|
810958.282
|
815831.519
|
0.953
|
S3
|
810716.585
|
815953.308
|
1.341
|
810716.562
|
815953.324
|
1.440
|
S4
|
811221.433
|
816151.381
|
0.931
|
811221.466
|
816151.504
|
1.094
|
Table 6.3 Comparison
of measurement
|
Comparison
of measurement
|
Remarks and Recommendation
|
Monitoring
Station
|
Easting
(m)
|
Northing
(m)
|
Surface
Level
(mPD)
|
S1
|
0.004
|
0.006
|
0.083
|
Level continuously
increased
|
S2
|
0.010
|
-0.012
|
0.089
|
Level continuously increased
|
S3
|
-0.023
|
0.016
|
0.099
|
Level continuously
increased
|
S4
|
0.033
|
0.122
|
0.163
|
Level continuously
increased
|
6.1.6
This measurement result was generally and relatively higher than the baseline
measurement at S1, S2, S3 and S4. The mudflat level is continuously increased.
6.2.1
The mudflat monitoring covered water quality
monitoring data. Reference was made
to the water quality monitoring data of the representative water quality
monitoring station (i.e. SR3) as in the EM&A Manual. The water quality monitoring location
(SR3) is shown in Figure 2.1.
6.2.2
Impact water quality monitoring in San Tau (monitoring
station SR3) was conducted in June 2015.
The monitoring parameters included dissolved oxygen (DO), turbidity and
suspended solids (SS).
6.2.3
The Impact monitoring results for SR3 were extracted
and summarised below:
Table 6.4 Impact
Water Quality Monitoring Results (Depth Average)
Date
|
Mid Ebb Tide
|
Mid Flood Tide
|
DO (mg/L)
|
Turbidity (NTU)
|
SS (mg/L)
|
DO (mg/L)
|
Turbidity (NTU)
|
SS (mg/L)
|
1-Jun-15
|
6.65
|
8.70
|
7.50
|
6.55
|
8.50
|
6.05
|
3-Jun-15
|
6.31
|
13.10
|
17.00
|
6.33
|
5.00
|
4.75
|
5-Jun-15
|
5.86
|
9.55
|
10.65
|
6.74
|
6.20
|
5.20
|
8-Jun-15
|
6.98
|
5.40
|
8.05
|
7.07
|
3.15
|
7.15
|
10-Jun-15
|
7.07
|
4.55
|
4.75
|
8.10
|
3.90
|
5.05
|
12-Jun-15
|
7.53
|
5.55
|
9.35
|
9.96
|
2.75
|
7.40
|
15-Jun-15
|
6.56
|
7.80
|
3.30
|
8.98
|
6.05
|
9.10
|
17-Jun-15
|
7.29
|
6.15
|
4.25
|
7.38
|
4.95
|
4.30
|
19-Jun-15
|
6.75
|
6.60
|
6.40
|
6.79
|
7.15
|
4.45
|
22-Jun-15
|
6.76
|
6.45
|
8.45
|
7.06
|
3.85
|
5.25
|
24-Jun-15
|
6.48
|
7.30
|
5.15
|
6.33
|
4.80
|
3.95
|
26-Jun-15
|
5.88
|
5.15
|
3.20
|
6.68
|
3.90
|
3.10
|
29-Jun-15
|
8.20
|
6.65
|
3.65
|
10.29
|
7.30
|
3.90
|
Average
|
6.79
|
7.15
|
7.05
|
7.56
|
5.19
|
5.36
|
Sampling Zone
6.3.1
In order to collect baseline
information of mudflats in the study site, the study site was divided into three sampling zones
(labeled as TC1, TC2, TC3) in Tung Chung Bay
and one zone in San Tau (labeled as ST) (Figure 2.1 of Appendix I). The
horizontal length of sampling zones TC1, TC2, TC3 and ST
were about 250 m, 300 m, 300 m and 250 m, respectively. Survey of horseshoe
crabs, seagrass beds and intertidal communities were
conducted in every sampling zone. The present survey
was conducted in June 2015
(totally 6 sampling days between 6th and 20th June 2015).
Horseshoe Crabs
6.3.2
Active search method was conducted for horseshoe crab monitoring by two experienced surveyors at every sampling zone. During the search period, any accessible and potential area would
be investigated for any horseshoe crab individuals within 2-3 hours in low tide period (tidal level
below 1.2 m above Chart Datum (C.D.)). Once a horseshoe crab individual was found, the species was identified
referencing to Li (2008). The prosomal width, inhabiting substratum and respective GPS coordinate were recorded. A photographic
record was taken for future investigation. Any
grouping behavior of individuals, if found, was recorded. The horseshoe crab surveys were
conducted on 16th (for TC3 and ST) and 17th (for TC1 and
TC2) June 2015. The weather was hot and sunny on both survey days.
Seagrass Beds
6.3.3
Active search method was conducted for seagrass bed monitoring
by two experienced surveyors at every sampling zone. During the search period, any accessible and potential area would
be investigated for any seagrass beds within 2-3
hours in low tide period. Once seagrass bed was found, the species, estimated area, estimated coverage percentage and respective GPS coordinate were recorded. A photographic
record was taken for future investigation. The seagrass
beds surveys were conducted on 16th (for TC3 and ST) and 17th
(for TC1 and TC2) June 2015. The weather was hot and sunny on both survey days.
Intertidal Soft Shore Communities
6.3.4
The intertidal soft shore community surveys were conducted in low tide
period on 6th (for ST), 14th (for TC2), 15st (for
TC3) and 20thJune 2015 (for TC1). At each sampling zone, three 100 m horizontal transects were laid at high tidal level (H: 2.0 m above C.D.), mid tidal level (M: 1.5 m above C.D.) and
low tidal level (L: 1.0 m above C.D.). Along every horizontal transect, ten random quadrats (0.5 m x 0.5m) were placed.
6.3.5
Inside a quadrat, any visible epifauna
were collected and were in-situ identified to the
lowest practical taxonomical resolution. Whenever possible a hand core sample (10 cm internal diameter ´ 20 cm depth) of sediments was collected
in the quadrat. The core sample was gently washed through a sieve of mesh size
2.0 mm in-situ. Any visible infauna
were collected and identified. Finally the top 5 cm surface sediments were dug for visible infauna in the quadrat regardless
of hand core sample was taken.
6.3.6
All collected fauna were
released after recording except some tiny individuals that are too small to be identified on
site. These tiny individuals were taken to laboratory for identification under dissecting microscope.
6.3.7
The taxonomic classification
was conducted in accordance to the following references: Polychaetes: Fauchald (1977),
Yang and Sun (1988); Arthropods: Dai and Yang (1991), Dong (1991); Mollusks: Chan and Caley (2003), Qi (2004).
Data Analysis
6.3.8
Data collected from direct search and core sampling
was pooled in every quadrat for data analysis.
Shannon-Weaver Diversity Index (Hˇ¦) and Pielouˇ¦s
Species Evenness (J) were calculated for every quadrat
using the formulae below,
Hˇ¦= -ŁU ( Ni / N ) ln ( Ni / N ) (Shannon and Weaver, 1963)
J = Hˇ¦ / ln S, (Pielou, 1966)
where S is the total number of species in the sample, N is
the total number of individuals, and Ni is the number of individuals of the ith species.
6.4.1
In the event of the impact monitoring results
indicating that the density or the distribution pattern of intertidal fauna and
seagrass is found to be significant different to the
baseline condition (taking into account natural fluctuation in the occurrence
and distribution pattern such as due to seasonal change), appropriate actions
should be taken and additional mitigation measures should be implemented as
necessary. Data should then be
re-assessed and the need for any further monitoring should be established. The action plan, as given in Table 6.5 should be undertaken within a
period of 1 month after a significant difference has been determined.
Table 6.5 Event
and Action Plan for Mudflat Monitoring
Event
|
ET Leader
|
IEC
|
SO
|
Contractor
|
Density or the distribution pattern of
horseshoe crab, seagrass or intertidal soft shore
communities recorded in the impact or post-construction monitoring are significantly lower than or different
from those recorded in the baseline monitoring.
|
Review historical data to ensure
differences are as a result of natural variation or previously observed
seasonal differences;
Identify source(s) of impact;
Inform the IEC, SO and Contractor;
Check monitoring data;
Discuss additional monitoring and any other
measures, with the IEC and Contractor.
|
Discuss monitoring with the ET and the
Contractor;
Review proposals for additional monitoring
and any other measures submitted by the Contractor and advise the SO
accordingly.
|
Discuss with the IEC additional monitoring
requirements and any other measures proposed by the ET;
Make agreement on the measures to be
implemented.
|
Inform the SO and in writing;
Discuss with the ET and the IEC and propose
measures to the IEC and the ER;
Implement the agreed measures.
|
Notes:
ET ˇV Environmental Team
IEC ˇV Independent Environmental Checker
SO ˇV Supervising Officer
Horseshoe Crabs
6.5.1
In general, two species of
horseshoe crab Carcinoscorpius rotundicauda
(total 66 ind.) and Tachypleus tridentatus (total 18 ind.) were recorded in the survey area. All individuals
were mainly found on fine sand or soft mud substrata. The group size varied
from 2 to 8 individuals for every sight record. Although less number of Tachypleus tridentatus
was recorded, the average body size was larger than that of Carcinoscorpius rotundicauda.
Photo records were shown in Figure 3.1
of Appendix I while the complete records of horseshoe crab survey in every sampling
zone were shown in Annex II of Appendix I.
6.5.2
Table 3.1 of Appendix I summarizes the survey
results of horseshoe crab in present survey. For Carcinoscorpius rotundicauda, it could be found in all sampling zones while more individuals were recorded
in TC1 and TC3 (TC1: 24 ind., TC2: 1 ind., TC3: 34 ind., ST: 7 ind.). The search record was 6.0 ind. hr-1 person-1, 0.3 ind. hr-1 person-1, 5.7 ind. hr-1 person-1,
1.2 ind. hr-1
person-1 in TC1, TC2, TC3 and ST respectively. Relatively TC3 was highest in
number of individuals but lots of individuals were smaller in size (mean prosomal width:
27.81 mm). Less numbers of individuals were found in TC1 and ST but most of them
were larger in size (TC1: 40.01 mm, ST: 48.96 mm). The largest individual reached
92.05 mm in TC1.
6.5.3
For Tachypleus tridentatus, it could be found in TC3 and ST only. There were 9 individuals found in
both sampling zones while search record was 1.5 ind. hr-1
person-1. The mean prosomal widths
were similar between two
sampling zones (TC3: 50.31 mm, ST: 63.67 mm). The largest individual
reached 118.34 mm in ST (Figure 3.1 of Appendix I).
6.5.4
In the previous survey of Mar. 2015, there was one important finding
that a mating pair of Carcinoscorpius rotundicauda was found in ST (prosomal width: male 155.1
mm, female 138.2 mm) (Figure 3.2 of Appendix I). It indicated the importance of ST as a breeding ground of horseshoe
crab. Moreover, two moults of Carcinoscorpius rotundicauda were found in TC1 with similar prosomal width
130-140 mm (Figure 3.2 of Appendix I). It reflected that a certain numbers of moderately sized individuals
inhabited the sub-tidal habitat of Tung Chung Wan after its nursery period on
soft shore. These individuals might move onto soft shore during high tide for
feeding, moulting and breeding. Then it would return
to sub-tidal habitat during low tide. Because the mating pair should be inhabiting sub-tidal habitat in most of the time. The record
was excluded from the data analysis to avoid mixing up with juvenile population
living on soft shore.
6.5.5
No marked individual of horseshoe crab was recorded in present survey.
Some marked individuals were found in previous surveys conducted in September
2013, March 2014 and September 2014. All of them were released through a conservation
programme conducted by Prof. Paul Shin (Department of
Biology and Chemistry, The City University of Hong Kong (CityU)).
It was a re-introduction trial of artificial bred horseshoe crab juvenile at
selected sites. So that the horseshoe crabs population might be restored in the
natural habitat. Through a personal conversation with Prof. Shin, about 100
individuals were released in the sampling zone ST on 20 June 2013. All of them
were marked with color tape and internal chip detected by specific chip sensor.
There should be second round of release between June and September 2014 since
new marked individuals were found in the survey of September 2014.
6.5.6
The artificial bred individuals, if found,
would be excluded from the results of present monitoring programme
in order to reflect the changes of natural population. However, the mark on
their prosoma might have been detached during moulting after a certain period of release. The
artificially released individuals were no longer distinguishable from the
natural population without the specific chip sensor. The survey data collected
would possibly cover both natural population and artificially bred individuals.
Population difference among
the sampling zones
6.5.7
Figures 3.3 and 3.4 of Appendix I show the changes of number of individuals, mean prosomal width
and search record of horseshoe crabs Carcinoscorpius rotundicauda
and Tachypleus tridentatus respectively in every sampling
zone along the sampling months. In general, higher search records (i.e. number of individuals)
of both species were always found in ST followed by TC3 from September 2012 to
September 2014. Then the search record in TC3 was even higher than that in ST
from March 2015 to June 2015. For TC1, the search record was at low to medium
level and fluctuated slightly along the sampling months. In contrast,
much lower search record was found in TC2 (2 ind. in
Sep. 2013, 1 ind. in Mar., Jun., Sep. 2014, Mar. and
Jun 2015). Although there was no obvious spatial difference of horseshoe crab
size (prosomal width) among the sampling zones,
larger individuals (prosomal width > 80 mm) were
usually found in TC1 and ST.
6.5.8
Throughout the monitoring period conducted, it was obvious that TC3 and ST (western
shore of Tung Chung Wan) was an important nursery ground for horseshoe crab
especially newly hatched individuals due to larger area of suitable substratum
(fine sand or soft mud) and less human disturbance (far from urban district).
Relatively, other sampling zones were not a suitable nursery ground especially
TC2. Possible factors were less area of suitable substratum (especially TC1)
and higher human disturbance (TC1 and TC2: close to urban district and easily
accessible). In TC2, large daily salinity fluctuation was a possible factor
either since it was flushed by two rivers under tidal inundation. The
individuals found in TC1 and TC2 were believed migrating from TC3 and ST during
high tide while it might leave over a certain period of time. It accounted for
the variable search records in the sampling zones along the sampling months.
For example, few individuals of Tachypleus tridentatus were found in TC1 only between
September 2012 and September 2013. However it no longer appeared while few
individuals of Carcinoscorpius rotundicauda were found after March 2014..
Seasonal
variation of horseshoe crab population
6.5.9
Throughout the monitoring period conducted, the search record of
horseshoe crab declined obviously during dry season especially December (Figures 3.3 and 3.4 of Appendix I). No individual of horseshoe crabwas found in the survey of December 2013. Next year, 2 individuals of Carcinoscorpius rotundicauda and 8 individuals of Tachypleus tridentatus were found only in December
2014. As mentioned, the horseshoe
crabs were inactive and burrowed in the sediments during cold weather (<15 ºC). Similar results of low search record in dry season were reported in a
previous territory-wide survey of horseshoe crab. For example, the search
records in Tung Chung Wan were 0.17 ind. hr-1 person-1and 0 ind. hr-1 person-1in wet season and dry season respectively (details see Li, 2008). After
the dry season, the search record increased with the warmer climate.
6.5.10
Between the sampling months September 2012 and December 2013, Carcinoscorpius rotundicauda was
a less common species relative to Tachypleus tridentatus. Only 4 individuals were ever
recorded in ST in December 2012. This species had ever been believed of very
low density in ST hence the encounter rate was very low. Since March 2014, it
was found in all sampling zones with higher abundance in ST. Based on its
average size (mean prosomal width 39.28-49.81 mm), it indicated that breeding and spawning of this species
had occurred 3-4 years ago along the coastline of Tung Chun Wan. However, these
individuals were still small while their walking trails were inconspicuous.
Hence there was no search record in previous sampling months. From March 2014
to June 2015, more individuals were recorded due to larger size and higher activity.
Focused on June 2015 (present survey), more small sized individuals (prosomal width 10-20 mm) were found in TC3 (specifically
soft mud area between TC3 and ST), it indicated another round of successful
breeding and spawning of Carcinoscorpius rotundicauda
along the western shore of Tung Chung Wan. It matched with the previous mating
record in March 2015.
6.5.11
For Tachypleus tridentatus, sharp increase of
number of individuals was recorded in ST with wet season (from March to
September 2013). According to a personal conversation with Prof. Shin (CityU), his monitoring team had recorded similar increase
of horseshoe crab population during wet season. It was believed that the
suitable ambient temperature increased its conspicuousness. However similar
pattern was not recorded during the wet season of 2014. The
number of individuals increased in March and June 2014 followed by a rapid
decline in September 2014. The number of individuals showed a general
decreasing trend from March 2014 to June 2015. Apart from natural mortality,
migration from nursery soft shore to subtidal habitat
was another possible cause. Since the mean prosomal
width of Tachypleus tridentatus continued to grow and reached
about 50 mm in March 2014. Then it varied slightly between 50-65 mm from
September 2014 to June 2015. Most of the individuals might have reached a
suitable size strong enough to forage in sub-tidal habitat.
6.5.12
Since TC3 and ST were regarded as important nursery ground for horseshoe
crab, box plots of prosomal width of two horseshoe
crab species were constructed to investigate the changes of population in
details.
Box plot of horseshoe
crab populations in TC3
6.5.13
Figure 3.5 of Appendix I shows the changes of prosomal width of Carcinoscorpius rotundicauda and Tachypleus tridentatus in TC3. As mentioned above, Carcinoscorpius rotundicauda was rarely found between
September 2012 and December 2013 hence the data were lacking. In March 2014,
the major size (50% of
individual records between upper and lower quartile) ranged 40-60 mm while only
few individuals were found. From June 2014 to June 2015, the size of major
population decreased and ranged 20-40 mm while more individuals were recorded.
Such decline was possibly due to variable encounter rate influenced by weather.
6.5.14
For Tachypleus tridentatus, the major size ranged
20-50 mm while the number of individuals found fluctuated from September 2012
to June 2014. Then a slight but consistent growing trend was observed. The prosomal width increased from 25-35 mm in September 2014 to
35-65 mm in June 2015. As mentioned, the large individuals might have reached a
suitable size for migrating from the nursery soft shore to subtidal
habitat. It accounted for the declined population in TC3.
Box plot of horseshoe
crab populations in ST
6.5.15
Figure 3.6 of Appendix I shows the changes of prosomal width of Carcinoscorpius rotundicauda and Tachypleus tridentatus in ST. As mentioned above, Carcinoscorpius rotundicauda was rarely found between
September 2012 and December 2013 hence the data were lacking. From March 2014
to June 2015, the size of major population (50% records between upper and lower quartile) fluctuated
between 30-40 mm and 45-60
mm. Similar to TC3, such fluctuation should be due to variable encounter
rate influenced by weather.
6.5.16
For Tachypleus tridentatus, a consistent growing
trend was observed for the major population from December 2012 to December. 2014 regardless of change of search record. The prosomal width increased from 15-30 mm to 55-70 mm. As
mentioned, the large individuals might have reached a suitable size for migrating from the
nursery soft shore to subtidal habitat. From March to
June 2015, the size of major population decreased slightly with prosomal width 40-60 mm. It further indicated some of order
individuals might have migrated to sub-tidal habitat.
Impact of the HKLR project
6.5.17
The present survey was the 11th time of the EM&A programme during the construction period. Based on the results, impact of the HKLR project could not be
detected on horseshoe crabs considering the factor of natural, seasonal
variation. In case, abnormal phenomenon (e.g. very few
numbers of horseshoe crab individuals in warm weather, large number of dead
individuals on the shore) is observed, it would be
reported as soon as possible.
Seagrass Beds
6.5.18
In general, two species of seagrass Halophila ovalis and Zostera japonica were
recorded in ST only. Both species were found on sandy substratum nearby the seaward side of
mangrove vegetation at 2.0 m above C.D. Photo records were shown in Figure 3.7 of Appendix I while the complete records of seagrass beds survey were shown in Annex III of Appendix I.
6.5.19
Table 3.2 of Appendix I summarize the results of seagrass beds survey in
ST. Two long strands (11.8-24.2 m) of Zostera japonica were found. The total seagrass bed area was about 90.0 m2 (average area 45.0 m2)
while
the estimated vegetation coverage was 50-80%. For Halophila ovalis, three small patches (1.0-3.4 m2) were found coinhabiting with the long strand of Zostera japonica. The total seagrass bed area was 6.8 m2 (average area 2.3 m2) while the estimated vegetation coverage was 50-80%.
Temporal
variation of seagrass beds
6.5.20
Figure 3.8 of Appendix I shows the changes of estimated total area of seagrass beds in ST along the sampling months. For Zostera japonica, it was not recorded in the 1st and 2nd surveys
of monitoring programme. Seasonal recruitment of few,
small patches (total seagrass area: 10 m2)
was found in March 2013 that grew within the large patch of seagrass Halophila ovalis. Then the patch size increased and merged gradually with the warmer
climate from March to June 2013 (15 m2). However the patch size
decreased sharply and remained similar from September 2013 (4 m2) to
March 2014 (3 m2). In June 2014, the patch size increased obviously
again (41 m2) with warmer climate. Similar to previous year, the
patch size decreased again and remained similar September 2014 (2 m2)
to December 2014 (5 m2). From March to June 2015, the patch size
increased sharply again (90.0 m2) and became the dominant seagrass in ST. It might be due to the disappearance of the
originally dominant seagrass Halophila ovalis resulting in less competition
for substratum and nutrients.
6.5.21 For Halophila ovalis, it was recorded as 3-4 medium
to large patches (area 18.9-251.7 m2; vegetation coverage 50-80%)
beside the mangrove vegetation at tidal level 2 m above C.D in the September
2012 (First survey). The
total seagrass bed area grew steadily from 332.3 m2
in September 2012 to 727.4 m2 in December 2013. Flowers could be
observed in the largest patch during its flowering period in December
2013. In March 2014, 31
small to medium patches were newly recorded (variable area 1-72 m2
per patch, vegetation coverage 40-80% per patch) in lower tidal zone between
1.0 and 1.5 m above C.D. The total seagrass area
increased further to 1350 m2. In June 2014, these small and medium
patches grew and extended to each others. These patches were no longer
distinguishable and were covering a significant mudflat area of ST. It was
generally grouped into 4 large areas (1116 ˇV 2443 m2) of seagrass beds characterized of patchy distribution,
variable vegetable coverage (40-80%) and smaller leaves. The total seagrass bed area increased sharply to 7629 m2.
In September 2014, the total seagrass area declined
sharply to 1111 m2. There were only 3-4 small to large patches
(6-253 m2) at high tidal level and 1 patch at low tidal level (786 m2). Typhoon or strong water current was a possible cause (Fong, 1998). In September
2014, there were two tropical cyclone records in Hong Kong (7th-8th
September: no cyclone name, maximum signal number 1; 14th-17th
September: Kalmaegi maximum signal number 8SE) before
the seagrass survey dated 21st September
2014. The strong water current caused by the cyclone, Kalmaegi
especially, might have given damage to the seagrass
beds. In addition, natural heat stress and grazing force were other possible
causes reducing seagrass beds area. Besides, Halophila ovalis could be found in other mud flat area surrounding the single patch.
But it was hardly distinguished into patches due to very low coverage (10-20%)
and small leaves.
6.5.22
In December 2014, all the seagrass
patches of Halophila ovalis disappeared in ST. Figure 3.9 of Appendix I shows the difference of the original seagrass
beds area nearby the mangrove vegetation at high tidal level between June 2014
and December 2014. Such rapid loss would not be seasonal phenomenon because the
seagrass beds at higher tidal level (2.0 m above
C.D.) were present and normal in December 2012 and 2013. According to Fong
(1998), similar incident had occurred in ST in the past. The original seagrass area had declined significantly during the
commencement of the construction and reclamation works for the international
airport at Chek Lap Kok in
1992. The seagrass almost disappeared in 1995 and
recovered gradually after the completion of reclamation works. Moreover,
incident of rapid loss of seagrass area was also
recorded in another intertidal mudflat in Lai Chi Wo
in 1998 with unknown reason. Hence Halophila ovalis was regarded as a short-lived
and r-strategy seagrass
that can colonize areas in short period but disappears quickly under unfavourable conditions (Fong, 1998).
Unfavourable
conditions to seagrass Halophila ovalis
6.5.23
Typhoon or strong water current was suggested as one unfavourable
condition to Halophila ovalis (Fong, 1998). As mentioned above, there were two tropical cyclone
records in Hong Kong in September 2014. The strong water current caused by the
cyclones might have given damage to the seagrass
beds.
6.5.24
Prolonged light deprivation due to turbid
water would be another unfavouable condition.
Previous studies reported that Halophila ovalis had little tolerance to light deprivation. During experimental darkness, seagrass biomass declined rapidly after 3-6 days and seagrass died completely after 30 days. The rapid death
might be due to shortage of available carbohydrate under limited photosynthesis
or accumulation of phytotoxic end products of
anaerobic respiration (details see Longstaff et al., 1999). Hence the seagrass bed of this species was susceptible to temporary
light deprivation events such as flooding river runoff (Longstaff and Dennison,
1999).
6.5.25
In order to investigate any deterioration of water quality (e.g. more
turbid) in ST, the water quality measurement results at two closest monitoring
stations SR3 and IS5 of the EM&A programme were
obtained from the water quality monitoring team. Based on the results from June
to December 2014, the overall water quality was in normal fluctuation except
there was one exceedance of suspended solids (SS) at
both stations in September. On 10th September, 2014, the SS
concentrations measured at mid-ebb tide at stations SR3 (27.5 mg/L) and IS5
(34.5 mg/L) exceeded the Action Level (≤23.5 mg/L and 120% of upstream control
stationˇ¦s reading) and Limit Level (≤34.4 mg/L and 130% of upstream control
stationˇ¦s reading) respectively. The turbidity readings at SR3 and IS5 reached
24.8-25.3 NTU and 22.3-22.5 NTU respectively. The temporary turbid water should
not be caused by the runoff from upstream rivers. Because there was no rain or
slight rain from 1st to 10th September 2014 (daily total
rainfall at the Hong Kong International Airport: 0-2.1 mm; extracted from the climatological data of Hong Kong Observatory). The effect
of upstream runoff on water quality should be neglectable
in that period. Moreover the exceedance of water
quality was considered unlikely to be related to the contract works of HKLR
according to the ˇĄNotifications of Environmental Quality Limits Exceedancesˇ¦ provided by the respective environmental team.
The respective construction of seawall and stone column works, which possibly
caused turbid water, were carried out within silt
curtain as recommended in the EIA report. Moreover there was no leakage of
turbid water, abnormity or malpractice recorded during water sampling. In
general, the exceedance of suspended solids
concentration was considered to be attributed to other external factors, rather
than the contract works.
6.5.26 Based on the weather condition
and water quality results in ST, the co-occurrence of cyclone hit and turbid
waters in September 2014 might have combined the adverse effects on Halophila ovalis that leaded to disappearance of this short-lived and r-strategy seagrass
species. Fortunately Halophila ovalis was a fast-growing species (Vermaat et al.,
1995). Previous studies showed that the seagrass bed
could be recovered to the original sizes in 2 months through vegetative
propagation after experimental clearance (Supanwanid,
1996). Moreover it was reported to recover rapidly in less than 20 days after
dugong herbivory (Nakaoka
and Aioi, 1999). As mentioned, the disappeared seagrass in ST in 1995 could recover gradually after the
completion of reclamation works for international airport (Fong, 1998). The seagrass beds of Halophila ovalis might recolonize the mudflat of ST through
seed reproduction as long as there was no unfavourable
condition in the coming months.
6.5.27 From March to June 2015, 2-3 small patches of Halophila ovalis were newly found coinhabiting with
another seagrass species Zostera japonica. But its total patch
area was still very low relative to the previous records. The recolonization rate was low while cold weather and
insufficient sunlight were possible factors between December 2014 and March
2015. Moreover, it would need to complete with more abundant seagrass Zostera japonica for substratum and nutrient. Since Zostera japonica had
extended and had covered the original seagrass bed of
Halophila ovalis at certain degree. Therefore it was too early to conclude if Halophila ovalis would recolonize
to its original size. Or the dominance of seagrass
bed would be replaced by Zostera japonica. Regular monitoring was necessary.
6.5.28
In previous survey of Mar. 2015, labelled
sticks were inserted in the area where used to be the seagrass
patch of highest coverage. Through informal enquiry with AFCD staffs on site,
the sticks were used to trace the recolonization
pattern of seagrass after the rapid disappearance
reported in December 2014. However, all labeled sticks were removed and were no
longer seen in present survey (June 2015)
Impact of the HKLR project
6.5.29 The present survey was the 11th
survey of the EM&A programme during the
construction period. According to the results of present survey, there was recolonization of both seagrass species Halophila ovalis and Zostera japonica in ST. The seagrass patches were predicted to increase in the coming
warm season. Hence the negative
impact of HKLR project on the seagrass was not
significant. In case, adverse phenomenon (e.g.
reduction of seagrass patch size, abnormal change of leave colour) is observed again, it would
be reported as soon as possible.
Intertidal Soft Shore Communities
6.5.30
Table 3.3 and
figure 3.10 of Appendix I show
the types of substratum along the horizontal transect at every tidal level in every sampling zone. The relative distribution of different substrata was
estimated by categorizing the substratum types (Gravels & Boulders / Sands /
Soft mud) of the ten random quadrats along the horizontal
transect. The distribution of substratum types varied
among tidal levels and sampling:
ˇP In TC1, high
percentage of ˇĄGravels and Bouldersˇ¦ was recorded (80-100%) at high and mid
tidal levels. But the substratum type was diverse relatively at low tidal level.
Higher percentage of ˇĄSandsˇ¦ (50%) was recorded followed by ˇĄGravels and
Bouldersˇ¦ (30%) and ˇĄSoft mudˇ¦ (20%).
ˇP In TC2, the substratum
distribution was similar at high and mid tidal levels. Higher percentage of
ˇĄSandsˇ¦ (60%) was recorded followed by ˇĄGravels and Bouldersˇ¦ (30%). At low
tidal level, the major substratum was ˇĄSoft mudˇ¦ (90%).
ˇP In TC3, the substratum type was
clearly different between high-mid tidal level and low tidal level. ˇĄSandsˇ¦ was the main substratum type (100%) at high and mid tidal
levels while ˇĄGravels and Bouldersˇ¦ was the main substratum type (90%) at low
tidal level.
ˇP In ST, the substratum type was
clearly different between high-mid tidal level and low tidal level. ˇĄGravels
and Bouldersˇ¦ (100%) was the main substratum at high and mid tidal levels. The
main substratum type was either ˇĄSoft mudˇ¦ (50%) and ˇĄSandsˇ¦ (40%) at low tidal
level.
6.5.31
There was neither consistent
vertical nor horizontal zonation pattern of substratum type in all sampling zones. Such heterogeneous variation should be caused by different hydrology (e.g. wave in
different direction and intensity) received by the four sampling zones.
6.5.32
Table 3.4 of Appendix I lists
the total abundance, density and number of taxon
of every phylum in this survey. A total of 13359 individuals
were recorded. Mollusca was significantly the most
abundant phylum (total individuals 12895, density 430 ind.
m-2, relative abundance 96.5%).
The second abundant phylum was Arthropoda (272 ind., 9 ind. m-2, 2.0%). The third and fourth abundant phyla were Annelida (84 ind., 3 ind. m-2, 0.6%) and Sipuncula (62 ind., 2 ind. m-2, 0.5%). Relatively other phyla were very low in abundances (density £1 ind. m-2, relative abundance £0.2%). Moreover, the most diverse phylum was Mollusca (37 taxa) followed by Arthropoda (12 taxa) and Annelida (8 taxa).
There were 1-2 taxa recorded only for other phyla. The complete list of collected specimens is shown in Annex V of Appendix I.
6.5.33
Table 3.5 of Appendix I show the number of individual, relative abundance and density of each
phylum in every sampling zone. The total abundance (3194-4481 ind.) varied among the four sampling zones while the phyla distributions were
similar. In general, Mollusca was the
most dominant phylum (no. of individuals: 3119-4357
ind.; relative abundance
96.6-97.7%; density 416-581 ind. m-2). Other phyla were significantly lower in number of individuals. Arthropoda was the second abundant phylum (23-90 ind.; 0.7-2.6%; 3-12 ind.
m-2). Annelida
was the third abundant
phylum (20-31 ind.; 0.5-0.9%; 3-4 ind.
m-2) in TC1, TC2 and TC3. Sipuncula was
the third or fourth abundant phylum (20-24 ind.;
0.6-0.7%; 3 ind. m-2) in TC3 and ST. Cnidaria (sea anemone) was the fourth abundant phylum (14 ind.; 0.4%; 2 ind.
m-2) in ST. Relatively, other phyla were low in abundance among the
four sampling zones (≤ 0.3%).
Dominant species in every sampling zone
6.5.34
Table 3.6 of Appendix I lists the abundant species (relative abundance >10%) in every sampling zone. In TC1,
gastropod Batillaria multiformis was the
most abundant clearly (698 ind. m-2,
relative abundance 82%) at high tidal level (major substratum: ˇĄGravels
and Bouldersˇ¦). It was also the most abundant species at moderate-high density (264 ind. m-2, 45%) at
mid tidal level (major substratum: ˇĄGravels and Bouldersˇ¦). Gastropod Monodonta labio (60-117 ind. m-2, 17-20%) was
the second abundant species at low to moderate density at mid and low tidal
levels. Gastropod Cerithidea djadjariensis
(80 ind. m-2,
13%) was
the third abundant species at low density at mid tidal level. At low tidal
level (major substratum: ˇĄSandsˇ¦), rock oyster Saccostrea cucullata (111 ind. m-2,
32%, attached on boulders) was the most abundant at
moderate density at low tidal level. Gastropod Batillaria zonalis (41 ind. m-2, 12%) was
the third abundant species at low density at low tidal level.
6.5.35
At TC2, gastropod Cerithidea djadjariensis (198 ind.
m-2, 45%) was the most abundant at moderate density at high tidal level (major
substratum: ˇĄSandsˇ¦). Rock oyster Saccostrea
cucullata (70 ind. m-2,
16%) and gastropod Cerithidea cingulata (58 ind. m-2,
13%) were the second and third abundant species
at low density. Relative to high tidal level, the density of every taxon was much lower and similar at mid and low tidal
levels. No dominant species was determined. At mid tidal level (major
substratum: ˇĄSandsˇ¦), rock oyster Saccostrea cucullata
(66 ind. m-2, 25%), gastropods
Cerithidea djadjariensis (57 ind. m-2,
21%) and Batillaria zonalis (35 ind. m-2, 13%) were commonly
occurring at low density. At low tidal level (major substratum: ˇĄSoft mudˇ¦), rock oyster Saccostrea
cucullata (27 ind. m-2,
21%), gastropods Cerithidea djadjariensis (30 ind. m-2,
23%), Batillaria zonalis (25 ind. m-2, 19%) and
barnacle Balanus amphitrite (13 ind. m-2, 10%,
attached on boulders) were commonly
occurring at low density.
6.5.36
At TC3, gastropod Cerithidea djadjariensis was the most abundant at moderate-high density (192-298 ind. m-2,
60-64%) at high and mid tidal levels (major
substratum: ˇĄSandsˇ¦)
followed by gastropod Cerithidea cingulata (58-116 ind. m-2,
19-24%) at
low to moderate density. Besides Batillaria multiformis (52 ind. m-2,
11%) was the third abundant species at high tidal
level at low density. At
low tidal level (major substratum: ˇĄGravels and Bouldersˇ¦), gastropod
Monodonta labio
(255 ind. m-2,
40%) and rock oyster Saccostrea
cucullata (229 ind. m-2,
36%) were both dominant and at moderate-high
density.
6.5.37
At ST,
gastropod Batillaria multiformis was most
abundant (276 ind. m-2,
42%) at high tidal level (major substratum:
ˇĄGravels and Bouldersˇ¦) followed by gastropod Monodonta labio (194 ind. m-2, 17%). Both
dominant species were at moderate-high density. At mid tidal level (major
substratum: ˇĄGravels and Bouldersˇ¦), gastropod Monodonta
labio (154 ind. m-2, 31%) was
the most abundant at moderate density. Other less abundant species were rock
oyster Saccostrea cucullata (89 ind. m-2, 18%) and gastropod Lunella coronata (56 ind. m-2,
11%) at low densities. At low tidal level (major
substrata: ˇĄSandsˇ¦ and ˇĄSoft mudˇ¦), gastropods Lunella
coronata (30 ind. m-2,
22%), Batillaria zonalis (21 ind. m-2, 15%), Cerithidea djadjariensis (16 ind. m-2,
12%), Batillaria bornii (13 ind. m-2,
10%) and rock oyster Saccostrea cucullata (20 ind. m-2,
15%) were common taxa
at low densities.
6.5.38 There was no consistent zonation pattern of species distribution observed across all sampling zones and tidal levels. The species distribution should be
affected by the type of substratum primarily. In general, gastropods Batillaria multiformis
(total number of individuals: individuals: 3454 ind.,
relative abundance 25.9%), Cerithidea djadjariensis (2395
ind., 17.9%) and Cerithidea cingulata (781 ind., 5.8%) were the most commonly occurring species on
sandy and soft mud substrata. Rock oyster Saccostrea cucullata (1923 ind., 14.4%) and gastropod Monodonta
labio (2227 ind.,
16.7%) were commonly occurring species inhabiting
gravel and boulders substratum.
Biodiversity and abundance of soft shore
communities
6.5.39
Table 3.7 of Appendix I shows the mean values of
number of species, density, biodiversity index Hˇ¦ and species evenness J of soft shore communities at every tidal level and in every sampling zone. Among the sampling zones, the
number of species (7-13 spp. 0.25 m-2) in ST was relatively higher
than other sampling zones (6-11 spp. 0.25 m-2). The mean Hˇ¦ (1.66) and J (0.74) in ST were relatively higher than that in TC1, TC2 and TC3
(Hˇ¦: 1.08-1.48; J: 0.54-0.76). The mean densities were highly variable and ranged
129-849 ind. m-2. No general difference
was observed among the sampling zones.
6.5.40 Across the tidal levels, there
was no consistent difference of the mean number of species, Hˇ¦ and J in all sampling zones. For the mean density, a general decreasing
trend was observed from high tidal level to low tidal level at TC1, TC2 and ST.
At TC3, the mean density at low tidal level was higher than that at high and
mid tidal levels. As mentioned, the variation of mean density should be
determined by the type of substratum primarily.
6.5.41
Figures 3.11 to 3.14 of Appendix I show the temporal changes of mean number of species, mean density,
Hˇ¦ and J at every tidal level and in every sampling
zone along the sampling months. No consistent temporal change of any
biological parameters was observed. All the parameters were under slight and
natural fluctuation with the seasonal variation.
Impact of the HKLR project
6.5.42
The present survey was the 11th survey of the EM&A programme during the construction period.
Based on the results, impacts
of the HKLR project were not detected on intertidal soft shore community. In
case, abnormal phenomenon (e.g. large reduction of fauna densities and species
number) is observed, it would be reported as soon as possible.
6.6.1
Chan, K.K., Caley, K.J., 2003. Sandy Shores,
Hong Kong Field Guides 4. The Department of Ecology & Biodiversity, The University of Hong Kong. pp 117.
6.6.2
Dai, A.Y., Yang, S.L., 1991. Crabs of the China Seas.
China Ocean Press. Beijing.
6.6.3
Dong, Y.M., 1991. Fauna of ZheJiang Crustacea. Zhejiang Science and Technology Publishing House. ZheJiang.
6.6.4
EPD, 1997. Technical
Memorandum on Environmental Impact Assessment Process (1st edition).
Environmental Protection Department, HKSAR Government.
6.6.5
Fauchald, K., 1977. The
polychaete worms. Definitions
and keys to the orders, families and genera. Natural
History Museum of Los Angeles County, Science Series 28. Los Angeles, U.S.A.
6.6.6
Fong, C.W., 1998. Distribution of Hong Kong seagrasses. In: Porcupine!
No. 18. The School of Biological Sciences, The
University of Hong Kong, in collaboration with Kadoorie
Farm & Botanic Garden Fauna Conservation Department, p10-12.
6.6.7
Li, H.Y., 2008. The Conservation of Horseshoe Crabs in
Hong Kong. MPhil Thesis, City University of Hong Kong, pp 277.
6.6.8
Longstaff, B.J., Dennison, W.C., 1999. Seagrass survival during pulsed turbidity events: the
effects of light deprivation on the seagrasses Halodule pinifolia and
Halophila ovalis.
Aquatic Botany 65 (1-4), 105-121.
6.6.9
Longstaff, B.J., Loneragan,
N.R., Oˇ¦Donohue, M.J., Dennison, W.C., 1999. Effects of light deprivation on the survival and recovery of the seagrass Halophila ovalis (R. Br.) Hook.
Journal of Experimental Marine Biology and Ecology 234 (1), 1-27.
6.6.10
Nakaoka, M., Aioi, K., 1999. Growth of seagrass Halophila ovalis at dugong trails compared to existing
within-patch variation in a Thailand intertidal flat. Marine Ecology
Progress Series 184, 97-103.
6.6.11
Pielou, E.C., 1966. Shannonˇ¦s formula
as a measure of species diversity: its use and misuse. American Naturalist 100,
463-465.
6.6.12
Qi, Z.Y., 2004. Seashells
of China. China Ocean Press. Beijing, China.
6.6.13
Qin, H., Chiu, H., Morton, B., 1998. Nursery beaches
for Horseshoe Crabs in Hong Kong. In: Porcupine! No. 18. The School of
Biological Sciences, The University of Hong Kong, in collaboration with Kadoorie Farm & Botanic Garden Fauna Conservation
Department, p 9-10.
6.6.14
Shannon, C.E., Weaver, W., 1963. The Mathematical Theory
of Communication. Urbana: University of Illinois
Press, USA.
6.6.15
Shin, P.K.S., Li, H.Y., Cheung, S.G., 2009. Horseshoe Crabs in Hong Kong:
Current Population Status and Human Exploitation. Biology and
Conservation of Horseshoe Crabs (part 2), 347-360.
6.6.16
Supanwanid, C., 1996. Recovery
of the seagrass Halophila ovalis after grazing by dugong.
In: Kuo, J., Philips, R.C., Walker, D.I., Kirkman, H. (eds),
Seagrass biology: Proc Int
workshop, Rottenest Island, Western Australia. Faculty of Science, The University of Western Australia, Nedlands,
315-318.
6.6.17
Vermaat, J.E., Agawin,
N.S.R., Duarte, C.M., Fortes, M.D., Marba. N., Uri,
J.S., 1995. Meadow maintenance, growth and productivity of a
mixed Philippine seagrass bed. Marine Ecology
Progress Series 124, 215-225.
6.6.18
Yang, D.J, Sun, R.P., 1988. Polychaetous annelids commonly seen
from the Chinese waters (Chinese version). China
Agriculture Press, China.
7
Environmental Site
Inspection and Audit
7.1.1
Site Inspections were carried out on a weekly basis to
monitor the implementation of proper environmental pollution control and
mitigation measures for the Project. During the reporting month, four site
inspections were carried out on 3, 10, 17 and 26 June 2015.
7.1.2
Particular observations during the site inspections and the follow up actions taken by the
Contractor are described below.
3
June 2015
(a)
A few patches
of concrete waste was observed on the ground at N20.
This observation was found on 30 April 2015. The Contractor was reminded to remove the
concrete waste at N20 as soon as possible.
(b)
The length of wheel washing bay at N20 is too short.
This observation was found on 29 May 2015. The Contractor was reminded to
modify the wheel washing bay.
(c)
Gap was found at the silt curtain. The gap was filled
with an additional silt curtain at Portion X. This observation was
found on 29 May 2015 and closed on 3 June 2015.
(d)
Chemical containers were not properly stored on Vessel
Shun Tat 82. The chemical containers were removed at Shun Tat 82. This observation was
found on 29 May 2015 and closed on 3 June 2015.
(e)
Sand bags along the water barrier at Airport Road were
insufficient. Sand bags were provided along the entire site
boundary at Airport Road to avoid water seepage at N20. This observation was
found on 29 May 2015 and closed on 3 June 2015.
(f)
Stagnant water was observed at the surface channel at
N20. The stagnant water was removed at the surface channel at N20. This observation was
found on 29 May 2015 and closed on 3 June 2015.
(g)
The gully was exposed at N20. A cover was provided for
the gully at N20 to avoid washing away of silt or other objects into the
drainage system. This observation was found on 29 May 2015 and
closed on 3 June 2015.
(h)
Muddy water was discharged
without any treatment at S7. The muddy water was cleaned at S7. This observation was
found on 3 June 2015 and closed on 10 June 2015.
(i)
Rubbish was accumulated at
S16. The rubbish was removed by a truck at S16. This observation was
found on 3 June 2015 and closed on 10 June 2015.
(j)
Construction waste near
abandoned cement mixing plant was not removed at S15. The construction waste
near abandoned cement mixing plant was removed at S15. This observation was
found on 3 June 2015 and closed on 10 June 2015.
(k)
Abandoned water barriers and rubbish were placed near
the resting station at N4. The abandoned water barriers and rubbish were
removed at N4. This observation was found on 3 June 2015 and
closed on 10 June 2015.
(l)
Silt curtains were not
maintained in accordance with the design plan at Portion X. The silt curtains
were maintained in accordance with the design plan at Portion X. This observation was
found on 3 June 2015 and closed on 10 June 2015.
(m)
A diesel container was
observed without a drip tray at N4. The diesel container was removed at N4. This observation was
found on 3 June 2015 and closed on 10 June 2015.
10 June 2015
(a)
A few patches
of concrete waste was observed on the ground at N20.
This observation was found on 30 April 2015. The Contractor was reminded to remove the
concrete waste at N20 as soon as possible.
(b)
The length of wheel washing bay at N20 is too short.
This observation was found on 29 May 2015. The Contractor was reminded to
modify the wheel washing bay.
(c)
A green screen used to
cover sand stockpile was broken at N1. A new green screen of sand stockpile was
provided at N1. This observation was found on 10 June 2015
and closed on 17 June 2015.
(d)
Unpaved road and stockpiles were observed to be dry at
S15. The unpaved road and stockpiles
were sprayed with water at S15. This observation was found on 10 June 2015
and closed on 17 June 2015.
(e)
A sand stockpile was
observed to be dry at S22. The sand stockpile was removed at S22. This observation was
found on 10 June 2015 and closed on 17 June 2015.
(f)
No water spraying was provided for the percussive
activity at S8-9. Water spraying was
provided for the percussive activity at S8-9. This observation was found on 10 June 2015
and closed on 17 June 2015.
(g)
Silt curtains were not maintained
in accordance with the design plan at Portion X. The silt curtains were
maintained in accordance with the design plan at Portion X. This observation was
found on 10 June 2015 and closed on 26 June 2015.
17 June 2015
(a)
A few patches
of concrete waste was observed on the ground at N20.
This observation was found on 30 April 2015. The Contractor was reminded to remove the
concrete waste at N20 as soon as possible.
(b)
The length of wheel washing bay at N20 is too short.
This observation was found on 29 May 2015. The Contractor was reminded to
modify the wheel washing bay.
(c)
An inadequate wheel
washing facility was provided at the entrance/exit of N1. This observation was found on 17 June 2015. The Contractor was reminded
to provide standard wheel washing facility at N1.
(d)
Concrete waste was observed on the ground at N1. This observation was found on 17 June 2015. The Contractor was reminded
to remove the concrete waste at N1.
(e)
Water spraying system did not function at S15. Water
spraying system was used at S15. This observation was
found on 17 June 2015 and closed on 26 June 2015.
(f)
Rubbish was accumulated at S16. Accumulated rubbish at
S16 was cleared. This observation was found
on 17 June 2015 and closed on 26 June 2015.
(h)
Silt curtains were not
maintained in accordance with the design plan at Portion X. The silt curtains
were maintained in accordance with the design plan at Portion X. This observation was
found on 17 June 2015 and closed on 26 June 2015.
26
June 2015
(a)
A few patches
of concrete waste was observed on the ground at N20.
This observation was found on 30 April 2015. The Contractor was reminded to remove the
concrete waste at N20 as soon as possible.
(b)
The length of wheel washing bay at N20 is too short.
This observation was found on 29 May 2015. The Contractor was reminded to
modify the wheel washing bay.
(c)
An inadequate wheel
washing facility was provided at the entrance/exit of N1. This observation was found on 17 June 2015. The Contractor was reminded
to provide standard wheel
washing facility at N1.
(d)
Concrete waste was
observed on the ground at N1. This observation was found on 17 June 2015. The Contractor was reminded
to remove the concrete waste at N1.
(e)
Construction
materials along the deck of barge was observed at Harbour Sky No. 68 at Portion X. The Contractor was
reminded to clean up the construction materials at Harbour Sky No. 68.
(f)
Stagnant water was found at
surface channel at site access of N1. The Contractor was reminded to remove
stagnant water at site access of N1.
(g)
Uneven ground was observed at
N1. The Contractor was reminded to level the ground to avoid accumulation of
water at N1.
(h)
Uneven ground was observed at
S19 site access. The Contractor was reminded to level the ground to avoid
accumulation of water at S19 site access.
The Contractor
has rectified most of the observations as
identified during environmental site inspections during the reporting month.
Follow-up actions for outstanding observations will be inspected during the
next site inspections.
7.2
Advice
on the Solid and Liquid Waste Management Status
7.2.1
The Contractor registered as a chemical waste producer
for the Project. Sufficient numbers of receptacles were available for general
refuse collection and sorting.
7.2.2
Monthly summary of waste flow table is detailed in Appendix J.
7.2.3
The Contractor was reminded that chemical waste
containers should be properly treated and stored temporarily in designated
chemical waste storage area on site in accordance with the Code of Practise on
the Packaging, Labelling and Storage of Chemical Wastes.
7.3.1
The valid environmental licenses and permits during
the reporting month are summarized in Appendix L.
7.4.1
In response to the site audit findings, the
Contractors have rectified
most of the observations as
identified during environmental site inspections during the reporting month.
Follow-up actions for outstanding observations will be inspected during the
next site inspections.
7.4.2
A summary of the Implementation Schedule of Environmental
Mitigation Measures (EMIS) is presented in Appendix M. Most of the
necessary mitigation measures were implemented properly.
7.4.3
Regular marine travel route for
marine vessels were implemented properly in accordance to the submitted plan
and relevant records were kept properly.
7.4.4
Dolphin Watching Plan was
implemented during the reporting month. No dolphins inside the silt curtain
were observed. The relevant records were kept properly.
7.5
Summary
of Exceedances of
the Environmental Quality Performance Limit
7.5.1
No Action and Limit Level exceedances of 1-hour TSP and 24-hour TSP were recorded at AMS5 and AMS6 during the reporting month.
7.5.2
For construction noise, no Action and Limit Level exceedances
were recorded at the monitoring stations during the reporting month.
7.5.3
For marine water quality
monitoring, no Action Level and Limit Level exceedances
of turbidity level, dissolved
oxygen level and suspended solid level were recorded during the reporting
month.
7.6
Summary of Complaints, Notification of Summons and Successful
Prosecution
7.6.1
There were no complaints received during the reporting month. The details of
cumulative statistics of Environmental Complaints are provided in Appendix K.
7.6.2
No notification of summons and prosecution was
received during the reporting period.
7.6.3
Statistics on notifications of summons and successful
prosecutions are summarized in Appendix N.
8.1.1
As informed by the Contractor, the major
construction activities for July 2015 are summarized in Table 8.1.
Table 8.1 Construction
Activities for July 2015
Site
Area
|
Description
of Activities
|
Portion X
|
Dismantling/Trimming of Temporary 40mm Stone
Platform for Construction of Seawall
|
Portion X
|
Filling Works behind Stone Platform
|
Portion X
|
Construction of Seawall
|
Portion X
|
Loading and Unloading of
Filling Material
|
Portion X
|
Temporary Stone Platform
Construction
|
Portion X
|
Pipe Piling
|
Portion X
|
Excavation and Lateral Support
Works at Scenic Hill Tunnel (Cut & Cover Tunnel)
|
Portion X
|
Laying blinding layer for
tunnel box structure at Scenic Hill Tunnel (Cut & Cover Tunnel)
|
Portion X
|
Construction of tunnel
box structure at Scenic Hill Tunnel (Cut & Cover Tunnel)
|
Portion X
|
Socket H-Piling work at
Scenic Hill Tunnel (Cut & Cover Tunnel
|
Portion X
|
Excavation works for
HKBCF to Airport Tunnel
|
Portion X
|
Socket H-Piling work for
HKBCF to Airport Tunnel East (Cut & Cover Tunnel)
|
Portion X
|
Pipe Piling works for
HKBCF to Airport Tunnel East (Cut &Cover Tunnel)
|
Airport Road
|
Works for Diversion of
Airport Road
|
Airport Road / Airport
Express Line/East Coast Road
|
Utilities Detection
|
Airport Road / Airport Express
Line/East Coast Road
|
Establishment of Site
Access
|
Airport Express Line
|
Canopy Pipe Drilling
underneath Airport Express Line
|
Kwo Lo Wan Road
|
Excavation and Lateral
Support Works at shaft 3 extension north shaft & south shaft
|
Airport Road
|
Excavation and Lateral
Support Works for HKBCF to Airport Tunnel West (Cut & Cover Tunnel)
|
Portion Y
|
Utility Culvert
Excavation
|
Portion Y
|
Highway Operation and
Maintenance Area Building
Foundation Works
|
West Portal
|
Excavation for Scenic
Hill Tunnel
|
West Portal
|
Ventilation Building
Foundation Works
|
8.2
Environmental Monitoring Schedule for the Coming
Month
8.2.1
The tentative schedule for environmental monitoring in July 2015 is
provided in Appendix D.
9.1.1
The construction phase and EM&A programme of the
Contract commenced on 17 October 2012.
Air Quality
9.1.2
No Action and Limit Level exceedances of 1-hour TSP and 24-hr TSP level were recorded
at AMS5 and AMS6 during the reporting month.
Noise
9.1.3
For construction noise, no Action and Limit Level exceedances were recorded at the monitoring stations during
the reporting month.
Water Quality
9.1.4
For marine water quality
monitoring, no Action Level and Limit Level exceedances
of turbidity level, dissolved
oxygen level and suspended solid level were recorded during the reporting month.
Dolphin
9.1.5
During the Juneˇ¦s surveys
of the Chinese White Dolphin, no adverse impact from the activities of this construction project on Chinese White Dolphins was
noticeable from general observations.
9.1.6
Due to monthly variation in dolphin occurrence within the study area, it
would be more appropriate to draw conclusion on whether any impacts on dolphins
have been detected related to the construction activities of this project in the
quarterly EM&A report, where comparison on distribution, group size and
encounter rates of dolphins between the quarterly impact monitoring period (June 2015 ˇV August 2015) and
baseline monitoring period (3-month period) will be made.
Mudflat
9.1.7
This measurement result was generally and relatively higher than the
baseline measurement at S1, S2, S3 and S4. The mudflat level is continuously
increased.
9.1.8
The June 2015 survey results indicate that the impacts
of the HKLR project could not be detected on horseshoe crabs and intertidal
soft shore community. Based on the results, there was recolonization
of both seagrass species Halophila ovalis and Zostera japonica in ST. The seagrass patches were predicted to increase in the coming
warm season. Hence the negative impact of HKLR project on the seagrass
was not significant.
Environmental Site
Inspection and Audit
9.1.9
Environmental site inspection
was carried out on 3, 10, 17, and 26 June 2015. Recommendations on remedial actions were
given to the Contractors for the deficiencies identified during the site
inspections.
9.1.10
There were no complaints received in relation to the environmental impact during the
reporting period.
9.1.11
No notification of summons and prosecution was received during the
reporting period.