Contract No.
HY/2011/03
Hong Kong-Zhuhai-Macao Bridge Hong Kong Link
Road
Section between Scenic Hill and Hong Kong Boundary Crossing
Facilities
Monthly EM&A Report No.58 (Jul 2017)
14 August
2017
Revision
1
Main
Contractor Designer
Contents
Executive Summary
1.4 Construction
Works Undertaken During the Reporting Month
2....... Air Quality Monitoring
2.4 Monitoring
Parameters, Frequency and Duration
2.6 Monitoring
Schedule for the Reporting Month
3.4 Monitoring
Parameters, Frequency and Duration
3.6 Monitoring
Schedule for the Reporting Month
4....... Water
Quality Monitoring
4.3 Monitoring
Parameters, Frequency and Duration
4.6 Monitoring
Schedule for the Reporting Month
6....... Environmental Site
Inspection and Audit
6.2 Advice
on the Solid and Liquid Waste Management Status
6.3 Environmental
Licenses and Permits
6.4 Implementation
Status of Environmental Mitigation Measures
6.5 Summary
of Exceedances of the Environmental Quality Performance Limit
6.6 Summary
of Complaints, Notification of Summons and Successful Prosecution
7.1 Construction
Programme for the Coming Months
7.2 Environmental
Monitoring Schedule for the Coming Month
Figures
Figure 1.1 Location of
the Site
Figure 2.1 Environmental
Monitoring Stations
Appendices
Appendix A Environmental
Management Structure
Appendix B Construction Programme
Appendix C Calibration
Certificates
Appendix D Monitoring Schedule
Appendix E Monitoring Data
and Graphical Plots
Appendix F Event and Action
Plan
Appendix H Dolphin Monitoring
Results
Appendix J Cumulative
Statistics on Complaints
Appendix K Environmental Licenses
and Permits
Appendix L Implementation Schedule
of Environmental Mitigation Measures
Executive
Summary
The Hong Kong-Zhuhai-Macao
Bridge (HZMB) Hong Kong Link Road (HKLR) serves to connect the HZMB Main Bridge
at the Hong Kong Special Administrative Region (HKSAR) Boundary and the HZMB
Hong Kong Boundary Crossing Facilities (HKBCF) located at the north eastern
waters of the Hong Kong International Airport (HKIA).
The HKLR project has been
separated into two contracts. They are Contract No. HY/2011/03 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between Scenic Hill and
Hong Kong Boundary Crossing Facilities (hereafter referred to as the Contract)
and Contract No. HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link
Road-Section between HKSAR Boundary and Scenic Hill.
China State Construction
Engineering (Hong Kong) Ltd. was awarded by Highways Department as the
Contractor to undertake the construction works of Contract No. HY/2011/03. The
main works of the Contract include land tunnel at Scenic Hill, tunnel
underneath Airport Road and Airport Express Line, reclamation and tunnel to the
east coast of the Airport Island, at-grade road connecting to the HKBCF and
highway works of the HKBCF within the Airport Island and in the vicinity of the
HKLR reclamation. The Contract is
part of the HKLR Project and HKBCF Project, these projects are considered to be
ˇ§Designated Projectsˇ¨, under Schedule 2 of the Environmental Impact Assessment
(EIA) Ordinance (Cap 499) and Environmental Impact Assessment (EIA) Reports
(Register No. AEIAR-144/2009 and AEIAR-145/2009) were prepared for the Project. The current Environmental Permit (EP)
EP-352/2009/D for HKLR and EP-353/2009/K for HKBCF were issued on 22 December
2014 and 11 April 2016, respectively. These documents are available through the
EIA Ordinance Register. The construction phase of Contract was commenced on 17 October 2012.
BMT Asia Pacific Limited
has been appointed by the Contractor to implement the Environmental Monitoring
& Audit (EM&A) programme for the Contract in accordance with the
Updated EM&A Manual for HKLR (Version 1.0) and will be providing
environmental team services to the Contract.
This is the fifty-eighth Monthly EM&A report for the Contract which summarizes the monitoring
results and audit findings of the EM&A programme during the reporting
period from 1 to 31 July 2017.
Environmental
Monitoring and Audit Progress
The monthly EM&A
programme was undertaken in accordance with the Updated EM&A Manual for
HKLR (Version 1.0). A summary of
the monitoring activities during this reporting month is listed below:
1-hr TSP Monitoring |
3,
7, 13, 19, 25 and 31 July 2017 |
24-hr TSP Monitoring |
4, 6, 12, 18, 24, 26 and 28 July 2017 |
Noise Monitoring |
3,
13, 19, 25 and 31 July 2017 |
Chinese White Dolphin
Monitoring |
20, 24, 27 and 28 July
2017 |
Site Inspection |
5, 13, 19 and 28 July
2017 |
Due to boat availability,
the dolphin monitoring schedule was rescheduled from 21 July 2017 to 20 July
2017, and from 26 July 2017 to 27 July 2017.
Due to motor failure of
high volume sampler, the 24-hour TSP monitoring at Station AMS5 (Ma Wan Chung
Village) was rescheduled from 24 July 2017 to 26 July 2017.
The monitoring schedule of
water quality monitoring for all stations except station CS2 were adopted from
the published Monthly Environmental Monitoring and Audit (EM&A) Report for July
2017 prepared for Contract No. HY/2010/02 Hong Kong-Zhuhai-Macao Bridge Hong
Kong Boundary Crossing Facilities ˇV Reclamation Works. The monitoring schedule
of water quality monitoring for station CS2 was adopted from the published
Monthly EM&A Report for July 2017 prepared by Contract No. HY/2011/09 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Link Road ˇV Section between HKSAR Boundary
and Scenic Hill.
Breaches of Action and Limit Levels
A summary of environmental
exceedances for this reporting month is as follows:
Environmental Monitoring |
Parameters |
Action Level (AL) |
Limit Level (LL) |
Air Quality |
1-hr TSP |
0 |
0 |
24-hr TSP |
0 |
0 |
|
Noise |
Leq (30 min) |
0 |
0 |
Water Quality |
Suspended solids level (SS) |
2 |
0 |
Turbidity level |
0 |
0 |
|
Dissolved oxygen level (DO) |
0 |
0 |
Complaint Log
There were no complaints
received in relation to the environmental impacts during the reporting period.
Notifications
of Summons and Prosecutions
There were no notifications of summons or
prosecutions received during this reporting month.
Reporting
Changes
This report has been
developed in compliance with the reporting requirements for the subsequent
EM&A reports as required by the Updated EM&A Manual for HKLR (Version
1.0).
The proposal for the change
of Action Level and Limit Level for suspended solid and turbidity was approved
by EPD on 25 March 2013.
The revised Event and
Action Plan for dolphin monitoring was approved by EPD on 6 May
2013.
The original monitoring
station at IS(Mf)9 (Coordinate: 813273E, 818850N) was observed inside the
perimeter silt curtain of Contract HY/2010/02 on 1 July 2013, as such the
original impact water quality monitoring location at IS(Mf)9 was temporarily
shifted outside the silt curtain. As
advised by the Contractor of HY/2010/02 in August 2013, the perimeter silt
curtain was shifted to facilitate safe anchorage zone of construction
barges/vessels until end of 2013 subject to construction progress. Therefore, water quality monitoring
station IS(Mf)9 was shifted to 813226E and 818708N since 1 July 2013. According to the water quality
monitoring teamˇ¦s observation on 24 March 2014, the original monitoring
location of IS(Mf)9 was no longer enclosed by the perimeter silt curtain of
Contract HY/2010/02. Thus, the impact water quality monitoring works at the original
monitoring location of IS(Mf)9 has been resumed since 24 March 2014.
Transect lines 1, 2, 7, 8,
9 and 11 for dolphin monitoring have been revised due to the obstruction of the
permanent structures associated with the construction works of HKLR and the
southern viaduct of TM-CLKL, as well as provision of adequate buffer distance
from the Airport Restricted Areas.
The EPD issued a memo and confirmed that they had no objection on the
revised transect lines on 19 August 2015.
Technical issues have been
observed from impact monitoring of the Contract and thus published information
from Monthly EM&A Report for Jun and July 2017 prepared for Contract No.
HY/2010/02 and Contract No. HY/2011/09 were adopted for the Contract.
Future Key
Issues
The future key issues
include potential noise, air quality, water quality and ecological impacts and
waste management arising from the following construction activities to be
undertaken in the upcoming month:
ˇP
Stockpiling at WA7;
ˇP
Removal of toe
loading at Portion X;
ˇP
Works for Diversion of
Airport Road;
ˇP
Construction of Tunnel Box Structure at Shaft 3 Extension North
Shaft;
ˇP
Superstructure &
Finishing Works for Scenic Hill Tunnel West Portal Ventilation building at West
Portal.
ˇP
New reclamation along
the east coast of the approximately 23 hectares.
ˇP
Tunnel of Scenic Hill
(Tunnel SHT) from Scenic Hill to the new reclamation, of approximately 1km in
length with three (3) lanes for the east bound carriageway heading to the HKBCF
and four (4) lanes for the westbound carriageway heading to the HZMB Main
Bridge.
ˇP
An abutment of the
viaduct portion of the HKLR at the west portal of Tunnel SHT and associated
road works at the west portal of Tunnel SHT.
ˇP
An at grade road on
the new reclamation along the east coast of the HKIA to connect with the HKBCF,
of approximately 1.6 km along dual 3-lane carriageway with hard shoulder for
each bound.
ˇP
Road links between
the HKBCF and the HKIA including new roads and the modification of existing
roads at the HKIA, involving viaducts, at grade roads and a Tunnel HAT.
ˇP
A highway operation
and maintenance area (HMA) located on the new reclamation, south of the
Dragonair Headquarters Building, including the construction of buildings,
connection roads and other associated facilities.
ˇP
Associated civil,
structural, building, geotechnical, marine, environmental protection,
landscaping, drainage and sewerage, tunnel and highway electrical and
mechanical works, together with the installation of street lightings, traffic
aids and sign gantries, water mains and fire hydrants, provision of facilities
for installation of traffic control and surveillance system (TCSS),
reprovisioning works of affected existing facilities, implementation of
transplanting, compensatory planting and protection of existing trees, and
implementation of an environmental monitoring and audit (EM&A) program.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
Supervising Officerˇ¦s Representative |
(Chief Resident Engineer,
CRE) |
Robert Antony Evans |
3968 0801 |
2109 1882 |
Environmental Project
Office / Independent Environmental Checker |
Environmental Project
Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental
Checker |
Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor |
Project Manager |
S. Y. Tse |
3968 7002 |
2109 2588 |
Environmental Officer |
Federick Wong |
3968 7117 |
2109 2588 |
|
Environmental Team |
Environmental Team Leader |
Claudine Lee |
2241 9847 |
2815 3377 |
24 hours complaint hotline |
--- |
--- |
5699 5730 |
--- |
Table 1.2 Construction
Activities During Reporting Month
Description of Activities |
Site Area |
Stockpiling
|
WA7 |
Dismantling/trimming
of temporary 40mm stone platform for construction of seawall |
Portion X |
Construction
of seawall |
Portion X |
Loading
and unloading of filling materials |
Portion X |
Backfilling
at Scenic Hill Tunnel (Cut & Cover Tunnel) |
Portion X |
Excavation for HKBCF to Airport Tunnel &
construction of tunnel box structure |
Portion X |
Excavation
for diversion of culvert PR14 |
Portion X |
Works for diversion |
Airport Road |
Utilities detection |
Airport Road/ Airport
Express Line/ East Coast Road |
Establishment of site access |
Airport Road/ Airport
Express Line/ East Coast Road |
Mined tunnel lining / box jacking transition
zone rebar fixing underneath Airport Road and Airport Express Line |
Airport Road and Airport Express Line |
Construction
of Tunnel box structure |
Shaft 3 Extension North Shaft |
Excavation
and lateral support works & Construction of Tunnel Box Structure for
HKBCF to Airport Tunnel West (Cut & Cover Tunnel) |
Airport Road |
Excavation
and lateral support works & construction of tunnel box structure for
HKBCF to Airport Tunnel East (Cut & Cover Tunnel) |
Portion X |
Sub-structure,
superstructure and finishing works for Highway Operation and Maintenance Area
Building |
Portion X |
Superstructure
& finishing works for Scenic Hill Tunnel West Portal Ventilation building
|
West Portal |
Table 2.1 Action
and Limit Levels for 1-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS 5 ˇV Ma Wan Chung Village (Tung Chung) |
352 |
500 |
AMS 6 ˇV Dragonair / CNAC (Group) Building (HKIA) |
360 |
Table 2.2 Action and
Limit Levels for 24-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS 5 ˇV Ma Wan Chung Village (Tung Chung) |
164 |
260 |
AMS 6 ˇV Dragonair / CNAC (Group) Building (HKIA) |
173 |
260 |
Table 2.3 Air
Quality Monitoring Equipment
Equipment |
Brand and Model |
Portable direct reading dust meter (1-hour
TSP) |
Sibata Digital Dust Monitor (Model No.
LD-3B) |
High Volume Sampler |
Tisch Environmental Mass Flow Controlled
Total Suspended Particulate (TSP) High Volume Air Sampler (Model No. TE-5170) |
Table 2.4 Locations
of Impact Air Quality Monitoring Stations
Monitoring
Station |
Location |
AMS5 |
Ma Wan Chung Village (Tung Chung) |
AMS6 |
Dragonair / CNAC (Group) Building (HKIA) |
Table 2.5 Air
Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency
and Duration |
1-hour TSP |
Three times every 6 days while the highest dust impact was expected |
24-hour TSP |
Once every 6 days |
(a) The HVS was installed in the vicinity of the air sensitive receivers.
The following criteria were considered in the installation of the HVS.
(i) A horizontal platform with appropriate support to secure the sampler
against gusty wind was provided.
(ii) The distance between the HVS and any obstacles, such as buildings, was
at least twice the height that the obstacle protrudes above the HVS.
(iii) A minimum of 2 meters separation from walls, parapets and penthouse for
rooftop sampler was provided.
(iv) No furnace or incinerator flues are nearby.
(v) Airflow around the sampler was unrestricted.
(vi) Permission was obtained to set up the samplers and access to the monitoring
stations.
(vii) A secured supply of electricity was obtained to operate the samplers.
(viii) The sampler was located more than 20 meters from any dripline.
(ix) Any wire fence and gate, required to protect the sampler, did not
obstruct the monitoring process.
(x) Flow control accuracy was kept within ˇÓ2.5% deviation over 24-hour
sampling period.
(b)
Preparation of Filter Papers
(i)
Glass fibre filters, G810 were labelled and sufficient filters that were
clean and without pinholes were selected.
(ii)
All filters were equilibrated in the conditioning environment for 24
hours before weighing. The conditioning environment temperature was around
(iii)
All filter papers were prepared and analysed by ALS Technichem (HK) Pty
Ltd., which is a HOKLAS accredited laboratory and has comprehensive quality
assurance and quality control programmes.
(c)
Field Monitoring
(i) The power supply was checked to ensure the HVS works properly.
(ii) The filter holder and the area surrounding the filter were cleaned.
(iii) The filter holder was removed by loosening the four bolts and a new
filter, with stamped number upward, on a supporting screen was aligned
carefully.
(iv) The filter was properly aligned on the screen so that the gasket formed
an airtight seal on the outer edges of the filter.
(v)
The swing bolts were fastened to hold the filter holder down to the frame. The pressure applied was sufficient to
avoid air leakage at the edges.
(vi) Then the shelter lid was closed and was secured with the aluminium
strip.
(vii) The HVS was warmed-up for about 5 minutes to establish run-temperature
conditions.
(viii) A new flow rate record sheet was set into the flow recorder.
(ix)
On site temperature and atmospheric pressure readings were taken and the
flow rate of the HVS was checked and adjusted at around 1.1 m3/min,
and complied with the range specified in the Updated EM&A Manual for HKLR
(Version 1.0) (i.e. 0.6-1.7 m3/min).
(x) The programmable digital timer was set for a sampling period of 24 hours,
and the starting time, weather condition and the filter number were recorded.
(xi) The initial elapsed time was recorded.
(xii) At the end of sampling, on site temperature and atmospheric pressure
readings were taken and the final flow rate of the HVS was checked and
recorded.
(xiii)
The final elapsed time was recorded.
(xiv)
The sampled filter was removed carefully and folded in half length so
that only surfaces with collected particulate matter were in contact.
(xv)
It was then placed in a clean plastic envelope and sealed.
(xvi) All monitoring information was recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.
(d)
Maintenance and Calibration
(i) The HVS and its accessories were maintained in good working condition,
such as replacing motor brushes routinely and checking electrical wiring to ensure
a continuous power supply.
(ii) 5-point calibration of the HVS was conducted using TE
(iii) Calibration certificate of the HVSs are provided in Appendix
C.
(a) Measuring Procedures
The measuring procedures of
the 1-hour dust meter were in accordance with the Manufacturerˇ¦s Instruction
Manual as follows:-
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the ˇ§TIME SETTINGˇ¨ switch to [BG].
(iv)
Push ˇ§START/STOPˇ¨ switch to perform background measurement for 6
seconds.
(v)
Turn the knob at SENSI ADJ position to insert the light scattering
plate.
(vi)
Leave the equipment for 1 minute upon ˇ§SPAN CHECKˇ¨ is indicated in the
display.
(vii)
Push ˇ§START/STOPˇ¨ switch to perform automatic sensitivity adjustment.
This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE position.
(ix)
Push the ˇ§TIME SETTINGˇ¨ switch the time set in the display to 3 hours.
(x)
Lower down the air collection opening cover.
(xi)
Push ˇ§START/STOPˇ¨ switch to start measurement.
(b) Maintenance
and Calibration
(i) The 1-hour TSP meter
was calibrated at 1-year intervals against a Tisch Environmental Mass Flow
Controlled Total Suspended Particulate (TSP) High Volume Air Sampler.
Calibration certificates of the Laser Dust Monitors are provided in Appendix
C.
Table 2.6 Summary
of 1-hour TSP Monitoring Results During the Reporting Month
Monitoring Station |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AMS5 |
23 |
3 ˇV 97 |
352 |
500 |
AMS6 |
22 |
2 ˇV 93 |
360 |
500 |
Table 2.7 Summary of 24-hour TSP Monitoring Results During the
Reporting Month
Monitoring Station |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AMS5 |
44 |
28 ˇV 54 |
164 |
260 |
AMS6 |
48 |
23 ˇV 118 |
173 |
260 |
Table 3.1 Action
and Limit Levels for Noise during Construction Period
Monitoring Station |
Time Period |
Action Level |
Limit Level |
NMS5 ˇV Ma Wan Chung
Village (Ma Wan Chung Resident Association) (Tung Chung) |
0700-1900 hours on normal
weekdays |
When one documented
complaint is received |
75 dB(A) |
Table 3.2 Noise
Monitoring Equipment
Equipment |
Brand and Model |
Integrated Sound Level
Meter |
B&K 2238 |
Acoustic Calibrator |
B&K 4231 |
Table 3.3 Locations
of Impact Noise Monitoring Stations
Monitoring Station |
Location |
NMS5 |
Ma Wan Chung Village (Ma
Wan Chung Resident Association) (Tung Chung) |
Table 3.4 Noise
Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
30-mins measurement at
each monitoring station between 0700 and 1900 on normal weekdays (Monday to
Saturday). Leq, L10 and L90 would be
recorded. |
At least once per week |
(a) The sound level meter was
set on a tripod at a height of
(b)
The battery condition was
checked to ensure the correct functioning of the meter.
(c)
Parameters such as
frequency weighting, the time weighting and the measurement time were set as
follows:-
(i) frequency weighting:
A
(ii) time weighting: Fast
(iii) time
measurement: Leq(30-minutes) during non-restricted hours i.e. 07:00
ˇV 1900 on normal weekdays
(d)
Prior to and after each
noise measurement, the meter was calibrated using the acoustic calibrator for
94.0 dB(A) at 1000 Hz. If the
difference in the calibration level before and after measurement was more than
1.0 dB(A), the measurement would be considered invalid and repeat of noise
measurement would be required after re-calibration or repair of the equipment.
(e)
During the monitoring
period, the Leq, L10 and L90 were
recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
(f)
Noise measurement was
paused during periods of high intrusive noise (e.g. dog barking, helicopter
noise) if possible. Observations were recorded when intrusive noise was
unavoidable.
(g)
Noise monitoring was
cancelled in the presence of fog, rain, wind with a steady speed exceeding
(a) The microphone head of the sound level
meter was cleaned with soft cloth at regular intervals.
(b) The meter and calibrator
were sent to the supplier or HOKLAS laboratory to check and calibrate at yearly
intervals.
(c) Calibration certificates
of the sound level meters and acoustic calibrators are provided in Appendix C.
Table 3.5 Summary
of Construction Noise Monitoring Results During the Reporting Month
Monitoring Station |
Average Leq (30 mins), dB(A) |
Range of Leq (30 mins), dB(A) |
Limit Level Leq (30 mins), dB(A) |
NMS5 |
58 |
57 ˇV 60 |
75 |
Table 4.1 Action
and Limit Levels for Water Quality
Parameter (unit) |
Water Depth |
Action Level |
Limit Level |
Dissolved Oxygen (mg/L)
(surface, middle and bottom) |
Surface and Middle |
5.0 |
4.2 except 5 for Fish
Culture Zone |
Bottom |
4.7 |
3.6 |
|
Turbidity (NTU) |
Depth average |
27.5 or 120% of upstream
control stationˇ¦s turbidity at the same tide of the same day; The action level has been
amended to ˇ§27.5 and 120% of upstream control stationˇ¦s turbidity at the same
tide of the same dayˇ¨ since 25 March 2013. |
47.0 or 130% of turbidity
at the upstream control station at the same tide of same day; The limit level has been amended
to ˇ§47.0 and 130% of turbidity at the upstream control station at the
same tide of same dayˇ¨ since 25 March 2013. |
Suspended Solid (SS)
(mg/L) |
Depth average |
23.5 or 120% of upstream
control stationˇ¦s SS at the same tide of the same day; The action level has been
amended to ˇ§23.5 and 120% of upstream control stationˇ¦s SS at the same tide of
the same dayˇ¨ since 25 March 2013. |
34.4 or 130% of SS at the
upstream control station at the same tide of same day and 10mg/L for Water
Services Department Seawater Intakes; The limit level has been
amended to ˇ§34.4 and 130% of SS at the upstream control station at the same
tide of same day and 10mg/L for Water Services Department Seawater Intakesˇ¨
since 25 March 2013 |
Notes:
(1)
Depth-averaged
is calculated by taking the arithmetic means of reading of all three depths.
(2)
For DO,
non-compliance of the water quality limit occurs when monitoring result is
lower that the limit.
(3)
For SS &
turbidity non-compliance of the water quality limits occur when monitoring
result is higher than the limits.
(4)
The change to
the Action and limit Levels for Water Quality Monitoring for the EM&A works
was approved by EPD on 25 March 2013.
Table 4.3 Impact
Water Quality Monitoring Parameters and Frequency
Monitoring Stations |
Parameter, unit |
Frequency |
No. of depth |
Impact Stations: Control/Far Field
Stations: Sensitive Receiver
Stations: |
ˇP
Depth, m ˇP
Temperature, oC ˇP
Salinity, ppt ˇP
Dissolved Oxygen
(DO), mg/L ˇP
DO Saturation, % ˇP
Turbidity, NTU ˇP
pH ˇP Suspended Solids (SS), mg/L |
Three times per week
during mid-ebb and mid-flood tides (within ˇÓ 1.75 hour of the predicted time) |
3 (1 m below water surface,
mid-depth and 1 m above sea bed, except where the water depth is less than 6
m, in which case the mid-depth station may be omitted. Should the water depth
be less than 3 m, only the mid-depth station will be monitored). |
Table 4.4 Impact
Water Quality Monitoring Stations
Monitoring Stations |
Description |
Coordinates |
|
Easting |
Northing |
||
IS5 |
Impact Station (Close to
HKLR construction site) |
811579 |
817106 |
IS(Mf)6 |
Impact Station (Close to
HKLR construction site) |
812101 |
817873 |
IS7 |
Impact Station (Close to
HKBCF construction site) |
812244 |
818777 |
IS8 |
Impact Station (Close to
HKBCF construction site) |
814251 |
818412 |
IS(Mf)9 |
Impact Station (Close to
HKBCF construction site) |
813273 |
818850 |
IS10 |
Impact Station (Close to
HKBCF construction site) |
812577 |
820670 |
IS10(N) |
Impact Station (Close to
HKBCF construction site) |
812942 |
820881 |
SR3 |
Sensitive receivers (San
Tau SSSI) |
810525 |
816456 |
SR4 |
Sensitive receivers (Tai
Ho Inlet) |
814760 |
817867 |
SR4(N) |
Sensitive receivers (Tai
Ho Inlet) |
814705 |
817859 |
SR5 |
Sensitive receivers
(Artificial Reef In NE Airport) |
811489 |
820455 |
SR5(N) |
Sensitive receivers
(Artificial Reef In NE Airport) |
812569 |
821475 |
SR10A |
Sensitive receivers (Ma
Wan Fish Culture Zone) |
823741 |
823495 |
SR10B |
Sensitive receivers (Ma
Wan Fish Culture Zone) |
823686 |
823213 |
SR10B(N) |
Sensitive receivers (Ma
Wan Fish Culture Zone) |
823683 |
823187 |
CS2 |
Control Station (Mid-Ebb) |
805849 |
818780 |
CS(Mf)5 |
Control Station
(Mid-Flood) |
817990 |
821129 |
Remarks: 1) Technical
issues have been observed from impact monitoring of the Contract and thus
published informatin from Monthly
EM&A Report for July 2017 prepared
for Contract No. HY/2010/02 and Contract No. HY/2011/09 were adopted for the Contract.
2)
Due to safety concern and topographical condition
of the original locations of SR4 and SR10B, alternative impact water quality
monitoring stations, naming as SR4(N) and SR10B(N), were adopted, which are
situated in vicinity of the original impact water quality monitoring stations
(SR4 and SR10B) and could be reachable.
3)
Due to marine work of the Expansion of Hong Kong
International Airport into a Three-Runway System (3RS Project), original
locations of water quality monitoring stations SR5 and IS10 are enclosed by
works boundary of 3RS Project. Alternative impact water quality monitoring
stations, naming as SR5(N) and IS10(N) was approved in 12 May 2017 and were
adopted starting from 15 May 2017 to replace the original locations of water
quality monitoring for Contract No. HY/2010/02.
|
Table
5.1 Action
and Limit Levels for Dolphin Monitoring
|
North Lantau Social Cluster |
|
NEL |
NWL |
|
Action
Level |
STG < 4.2 & ANI < 15.5 |
STG < 6.9 & ANI <
31.3 |
Limit Level |
(STG < 2.4 & ANI
< 8.9) and (STG < 3.9 & ANI < 17.9) |
Remarks:
1. STG means quarterly encounter rate of number of dolphin sightings.
2. ANI means quarterly encounter rate of total number of dolphins.
3. For North Lantau Social Cluster, AL will be trigger if either NEL or NWL fall below the criteria; LL will
be triggered if both NEL and NWL
fall below the criteria.
Table 5.2 Co-ordinates
of Transect Lines
Line No. |
Easting |
Northing |
|
Line No. |
Easting |
Northing |
||
1 |
Start Point |
804671 |
815456* |
|
13 |
Start Point |
816506 |
819480 |
1 |
End Point |
804671 |
831404 |
|
13 |
End Point |
816506 |
824859 |
2 |
Start Point |
805475 |
815913* |
|
14 |
Start Point |
817537 |
820220 |
2 |
End Point |
805477 |
826654 |
|
14 |
End Point |
817537 |
824613 |
3 |
Start Point |
806464 |
819435 |
|
15 |
Start Point |
818568 |
820735 |
3 |
End Point |
806464 |
822911 |
|
15 |
End Point |
818568 |
824433 |
4 |
Start Point |
807518 |
819771 |
|
16 |
Start Point |
819532 |
821420 |
4 |
End Point |
807518 |
829230 |
|
16 |
End Point |
819532 |
824209 |
5 |
Start Point |
808504 |
820220 |
|
17 |
Start Point |
820451 |
822125 |
5 |
End Point |
808504 |
828602 |
|
17 |
End Point |
820451 |
823671 |
6 |
Start Point |
809490 |
820466 |
|
18 |
Start Point |
821504 |
822371 |
6 |
End Point |
809490 |
825352 |
|
18 |
End Point |
821504 |
823761 |
7 |
Start Point |
810499 |
820880* |
|
19 |
Start Point |
822513 |
823268 |
7 |
End Point |
810499 |
824613 |
|
19 |
End Point |
822513 |
824321 |
8 |
Start Point |
811508 |
821123* |
|
20 |
Start Point |
823477 |
823402 |
8 |
End Point |
811508 |
824254 |
|
20 |
End Point |
823477 |
824613 |
9 |
Start Point |
812516 |
821303* |
|
21 |
Start Point |
805476 |
827081 |
9 |
End Point |
812516 |
824254 |
|
21 |
End Point |
805476 |
830562 |
10 |
Start Point |
813525 |
820872 |
|
22 |
Start Point |
806464 |
824033 |
10 |
End Point |
813525 |
824657 |
|
22 |
End Point |
806464 |
829598 |
11 |
Start Point |
814556 |
818853* |
|
23 |
Start Point |
814559 |
821739 |
11 |
End Point |
814556 |
820992 |
|
23 |
End Point |
814559 |
824768 |
12 |
Start Point |
815542 |
818807 |
|
|
|
|
|
12 |
End Point |
815542 |
824882 |
|
|
|
|
|
Note:
Co-ordinates in red and marked with asterisk are revised co-ordinates of
transect line.
Table 5.3 Individual Survey Event
Encounter Rates
|
Encounter rate (STG) (no. of on-effort dolphin
sightings per 100 km of survey effort) |
Encounter rate (ANI) (no. of dolphins from all
on-effort sightings per 100 km of survey effort) |
|
Primary Lines Only |
Primary Lines Only |
||
NEL |
Set
1: July 20th / 24th |
0.0 |
0.0 |
Set
2: July 27th / 28th |
0.0 |
0.0 |
|
NWL |
Set
1: July 20th / 24th |
1.6 |
14.8 |
Set
2: July 27th / 28th |
0.0 |
0.0 |
Remarks:
1. Dolphin Encounter Rates
Deduced from the Two Sets of Surveys (Two Surveys in Each Set) in July 2017 in
Northeast Lantau (NEL) and Northwest Lantau (NWL).
Table 5.4 Monthly
Average Encounter Rates
|
Encounter rate (STG) (no. of on-effort dolphin
sightings per 100 km of survey effort) |
Encounter rate (ANI) (no. of dolphins from all
on-effort sightings per 100 km of survey effort) |
||
Primary Lines Only |
Both Primary and Secondary Lines |
Primary Lines Only |
Both Primary and Secondary Lines |
|
Northeast Lantau |
0.0 |
0.0 |
0.0 |
0.0 |
Northwest Lantau |
0.8 |
1.2 |
7.3 |
6.6 |
Remarks:
1. Monthly Average Dolphin
Encounter Rates (Sightings Per 100 km of Survey Effort) from All Four Surveys
Conducted in July 2017 on Primary Lines only as well as Both Primary Lines and
Secondary Lines in Northeast Lantau (NEL) and Northwest Lantau (NWL).
Table 6.1 Summary
of Environmental Site Inspections
Date of
Audit |
Observations |
Actions
Taken by Contractor / Recommendation |
Date of
Observations Closed |
30 Jun 2017 |
1. Silt curtain with gap was
observed at Portion X. 2. Oil drum was observed without
drip tray at N26. 3. Concrete waste was observed at
N26. 4. Wastewater treatment facility
was not connected properly at N26. 5. Waste was not properly
collected by using waste separation facilities at N26. 6. Stagnant water was observed at
N26. 7. Inadequate wheel washing
facility was observed at N26. |
1. The silt curtains were
maintained at Portion X. 2. The oil drum was removed from
N26. 3. The concrete waste was removed
from N26. 4. The wastewater treatment
facility was connected and operated properly at N26. 5. The accumulated waste was
removed from N26. 6. Larvicide was applied to the
stagnant water in the H-beam at N26. 7. An improved wheel washing
facility was provided at N26. |
5 Jul 2017 |
5 Jul 2017 |
1. General refuse was observed in
a skip at HAT. 2. Concrete waste was observed on
the ground at HAT. 3. Stagnant water was observed at
S15. 4. Gaps of silt curtain were
observed at Portion X. 5. Waste was observed on the
ground at S9. 6. Waste was observed on the
ground at S15. 7. An oil drum was observed
without drip tray at HAT. 8. Fill cap of water barrier was found missing at WA6. |
1. The general refuse was removed
from HAT. 2. The concrete waste was removed
from the ground at HAT. 3. The stagnant water was removed
from S15. 4. The gaps of silt curtain were
closed at Portion X. 5. The waste was removed from S9. 6. The waste was removed from
S15. 7. The oil drum was removed from
HAT. 8. The water barrier was covered with fill cap at WA6. |
13 Jul 2017 |
13 Jul 2017 |
1. Stagnant water was observed at
N4. 2. Waste was observed at N1. 3. Gaps of silt curtain were
observed at Portion X. 4. Stagnant water was observed at
S9. 5. Stagnant water was observed
inside a pipe at N4. 6. An oil drum was observed
without drip tray at S15. 7. A loaded dump truck was
observed without cover during transport of materials at S16. 8. An oil drum was observed without
drip tray at S25. |
1. The stagnant water was removed
from N4. 2. The waste was removed from N1. 3. The gaps of silt curtain were
closed at Portion X. 4. The stagnant water was removed
from S9. 5. The pipe containing stagnant
water was removed from N4. 6. The oil drum was removed from
S15. 7. The loaded dump truck was
covered by impervious sheeting while it is transporting in S16. 8. The oil drum was removed from
S25. |
19 Jul 2017 |
19 Jul 2017 |
1. Gaps of silt curtain were
observed at Portion X. 2. Rubbish bin was full and waste
was observed on the ground at WA6. 3. Waste was observed at S15. 4. Effluent leaking from a broken
blue hose was observed at S15. 5. Concrete waste was observed in
an undesignated area at S16. 6. Stagnant water was observed at
S16. 7. Waste was observed at
Ventilation Building. |
1. The gaps of silt curtain were
closed at Portion X. 2. The waste was removed from
WA6. 3. The waste was removed from
S15. 4. The broken blue hose was
removed from S15. 5. A designated area was provided
for the temporarily storage of concrete waste at S16. 6. The stagnant water was removed
from S16. 7. The waste was removed from Ventilation Building. |
28 Jul 2017 |
28 Jul 2017 |
1. Waste was observed at Cut &
Cover. 2. Gaps of silt curtain were
observed at Portion X. 3. No proper cover for the stored
cement bags was observed at Ventilation Building. 4. Waste was observed at
Ventilation Building. 5. Stagnant water was observed at Ventilation Building. |
The Contractor was recommended
to: 1. Remove the waste at Cut &
Cover. 2. Close the gaps of silt curtain
at Portion X. 3. Cover the cement bags with properly
at Ventilation Building. 4. Remove the waste at
Ventilation Building. 5. Remove the
stagnant water at Ventilation Building. |
Follow-up actions for the
observations issued for the last weekly site inspection of the reporting
month will be inspected during the next site inspections |
Table 7.1 Construction
Activities for August 2017
Site Area |
Description
of Activities |
WA7 |
Stockpiling |
Portion X |
Removal of toe loading |
Portion X |
Dismantling/Trimming of
Temporary 40mm Stone Platform for Construction of Seawall |
Portion X |
Construction of Seawall |
Portion X |
Loading and Unloading of
Filling Materials |
Portion X |
Backfilling at Scenic
Hill Tunnel (Cut & Cover Tunnel) |
Portion X |
Excavation for HKBCF to
Airport Tunnel & Construction of Tunnel Box structure |
Portion X |
Excavation for Diversion
of Culvert PR14 |
Airport Road |
Works for Diversion of Airport
Road |
Airport Road / Airport
Express Line / East Coast Road |
Utilities Detection |
Airport Road / Airport
Express Line/ East Coast Road |
Establishment of Site
Access |
Shaft 3 Extension North
Shaft |
Construction of Tunnel
Box Structure |
Airport Road |
Excavation and Lateral
Support Works & Construction of Tunnel Box Structure for HKBCF to Airport
Tunnel West (Cut & Cover Tunnel) |
Portion X |
Excavation and Lateral
Support Works & Construction of Tunnel Box Structure for HKBCF to Airport
Tunnel East (Cut & Cover Tunnel) |
Portion X |
Sub-structure, Superstructure
& Finishing works for Highway Operation and Maintenance Area Building |
West Portal |
Superstructure &
Finishing Works for Scenic Hill Tunnel West Portal Ventilation building |