Executive
Summary
The Hong Kong-Zhuhai-Macao
Bridge (HZMB) Hong Kong Link Road (HKLR) serves to connect the HZMB Main Bridge
at the Hong Kong Special Administrative Region (HKSAR) Boundary and the HZMB
Hong Kong Boundary Crossing Facilities (HKBCF) located at the north eastern
waters of the Hong Kong International Airport (HKIA).
The HKLR project has been
separated into two contracts. They are Contract No. HY/2011/03 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between Scenic Hill and
Hong Kong Boundary Crossing Facilities (hereafter referred to as the Contract)
and Contract No. HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link
Road-Section between HKSAR Boundary and Scenic Hill.
China State Construction
Engineering (Hong Kong) Ltd. was awarded by Highways Department as the
Contractor to undertake the construction works of Contract No. HY/2011/03. The main works of the Contract include
land tunnel at Scenic Hill, tunnel underneath Airport Road and Airport Express
Line, reclamation and tunnel to the east coast of the Airport Island, at-grade road
connecting to the HKBCF and highway works of the HKBCF within the Airport
Island and in the vicinity of the HKLR reclamation. The Contract is part of the HKLR Project
and HKBCF Project, these projects are considered to be ˇ§Designated Projectsˇ¨,
under Schedule 2 of the Environmental Impact Assessment (EIA) Ordinance (Cap
499) and Environmental Impact Assessment (EIA) Reports (Register No.
AEIAR-144/2009 and AEIAR-145/2009) were prepared for the Project. The current Environmental Permit (EP)
EP-352/2009/D for HKLR and EP-353/2009/K for HKBCF were issued on 22 December
2014 and 11 April 2016, respectively. These documents are available through the
EIA Ordinance Register. The construction phase of Contract was commenced on 17 October 2012.
BMT Asia Pacific Limited
has been appointed by the Contractor to implement the Environmental Monitoring
& Audit (EM&A) programme for the Contract in accordance with the
Updated EM&A Manual for HKLR (Version 1.0) and will be providing
environmental team services to the Contract.
This is the fifty-seventh Monthly EM&A report for the Contract which summarizes the monitoring
results and audit findings of the EM&A programme during the reporting
period from 1 to 30 June 2017.
Environmental
Monitoring and Audit Progress
The monthly EM&A
programme was undertaken in accordance with the Updated EM&A Manual for
HKLR (Version 1.0). A summary of
the monitoring activities during this reporting month is listed below:
1-hr TSP Monitoring
|
1,
7, 13, 19, 23 and 29 June 2017
|
24-hr TSP Monitoring
|
6, 12, 17, 22, 28 and 29 June 2017
|
Noise Monitoring
|
1,
7, 15, 19 and 29 June 2017
|
Mudflat Monitoring (Mudflat)
|
2,
3, 9, 10 and 11 June 2017
|
Mudflat Monitoring (Sedimentation Rate)
|
8 June 2017
|
Chinese White Dolphin
Monitoring
|
14, 15, 20 and 26 June
2017
|
Site Inspection
|
1, 7, 14, 21 and 30 June
2017
|
Due to power
supply failure, the 24-hour TSP monitoring at AMS5 was rescheduled from 28 June
2017 to 29 June 2017.
Due to weather
condition, the noise monitoring schedule was rescheduled from 13 June 2017 to
15 June 2017.
The monitoirng
schedule of water quality monitoring for all stations except station CS2 were
adopted from the published Monthly Environmental Monitoring and Audit
(EM&A) Report for June 2017 prepared for Contract No. HY/2010/02 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities ˇV Reclamation
Works. The monitoirng schedule of water quality monitoring for station CS2 was
adopted from the published Monthly EM&A Report for June 2017 prepared by Contract
No. HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ˇV Section
between HKSAR Boundary and Scenic Hill.
Due to suitable
weather and ambient temperature, the mudflat monitoring was rescheduled from 12
June 2017 to 2 and 3 June 2017.
Due to weather
condition, the dolphin monitoring schedule was rescheduled from 19 June 2017 to
20 June 2017.
Breaches of Action and Limit Levels
A summary of environmental
exceedances for this reporting month is as follows:
Environmental Monitoring
|
Parameters
|
Action Level (AL)
|
Limit Level (LL)
|
Air Quality
|
1-hr TSP
|
0
|
0
|
24-hr TSP
|
0
|
0
|
Noise
|
Leq (30 min)
|
0
|
0
|
Water Quality
|
Suspended solids level (SS)
|
0
|
0
|
Turbidity level
|
0
|
0
|
Dissolved oxygen level (DO)
|
0
|
0
|
Complaint Log
For Environmental Complaint
No. COM-2017-095(3) mentioned in previously Monthly EM&A Report for May 2017,
it was considered that the complaint was likely related to Contract No.
HY/2011/03. The Contractor has implemented the following measures to minimize
the potential noise impact:
- Additional
noise barriers have been erected in the active working area to further mitigate
the associated noise emissions as far as practicable;
- Cover the breaker tip with acoustic material;
- Noise barriers have been located as close as possible
to the noise source. Also, gaps and openings at joints in the barriers material
have been minimized;
- Speed up of construction works in order to shorten the
duration noise impact/nuisance to the surrounding;
- Minimize the quantities of noisy plant as far as
practicable; and
- Regular review of working duration and switch off all
unnecessary machinery and plant.
There was no complaint received
in relation to the environmental impacts during the reporting period.
Notifications
of Summons and Prosecutions
There were no notifications of summons or
prosecutions received during this reporting month.
Reporting
Changes
This report has been
developed in compliance with the reporting requirements for the subsequent
EM&A reports as required by the Updated EM&A Manual for HKLR (Version
1.0).
The proposal for the change
of Action Level and Limit Level for suspended solid and turbidity was approved
by EPD on 25 March 2013.
The revised Event and
Action Plan for dolphin monitoring was approved by EPD on 6 May
2013.
The original monitoring
station at IS(Mf)9 (Coordinate: 813273E, 818850N) was observed inside the
perimeter silt curtain of Contract HY/2010/02 on 1 July 2013, as such the
original impact water quality monitoring location at IS(Mf)9 was temporarily
shifted outside the silt curtain. As
advised by the Contractor of HY/2010/02 in August 2013, the perimeter silt
curtain was shifted to facilitate safe anchorage zone of construction
barges/vessels until end of 2013 subject to construction progress. Therefore, water quality monitoring
station IS(Mf)9 was shifted to 813226E and 818708N since 1 July 2013. According to the water quality
monitoring teamˇ¦s observation on 24 March 2014, the original monitoring
location of IS(Mf)9 was no longer enclosed by the perimeter silt curtain of
Contract HY/2010/02. Thus, the impact water quality monitoring works at the
original monitoring location of IS(Mf)9 has been resumed since 24 March 2014.
Transect lines 1, 2, 7, 8,
9 and 11 for dolphin monitoring have been revised due to the obstruction of the
permanent structures associated with the construction works of HKLR and the
southern viaduct of TM-CLKL, as well as provision of adequate buffer distance
from the Airport Restricted Areas.
The EPD issued a memo and confirmed that they had no objection on the
revised transect lines on 19 August 2015.
Technical issues had been observed from impact
monitoirng of the Contract and thus published information from Monthly EM&A Report for June 2017 prepared for Contract No. HY/2010/02 and Contract No.
HY/2011/09 were adopted for the Contract.
Future Key
Issues
The future key issues
include potential noise, air quality, water quality and ecological impacts and
waste management arising from the following construction activities to be
undertaken in the upcoming month:
ˇP
Stockpiling at WA7;
ˇP
Removal of toe
loading at Portion X;
- Dismantling/trimming
of Temporary 40mm Stone Platform for Construction of Seawall at Portion X;
- Construction of
Seawall at Portion X;
- Loading and Unloading
Filling Materials at Portion X;
- Backfilling at Scenic
Hill Tunnel (Cut & Cover Tunnel) at Portion X;
- Excavation for HKBCF
to Airport Tunnel & Construction of Tunnel Box Structure at Portion X;
- Excavation for
Diversion of Culvert PR14 at Portion X;
ˇP
Works for Diversion of
Airport Road;
- Utilities Detection at
Airport Road / Airport Express Line/ East Coast Road;
- Establishment of Site
Access at Airport Road / Airport Express Line/East Coast Road;
ˇP
Construction of Tunnel Box Structure at Shaft 3 Extension North
Shaft;
- Excavation and Lateral
Support Works & Construction of Tunnel Box Structure for HKBCF to
Airport Tunnel West (Cut & Cover Tunnel) at Airport Road;
- Excavation and Lateral
Support Works & Construction of Tunnel Box Structure for HKBCF to
Airport Tunnel East (Cut & Cover Tunnel) at Portion X;
- Sub-structure &
Superstructure Works for Highway Operation and Maintenance Area Building at
Portion X; and
ˇP
Superstructure Works
for Scenic Hill Tunnel West Portal Ventilation building at West Portal.
1.1.2 The HKLR project has been
separated into two contracts. They
are Contract
No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section
between Scenic Hill and Hong Kong Boundary Crossing Facilities (hereafter
referred to as the Contract) and Contract No. HY/2011/09 Hong Kong-Zhuhai-Macao
Bridge Hong Kong Link Road-Section between HKSAR Boundary and Scenic Hill.
1.1.3 China State Construction
Engineering (Hong Kong) Ltd. was awarded by Highways Department (HyD) as the Contractor to undertake
the construction works of Contract No. HY/2011/03. The Contract is part of the HKLR Project
and HKBCF Project, these projects are considered to be ˇ§Designated Projectsˇ¨,
under Schedule 2 of the Environmental Impact Assessment (EIA) Ordinance (Cap
499) and Environmental Impact Assessment (EIA) Reports (Register No.
AEIAR-144/2009 and AEIAR-145/2009) were prepared for the Project. The current Environmental Permit (EP)
EP-352/2009/D for HKLR and EP-353/2009/K for HKBCF were issued on 22 December
2014 and 11 April 2016, respectively. These documents are available through the
EIA Ordinance Register. The construction
phase of Contract was commenced on 17
October 2012. Figure 1.1 shows the project site boundary. The works areas are shown in Appendix O.
1.1.4 The Contract includes the following key aspects:
ˇP
New reclamation along
the east coast of the approximately 23 hectares.
ˇP
Tunnel of Scenic Hill
(Tunnel SHT) from Scenic Hill to the new reclamation, of approximately 1km in
length with three (3) lanes for the east bound carriageway heading to the HKBCF
and four (4) lanes for the westbound carriageway heading to the HZMB Main
Bridge.
ˇP
An abutment of the
viaduct portion of the HKLR at the west portal of Tunnel SHT and associated
road works at the west portal of Tunnel SHT.
ˇP
An at grade road on
the new reclamation along the east coast of the HKIA to connect with the HKBCF,
of approximately 1.6 km along dual 3-lane carriageway with hard shoulder for
each bound.
ˇP
Road links between
the HKBCF and the HKIA including new roads and the modification of existing
roads at the HKIA, involving viaducts, at grade roads and a Tunnel HAT.
ˇP
A highway operation
and maintenance area (HMA) located on the new reclamation, south of the
Dragonair Headquarters Building, including the construction of buildings,
connection roads and other associated facilities.
ˇP
Associated civil,
structural, building, geotechnical, marine, environmental protection,
landscaping, drainage and sewerage, tunnel and highway electrical and
mechanical works, together with the installation of street lightings, traffic
aids and sign gantries, water mains and fire hydrants, provision of facilities
for installation of traffic control and surveillance system (TCSS),
reprovisioning works of affected existing facilities, implementation of
transplanting, compensatory planting and protection of existing trees, and
implementation of an environmental monitoring and audit (EM&A) program.
1.1.6 BMT Asia Pacific Limited has been
appointed by the Contractor to implement the EM&A programme for the
Contract in accordance with the Updated EM&A Manual for HKLR (Version 1.0) for
HKLR and will be providing environmental team services to the Contract. Ramboll
Environ Hong
Kong Ltd. was employed by HyD as the Independent
Environmental Checker (IEC) and Environmental Project Office (ENPO) for the
Project. The project
organization with regard to the environmental works is as follows.
1.2.1
The project organization
structure and lines of communication with respect to the on-site environmental
management structure is shown in Appendix A. The key personnel contact names and
numbers are summarized in Table 1.1.
Table 1.1 Contact
Information of Key Personnel
Party
|
Position
|
Name
|
Telephone
|
Fax
|
Supervising Officerˇ¦s Representative
(Ove Arup & Partners Hong Kong
Limited)
|
(Chief Resident Engineer,
CRE)
|
Robert Antony Evans
|
3968 0801
|
2109 1882
|
Environmental Project Office / Independent
Environmental Checker
(Ramboll Environ Hong Kong Limited)
|
Environmental Project Office Leader
|
Y. H. Hui
|
3465 2888
|
3465 2899
|
Independent Environmental Checker
|
Antony Wong
|
3465 2888
|
3465 2899
|
Contractor
(China State Construction Engineering (Hong Kong) Ltd)
|
Project Manager
|
S. Y. Tse
|
3968 7002
|
2109 2588
|
Environmental Officer
|
Federick Wong
|
3968 7117
|
2109 2588
|
Environmental Team
(BMT Asia Pacific)
|
Environmental Team Leader
|
Claudine Lee
|
2241 9847
|
2815 3377
|
24 hours
complaint hotline
|
---
|
---
|
5699 5730
|
---
|
1.3
Construction
Programme
1.3.1
A copy of the
Contractorˇ¦s construction programme is provided in Appendix B.
1.4
Construction
Works Undertaken During the Reporting Month
1.4.1 A summary of the construction activities undertaken
during this reporting month is shown in Table 1.2.
Table 1.2 Construction
Activities During Reporting Month
Description of Activities
|
Site Area
|
Stockpiling
|
WA7
|
Dismantling/trimming
of temporary 40mm stone platform for construction of seawall
|
Portion X
|
Construction
of seawall
|
Portion X
|
Loading
and unloading of filling materials
|
Portion X
|
Backfilling
at Scenic Hill Tunnel (Cut & Cover Tunnel)
|
Portion X
|
Excavation for HKBCF to Airport Tunnel &
construction of tunnel box structure
|
Portion X
|
Excavation
for diversion of culvert PR14
|
Portion X
|
Works for diversion
|
Airport Road
|
Utilities detection
|
Airport Road/ Airport
Express Line/ East Coast Road
|
Establishment of site access
|
Airport Road/ Airport
Express Line/ East Coast Road
|
Mined tunnel excavation/ box jacking
underneath Airport Road and Airport Express Line
|
Airport Road and Airport Express Line
|
Construction
of Tunnel box structure at Package T1.12.1
|
Near Kwo Lo Wan Road
|
Construction
of Tunnel box structure
|
Shaft 3 Extension South &
North Shaft
|
Excavation
and lateral support works & Construction of Tunnel Box Structure for
HKBCF to Airport Tunnel West (Cut & Cover Tunnel)
|
Airport Road
|
Excavation
and lateral support works & construction of tunnel box structure for
HKBCF to Airport Tunnel East (Cut & Cover Tunnel)
|
Portion X
|
Sub-structure
& superstructure works for Highway Operation and Maintenance Area
Building
|
Portion X
|
Superstructure
works for Scenic Hill Tunnel West Portal Ventilation building
|
West Portal
|
2.1
Monitoring Requirements
2.1.1 In accordance with
the Contract Specific EM&A Manual, baseline 1-hour and 24-hour TSP levels
at two air quality monitoring stations were established. Impact 1-hour TSP monitoring was
conducted for at least three times every 6 days, while impact 24-hour TSP
monitoring was carried out for at least once every 6 days. The Action and Limit Level for 1-hr TSP
and 24-hr TSP are provided in Table 2.1 and
Table 2.2, respectively.
Table 2.1 Action
and Limit Levels for 1-hour TSP
Monitoring Station
|
Action Level, µg/m3
|
Limit Level, µg/m3
|
AMS 5 ˇV Ma Wan Chung Village (Tung Chung)
|
352
|
500
|
AMS 6 ˇV Dragonair / CNAC (Group) Building (HKIA)
|
360
|
Table 2.2 Action and
Limit Levels for 24-hour TSP
Monitoring Station
|
Action Level, µg/m3
|
Limit Level, µg/m3
|
AMS 5 ˇV Ma Wan Chung Village (Tung Chung)
|
164
|
260
|
AMS 6 ˇV Dragonair / CNAC (Group) Building (HKIA)
|
173
|
260
|
2.2.1 24-hour TSP air quality
monitoring was performed using High Volume Sampler (HVS) located at each
designated monitoring station. The HVS meets all the requirements of the Contract
Specific EM&A Manual. Portable
direct reading dust meters were used to carry out the 1-hour TSP
monitoring. Brand and model of the
equipment is given in Table 2.3.
Table 2.3 Air
Quality Monitoring Equipment
Equipment
|
Brand and Model
|
Portable direct reading dust meter (1-hour
TSP)
|
Sibata Digital Dust Monitor (Model No.
LD-3B)
|
High Volume Sampler
(24-hour TSP)
|
Tisch Environmental Mass Flow Controlled
Total Suspended Particulate (TSP) High Volume Air Sampler (Model No. TE-5170)
|
2.3.1 Monitoring locations
AMS5 and AMS6 were set up at the proposed locations in accordance
with Contract Specific EM&A Manual.
2.3.2
Figure 2.1 shows the locations
of monitoring stations. Table 2.4
describes the details of the monitoring stations.
Table 2.4 Locations
of Impact Air Quality Monitoring Stations
Monitoring
Station
|
Location
|
AMS5
|
Ma Wan Chung Village (Tung Chung)
|
AMS6
|
Dragonair / CNAC (Group) Building (HKIA)
|
2.4.1 Table 2.5
summarizes the monitoring parameters, frequency and duration of impact TSP
monitoring.
Table 2.5 Air
Quality Monitoring Parameters, Frequency and Duration
Parameter
|
Frequency
and Duration
|
1-hour TSP
|
Three times every 6 days while the highest dust impact was expected
|
24-hour TSP
|
Once every 6 days
|
2.5.1
24-hour TSP Monitoring.
(a) The HVS was installed in the vicinity of the air sensitive receivers.
The following criteria were considered in the installation of the HVS.
(i) A horizontal platform with appropriate support to secure the sampler
against gusty wind was provided.
(ii) The distance between the HVS and any obstacles, such as buildings, was
at least twice the height that the obstacle protrudes above the HVS.
(iii) A minimum of 2 meters separation from walls, parapets and penthouse for
rooftop sampler was provided.
(iv) No furnace or incinerator flues are nearby.
(v) Airflow around the sampler was unrestricted.
(vi) Permission was obtained to set up the samplers and access to the
monitoring stations.
(vii) A secured supply of electricity was obtained to operate the samplers.
(viii) The sampler was located more than 20 meters from any dripline.
(ix) Any wire fence and gate, required to protect the sampler, did not
obstruct the monitoring process.
(x) Flow control accuracy was kept within ˇÓ2.5% deviation over 24-hour
sampling period.
(b)
Preparation of Filter Papers
(i)
Glass fibre filters, G810 were labelled and sufficient filters that were
clean and without pinholes were selected.
(ii)
All filters were equilibrated in the conditioning environment for 24
hours before weighing. The conditioning environment temperature was around 25 ˘XC and not variable by more than ˇÓ3 ˘XC; the relative humidity (RH) was
< 50% and not variable by more than ˇÓ5%. A convenient working RH was 40%.
(iii)
All filter papers were prepared and analysed by ALS Technichem (HK) Pty
Ltd., which is a HOKLAS accredited laboratory and has comprehensive quality
assurance and quality control programmes.
(c)
Field Monitoring
(i) The power supply was checked to ensure the HVS works properly.
(ii) The filter holder and the area surrounding the filter were cleaned.
(iii) The filter holder was removed by loosening the four bolts and a new
filter, with stamped number upward, on a supporting screen was aligned
carefully.
(iv) The filter was properly aligned on the screen so that the gasket formed
an airtight seal on the outer edges of the filter.
(v)
The swing bolts were fastened to hold the filter holder down to the
frame. The pressure applied was
sufficient to avoid air leakage at the edges.
(vi) Then the shelter lid was closed and was secured with the aluminium
strip.
(vii) The HVS was warmed-up for about 5 minutes to establish run-temperature
conditions.
(viii) A new flow rate record sheet was set into the flow recorder.
(ix)
On site temperature and atmospheric pressure readings were taken and the
flow rate of the HVS was checked and adjusted at around 1.1 m3/min,
and complied with the range specified in the Updated EM&A Manual for HKLR
(Version 1.0) (i.e. 0.6-1.7 m3/min).
(x) The programmable digital timer was set for a sampling period of 24 hours,
and the starting time, weather condition and the filter number were recorded.
(xi) The initial elapsed time was recorded.
(xii) At the end of sampling, on site temperature and atmospheric pressure
readings were taken and the final flow rate of the HVS was checked and
recorded.
(xiii)
The final elapsed time was recorded.
(xiv)
The sampled filter was removed carefully and folded in half length so
that only surfaces with collected particulate matter were in contact.
(xv)
It was then placed in a clean plastic envelope and sealed.
(xvi) All monitoring information was recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.
(d)
Maintenance and Calibration
(i) The HVS and its accessories were maintained in good working condition,
such as replacing motor brushes routinely and checking electrical wiring to
ensure a continuous power supply.
(ii) 5-point calibration of the HVS was conducted using TE-5025A Calibration Kit prior to the
commencement of baseline monitoring. Bi-monthly 5-point calibration of the HVS
will be carried out during impact monitoring.
(iii) Calibration certificate of the HVSs are provided in Appendix C.
2.5.2 1-hour TSP
Monitoring
(a) Measuring Procedures
The measuring procedures of
the 1-hour dust meter were in accordance with the Manufacturerˇ¦s Instruction
Manual as follows:-
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the ˇ§TIME SETTINGˇ¨ switch to [BG].
(iv)
Push ˇ§START/STOPˇ¨ switch to perform background measurement for 6
seconds.
(v)
Turn the knob at SENSI ADJ position to insert the light scattering
plate.
(vi)
Leave the equipment for 1 minute upon ˇ§SPAN CHECKˇ¨ is indicated in the
display.
(vii)
Push ˇ§START/STOPˇ¨ switch to perform automatic sensitivity adjustment.
This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE position.
(ix)
Push the ˇ§TIME SETTINGˇ¨ switch the time set in the display to 3 hours.
(x)
Lower down the air collection opening cover.
(xi)
Push ˇ§START/STOPˇ¨ switch to start measurement.
(b) Maintenance
and Calibration
(i) The 1-hour TSP meter
was calibrated at 1-year intervals against a Tisch Environmental Mass Flow
Controlled Total Suspended Particulate (TSP) High Volume Air Sampler.
Calibration certificates of the Laser Dust Monitors are provided in Appendix C.
2.6.1
The schedule for air quality monitoring in June 2017
is provided in Appendix D.
2.7.1
The monitoring results for 1-hour TSP and 24-hour TSP
are summarized in Tables 2.6 and 2.7 respectively. Detailed impact air
quality monitoring results and relevant graphical plots are presented in Appendix E.
Table 2.6 Summary
of 1-hour TSP Monitoring Results During the Reporting Month
Monitoring Station
|
Average (mg/m3)
|
Range (mg/m3)
|
Action Level (mg/m3)
|
Limit Level (mg/m3)
|
AMS5
|
16
|
8 ˇV 36
|
352
|
500
|
AMS6
|
13
|
4 ˇV 28
|
360
|
500
|
Table 2.7 Summary of 24-hour TSP Monitoring Results During the
Reporting Month
Monitoring Station
|
Average (mg/m3)
|
Range (mg/m3)
|
Action Level (mg/m3)
|
Limit Level (mg/m3)
|
AMS5
|
34
|
30 ˇV 39
|
164
|
260
|
AMS6
|
48
|
23 ˇV 95
|
173
|
260
|
2.7.2 No Action and Limit Level exceedances of 1-hr TSP
and 24-hr TSP were recorded at AMS5 and AMS6 during the reporting month.
2.7.3 The event action plan
is annexed in Appendix F.
2.7.4
The
wind data obtained from the on-site weather station
during the reporting month is
shown in Appendix G.
3.1.1 In accordance with
the Contract Specific EM&A Manual, impact noise monitoring was conducted
for at least once per week during the construction phase of the Project. The
Action and Limit level of the noise monitoring is provided in Table 3.1.
Table 3.1 Action
and Limit Levels for Noise during Construction Period
Monitoring Station
|
Time Period
|
Action Level
|
Limit Level
|
NMS5 ˇV Ma Wan Chung
Village (Ma Wan Chung Resident Association) (Tung Chung)
|
0700-1900 hours on normal
weekdays
|
When one documented
complaint is received
|
75 dB(A)
|
3.2.1 Noise monitoring was
performed using sound level meters at each designated monitoring station. The sound level meters deployed comply
with the International Electrotechnical Commission Publications (IEC) 651:1979
(Type 1) and 804:1985 (Type 1) specifications. Acoustic calibrator was deployed to
check the sound level meters at a known sound pressure level. Brand and model of the equipment are
given in Table 3.2.
Table 3.2 Noise
Monitoring Equipment
Equipment
|
Brand and Model
|
Integrated Sound Level
Meter
|
B&K 2238
|
Acoustic Calibrator
|
B&K 4231
|
3.3.1
Monitoring location NMS5 was set up at the
proposed locations in accordance with Contract Specific EM&A Manual.
3.3.2
Figure 2.1 shows the locations
of monitoring stations. Table 3.3 describes the details of the monitoring
stations.
Table 3.3 Locations
of Impact Noise Monitoring Stations
Monitoring Station
|
Location
|
NMS5
|
Ma Wan Chung Village (Ma
Wan Chung Resident Association) (Tung Chung)
|
3.4.1
Table 3.4 summarizes the
monitoring parameters, frequency and duration of impact noise monitoring.
Table 3.4 Noise
Monitoring Parameters, Frequency and Duration
Parameter
|
Frequency and Duration
|
30-mins measurement at
each monitoring station between 0700 and 1900 on normal weekdays (Monday to
Saturday). Leq, L10 and L90 would be recorded.
|
At least once per week
|
3.5.1
Monitoring Procedure
(a) The sound level meter was
set on a tripod at a height of 1.2 m
above the podium for free-field
measurements at NMS5. A correction of +3 dB(A) shall be made to
the free field measurements.
(b)
The battery condition was
checked to ensure the correct functioning of the meter.
(c)
Parameters such as
frequency weighting, the time weighting and the measurement time were set as
follows:-
(i) frequency weighting:
A
(ii) time weighting: Fast
(iii) time
measurement: Leq(30-minutes) during non-restricted hours i.e. 07:00
ˇV 1900 on normal weekdays
(d)
Prior to and after each
noise measurement, the meter was calibrated using the acoustic calibrator for
94.0 dB(A) at 1000 Hz. If the difference
in the calibration level before and after measurement was more than 1.0 dB(A),
the measurement would be considered invalid and repeat of noise measurement
would be required after re-calibration or repair of the equipment.
(e)
During the monitoring period,
the Leq, L10 and L90 were recorded. In addition, site conditions and noise
sources were recorded on a standard record sheet.
(f)
Noise measurement was
paused during periods of high intrusive noise (e.g. dog barking, helicopter
noise) if possible. Observations were recorded when intrusive noise was
unavoidable.
(g)
Noise monitoring was
cancelled in the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind with gusts exceeding 10m/s. The wind speed shall be checked
with a portable wind speed meter capable of measuring the wind speed in m/s.
3.5.2
Maintenance and Calibration
(a) The microphone head of the sound level
meter was cleaned with soft cloth at regular intervals.
(b) The meter and calibrator
were sent to the supplier or HOKLAS laboratory to check and calibrate at yearly
intervals.
(c) Calibration certificates
of the sound level meters and acoustic calibrators are provided in Appendix C.
3.6.1
The schedule for construction noise monitoring in June
2017 is provided in Appendix D.
3.7.1 The monitoring
results for construction noise are summarized in Table 3.5 and the monitoring results and relevant graphical plots
are provided in Appendix E.
Table 3.5 Summary
of Construction Noise Monitoring Results During the Reporting Month
Monitoring Station
|
Average Leq (30 mins), dB(A)
|
Range of Leq (30 mins), dB(A)
|
Limit Level Leq (30 mins), dB(A)
|
NMS5
|
66
|
60 ˇV 70
|
75
|
3.7.2 There were no Action and Limit
Level exceedances for noise during daytime on normal weekdays of the reporting month.
3.7.3 Major noise sources
during the noise monitoring included construction activities of the Contract and nearby traffic.
3.7.4
The event action plan is annexed in Appendix F.
4
Water Quality Monitoring
4.1.1
Impact water quality monitoring was carried out to
ensure that any deterioration of water quality is detected, and that timely
action is taken to rectify the situation.
For impact water quality monitoring, measurements were taken in
accordance with the Contract Specific EM&A Manual. Table 4.1 shows the established Action/Limit Levels for the
environmental monitoring works. The ET proposed to amend the Acton Level
and Limit Level for turbidity and suspended solid and EPD approved ETˇ¦s
proposal on 25 March 2013. Therefore,
Action Level and Limit Level for the Contract have been changed since 25 March
2013.
4.1.2
The original and revised Action Level and
Limit Level for turbidity and suspended solid are shown in Table 4.1.
Table 4.1 Action
and Limit Levels for Water Quality
Parameter (unit)
|
Water Depth
|
Action Level
|
Limit Level
|
Dissolved Oxygen (mg/L)
(surface, middle and bottom)
|
Surface and Middle
|
5.0
|
4.2 except 5 for Fish Culture
Zone
|
Bottom
|
4.7
|
3.6
|
Turbidity (NTU)
|
Depth average
|
27.5 or 120% of upstream
control stationˇ¦s turbidity at the same tide of the same day;
The action level has been
amended to ˇ§27.5 and 120% of upstream control stationˇ¦s turbidity at the same
tide of the same dayˇ¨ since 25 March 2013.
|
47.0 or 130% of turbidity
at the upstream control station at the same tide of same day;
The limit level has been amended
to ˇ§47.0 and 130% of turbidity at the upstream control station at the
same tide of same dayˇ¨ since 25 March 2013.
|
Suspended Solid (SS)
(mg/L)
|
Depth average
|
23.5 or 120% of upstream
control stationˇ¦s SS at the same tide of the same day;
The action level has been
amended to ˇ§23.5 and 120% of upstream control stationˇ¦s SS at the same tide of
the same dayˇ¨ since 25 March 2013.
|
34.4 or 130% of SS at the
upstream control station at the same tide of same day and 10mg/L for Water
Services Department Seawater Intakes;
The limit level has been
amended to ˇ§34.4 and 130% of SS at the upstream control station at the same
tide of same day and 10mg/L for Water Services Department Seawater Intakesˇ¨
since 25 March 2013
|
Notes:
(1)
Depth-averaged
is calculated by taking the arithmetic means of reading of all three depths.
(2)
For DO,
non-compliance of the water quality limit occurs when monitoring result is
lower that the limit.
(3)
For SS &
turbidity non-compliance of the water quality limits occur when monitoring
result is higher than the limits.
(4)
The change to
the Action and limit Levels for Water Quality Monitoring for the EM&A works
was approved by EPD on 25 March 2013.
4.2.1 The monitoring
equipment used in the impact water quality monitoring programme are detailed in
the Monthly EM&A Report for June 2017 prepared for Contract No. HY/2010/02
and Contract No. HY/2011/09.
4.3.1 Table 4.3 summarizes the monitoring parameters, frequency and
monitoring depths of impact water quality monitoring as required in the Contract
Specific EM&A Manual.
Table 4.3 Impact
Water Quality Monitoring Parameters and Frequency
Monitoring Stations
|
Parameter, unit
|
Frequency
|
No. of depth
|
Impact Stations:
IS5, IS(Mf)6, IS7, IS8, IS(Mf)9 & IS10,
Control/Far Field
Stations:
CS2 & CS(Mf)5,
Sensitive Receiver
Stations:
SR3, SR4, SR5, SR10A & SR10B
|
ˇP
Depth, m
ˇP
Temperature, oC
ˇP
Salinity, ppt
ˇP
Dissolved Oxygen
(DO), mg/L
ˇP
DO Saturation, %
ˇP
Turbidity, NTU
ˇP
pH
ˇP Suspended Solids (SS), mg/L
|
Three times per week
during mid-ebb and mid-flood tides (within ˇÓ 1.75 hour of the predicted time)
|
3
(1 m below water surface,
mid-depth and 1 m above sea bed, except where the water depth is less than 6
m, in which case the mid-depth station may be omitted. Should the water depth
be less than 3 m, only the mid-depth station will be monitored).
|
4.4.1 In accordance with
the Contract Specific EM&A Manual, thirteen stations (6 Impact Stations, 5 Sensitive Receiver
Stations and 2 Control Stations) were designated for impact
water quality monitoring. The six Impact Stations
(IS) were chosen on the basis of their proximity to the reclamation and thus
the greatest potential for water quality impacts, the five Sensitive Receiver
Stations (SR) were chosen as they are close to the key sensitive receives and
the two Control Stations (CS) were chosen to facilitate comparison of the water
quality of the IS stations with less influence by the Project/ ambient water
quality conditions.
4.4.2
Technical issues have been observed from impact
monitoirng of the Contract and thus published information from Monthly EM&A
Report for June 2017 prepared for Contract No. HY/2010/02 and Contract No.
HY/2011/09 were adopted for the Contract.
4.4.3
Due to safety concern and topographical condition of the original
locations of SR4 and SR10B, alternative impact water quality monitoring
stations, naming as SR4(N) and SR10B(N), were adopted, which are situated in
vicinity of the original impact water quality monitoring stations (SR4 and
SR10B) and could be reachable.
4.4.4
Due to marine work of the Expansion of Hong Kong International Airport
into a Three-Runway System (3RS Project), original locations of water quality
monitoring stations SR5 and IS10 are enclosed by works boundary of 3RS Project.
Alternative impact water quality monitoring stations, naming as SR5(N) and
IS10(N) was approved in 12 May 2017 and were adopted starting from 15 May 2017
to replace the original locations of water quality monitoring for Contract No.
HY/2010/02.
4.4.5
The locations of these monitoring stations are
summarized in Table 4.4 and shown in
Figure 2.1.
Table 4.4 Impact
Water Quality Monitoring Stations
Monitoring Stations
|
Description
|
Coordinates
|
Easting
|
Northing
|
IS5
|
Impact Station (Close to
HKLR construction site)
|
811579
|
817106
|
IS(Mf)6
|
Impact Station (Close to
HKLR construction site)
|
812101
|
817873
|
IS7
|
Impact Station (Close to HKBCF
construction site)
|
812244
|
818777
|
IS8
|
Impact Station (Close to
HKBCF construction site)
|
814251
|
818412
|
IS(Mf)9
|
Impact Station (Close to
HKBCF construction site)
|
813273
|
818850
|
IS10
|
Impact Station (Close to
HKBCF construction site)
|
812577
|
820670
|
IS10(N)
|
Impact Station (Close to
HKBCF construction site)
|
812942
|
820881
|
SR3
|
Sensitive receivers (San
Tau SSSI)
|
810525
|
816456
|
SR4
|
Sensitive receivers (Tai
Ho Inlet)
|
814760
|
817867
|
SR4(N)
|
Sensitive receivers (Tai
Ho Inlet)
|
814705
|
817859
|
SR5
|
Sensitive receivers
(Artificial Reef In NE Airport)
|
811489
|
820455
|
SR5(N)
|
Sensitive receivers
(Artificial Reef In NE Airport)
|
812569
|
821475
|
SR10A
|
Sensitive receivers (Ma
Wan Fish Culture Zone)
|
823741
|
823495
|
SR10B
|
Sensitive receivers (Ma
Wan Fish Culture Zone)
|
823686
|
823213
|
SR10B(N)
|
Sensitive receivers (Ma
Wan Fish Culture Zone)
|
823683
|
823187
|
CS2
|
Control Station (Mid-Ebb)
|
805849
|
818780
|
CS(Mf)5
|
Control Station
(Mid-Flood)
|
817990
|
821129
|
Remarks:
1) Technical
issues have been observed from impact monitoirng of the Contract and thus
published informatin from Monthly
EM&A Report for June 2017 prepared
for Contract No. HY/2010/02 and Contract No. HY/2011/09 were adopted for the
Contract.
2)
Due to safety concern and topographical condition
of the original locations of SR4 and SR10B, alternative impact water quality
monitoring stations, naming as SR4(N) and SR10B(N), were adopted, which are
situated in vicinity of the original impact water quality monitoring stations
(SR4 and SR10B) and could be reachable.
3)
Due to marine work of the Expansion of Hong Kong
International Airport into a Three-Runway System (3RS Project), original
locations of water quality monitoring stations SR5 and IS10 are enclosed by
works boundary of 3RS Project. Alternative impact water quality monitoring
stations, naming as SR5(N) and IS10(N) was approved in 12 May 2017 and were
adopted starting from 15 May 2017 to replace the original locations of water
quality monitoring for Contract No. HY/2010/02.
|
4.5
Monitoring Methodology
4.5.1 The monitoring
methodology is detailed in the Monthly EM&A Report for June 2017 prepared
for Contract No. HY/2010/02 and Contract No. HY/2011/09.
4.6
Monitoring Schedule for the Reporting Month
4.6.1 The monitoring schedule
for impact water quality monitoring in June 2017 is detailed in the Monthly
EM&A Report prepared for Contract No. HY/2010/02 and Contract No.
HY/2011/09.
4.7.1 The monitoirng
results of water quality monitoring for all stations except station CS2 were
adopted from the published Monthly EM&A Report for Contract No. HY/2010/02.
4.7.2 The monitoirng
results of water quality monitoring for station CS2 was adopted from the
published Monthly EM&A Report Contract No. HY/2011/09.
4.7.3 For marine water quality monitoring,
no Action Level and Limit Level exceedances of dissolved oxygen, turbidity and
suspended solid levels were recorded by the ET of Contract No. HY/2010/02 and
Contract No. HY/2011/09 during the reporting month.
4.7.4
The event action plan is annexed in Appendix F.
5.1.1
Impact dolphin monitoring is required to be conducted by a qualified dolphin specialist team to
evaluate whether there have
been any effects on the
dolphins.
5.1.2
The Action Level and Limit Level for dolphin monitoring are shown in Table 5.1.
Table
5.1 Action
and Limit Levels for Dolphin Monitoring
|
North Lantau Social Cluster
|
NEL
|
NWL
|
Action
Level
|
STG < 4.2 & ANI < 15.5
|
STG < 6.9 & ANI <
31.3
|
Limit Level
|
(STG < 2.4 & ANI
< 8.9) and (STG < 3.9 & ANI < 17.9)
|
Remarks:
1. STG means quarterly encounter rate of number of dolphin sightings.
2. ANI means quarterly encounter rate of total number of dolphins.
3. For North Lantau Social Cluster, AL will be trigger if either NEL or NWL fall below the criteria; LL will
be triggered if both NEL and NWL
fall below the criteria.
5.1.3 The revised Event and Action Plan
for dolphin Monitoring was approved by EPD in 6 May 2013. The revised Event and Action
Plan is annexed in Appendix F.
Vessel-based Line-transect Survey
5.2.1 According to the requirements of
the Updated EM&A Manual for HKLR (Version 1.0), dolphin monitoring
programme should cover all transect lines in NEL and NWL survey areas (see Figure 1 of Appendix H) twice per month. The
co-ordinates of all transect lines are shown in Table 5.2. The coordinates of several starting
points have been revised due to the obstruction of the permanent structures
associated with the construction works of HKLR and the southern viaduct of
TM-CLKL, as well as provision of adequate buffer distance from the Airport
Restricted Areas. The EPD issued a memo and
confirmed that they had no objection on the revised transect lines on 19 August
2015, and the revised coordinates are in red and marked with an asterisk in Table 5.2.
Table 5.2 Co-ordinates
of Transect Lines
Line No.
|
Easting
|
Northing
|
|
Line No.
|
Easting
|
Northing
|
1
|
Start Point
|
804671
|
815456*
|
|
13
|
Start Point
|
816506
|
819480
|
1
|
End Point
|
804671
|
831404
|
|
13
|
End Point
|
816506
|
824859
|
2
|
Start Point
|
805475
|
815913*
|
|
14
|
Start Point
|
817537
|
820220
|
2
|
End Point
|
805477
|
826654
|
|
14
|
End Point
|
817537
|
824613
|
3
|
Start Point
|
806464
|
819435
|
|
15
|
Start Point
|
818568
|
820735
|
3
|
End Point
|
806464
|
822911
|
|
15
|
End Point
|
818568
|
824433
|
4
|
Start Point
|
807518
|
819771
|
|
16
|
Start Point
|
819532
|
821420
|
4
|
End Point
|
807518
|
829230
|
|
16
|
End Point
|
819532
|
824209
|
5
|
Start Point
|
808504
|
820220
|
|
17
|
Start Point
|
820451
|
822125
|
5
|
End Point
|
808504
|
828602
|
|
17
|
End Point
|
820451
|
823671
|
6
|
Start Point
|
809490
|
820466
|
|
18
|
Start Point
|
821504
|
822371
|
6
|
End Point
|
809490
|
825352
|
|
18
|
End Point
|
821504
|
823761
|
7
|
Start Point
|
810499
|
820880*
|
|
19
|
Start Point
|
822513
|
823268
|
7
|
End Point
|
810499
|
824613
|
|
19
|
End Point
|
822513
|
824321
|
8
|
Start Point
|
811508
|
821123*
|
|
20
|
Start Point
|
823477
|
823402
|
8
|
End Point
|
811508
|
824254
|
|
20
|
End Point
|
823477
|
824613
|
9
|
Start Point
|
812516
|
821303*
|
|
21
|
Start Point
|
805476
|
827081
|
9
|
End Point
|
812516
|
824254
|
|
21
|
End Point
|
805476
|
830562
|
10
|
Start Point
|
813525
|
820872
|
|
22
|
Start Point
|
806464
|
824033
|
10
|
End Point
|
813525
|
824657
|
|
22
|
End Point
|
806464
|
829598
|
11
|
Start Point
|
814556
|
818853*
|
|
23
|
Start Point
|
814559
|
821739
|
11
|
End Point
|
814556
|
820992
|
|
23
|
End Point
|
814559
|
824768
|
12
|
Start Point
|
815542
|
818807
|
|
|
|
|
|
12
|
End Point
|
815542
|
824882
|
|
|
|
|
|
Note:
Co-ordinates in red and marked with asterisk are revised co-ordinates of
transect line.
5.2.2
The survey team used standard line-transect methods
(Buckland et al. 2001) to conduct the systematic vessel surveys, and followed
the same technique of data collection that has been adopted over the last 18
years of marine mammal monitoring surveys in Hong Kong developed by HKCRP (see
Hung 2015). For each monitoring
vessel survey, a 15-m inboard vessel with an open upper deck (about 4.5 m above
water surface) was used to make observations from the flying bridge area.
5.2.3
Two experienced observers (a data recorder and a
primary observer) made up the on-effort survey team, and the survey vessel
transited different transect lines at a constant speed of 13-15 km per
hour. The data recorder searched
with unaided eyes and filled out the datasheets, while the primary observer
searched for dolphins and porpoises continuously through 7 x 50 Fujinon marine binoculars. Both observers searched the sea ahead of
the vessel, between 270o and 90o (in relation to the bow,
which is defined as 0o).
One to two additional experienced observers were available on the boat
to work in shift (i.e. rotate every 30 minutes) in order to minimize fatigue of
the survey team members. All
observers were experienced in small cetacean survey techniques and identifying
local cetacean species.
5.2.4
During on-effort survey periods, the survey team
recorded effort data including time, position (latitude and longitude), weather
conditions (Beaufort sea state and visibility), and distance traveled in each
series (a continuous period of search effort) with the assistance of a handheld
GPS (Garmin eTrex Legend).
5.2.5
Data including time, position and vessel speed were
also automatically and continuously logged by handheld GPS throughout the
entire survey for subsequent review.
5.2.6
When dolphins were sighted, the survey team would end
the survey effort, and immediately record the initial sighting distance and
angle of the dolphin group from the survey vessel, as well as the sighting time
and position. Then the research
vessel was diverted from its course to approach the animals for species
identification, group size estimation, assessment of group composition, and
behavioural observations. The
perpendicular distance (PSD) of the dolphin group to the transect line was
later calculated from the initial sighting distance and angle.
5.2.7
Survey effort being conducted along the parallel
transect lines that were perpendicular to the coastlines (as indicated in Figure 1 of Appendix
H) was labeled as
ˇ§primaryˇ¨ survey effort, while the survey effort conducted along the connecting
lines between parallel lines was labeled as ˇ§secondaryˇ¨ survey effort. According to HKCRP long-term dolphin
monitoring data, encounter rates of Chinese white dolphins deduced from effort
and sighting data collected along primary and secondary lines were similar in
NEL and NWL survey areas.
Therefore, both primary and secondary survey effort were presented as
on-effort survey effort in this report.
5.2.8
Encounter rates of Chinese white dolphins (number
of on-effort sightings per 100 km of survey effort and number of dolphins from
all on-effort sightings per 100 km of survey effort) were calculated in NEL and
NWL survey areas in relation to the amount of survey effort conducted during
each month of monitoring survey.
Only data collected under Beaufort 3 or below condition would be used
for encounter rate analysis.
Dolphin encounter rates were calculated using primary survey effort
alone, as well as the combined survey effort from both primary and secondary
lines.
Photo-identification Work
5.2.9
When a group of Chinese White Dolphins were sighted
during the line-transect survey, the survey team would end effort and approach
the group slowly from the side and behind to take photographs of them. Every attempt was made to photograph
every dolphin in the group, and even photograph both sides of the dolphins,
since the colouration and markings on both sides may not be symmetrical.
5.2.10
A professional digital camera (Canon EOS 7D or 60D model), equipped with long telephoto lenses
(100-400 mm zoom), were available on board for researchers to take sharp,
close-up photographs of dolphins as they surfaced. The images were shot at the highest
available resolution and stored on Compact Flash memory cards for downloading
onto a computer.
5.2.11
All digital images taken in the field were first
examined, and those containing potentially identifiable individuals were sorted
out. These photographs would then
be examined in greater detail, and were carefully compared to the existing
Chinese White Dolphin photo-identification catalogue maintained by HKCRP since
1995.
5.2.12
Chinese White Dolphins can be identified by their
natural markings, such as nicks, cuts, scars and deformities on their dorsal
fin and body, and their unique spotting patterns were also used as secondary
identifying features (Jefferson 2000).
5.2.13 All
photographs of each individual were then compiled and arranged in chronological
order, with data including the date and location first identified (initial
sighting), re-sightings, associated dolphins, distinctive features, and age
classes entered into a computer database.
Detailed information on all identified individuals will be further
presented as an appendix in quarterly EM&A reports.
Vessel-based Line-transect Survey
5.3.1
During the month of June
2017, two sets of systematic line-transect vessel surveys were conducted on the
14th, 15th, 20th and 26th to cover
all transect lines in NWL and NEL survey areas twice. The survey routes of each
survey day are presented in Figures 2 to
5 of Appendix H.
5.3.2
From these surveys, a total of 258.04 km of survey
effort was collected, with 93.8% of the total survey effort being conducted
under favourable weather conditions (i.e. Beaufort Sea State 3 or below with
good visibility) (Annex I of Appendix H).
Among the two areas, 90.70 km and 167.34 km of survey effort were
collected from NEL and NWL survey areas respectively. Moreover, the total survey effort
conducted on primary lines was 189.45 km, while the effort on secondary lines
was 68.59 km.
5.3.3
During the two sets of monitoring surveys in June 2017, only two groups
of five Chinese White Dolphins were sighted (see Annex II of Appendix H). Both dolphin sightings were made in NWL,
while none was sighted in NEL.
5.3.4
For the surveys conducted in June 2017, both dolphin groups were sighted
during on-effort search on secondary lines (Annex II of Appendix H). The sightings were not associated with
any operating fishing vessel.
5.3.5
Distribution of the dolphin sightings made in June 2017 is shown in Figure 6 of Appendix H. One of the dolphin groups was sighted
near Black Point at the mouth of Deep Bay, and another dolphin group was
sighted near Castle Peak Power Station (Figure
6 of Appendix H). As in previous monitoring months, both
sightings were made far away from the HKLR03/HKBCF reclamation sites as well as
the HKLR09/TMCLKL alignments (Figure 6 of
Appendix H).
5.3.6
During the Juneˇ¦s surveys, encounter rates of Chinese White Dolphins
deduced from the survey effort and on-effort sighting data made under
favourable conditions (Beaufort 3 or below) are shown in Tables 5.3 and 5.4.
Table 5.3 Individual
Survey Event Encounter Rates
|
Encounter rate (STG)
(no. of on-effort dolphin
sightings per 100 km of survey effort)
|
Encounter rate (ANI)
(no. of dolphins from all
on-effort sightings per 100 km of survey effort)
|
Primary Lines Only
|
Primary Lines Only
|
NEL
|
Set
1: June 14th / 15th
|
0.0
|
0.0
|
Set
2: June 20th / 26th
|
0.0
|
0.0
|
NWL
|
Set
1: June 14th / 15th
|
0.0
|
0.0
|
Set
2: June 20th / 26th
|
0.0
|
0.0
|
Remarks:
1. Dolphin Encounter Rates
Deduced from the Two Sets of Surveys (Two Surveys in Each Set) in June 2017 in
Northeast Lantau (NEL) and Northwest Lantau (NWL).
Table 5.4 Monthly
Average Encounter Rates
|
Encounter rate (STG)
(no. of on-effort dolphin sightings per 100 km of survey effort)
|
Encounter rate (ANI)
(no. of dolphins from all
on-effort sightings per 100 km of survey effort)
|
Primary Lines Only
|
Both Primary and Secondary Lines
|
Primary Lines Only
|
Both Primary and Secondary Lines
|
Northeast Lantau
|
0.0
|
0.0
|
0.0
|
0.0
|
Northwest Lantau
|
0.0
|
0.7
|
0.0
|
0.7
|
Remarks:
1. Monthly Average Dolphin Encounter
Rates (Sightings Per 100 km of Survey Effort) from All Four Surveys Conducted
in June 2017 on Primary Lines only as well as Both Primary Lines and Secondary
Lines in Northeast Lantau (NEL) and Northwest Lantau (NWL).
5.3.7
The average dolphin group size
in June 2017 was 2.5 individuals per group, which was lower than the ones in
previous months of monitoring surveys despite the very small sample size (with
only two groups).
Photo-identification Work
5.3.8
Five known individual dolphins
were sighted five times during Juneˇ¦s surveys (Annexes III and IV of Appendix H). All individuals were re-sighted only
once during the monthly surveys in June.
5.3.9
Notably, two of these
individuals (i.e. NL33 and NL322) were mother-calf pair during their
re-sightings in June 2017.
Conclusion
5.3.10
During this month of dolphin
monitoring, no adverse impact from the activities of this construction project
on Chinese White Dolphins was noticeable from general observations.
5.3.11
Due to monthly variation in
dolphin occurrence within the study area, it would be more appropriate to draw
conclusion on whether any impacts on dolphins have been detected related to the
construction activities of this project in the quarterly EM&A report, where
comparison on distribution, group size and encounter rates of dolphins between
the quarterly impact monitoring period (June ˇV August 2017) and baseline
monitoring period (3-month period) will be made.
5.4.1 Buckland,
S. T., Anderson, D. R., Burnham, K. P., Laake, J. L., Borchers, D. L., and
Thomas, L. 2001. Introduction to distance sampling:
estimating abundance of biological populations. Oxford University Press, London.
5.4.2 Hung,
S. K. 2015. Monitoring of Marine Mammals in Hong
Kong waters: final report (2014-15).
An unpublished report submitted to the Agriculture, Fisheries and
Conservation Department, 198 pp.
5.4.3 Jefferson, T. A. 2000. Population biology of the Indo-Pacific
hump-backed dolphin in Hong Kong waters.
Wildlife Monographs 144:1-65.
Methodology
6.1.1 To avoid disturbance
to the mudflat and nuisance to navigation, no fixed marker/monitoring rod was
installed at the monitoring stations. A high precision Global Navigation
Satellite System (GNSS) real time location fixing system (or equivalent
technology) was used to locate the station in the precision of 1mm, which is
reasonable under flat mudflat topography with uneven mudflat surface only at
micro level. This method has been
used on Agricultural Fisheries and Conservation Departmentˇ¦s (AFCD) project,
namely Baseline Ecological Monitoring Programme for the Mai Po Inner Deep Bay
Ramsar Site for measurement of seabed levels.
6.1.2 Measurements were
taken directly on the mudflat surface.
The Real Time Kinematic GNSS (RTK GNSS) surveying technology was used to
measure mudflat surface levels and 3D coordinates of a survey point. The RTK GNSS survey was calibrated
against a reference station in the field before and after each survey. The reference station is a survey
control point established by the Lands Department of the HKSAR Government or
traditional land surveying methods using professional surveying instruments
such as total station, level and/or geodetic GNSS. The coordinates system was in HK1980
GRID system. For this contract, the
reference control station was surveyed and established by traditional land
surveying methods using professional surveying instruments such as total
station, level and RTK GNSS. The
accuracy was down to mm level so that the reference control station has
relatively higher accuracy. As the
reference control station has higher accuracy, it was set as true evaluation
relative to the RTK GNSS measurement.
All position and height correction were adjusted and corrected to the
reference control station.
Reference station survey result and professional land surveying
calibration is shown as Table 6.1:
Table 6.1 Reference
Station Survey result and GNSS RTK calibration result of Round 1
Reference Station
|
Easting (m)
|
Northing (m)
|
Baseline reference elevation (mPD) (A)
|
Round 1 Survey (mPD) (B)
|
Calibration Adjustment (B-A)
|
T1
|
811248.660mE
|
816393.173mN
|
3.840
|
3.817
|
-0.023
|
T2
|
810806.297mE
|
815691.822mN
|
4.625
|
4.653
|
+0.028
|
T3
|
810778.098mE
|
815689.918mN
|
4.651
|
4.660
|
+0.009
|
T4
|
810274.783mE
|
816689.068mN
|
2.637
|
2.709
|
+0.072
|
6.1.3 The precision of the
measured mudflat surface level reading (vertical precision setting) was within
10 mm (standard deviation) after averaging the valid survey records of the XYZ
HK1980 GRID coordinates. Each
survey record at each station was computed by averaging at least three measurements
that are within the above specified precision setting. Both digital data
logging and written records were collected in the field. Field data on station fixing and mudflat
surface measurement were recorded.
Monitoring Locations
6.1.4 Four monitoring stations
were established based on the site conditions for the sedimentation monitoring
and are shown in Figure 6.1.
Monitoring Results
6.1.5 The baseline
sedimentation rate monitoring was in September 2012 and impact sedimentation
rate monitoring was undertaken on 8
June 2017. The mudflat
surface levels at the four established monitoring stations and the
corresponding XYZ HK1980 GRID coordinates are presented in Table 6.2 and Table 6.3.
Table 6.2 Measured
Mudflat Surface Level Results
|
Baseline Monitoring (September
2012)
|
Impact Monitoring
(June 2017)
|
Monitoring
Station
|
Easting
(m)
|
Northing
(m)
|
Surface
Level
(mPD)
|
Easting
(m)
|
Northing
(m)
|
Surface
Level
(mPD)
|
S1
|
810291.160
|
816678.727
|
0.950
|
810291.155
|
816678.715
|
1.078
|
S2
|
810958.272
|
815831.531
|
0.864
|
810958.328
|
815831.484
|
0.990
|
S3
|
810716.585
|
815953.308
|
1.341
|
810716.604
|
815953.296
|
1.447
|
S4
|
811221.433
|
816151.381
|
0.931
|
811221.440
|
816151.355
|
1.116
|
Table 6.3 Comparison
of measurement
|
Comparison of measurement
|
Remarks and Recommendation
|
Monitoring
Station
|
Easting
(m)
|
Northing
(m)
|
Surface
Level
(mPD)
|
S1
|
-0.005
|
-0.012
|
0.128
|
Level continuously increased
|
S2
|
0.056
|
-0.047
|
0.126
|
Level continuously increased
|
S3
|
0.019
|
-0.012
|
0.106
|
Level continuously increased
|
S4
|
0.007
|
-0.026
|
0.185
|
Level continuously increased
|
6.1.6
This measurement result was
generally and relatively higher than the baseline measurement at S1, S2, S3 and
S4. The mudflat level is continuously increased.
6.2.1 The mudflat
monitoring covered water quality monitoring data. Reference was made to the water quality
monitoring data of the representative water quality monitoring station (i.e.
SR3) as in the EM&A Manual. The
water quality monitoring location (SR3) is shown in Figure 2.1.
6.2.2 Impact water quality
monitoring in San Tau (monitoring station SR3) was conducted in June 2017. The monitoring parameters included
dissolved oxygen (DO), turbidity and suspended solids (SS).
6.2.3 The impact water
quality monitoring results for SR3 in June 2017 were adopted from the
published Monthly EM&A Report for Contract No. HY/2010/02.
6.3
Mudflat
Ecology Monitoring Methodology
Sampling Zone
6.3.1
In order to collect baseline information of mudflats in the study site,
the study site was divided into three sampling zones (labeled as TC1, TC2, TC3)
in Tung Chung Bay and one zone in San Tau (labeled
as ST) (Figure 2.1 of Appendix
I). The
horizontal shoreline of sampling zones TC1, TC2, TC3 and ST were about 250 m,
300 m, 300 m and 250 m respectively (Figure
2.2 of Appendix
I).
Survey of horseshoe crabs, seagrass beds and intertidal communities were
conducted in every sampling zone. The present survey was conducted in June 2017
(totally 5 sampling days between 2nd and 11th June 2017).
6.3.2
Since the field survey of Jun. 2016, increasing number of trashes and
even big trashes (Figure 2.3 of Appendix I) were found in every sampling
zone. It raised a concern about the solid waste dumping and current-driven waste
issues in Tung Chung Wan. Respective measures (e.g. manual clean-up) should be
implemented by responsible units.
Horseshoe Crabs
6.3.3 Active
search method was conducted for horseshoe crab monitoring by two experienced
surveyors in every sampling zone. During the search period, any accessible and
potential area would be investigated for any horseshoe crab individuals within
2-3 hours of low tide period (tidal level below 1.2 m above Chart Datum
(C.D.)). Once a horseshoe crab individual was found, the species was identified
referencing to Li (2008). The prosomal width, inhabiting substratum and
respective GPS coordinate were recorded. A photographic record was taken for
future investigation. Any grouping behavior of individuals, if found, was
recorded. The horseshoe crab surveys were conducted on 2nd (for
TC1), 3rd (for TC2) and 9th (for TC3 and ST) June 2017.
The weather was generally hot on all field days without rainfall.
6.3.4 In
present survey (Jun. 2017), a big horseshoe crab was tangled by a trash gill
net in ST mudflat (Figure 2.3 of Appendix
I). It
was released to sea once after photo recording. The horseshoe crab of such size
should be inhabitating sub-tidal environment while it forages on intertidal
shore occasionally during high tide period. If it is tangled by the trash net
for few days, it may die due to starvation or overheat during low tide period.
These trash gill nets are definitely ˇĄfatal trapˇ¦ for the horseshoe crabs and
other marine life. Manual clean-up should be implemented as soon as possible by
responsible units.
Seagrass Beds
6.3.5
Active search method was conducted for
seagrass bed monitoring by two experienced surveyors in every sampling zone.
During the search period, any accessible and potential area would be
investigated for any seagrass beds within 2-3 hours of low tide period. Once
seagrass bed was found, the species, estimated area, estimated coverage
percentage and respective GPS coordinates were recorded. The seagrass beds
surveys were conducted on 2nd (for TC1), 3rd (for TC2)
and 9th (for TC3 and ST) June 2017. The weather was generally hot on
all field days without rainfall.
Intertidal Soft Shore Communities
6.3.6 The
intertidal soft shore community surveys were conducted in low tide period on 2nd
(for TC1), 3rd (for TC2), 10th (for TC3) and 11th
(for ST) June 2017. In every sampling zone, three 100m horizontal transect
lines were laid at high tidal level (H: 2.0 m above C.D.), mid tidal level (M:
1.5 m above C.D.) and low tidal level (L: 1.0 m above C.D.). Along every
horizontal transect line, ten random quadrats (0.5 m x 0.5 m) were placed.
6.3.7 Inside
a quadrat, any visible epifauna were collected and were in-situ identified to the lowest practical taxonomical resolution.
Whenever possible a hand core sample (10 cm internal diameter 20 cm depth) of sediments
was collected in the quadrat. The core sample was gently washed through a sieve
of mesh size 2.0 mm in-situ. Any
visible infauna were collected and identified. Finally the top 5 cm surface
sediments was dug for visible infauna in the quadrat regardless of hand core
sample was taken.
6.3.8 All collected fauna were released
after recording except some tiny individuals that are too small to be
identified on site. These tiny individuals were taken to laboratory for
identification under dissecting microscope.
6.3.9 The
taxonomic classification was conducted in accordance to the following
references: Polychaetes: Fauchald (1977), Yang and Sun (1988); Arthropods: Dai
and Yang (1991), Dong (1991); Mollusks: Chan and Caley (2003), Qi (2004).
Data Analysis
6.3.10 Data collected from
direct search and core sampling was pooled in every quadrat for data analysis.
Shannon-Weaver Diversity Index (Hˇ¦)
and Pielouˇ¦s Species Evenness (J)
were calculated for every quadrat using the formulae below,
Hˇ¦= -ŁU ( Ni / N ) ln ( Ni / N
) (Shannon and Weaver, 1963)
J = Hˇ¦ / ln S (Pielou, 1966)
where S is the total number
of species in the sample, N is the total number of individuals, and Ni is the
number of individuals of the ith species.
6.4.1
In the event of the impact monitoring results
indicating that the density or the distribution pattern of intertidal fauna and
seagrass is found to be significant different to the baseline condition (taking
into account natural fluctuation in the occurrence and distribution pattern
such as due to seasonal change), appropriate actions should be taken and
additional mitigation measures should be implemented as necessary. Data should then be re-assessed and the
need for any further monitoring should be established. The action plan, as given in Table 6.5 should be undertaken within a
period of 1 month after a significant difference has been determined.
Table 6.5 Event
and Action Plan for Mudflat Monitoring
Event
|
ET Leader
|
IEC
|
SO
|
Contractor
|
Density or the
distribution pattern of horseshoe crab, seagrass or intertidal soft shore
communities recorded in the impact or post-construction monitoring are significantly lower than or different
from those recorded in the baseline monitoring.
|
Review historical data
to ensure differences are as a result of natural variation or previously
observed seasonal differences;
Identify source(s) of
impact;
Inform the IEC, SO and
Contractor;
Check monitoring data;
Discuss additional monitoring
and any other measures, with the IEC and Contractor.
|
Discuss monitoring with
the ET and the Contractor;
Review proposals for
additional monitoring and any other measures submitted by the Contractor and
advise the SO accordingly.
|
Discuss with the IEC
additional monitoring requirements and any other measures proposed by the ET;
Make agreement on the
measures to be implemented.
|
Inform the SO and in
writing;
Discuss with the ET and
the IEC and propose measures to the IEC and the ER;
Implement the agreed
measures.
|
Notes:
ET ˇV Environmental Team
IEC ˇV Independent
Environmental Checker
SO ˇV Supervising Officer
Horseshoe Crabs
6.5.1
In the
present survey, two species of horseshoe crab Carcinoscorpius rotundicauda (total 133 ind.) and Tachypleus tridentatus (total 125 ind.)
were recorded. For one sight record, grouping of 2-20 individuals was observed
at same locations with similar substratum (fine sand or soft mud, slightly
submerged). Photo records were shown in Figure
3.1 of Appendix I while the complete survey records were
listed in Annex II of Appendix I. Besides, one tiny individual (prosomal
width ~8 mm) was found in TC3 but identification to species was not possible.
Hence this record was excluded from the data analysis.
6.5.2
Table 3.1 of Appendix I summarizes the survey results of
horseshoe crab in the present survey. For Carcinoscorpius
rotundicauda, moderate number of individuals (22 ind.) were found in TC1
that search record was at low-moderate level (5.5 ind. hr-1 person-1).
The average body size was 46.69 mm (prosomal width ranged 15.72-72.49 mm) in
TC1. More individuals were found in TC3 (57 ind.) and ST (54 ind.) resulting in
relatively higher search records (9.0-9.5 ind. hr-1 person-1).
Smaller individuals were found in TC3 that the average body size was 38.95 mm
(prosomal width ranged 14.29-86.73 mm). The average body size was 53.94 mm
(prosomal width ranged 38.83-83.33 mm) in ST. No individual was found in TC2
regardless of a mating pair (to be discussed below).
6.5.3
For Tachypleus
tridentatus, there were only 1-2 individuals in TC1 and TC2 (prosomal width
ranged 36.33-67.42 mm). The search record was very low (0.3-0.5 ind. hr-1
person-1). Similarly, more individuals were found in TC3 (70 ind.)
and ST (52 ind.) respectively. In TC3, the search record was relatlively higher
(11.7 ind. hr-1 person-1) while the average body size was
54.24 mm (prosomal width ranged 27.57-93.44 mm). In ST, the search record was
8.7 ind. hr-1 person-1 while the average body size was
53.74 mm (prosomal width ranged 40.41-76.37 mm).
6.5.4 In the
previous survey of Mar. 2015, there was one important finding that a mating
pair of Carcinoscorpius rotundicauda
was found in ST (prosomal width: male 155.1 mm, female 138.2 mm) (Figure 3.2 of Appendix
I). It
indicated the importance of ST as a breeding ground of horseshoe crab. In the
present survey (Jun. 2017), mating pairs of Carcinoscorpius
rotundicauda were also found in TC2 (prosomal width: male 175.27 mm, female
143.51 mm) and TC3 (prosomal width: male 182.08 mm, female 145.63 mm) (Figure 3.2 of Appendix
I). It
indicated that breeding of horseshoe crab could occur along the coast of Tung
Chung Wan rather than ST only, as long as suitable substratum was available.
The mating pairs were found nearly burrowing in soft mud at low tidal level
(0.5-1.0 m above C.D.). The smaller male was holding the opisthosoma (abdomen
carapace) of larger female from behind.
6.5.5 In the present survey (Jun.
2017), one large individual of Carcinoscorpius
rotundicauda (prosomal width 178.67 mm) was tangled by a trash gill net in
ST (Figure 3.3 of Appendix I). Based on the sizes of these
mating pairs and tangled individuals, it indicated that individuals of prosomal
width larger than 100 mm would progress its nursery stage from intertidal
habitat to sub-tidal habitat of Tung Chung Wan. These large individuals might
move onto intertidal shore occasionally during high tide for foraging and
breeding.
6.5.6 Because
the large individuals (prosomal width > 100 mm) should be inhabiting
sub-tidal habitat in most of the time. The records of mating pair and large,
tangled individuals were excluded from the data analysis to avoid mixing up
with juvenile population living on intertidal habitat. In the previous survey
of Jun. 2016, the records of two large individuals of Carcinoscorpius rotundicauda (prosomal width 117.37 mm and 178.17
mm) in TC1 were excluded from data analysis according to the same principle.
6.5.7 No marked individual of horseshoe crab was
recorded in the present survey. Some marked individuals were found in the
previous surveys of Sep. 2013, Mar. 2014 and Sep. 2014. All of them were
released through a conservation programme conducted by Prof. Paul Shin
(Department of Biology and Chemistry, The City University of Hong Kong (CityU)).
It was a re-introduction trial of artificial bred horseshoe crab juvenile at
selected sites. So, that the horseshoe crabs population might be restored in
the natural habitat. Through a personal conversation with Prof. Shin, about 100
individuals were released in the sampling zone ST on 20 June 2013. All of them
were marked with color tape and internal chip detected by specific chip sensor.
There should be second round of release between June and September 2014 since
new marked individuals were found in the survey of Sep. 2014.
6.5.8 The artificial bred individuals, if found,
would be excluded from the results of present monitoring programme in order to
reflect the changes of natural population. However, the mark on their prosoma
might have been detached during moulting after a certain period of release. The
artificially released individuals were no longer distinguishable from the
natural population without the specific chip sensor. The survey data collected
would possibly cover both natural population and artificially bred individuals.
Population difference among the sampling
zones
6.5.9 Figures 3.4 and 3.5 of Appendix
I show
the changes of number of individuals, mean prosomal width and search record of
horseshoe crabs Carcinoscorpius
rotundicauda and Tachypleus tridentatus
respectively in every sampling zone throughout the monitoring period.
6.5.10 For TC3 and ST, medium to high
search records (i.e. number of individuals) of both species were always found
in wet season (Jun. and Sep.). The search record of ST was higher from Sep.
2012 to Jun. 2014 while it was replaced by TC3 from Sep. 2014 to Jun. 2015. The
search records were similar between two sampling zones from Sep. 2015 to Jun.
2016. In Sep. 2016, the search record of Carcinoscorpius
rotundicauda in ST was much higher than TC3. From Mar. to Jun. 2017
(present survey), the search records of both species were similar again between
two sampling zones and increased with warmer climate. It showed a natural
variation of horseshoe crab population in these two zones due to weather
condition and tidal effect during the survey. No obvious difference of
horseshoe crab population was noted between TC3 and ST.
6.5.11 For TC1, the search record was at
low to medium level throughout the monitoring period. The change of Carcinoscorpius rotundicauda was
relatively more variable than that of Tachypleus
tridentatus. Relatively, the search record was very low in TC2 (2 ind. in
Sep. 2013; 1 ind. in Mar., Jun., Sep. 2014, Mar. and Jun. 2015; 4 ind. in Sep.
2015; 6 ind. in Jun. 2016; 1 ind. in Sep. 2016, Mar. and Jun. 2017).
6.5.12 About
the body size, larger individuals of Carcinoscorpius
rotundicauda were usually found in ST and TC1 relative to those in TC3. For
Tachypleus tridentatus, larger
individuals were usually found in ST followed by TC3 and TC1.
6.5.13 Throughout the monitoring period,
it was obvious that TC3 and ST (western shore of Tung Chung Wan) was an
important nursery ground for horseshoe crab especially newly hatched
individuals due to larger area of suitable substratum (fine sand or soft mud)
and less human disturbance (far from urban district). Relatively, other
sampling zones were not a suitable nursery ground especially TC2. Possible
factors were less area of suitable substratum (especially TC1) and higher human
disturbance (TC1 and TC2: close to urban district and easily accessible). In
TC2, large daily salinity fluctuation was a possible factor either since it was
flushed by two rivers under tidal inundation. The individuals inhabiting TC1
and TC2 were confined in small foraging area due to limited area of suitable
substrata. Although a mating pair of Carcinoscorpius
rotundicauda was found in TC2, the hatching rate and survival rate of newly
hatched individuals were believed very low.
Seasonal variation of horseshoe crab population
6.5.14
Throughout the monitoring period, the search
record of horseshoe crab declined obviously during dry season especially
December (Figures 3.3 and 3.4 of Appendix
I). In
Dec. 2012, 4 individuals of Carcinoscorpius
rotundicauda and 12 individuals of Tachypleus
tridentatus were found only. In Dec. 2013, no individual of horseshoe crab
was found. In Dec. 2014, 2 individuals of Carcinoscorpius
rotundicauda and 8 individuals of Tachypleus
tridentatus were found only. In Dec. 2015, 2 individuals of Carcinoscorpius rotundicauda, 6
individuals of Tachypleus tridentatus
and one newly hatched, unidentified individual were found only. The horseshoe
crabs were inactive and burrowed in the sediments during cold weather (<15
ºC). Similar results of low search record in dry season were reported in a
previous territory-wide survey of horseshoe crab. For example, the search
records in Tung Chung Wan were 0.17 ind. hr-1 person-1
and 0.00 ind. hr-1 person-1 in wet season and dry season
respectively (details see Li, 2008). Relatively the search records were much
higher in Dec. 2016. There were totally 70 individuals of Carcinoscorpius rotundicauda and 24 individuals of Tachypleus tridentatus in TC3 and ST.
Because the survey was arranged in early December while the weather was warm
with sunlight (~22 ºC during dawn according to Hong Kong Observatory database,
Chek Lap Kok station on 5 Dec). In contrast, there was no search record in TC1
and TC2 because the survey was conducted in mid-December with colder and cloudy
weather (~20 ºC during dawn on 19 Dec). The horseshoe crab activity would
decrease gradually with the colder climate.
6.5.15
From Sep. 2012 to Dec. 2013, Carcinoscorpius rotundicauda was a less
common species relative to Tachypleus
tridentatus. Only 4 individuals were ever recorded in ST in Dec. 2012. This
species had ever been believed of very low density in ST hence the encounter
rate was very low. Since Mar. 2014, it was found in all sampling zones with
higher abundance in ST. Based on its average size (mean prosomal width
39.28-49.81 mm), it indicated that breeding and spawning of this species had
occurred about 3 years ago, along the coastline of Tung Chun Wan. However,
these individuals were still small while their walking trails were
inconspicuous. Hence there was no search record in previous sampling months.
Since Mar. 2014, more individuals were recorded due to larger size and higher
activity (i.e. more conspicuous walking trail).
6.5.16 For Tachypleus tridentatus, sharp
increase of number of individuals was recorded in ST during the wet season of
2013 (from Mar. to Sep.). According to a personal conversation with Prof. Shin
(CityU), his monitoring team had recorded similar increase of horseshoe crab
population during wet season. It was believed that the suitable ambient
temperature increased its conspicuousness. However similar pattern was not
recorded in the following wet seasons. The number of individuals increased in
Mar. and Jun. 2014 followed by a rapid decline in Sep. 2014. Then the number of
individuals fluctuated slightly in TC3 and ST until Mar. 2017. Apart from
natural mortality, migration from nursery soft shore to subtidal habitat was
another possible cause. Since the mean prosomal width of Tachypleus
tridentatus continued to grow and reached about 50 mm since Mar. 2014. Then
it varied slightly between 35-65 mm from Sep. 2014 to Mar. 2017. Most of the
individuals might have reached a suitable size (e.g. prosomal width 50-60 mm)
strong enough to forage in sub-tidal habitat. In the present survey (Jun.
2017), the number of individuals increased sharply again in TC3 and ST.
Although mating pair of Tachypleus tridentatus was not found in previous
surveys, there should be new round of spawning in the wet season of 2016. The
individuals might have grown to a more conspicuous size in 2017 accounting for
higher search record.
6.5.17
Recently, Carcinoscorpius
rotundicauda was a more common horseshoe crab species in Tung Chung Wan. It
was recorded in the four sampling zones while the majority located in TC3 and
ST. Due to potential breeding last year, Tachypleus
tridentatus became common again and distributed in TC3 and ST only. Since
TC3 and ST were regarded as important nursery ground for both horseshoe crab
species, box plots of prosomal width of two horseshoe crab species were
constructed to investigate the changes of population in details.
Box plot of horseshoe crab populations in TC3
6.5.18
Figure 3.6 of Appendix
I shows the changes of prosomal width of Carcinoscorpius
rotundicauda and Tachypleus tridentatus in TC3. As mentioned above, Carcinoscorpius
rotundicauda was rarely found between Sep. 2012 and Dec. 2013 hence the
data were lacking. In Mar 2014, the major size (50% of individual records
between upper (top of box) and lower quartile (bottom of box)) ranged 40-60 mm
while only few individuals were found. From Mar. 2014 to Mar. 2017, the median
prosomal width (middle line of box) and major size (box) decreased after Mar.
of every year. It was due to more small individuals found. It indicated new
rounds of spawning. Also, there were slight increasing trends of body size from
Jun. to Mar. of next year since 2015. It indicated a stable growth of
individuals. Focused on larger juveniles (circle dots above the box), the size
range was quite variable (prosomal width 60-90 mm) along the sampling months.
Juveniles reaching this size might gradually migrate to sub-tidal habitats.
6.5.19 For Tachypleus tridentatus, the major
size ranged 20-50 mm while the number of individuals fluctuated from Sep. 2012
to Jun. 2014. Then a slight but consistent growing trend was observed from Sep.
2014 to Jun. 2015. The prosomal width increased from 25-35 mm to 35-65 mm. As
mentioned, the large individuals might have reached a suitable size for
migrating from the nursery soft shore to subtidal habitat. It accounted for the
declined population in TC3. From Mar. to Sep. 2016, slight increasing trend of
major size was noticed again. From Dec. 2016 to Jun. 2017 (present survey),
similar increasing trend of major size was noted with much higher number of
individuals. It reflected new round of spawning. Across the whole monitoring
period, the larger juveniles (circle dots above the box) reached 60-80 mm in
prosomal width while it could reach 90 mm in present survey. Juveniles reaching
this size might gradually migrate to sub-tidal habitats.
Box plot of horseshoe crab populations in ST
6.5.20
Figure 3.7 of Appendix
I shows the changes of prosomal width of Carcinoscorpius
rotundicauda and Tachypleus tridentatus in ST. As mentioned above, Carcinoscorpius
rotundicauda was rarely found between Sep. 2012 and Dec. 2013 hence the
data were lacking. From Mar. 2014 to Sep. 2016, the size of major population
decreased and more small individuals (i.e. circle dots below the box) were
recorded after Jun. of every year. It indicated new round of spawning. Also,
there were similar increasing trends of body size from Sep. to Jun. of next
year between 2014 and 2017. It indicated a stable growth of individuals. Across
the whole monitoring period, the larger juveniles (i.e. circle dots above the
box) usually ranged 70-80 mm in prosomal width except one individual (prosomal
width 107.04 mm) found in Mar. 2017. It reflected juveniles reaching this size
would gradually migrate to sub-tidal habitats.
6.5.21
For Tachypleus tridentatus, a
consistent growing trend was observed for the major population from Dec. 2012
to Dec. 2014 regardless of change of search record. The prosomal width
increased from 15-30 mm to 55-70 mm. As mentioned, the large juveniles might
have reached a suitable size for migrating from the nursery soft shore to subtidal
habitat. From Mar. to Sep. 2015, the size of major population decreased
slightly to a prosomal width 40-60 mm. At the same time, the number of
individuals decreased gradually. It further indicated some of large juveniles
might have migrated to sub-tidal habitat, leaving the smaller individuals on
shore. There was an overall growth trend. In Dec. 2015, two big individuals
(prosomal width 89.27 mm and 98.89 mm) were recorded only while it could not
represent the major population. From Dec. 2015 to Mar. 2016, the number of
individual was very few in ST that no boxplot could be produced. In Jun. 2016,
the prosomal width of major population ranged 50-70 mm. But it dropped clearly
to 30-40 mm in Sep. 2016 followed by an increase to 40-50 mm in Dec. 2016, 40-70
mm in Mar. 2017 and 50-60mm in Jun. 2017 (present survey). Based on overall
higher number of small individuals from Jun. 2016 to Jun. 2017, it indicated
new round of spawning. Throughout the monitoring period, the larger juveniles
ranged 60-80 mm in prosomal width. Juveniles reaching this size would gradually
migrate to sub-tidal habitats.
6.5.22
As a summary for horseshoe crab populations in TC3 and ST, there were
spawning of Carcinoscorpius rotundicauda
from 2014 to 2016 while the spawning time should be in spring. There were
consistent, increasing trends of population size in these two sampling zones.
For Tachypleus tridentatus, small
individuals were rarely found in both zones from 2014 to 2015. It was believed
no occurrence of successful spawning. The existing individuals (that recorded
since 2012) grew to a mature size and migrated to sub-tidal habitat. Hence the
number of individuals decreased gradually. In 2016, new round of spawning was
recorded in ST while increasing number of individuals and body size was
noticed.
Impact of the HKLR project
6.5.23
It was the 19th survey of the
EM&A programme during the construction period. Based on the results, impact
of the HKLR project could not be detected on horseshoe crabs. The population
change was mainly determined by seasonal variation while new rounds of spawning
were observed for both species. In case, abnormal phenomenon (e.g. very few
numbers of horseshoe crab individuals in wet season, large number of dead
individuals on the shore) is found, it would be reported as soon as possible.
Seagrass Beds
6.5.24 In the
present survey, seagrass species Halophila ovalis and Zostera japonica were
recorded in TC3 and ST. Photo records were shown in Figure 3.8 of Appendix
I while
the complete records of seagrass beds survey were shown in Annex III of Appendix
I.
6.5.25 Table 3.2 of Appendix
I summarizes
the results of seagrass beds survey. In TC3, two small patches of Halophila ovalis was found in soft mud
area at 0.5-1.0 m above C.D. while the total seagrass bed area and vegetation
coverage were about 140.4 m2 (average seagrass bed area 70.2 m2)
and 100% respectively.
6.5.26 In ST,
two large patches of Halophila ovalis
were found while the total seagrass bed area was about 17046.5 m2.
The largest patch was an extensive, horizontal strand with area ~12334.4 m2
and vegetation coverage 80-100%, located in the soft mud area at 0.5-2.0 m
above C.D.. It had covered significant portion of the mud flat area southward
from TC3 boundary to ST (i.e. western shore of Tung Chung Wan). At vicinity,
there was another large patch (4712.1 m2, coverage 80-100%), located
in the sandy area at 1.0-2.0 m above C.D..
6.5.27 For Zostera japonica, there was one,
small horizontal strand in the sandy area nearby the seaward mangrove. The
seagrass bed area and vegetation coverage were 105.4 m2 and 100%
respectively.
6.5.28
Since
majority of seagrass bed was confined in ST, the temporal change of both
seagrass species was investigated in details.
Temporal variation of seagrass beds
6.5.29 Figure
3.9 of Appendix
I shows the changes of estimated total area of
seagrass beds in ST along the sampling months. For Zostera japonica, it
was not recorded in the 1st and 2nd surveys of monitoring
programme. Seasonal recruitment of few, small patches (total seagrass area: 10
m2) was found in Mar. 2013 that grew within the large patch of
seagrass Halophila ovalis. Then the patch size increased and merged
gradually with the warmer climate from Mar. to Jun. 2013 (15 m2). However,
the patch size decreased and remained similar from Sep. 2013 (4 m2)
to Mar. 2014 (3 m2). In Jun. 2014, the patch size increased
obviously again (41 m2) with warmer climate followed by a decrease
between Sep. 2014 (2 m2) and Dec. 2014 (5 m2). From Mar.
to Jun. 2015, the patch size increased sharply again (90 m2). It
might be due to the disappearance of the originally dominant seagrass Halophila
ovalis resulting in less competition for substratum and nutrients. From
Sep.2015 to Jun.2016, it was found coexisting with seagrass Halophila ovalis
with steady increasing patch size (from 44 m2 to 115 m2)
and variable coverage. In Sep. 2016, the patch size decreased again to (38 m2)
followed by an increase to a horizontal strand (105.4 m2) in Jun.
2017 (present survey). And it was no longer co-existing with Halophila
ovalis. Between Sep. 2014 and Jun. 2017, an increasing trend was noticed
from Sep. to Jun. of next year followed by a rapid decline in Sep. of next
year. It was possibly the causes of heat stress, typhoon and stronger grazing
pressure during wet season.
6.5.30 For Halophila ovalis, it was recorded
as 3-4 medium to large patches (area 18.9-251.7 m2; vegetation
coverage 50-80%) beside the mangrove vegetation at tidal level 2 m above C.D.
in Sep. 2012 (first survey). The total seagrass bed area grew steadily from
332.3 m2 in Sep. 2012 to 727.4 m2 in Dec. 2013. Flowers
were observed in the largest patch during its flowering period. In Mar. 2014,
31 small to medium patches were newly recorded (variable area 1-72 m2
per patch, vegetation coverage 40-80% per patch) in lower tidal zone between
1.0 and 1.5 m above C.D. The total seagrass area increased further to 1350 m2.
In Jun. 2014, these small and medium patches grew and extended to each other.
These patches were no longer distinguishable and were covering a significant
mudflat area of ST. It was generally grouped into 4 large patches (1116 ˇV 2443
m2) of seagrass beds characterized of patchy distribution, variable
vegetable coverage (40-80%) and smaller leaves. The total seagrass bed area
increased sharply to 7629 m2. In Sep. 2014, the total seagrass area
declined sharply to 1111 m2. There were only 3-4 small to large
patches (6-253 m2) at high tidal level and 1 patch at low tidal
level (786 m2). Typhoon or strong water current was a possible cause
(Fong, 1998). In Sep. 2014, there were two tropical cyclone records in Hong
Kong (7th-8th Sep.: no cyclone name, maximum signal
number 1; 14th-17th Sep.: Kalmaegi, maximum signal number
8SE) before the seagrass survey dated 21st Sep. 2014. The strong water current
caused by the cyclone, Kalmaegi especially, might have given damage to the
seagrass beds. In addition, natural heat stress and grazing force were other
possible causes reducing seagrass beds area. Besides, very small patches of Halophila
ovalis could be found in other mud flat area in addition to the recorded
patches. But it was hardly distinguished due to very low coverage (10-20%) and
small leaves.
6.5.31 In
Dec. 2014, all the seagrass patches of Halophila
ovalis disappeared in ST. Figure
3.10 of Appendix
I shows
the difference of the original seagrass beds area nearby the mangrove
vegetation at high tidal level between Jun. 2014 and Dec. 2014. Such rapid loss
would not be seasonal phenomenon because the seagrass beds at higher tidal
level (2.0 m above C.D.) were present and normal in December 2012 and 2013.
According to Fong (1998), similar incident had occurred in ST in the past. The
original seagrass area had declined significantly during the commencement of
the construction and reclamation works for the international airport at Chek
Lap Kok in 1992. The seagrass almost disappeared in 1995 and recovered
gradually after the completion of reclamation works. Moreover, incident of
rapid loss of seagrass area was also recorded in another intertidal mudflat in
Lai Chi Wo in 1998 with unknown reason.
Hence Halophila ovalis was
regarded as a short-lived and r-strategy seagrass that could colonize areas in
short period but disappears quickly under unfavorable conditions (Fong, 1998).
Unfavourable conditions to seagrass Halophila
ovalis
6.5.32 Typhoon or strong water current was suggested as one unfavourable
condition to Halophila ovalis (Fong,
1998). As mentioned above, there were two tropical cyclone records in Hong Kong
in Sep. 2014. The strong water current caused by the cyclones might have given
damage to the seagrass beds.
6.5.33
Prolonged
light deprivation due to turbid water would be another unfavorable condition.
Previous studies reported that Halophila ovalis had little tolerance to
light deprivation. During experimental darkness, seagrass biomass declined
rapidly after 3-6 days and seagrass died completely after 30 days. The rapid
death might be due to shortage of available carbohydrate under limited
photosynthesis or accumulation of phytotoxic end products of anaerobic
respiration (details see Longstaff et al., 1999). Hence the seagrass bed
of this species was susceptible to temporary light deprivation events such as
flooding river runoff (Longstaff and Dennison, 1999).
6.5.34
In order to investigate any deterioration of
water quality (e.g. more turbid) in ST, the water quality measurement results
at two closest monitoring stations SR3 and IS5 of the EM&A programme were
obtained from the water quality monitoring team. Based on the results from June
to December 2014, the overall water quality was in normal fluctuation except
there was one exceedance of suspended solids (SS) at both stations in
September. On 10th Sep., 2014, the SS concentrations measured during
mid-ebb tide at stations SR3 (27.5 mg/L) and IS5 (34.5 mg/L) exceeded the
Action Level (≤23.5 mg/L and 120% of upstream control stationˇ¦s reading) and
Limit Level (≤34.4 mg/L and 130% of upstream control stationˇ¦s reading)
respectively. The turbidity readings at SR3 and IS5 reached 24.8-25.3 NTU and
22.3-22.5 NTU respectively. The temporary turbid water should not be caused by
the runoff from upstream rivers. Because there was no rain or slight rain from 1st
to 10th Sep. 2014 (daily total rainfall at the Hong Kong International Airport:
0-2.1 mm; extracted from the climatological data of Hong Kong Observatory). The
effect of upstream runoff on water quality should be neglectable in that
period. Moreover, the exceedance of water quality was considered unlikely to be
related to the contract works of HKLR according to the ˇĄNotifications of
Environmental Quality Limits Exceedancesˇ¦ provided by the respective
environmental team. The respective construction of seawall and stone column
works, which possibly caused turbid water, were carried out within silt curtain
as recommended in the EIA report. Moreover, there was no leakage of turbid
water, abnormity or malpractice recorded during water sampling. In general, the
exceedance of suspended solids concentration was considered to be attributed to
other external factors, rather than the contract works.
6.5.35
Based on the weather condition and water
quality results in ST, the co-occurrence of cyclone hit and turbid waters in Sep.
2014 might have combined the adverse effects on Halophila ovalis that leaded to disappearance of this short-lived
and r-strategy seagrass species. Fortunately, Halophila ovalis was a fast-growing species (Vermaat et al., 1995). Previous studies showed that
the seagrass bed could be recovered to the original sizes in 2 months through
vegetative propagation after experimental clearance (Supanwanid, 1996). Moreover,
it was reported to recover rapidly in less than 20 days after dugong herbivory
(Nakaoka and Aioi, 1999). As mentioned, the disappeared seagrass in ST in 1995
could recover gradually after the completion of reclamation works for
international airport (Fong, 1998). The seagrass beds of Halophila ovalis might recolonize the mudflat of ST through seed
reproduction as long as there was no unfavorable condition in the coming
months.
Recolonization of seagrass beds
6.5.36 Figure 3.10 of Appendix I shows the recolonization of seagrass bed area in ST from Dec. 2014
to Jun. 2017. From Mar. to Jun. 2015, 2-3 small patches of Halophila ovalis were newly found coinhabiting with another
seagrass species Zostera japonica.
But its total patch area was still very low relative to the previous records.
The recolonization rate was low while cold weather and insufficient sunlight
were possible factors between Dec. 2014 and Mar. 2015. Moreover, it would need
to compete with seagrass Zostera japonica
for substratum and nutrient. Since Zostera
japonica had extended and had covered the original seagrass bed of Halophila ovalis at certain degree. From
Jun. 2015 to Mar. 2016, the total seagrass area of Halophila ovalis had increased rapidly from 6.8 m2 to
230.63 m2. It had recolonized its original patch locations and
covered Zostera japonica. In Jun.
2016, the total seagrass area increased sharply to 4707.3 m2.
Similar to the previous records of Mar to Jun. 2014, the original patch area
increased further to a horizontally long strand. Another large seagrass beds
colonized the lower tidal zone (1.0-1.5 m above C.D.). In Sep. 2016, this patch
extended much and covered significant soft mud area of ST, resulting in sharp
increase of total area (24245 m2). It indicated the second extensive
colonization of this r-strategy
seagrass. In Dec. 2016, this extensive seagrass patch decreased in size and had
separated into few, undistinguishable patches. Moreover, the horizontal strand
nearby the mangrove vegetation decreased in size (Figure 3.10 of Appendix I). The total seagrass bed decreased to 12550 m2. In Mar.
2017, the seagrass bed area remained stable (12438 m2) while the
vegetation coverage decreased clearly (20-50%). It was once predicted that the
seagrass bed area would continue to decrease, similar to the record in Sep-Dec.
2014. However, it increased in both area (17046.5 m2) and vegetation
coverage (80-100%) in Jun. 2017 (present survey).
Impact of the HKLR
project
6.5.37
It was the 19th survey of the
EM&A programme during the construction period. According to the results of
present survey, there was clear recolonization of both seagrass species Halophila ovalis and Zostera japonica in ST. Hence the
negative impact of HKLR project on the seagrass was not significant. In case
unfavorable phenomenon (e.g. reduction of seagrass patch size, abnormal change
of leave color) is found persistent, it would be reported as soon as possible.
Intertidal Soft Shore Communities
6.5.38 Table 3.3 and Figure 3.11 of Appendix I show the types of substratum
along the horizontal transect at every tidal level in all sampling zones. The
relative distribution of different substrata was estimated by categorizing the
substratum types (Gravels & Boulders / Sands / Soft mud) of the ten random
quadrats along the horizontal transect. The distribution of substratum types
varied among tidal levels and sampling zones:
ˇP In
TC1, high percentages of ˇĄGravels and Bouldersˇ¦ (70-80%) were recorded at all
tidal levels. The minor substratum types were 'Sands' (20% at high and low
tidal levels) and 'Soft mud' (10-20% at low and mid tidal levels).
ˇP In
TC2, the major substratum type was ˇĄSandsˇ¦ (60%) at high tidal level followed
by 'Gravels and Boulders' (30%). The substratum types were recorded evenly at
mid tidal level ('Soft mud' 40%, 'Sands' 30%, 'Gravels and Boulders' 30%). At
low tidal level, the major substratum type was 'Soft mud' (70%) followed by
'Gravels and Boulders' (20%)
ˇP In
TC3, high percentages of ˇĄSandsˇ¦ (90-100%) were recorded at high and mid tidal
levels. At low tidal level, the major substratum type was ˇĄGravels and
Bouldersˇ¦ (90%).
ˇP In ST,
high percentages of ˇĄGravels and Bouldersˇ¦ (80-100%) were recorded at high and
mid tidal levels. At low tidal level, the substratum types were recorded evenly
('Sands' 40%, 'Soft mud' 30%, 'Gravels and Boulders' 30%).
6.5.39 There was neither consistent
vertical nor horizontal zonation pattern of substratum type in all sampling
zones. Such heterogeneous variation should be caused by different hydrology
(e.g. wave in different direction and intensity) received by the four sampling
zones.
6.5.40 Table 3.4 of Appendix I lists the total abundance,
density and number of taxon of every phylum in this survey. A total of 16420
individuals were recorded. Mollusca was clearly the most abundant phylum (total
abundance 15648 ind., density 522 ind. m-2, relative abundance
95.3%). The second and third abundant phyla were Arthropoda (578 ind., 19 ind.
m-2, 3.5%) and Annelida (91 ind., 3 ind. m-2, 0.6%)
respectively. Relatively other phyla were very low in abundances (density ≤1
ind. m-2, relative abundance ≤0.2%). Moreover, the most diverse
phylum was Mollusca (40 taxa) followed by Arthropoda (14 taxa) and Annelida (11
taxa). There were 1-3 taxa recorded only for other phyla. The taxonomic
resolution and complete list of collected specimens are shown in Appendix IV
and V respectively.
6.5.41 Table 3.5 of Appendix I shows the number of individual,
relative abundance and density of each phylum in every sampling zone. The total
abundance (2830-5517 ind.) varied among the four sampling zones while the phyla
distributions were similar. In general, Mollusca was the most dominant phylum
(no. of individuals: 2589-5336 ind.; relative abundance 91.5-97.0%; density
345-711 ind. m-2). Other phyla were much lower in number of
individuals. Arthropoda was the second abundant phylum (119-172 ind.; 2.2-5.8%;
16-23 ind. m-2). Annelida was the third abundant phylum in TC2 and
TC3 (33-40 ind.; 0.6-1.4%; 4-5 ind. m-2). Nemertea was relatively
common in TC2 (17 ind.; 0.6%; 2 ind. m-2). Relatively other phyla
were low in abundance in all sampling zones (≤ 0.5%).
Dominant species in every sampling zone
6.5.42
Table 3.6 of Appendix I lists the abundant species (relative abundance >10%) in every
sampling zone. In the present survey, most of the listed abundant species were
of low to moderate densities (50-250 ind. m-2). Few listed species
of high or very high density (> 250 ind. m-2) were regarded as dominant
species. Other listed species of lower density (< 50 ind. m-2)
were regarded as common species.
6.5.43
In TC1, the major substratum was ˇĄGravels and Bouldersˇ¦ at all tidal
levels. The most abundant gastropod was Batillaria
multiformis at moderate-high densities (248-291 ind. m-2,
relative abundance 35-50%) at high and mid tidal levels. Another abundant
gastropod Cerithidea djadjariensis
was at moderate densities (84-155 ind. m-2, 12-26%) at all tidal
levels. Gastropod Monodonta labio
(138-209 ind. m-2, 24-29%) and rock oyster Saccostrea cucullata (78-104 ind. m-2, 11-18%, attached
on boulders) were at moderate densities at mid and low tidal levels.
6.5.44
In TC2, gastropod Cerithidea
djadjariensis (297 ind. m-2, 60 %) was abundant at moderate-high
density at high tidal level (major substratum: 'Sands') followed by common
gastropod Batillaria multiformis (50 ind.
m-2, 10 %). Moreover, gastropod Cerithidea
djadjariensis was also abundant at moderate density (164 ind. m-2,
42 %) at mid tidal level (major substrata: 'Sands' and 'Soft mud') with common
gastropod Batillaria zonalis (64 ind.
m-2, 16 %) and rock oyster Saccostrea
cucullata (44 ind. m-2, 11 %). There was no clearly abundant species at low
tidal level (major substratum: 'Soft mud'). There were few common taxa at
low-moderate densities such as gastropods Cerithidea
djadjariensis (62 ind. m-2, 25 %), Batillaria zonalis (39 ind. m-2, 16 %), rock oyster Saccostrea cucullata (49 ind. m-2,
20 %) and barnacle Balanus amphitrite
(38 ind. m-2, 15 %, attached on boulders).
6.5.45
In TC3, the major
substratum was ˇĄSandsˇ¦ at both high and mid tidal levels. Gastropod Cerithidea
djadjariensis was dominant species of high densities (412-444 ind. m-2,
53-57 %) followed by two abundant gastropods Batillaria multiformis
(142-185 ind. m-2, 18-24 %) and Cerithidea cingulata (98-130
ind. m-2, 13-17 %). At low tidal level (major substratum: ˇĄGravels
and Bouldersˇ¦), rock oyster Saccostrea cucullata (265 ind. m-2,
40%) and gastropod Monodonta labio (194 ind. m-2, 30%) were
abundant at moderate densities.
6.5.46
In ST, gastropod Batillaria
multiformis was abundant at moderate density (207 ind. m-2, 35
%) followed by Monodonta labio (143
ind. m-2, 24 %) and limpet Cellana
toreuma (97 ind. m-2, 16 %) at high tidal level (major
substratum: ˇĄGravels and Bouldersˇ¦). At mid tidal level (major substratum:
ˇĄGravels and Bouldersˇ¦), there were gastropods Monodonta labio (90 ind. m-2, 18 %), Cerithidea djadjariensis (82 ind. m-2,
16 %) and rock oyster Saccostrea
cucullata (88 ind. m-2, 18%) at low-moderate densities. No
single species was clearly abundant at low tidal level (major substrata:
ˇĄSandsˇ¦ and ˇĄSoft mudˇ¦). The gastropod Cerithidea
djadjariensis was at low-moderate density (75 ind. m-2, 28 %)
followed by common gastropod Lunella
coronata (42 ind. m-2, 16%) and rock oyster Saccostrea cucullata (37 ind. m-2, 14%).
6.5.47
In general, there was no consistent zonation pattern of species
distribution across all sampling zones and tidal levels. The species
distribution should be determined by the type of substratum primarily. In
general, gastropods Cerithidea
djadjariensis (total number of individuals: 4746 ind., relative abundance
28.9%), Batillaria multiformis (3076
ind., 18.7%), Cerithidea cingulata
(1015 ind., 6.2%) and Batillaria zonalis
(519 ind., 3.2%) were the most commonly occurring species on sandy and soft mud
substrata. Rock oyster Saccostrea
cucullata (1887 ind., 11.5%), gastropods Monodonta labio (2181 ind., 13.3%) and Lunella coronata (473 ind., 2.9%) were commonly occurring species
inhabiting gravel and boulders substratum.
Biodiversity and abundance of soft shore communities
6.5.48 Table 3.7 of Appendix
I shows
the mean values of species number, density, biodiversity index Hˇ¦ and species evenness J of soft shore communities at every
tidal level and in every sampling zone. As mentioned above, the differences
among sampling zones and tidal levels were determined by the major type of
substratum primarily.
6.5.49 Among the sampling zones, the mean species numbers (10-12 spp. 0.25 m-2)
and J (0.6-0.7) were similar. The
mean densities of TC1 and TC3 (625-736 ind. m-2) were higher than
TC2 and ST (377-451 ind. m-2). Due to different density, the mean Hˇ¦ of ST (1.7) was higher than that of
TC1, TC2 (1.5) and TC3 (1.2).
6.5.50 Across the tidal levels, there was no consistent difference of the mean
species number and H' in all sampling
zones. For the mean density, there were generally decreasing trends in TC2, TC3
and ST from high to low tidal level. For the mean J, there was a slightly increasing trend from high to low tidal
level in all sampling zones.
6.5.51 Figures 3.12-3.15 of Appendix I show the temporal changes of mean species number, mean density, Hˇ¦ and J at every tidal level and in every sampling zone along the
sampling months. In general, all the biological parameters fluctuated
seasonally throughout the monitoring period. Lower mean species number and
density were recorded in dry season (Dec.) but the mean H' and J fluctuated
within a stable range.
6.5.52 Focusing on the changes of mean density in ST, there were steady
decreasing trends regardless of tidal levels since the beginning of monitoring
period. It might be an unfavourable change that reflected environmental
stresses. However, the mean densities increased again from Dec. 2016 to Jun.
2017 (present survey). The faunal populations were believed in recovery.
Impact
of the HKLR project
6.5.53 It was
the 19th survey of the EM&A programme during the construction
period. Based on the results, impacts of the HKLR project were not detected on
intertidal soft shore community. In case of other abnormal phenomena (e.g.
rapid or consistent decline of fauna densities and species number) are observed,
it would be reported as soon as possible.
6.6.1 Chan,
K.K., Caley, K.J., 2003. Sandy Shores, Hong Kong Field Guides 4. The Department
of Ecology & Biodiversity, The University of Hong Kong. pp 117.
6.6.2 Dai,
A.Y., Yang, S.L., 1991. Crabs of the China Seas. China Ocean Press. Beijing.
6.6.3 Dong,
Y.M., 1991. Fauna of ZheJiang Crustacea. Zhejiang Science and Technology
Publishing House. ZheJiang.
6.6.4 EPD,
1997. Technical Memorandum on Environmental Impact Assessment Process (1st
edition). Environmental Protection Department, HKSAR Government.
6.6.5 Fauchald,
K., 1977. The polychaete worms. Definitions and keys to the orders, families
and genera. Natural History Museum of Los Angeles County, Science Series 28.
Los Angeles, U.S.A..
6.6.6 Fong,
C.W., 1998. Distribution of Hong Kong seagrasses. In: Porcupine! No. 18. The School of Biological Sciences, The
University of Hong Kong, in collaboration with Kadoorie Farm & Botanic
Garden Fauna Conservation Department, p10-12.
6.6.7 Li,
H.Y., 2008. The Conservation of Horseshoe Crabs in Hong Kong. MPhil Thesis,
City University of Hong Kong, pp 277.
6.6.8 Longstaff,
B.J., Dennison, W.C., 1999. Seagrass survival during pulsed turbidity events:
the effects of light deprivation on the seagrasses Halodule pinifolia and Halophila
ovalis. Aquatic Botany 65 (1-4), 105-121.
6.6.9 Longstaff,
B.J., Loneragan, N.R., Oˇ¦Donohue, M.J., Dennison, W.C., 1999. Effects of light
deprivation on the survival and recovery of the seagrass Halophila ovalis (R. Br.) Hook. Journal of Experimental Marine
Biology and Ecology 234 (1), 1-27.
6.6.10 Nakaoka,
M., Aioi, K., 1999. Growth of seagrass Halophila
ovalis at dugong trails compared to existing within-patch variation in a
Thailand intertidal flat. Marine Ecology Progress Series 184, 97-103.
6.6.11 Pielou,
E.C., 1966. Shannonˇ¦s formula as a measure of species diversity: its use and
misuse. American Naturalist 100, 463-465.
6.6.12 Qi,
Z.Y., 2004. Seashells of China. China Ocean Press. Beijing, China.
6.6.13 Qin,
H., Chiu, H., Morton, B., 1998. Nursery beaches for Horseshoe Crabs in Hong
Kong. In: Porcupine! No. 18. The School of Biological Sciences, The University
of Hong Kong, in collaboration with Kadoorie Farm & Botanic Garden Fauna
Conservation Department, p9-10.
6.6.14 Shannon,
C.E., Weaver, W., 1963. The Mathematical Theory of Communication. Urbana:
University of Illinois Press, USA.
6.6.15 Shin,
P.K.S., Li, H.Y., Cheung, S.G., 2009. Horseshoe Crabs in Hong Kong: Current
Population Status and Human Exploitation. Biology and Conservation of Horseshoe
Crabs (part 2), 347-360.
6.6.16 Supanwanid,
C., 1996. Recovery of the seagrass Halophila
ovalis after grazing by dugong. In: Kuo, J., Philips, R.C., Walker, D.I.,
Kirkman, H. (eds), Seagrass biology: Proc Int workshop, Rottenest Island,
Western Australia. Faculty of Science, The University of Western Australia,
Nedlands, 315-318.
6.6.17 Vermaat,
J.E., Agawin, N.S.R., Duarte, C.M., Fortes, M.D., Marba. N., Uri, J.S., 1995.
Meadow maintenance, growth and productivity of a mixed Philippine seagrass bed.
Marine Ecology Progress Series 124, 215-225.
6.6.18 Yang,
D.J, Sun, R.P., 1988. Polychaetous annelids commonly seen from the Chinese
waters (Chinese version). China Agriculture Press, China.
7.1.1
Site Inspections were carried out on a weekly basis to monitor the
implementation of proper environmental pollution control and mitigation
measures for the Project. During the reporting month, five site inspections
were carried out on 1, 7 14, 21 and 30 June 2017.
7.1.2 A summary of observations
found during the site inspections and the follow up actions taken by the Contractor are described in Table 7.1.
Table 7.1 Summary
of Environmental Site Inspections
Date of Audit
|
Observations
|
Actions Taken by
Contractor / Recommendation
|
Date of Observations
Closed
|
26 May 2017
|
1.
Waste was observed at S25.
2. Oil
stain was observed on the ground of S25.
3. Stagnant
water was observed at S25.
4. Waste
accumulated was observed at S25.
5. Silt
curtain with gap was observed at Portion X.
|
1.
The
waste was removed from S25.
2.
The
oil stain was removed from the ground of S25.
3.
The
stagnant water was removed from S25.
4.
The
accumulated waste was removed at S25.
5.
The
silt curtain was properly maintained at Portion X.
|
1 Jun 2017
|
1 Jun 2017
|
1. Waste was observed at HMA.
2. Waste was scattered on the ground at N26.
3. Gaps of silt curtain were observed at Portion X.
4. Concrete waste was observed on the ground at S15.
5. A skip was overloaded with waste at S15.
|
1.
The
waste was removed from HMA.
2.
The
waste was removed from N26.
3.
The
gaps of silt curtain were closed at Portion X.
4.
The
concrete waste was removed from S15.
5.
The
waste was removed from S15.
|
7 Jun 2017
|
7 Jun 2017
|
1. Concrete waste was observed at S15.
2. Gaps of silt curtain were observed at Portion X.
3. A skip was overloaded with waste at S15.
4. Dust emission was observed during vehicle movement at S25.
5. Waste was observed at N1.
|
1.
The concrete waste was removed from S15.
2.
The gaps of silt curtain were closed at
Portion X.
3.
The waste was removed from the overloaded
skip at S15.
4.
Water spraying was provided to suppress
dust emission caused by vehicle movement S25.
5. The waste was removed from N1.
|
14 Jun 2017
|
14 Jun 2017
|
1.
Exposed soil surface was observed
at N1.
2.
Gaps of silt curtain were
observed at Portion X.
3.
Wheels of dump truck was not
washed sufficiently and muddy tracks were observed at the entrance / exit of
S8.
4.
Waste was accumulated in Ventilation
Building.
5. Stockpile of dusty material was not covered properly at N1.
|
1.
The exposed soil surface was hard-paved at
N1.
2.
The gaps of silt curtain were closed at
Portion X.
3.
Sufficient wheel washing was provided for
dump trucks before leaving the site at S8. No muddy track was observed at the
entrance / exit of S8.
4.
The accumulated waste was removed from
Ventilation Building.
5.
The stockpile of dusty material was cover
properly at N1.
|
21 Jun 2017
|
21 Jun 2017
|
1.
Waste was observed at N1.
2.
Stagnant water was observed at
HMA.
3.
More than 20 bags of cement were
observed without properly cover at HMA.
4.
Gaps of silt curtain were observed at
Portion X.
|
1.
The waste was removed from N1.
2.
The stagnant water was removed from HMA.
3.
The cement bags were removed from HMA.
4.
The gaps of silt curtain were closed at
Portion X.
|
30 Jun 2017
|
30 Jun 2017
|
1.
Silt curtain with gap was
observed at Portion X.
2.
Oil drum was observed without
drip tray at N26.
3.
Concrete waste was observed at
N26.
4.
Wastewater treatment facility was not
connected properly at N26.
5.
Waste was not properly collected by using
waste separation facilities at N26.
6.
Stagnant water was observed at N26.
7.
Inadequate wheel washing facility was
observed at N26.
|
The Contractor
was recommended to:
1. Maintain the silt curtain
properly at Portion X.
2.
Provide drip
tray for the oil drum or remove it immediately from N26.
3.
Remove the
concrete waste from N26.
4.
Connect the
wastewater treatment facility properly at N26.
5.
Provide waste
separation facilities at N26.
6.
Remove the
stagnant water at N26.
7. Provide adequate wheel washing
facility at N26.
|
Follow-up actions for the observations
issued for the last weekly site inspection of the reporting month will be
inspected during the next site inspections
|
7.1.3 The Contractor has
rectified most of the observations as identified during environmental site
inspections within the reporting month. Follow-up actions for outstanding
observations will be inspected during the next site inspections.
7.2
Advice on the Solid and Liquid Waste Management
Status
7.2.1 The Contractor
registered as a chemical waste producer for the Project. Sufficient numbers of
receptacles were available for general refuse collection and sorting.
7.2.2
Monthly summary of waste flow table is detailed in Appendix J.
7.2.3 The Contractor was reminded that
chemical waste containers should be properly treated and stored temporarily in
designated chemical waste storage area on site in accordance with the Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes.
7.3.1 The valid environmental
licenses and permits during the reporting month are summarized in Appendix L.
7.4
Implementation
Status of Environmental Mitigation Measures
7.4.1 In response to the
site audit findings, the Contractors have rectified most of the observations as identified during environmental site
inspections during the reporting month. Follow-up actions for outstanding
observations will be inspected during the next site inspections.
7.4.2 A summary of the
Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented
in Appendix M. Most of the
necessary mitigation measures were implemented properly.
7.4.3 Regular marine travel route for
marine vessels were implemented properly in accordance to the submitted plan
and relevant records were kept properly.
7.4.4 Dolphin Watching Plan was
implemented during the reporting month. No dolphins inside the silt curtain
were observed. The relevant records were kept properly.
7.5.1 No Action and Limit Level exceedances of 1-hr TSP
and 24-hr TSP were recorded at AMS5 and AMS6 during the reporting month.
7.5.2 For construction noise, no Action
and Limit Level exceedances were recorded at the monitoring station during the
reporting month.
7.5.1 For marine water quality
monitoring, no Action Level and Limit Level
exceedances of dissolved oxygen, turbidity and suspended solid levels were recorded by
the ET of Contract No. HY/2010/02 and Contract No. HY/2011/09 during the reporting month.
7.6
Summary of Complaints, Notification of Summons and Successful
Prosecution
7.6.1
For Environmental Complaint No. COM-2017-095(3) mentioned in previously
Monthly EM&A Report for May 2017, it was considered that the complaint was
likely related to Contract No. HY/2011/03. The Contractor has implemented the
following measures to minimize the potential noise impact:
-
Additional noise barriers have been erected in
the active working area to further mitigate the associated noise emissions as
far as practicable;
-
Cover the breaker tip with acoustic material;
-
Noise barriers have been located as close as
possible to the noise source. Also, gaps and openings at joints in the barriers
material have been minimized;
-
Speed up of construction works in order to
shorten the duration noise impact/nuisance to the surrounding;
-
Minimize the quantities of noisy plant as far
as practicable; and
-
Regular review of working duration and switch
off all unnecessary machinery and plant.
7.6.2
There was no complaint received in relation to the environmental impacts
during the reporting period.
7.6.3 There was no complaints received
in relation to the environmental impacts during the reporting month. The details
of cumulative statistics of Environmental Complaints are provided in Appendix K.
7.6.4
No notification of summons and prosecution was
received during the reporting period. Statistics on notifications of summons
and successful
prosecutions are summarized in Appendix N.
8.1.1 As informed by the Contractor, the major construction
activities for July 2017 are summarized in Table
8.1.
Table 8.1 Construction
Activities for July 2017
Site Area
|
Description
of Activities
|
WA7
|
Stockpiling
|
Portion X
|
Removal of toe loading
|
Portion X
|
Dismantling/Trimming of
Temporary 40mm Stone Platform for Construction of Seawall
|
Portion X
|
Construction of Seawall
|
Portion X
|
Loading and Unloading of
Filling Materials
|
Portion X
|
Backfilling at Scenic
Hill Tunnel (Cut & Cover Tunnel)
|
Portion X
|
Excavation for HKBCF to
Airport Tunnel & Construction of Tunnel Box structure
|
Portion X
|
Excavation for Diversion
of Culvert PR14
|
Airport Road
|
Works for Diversion of
Airport Road
|
Airport Road / Airport
Express Line / East Coast Road
|
Utilities Detection
|
Airport Road / Airport
Express Line/ East Coast Road
|
Establishment of Site
Access
|
Shaft 3 Extension North
Shaft
|
Construction of Tunnel
Box Structure
|
Airport Road
|
Excavation and Lateral
Support Works & Construction of Tunnel Box Structure for HKBCF to Airport
Tunnel West (Cut & Cover Tunnel)
|
Portion X
|
Excavation and Lateral
Support Works & Construction of Tunnel Box Structure for HKBCF to Airport
Tunnel East (Cut & Cover Tunnel)
|
Portion X
|
Sub-structure &
Superstructure Works for Highway Operation and Maintenance Area Building
|
West Portal
|
Superstructure Works for
Scenic Hill Tunnel West Portal Ventilation building
|
8.2
Environmental Monitoring Schedule for the
Coming Month
8.2.1 The tentative schedule for
environmental monitoring in July 2017 is provided in Appendix D.
9.1.1
The construction phase and EM&A programme of the
Contract commenced on 17 October 2012. This is the fifty-seventh Monthly
EM&A report for the Contract which summarizes the monitoring results and
audit findings of the EM&A programme during the reporting period from 1 to 30
June 2017.
Air Quality
9.1.2
No Action and
Limit Level exceedances of 1-hr TSP and 24-hr TSP were recorded at AMS5 and
AMS6 during the reporting month.
Noise
9.1.3 For construction
noise, no Action and Limit Level exceedances were recorded at the monitoring
station during the reporting month.
Water Quality
9.1.4 For marine water quality
monitoring, no Action Level and Limit Level
exceedances of dissolved oxygen, turbidity and suspended solid levels were recorded by
the ET of Contract No. HY/2010/02 and Contract No. HY/2011/09 during the reporting month.
Dolphin
9.1.5
During the Juneˇ¦s surveys
of the Chinese White Dolphin, no adverse impact from the activities of this
construction project on Chinese White Dolphins was noticeable from general
observations.
9.1.6
Due to monthly variation in dolphin occurrence within
the study area, it would be more appropriate to draw conclusion on whether any
impacts on dolphins have been detected related to the construction activities
of this project in the quarterly EM&A report, where comparison on
distribution, group size and encounter rates of dolphins between the quarterly
impact monitoring period (June 2017 ˇV August 2017) and baseline monitoring
period (3-month period) will be made.
Mudflat
9.1.7
This measurement result was
generally and relatively higher than the baseline measurement at S1, S2, S3 and
S4. The mudflat level is continuously increased.
9.1.8 The June 2017 survey results
indicate that the impacts of the HKLR project could not
be detected on horseshoe crabs and intertidal soft shore community. There
was clear recolonization of both seagrass species Halophila ovalis and Zostera
japonica in ST. Hence, the negative impact of HKLR project on the seagrass
was not significant.
Environmental Site
Inspection and Audit
9.1.9
Environmental site inspections were carried out on 1, 7, 14, 21 and 30 June
2017. Recommendations on remedial actions were given to the Contractors for the
deficiencies identified during the site inspections.
9.1.10
For Environmental Complaint No. COM-2017-095(3) mentioned in previously
Monthly EM&A Report for May 2017, it was considered that the complaint was
likely related to Contract No. HY/2011/03.
9.1.11
There was no received in relation to the environmental impact during the
reporting period.
9.1.12 No notification of summons and prosecution was
received during the reporting period.