Contract No.
HY/2011/03
Hong Kong-Zhuhai-Macao Bridge Hong Kong Link
Road
Section between Scenic Hill and Hong Kong Boundary Crossing
Facilities
Monthly EM&A Report No.64 (January 2018)
14 January 2018
Revision
1
Main
Contractor Designer
Contents
Executive Summary
1.4 Construction
Works Undertaken During the Reporting Month
2....... Air Quality Monitoring
2.4 Monitoring
Parameters, Frequency and Duration
2.6 Monitoring
Schedule for the Reporting Month
3.4 Monitoring
Parameters, Frequency and Duration
3.6 Monitoring
Schedule for the Reporting Month
4....... Water
Quality Monitoring
4.3 Monitoring
Parameters, Frequency and Duration
4.6 Monitoring
Schedule for the Reporting Month
6....... Environmental Site
Inspection and Audit
6.2 Advice
on the Solid and Liquid Waste Management Status
6.3 Environmental
Licenses and Permits
6.4 Implementation
Status of Environmental Mitigation Measures
6.5 Summary
of Exceedances of the Environmental Quality Performance Limit
6.6 Summary
of Complaints, Notification of Summons and Successful Prosecution
7.1 Construction
Programme for the Coming Months
7.2 Environmental
Monitoring Schedule for the Coming Month
Figures
Figure 1.1 Location of the
Site
Figure 2.1 Environmental
Monitoring Stations
Appendices
Appendix A Environmental
Management Structure
Appendix B Construction Programme
Appendix C Calibration Certificates
Appendix D Monitoring Schedule
Appendix E Monitoring Data and
Graphical Plots
Appendix F Event and Action Plan
Appendix G Wind
Data
Appendix H Dolphin Monitoring Results
Appendix I Waste
Flow Table
Appendix J Cumulative Statistics
on Complaints
Appendix K Environmental Licenses
and Permits
Appendix L Implementation Schedule of
Environmental Mitigation Measures
Appendix M Record of ¡§Notification of
Environmental Quality Limit Exceedances¡¨ and Record of ¡§Notification of Summons
and Prosecutions¡¨
Appendix N Location of Works Areas
Executive
Summary
The Hong Kong-Zhuhai-Macao
Bridge (HZMB) Hong Kong Link Road (HKLR) serves to connect the HZMB Main Bridge
at the Hong Kong Special Administrative Region (HKSAR) Boundary and the HZMB
Hong Kong Boundary Crossing Facilities (HKBCF) located at the north eastern
waters of the Hong Kong International Airport (HKIA).
The HKLR project has been
separated into two contracts. They are Contract No. HY/2011/03 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between Scenic Hill and
Hong Kong Boundary Crossing Facilities (hereafter referred to as the Contract)
and Contract No. HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link
Road-Section between HKSAR Boundary and Scenic Hill.
China State Construction
Engineering (Hong Kong) Ltd. was awarded by Highways Department as the
Contractor to undertake the construction works of Contract No. HY/2011/03. The main works of the Contract include
land tunnel at Scenic Hill, tunnel underneath Airport Road and Airport Express
Line, reclamation and tunnel to the east coast of the Airport Island, at-grade
road connecting to the HKBCF and highway works of the HKBCF within the Airport
Island and in the vicinity of the HKLR reclamation. The Contract is part of the HKLR Project
and HKBCF Project, these projects are considered to be ¡§Designated Projects¡¨,
under Schedule 2 of the Environmental Impact Assessment (EIA) Ordinance (Cap
499) and Environmental Impact Assessment (EIA) Reports (Register No.
AEIAR-144/2009 and AEIAR-145/2009) were prepared for the Project. The current Environmental Permit (EP)
EP-352/2009/D for HKLR and EP-353/2009/K for HKBCF were issued on 22 December
2014 and 11 April 2016, respectively. These documents are available through the
EIA Ordinance Register. The construction phase of Contract was commenced on 17 October 2012.
BMT Asia Pacific Limited
has been appointed by the Contractor to implement the Environmental Monitoring
& Audit (EM&A) programme for the Contract in accordance with the
Updated EM&A Manual for HKLR (Version 1.0) and will be providing
environmental team services to the Contract.
This is the sixty-fourth Monthly EM&A report for the Contract which summarizes the monitoring
results and audit findings of the EM&A programme during the reporting
period from 1 to 31 January 2018.
Environmental
Monitoring and Audit Progress
The monthly EM&A
programme was undertaken in accordance with the Updated EM&A Manual for
HKLR (Version 1.0). A summary of
the monitoring activities during this reporting month is listed below:
1-hr TSP Monitoring |
4,
10, 16, 22 and 26 January 2018 |
24-hr TSP Monitoring at
AMS5 |
3,
9, 15, 19, 25 and 31 January 2018 |
24-hr TSP Monitoring at
AMS6 |
4,
9, 15, 19, 25 and 31 January 2018 |
Noise Monitoring |
4,
10, 16 and 22 January 2018 |
Water Quality Monitoring |
1,
3, 5, 8, 10, 12, 15, 17, 19, 22, 24, 26, 29 and 31 January 2018 |
Chinese White Dolphin
Monitoring |
2,
8, 16 and 25 January 2018 |
Site Inspection |
3
,10, 17 and 26 January 2018 |
Due to power
failure and malfunction of HVS at AMS6 from 29 December 2017 to 3 January 2018,
24-hr TSP monitoring could not be conducted at such period. Competent people
were arranged to check the power supply and repair HVS on 3 and 4 January 2018
respectively. 24-hr TSP monitoring at AMS6 has been resumed on 4 January 2018.
Water quality
monitoring was not conducted at station CS2(A) during mid ebb and mid flood tide
on 8 January 2018 due to rough sea condition and safety concern. Substitute
monitoring was not conducted on 9 January 2018 at station CS2(A) due to rough
sea condition and safety concern.
Due to boat
unavailability, the dolphin monitoring was rescheduled from 22 January 2018 to
25 January 2018.
Due to rough sea condition on 31 January 2018, the
water quality monitoring at Station IS10(N) was temporarily conducted at
coordinate: 812886E, 820855N during mid flood tide while the water quality
monitoring at Station SR5(N) was temporarily conducted at coordinate: 812557E,
821522N during mid flood tide.
Breaches of Action and Limit Levels
A summary of environmental
exceedances for this reporting month is as follows:
Environmental Monitoring |
Parameters |
Action Level (AL) |
Limit Level (LL) |
Air Quality |
1-hr TSP |
5 |
0 |
24-hr TSP |
0 |
0 |
|
Noise |
Leq (30 min) |
0 |
0 |
Water Quality |
Suspended solids level (SS) |
3 |
0 |
Turbidity level |
0 |
0 |
|
Dissolved oxygen level (DO) |
0 |
0 |
Complaint Log
There was one complaint
received in relation to the environmental impacts (Cleanliness problem at East
Coast Road) which was mentioned in previously Monthly EM&A Report for
December 2017. Complaint investigation is being undertaken.
A summary of environmental complaint
for previous reporting month is as follows:
Environmental Complaint No. |
Date of Complaint Received |
Description of Environmental Complaint |
COM-2017-129 |
ENPO¡¦s email to the Supervising Officer¡¦s
Representative and Contractor on 8 January 2018 that HyD received a
complaint lodged by a member of the public regarding cleanliness problem at
East Coast Road on 29 December 2017 |
Cleanliness problem at East Coast Road |
Notifications
of Summons and Prosecutions
There were no
notifications of summons or prosecutions received during this reporting month.
Reporting
Changes
This report has been
developed in compliance with the reporting requirements for the subsequent
EM&A reports as required by the Updated EM&A Manual for HKLR (Version
1.0).
The proposal for the change
of Action Level and Limit Level for suspended solid and turbidity was approved
by EPD on 25 March 2013.
The revised Event and
Action Plan for dolphin monitoring was approved by EPD on 6 May
2013.
The original monitoring
station at IS(Mf)9 (Coordinate: 813273E, 818850N) was observed inside the
perimeter silt curtain of Contract HY/2010/02 on 1 July 2013, as such the
original impact water quality monitoring location at IS(Mf)9 was temporarily
shifted outside the silt curtain. As advised
by the Contractor of HY/2010/02 in August 2013, the perimeter silt curtain was
shifted to facilitate safe anchorage zone of construction barges/vessels until
end of 2013 subject to construction progress. Therefore, water quality monitoring
station IS(Mf)9 was shifted to 813226E and 818708N since 1 July 2013. According to the water quality
monitoring team¡¦s observation on 24 March 2014, the original monitoring
location of IS(Mf)9 was no longer enclosed by the perimeter silt curtain of
Contract HY/2010/02. Thus, the impact water quality monitoring works at the
original monitoring location of IS(Mf)9 has been resumed since 24 March 2014.
Transect lines 1, 2, 7, 8,
9 and 11 for dolphin monitoring have been revised due to the obstruction of the
permanent structures associated with the construction works of HKLR and the
southern viaduct of TM-CLKL, as well as provision of adequate buffer distance
from the Airport Restricted Areas.
The EPD issued a memo and confirmed that they had no objection on the
revised transect lines on 19 August 2015.
The water quality
monitoring stations at IS10 (Coordinate: 812577E, 820670N) and SR5 (811489E,
820455N) are located inside Hong Kong International Airport (HKIA) Approach
Restricted Areas. The previously granted Vessel's Entry Permit for accessing
stations IS10 and SR5 were expired on 31 December 2016. During the permit
renewing process, the water quality monitoring location was shifted to IS10(N)
(Coordinate: 813060E, 820540N) and SR5(N) (Coordinate: 811430E, 820978N) on 2,
4 and 6 January 2017 temporarily. The permit has been granted by Marine
Department on 6 January 2017. Thus, the impact water quality monitoring works
at original monitoring location of IS10 and SR5 has been resumed since 9
January 2017.
Transect lines 2, 3, 4, 5,
6 and 7 for dolphin monitoring have been revised and transect line 24 has been
added due to the presence of a work zone to the north of the airport platform
with intense construction activities in association with the construction of
the third runway expansion for the Hong Kong International Airport. The EPD
issued a memo and confirmed that they had no objection on the revised transect
lines on 28 July 2017. The alternative dolphin transect lines are adopted
starting from August¡¦s dolphin monitoring.
The role and responsibilities as the ET Leader of the Contract was
temporarily taken up by Mr Willie Wong instead of Ms Claudine Lee from 25
September 2017 to 31 December 2017.
The topographical condition of the water monitoring
stations SR3 (Coordinate: 810525E, 816456N), SR4 (Coordinate: 814760E,
817867N), SR10A (Coordinate: 823741E, 823495N) and SR10B (Coordinate: 823686E,
823213N) cannot be accessed safely for undertaking water quality monitoring.
The water quality monitoring has been temporarily conducted at alternative
stations, namely SR3(N) (Coordinate 810689E, 816591N), SR4(N) (Coordinate:
814705E, 817859N) and SR10A(N) (Coordinate: 823644E, 823484N) since 1 September
2017. The water quality monitoring at station SR10B was temporarily conducted
at Coordinate: 823683E, 823187N on 1, 4, 6, 8 September 2017 and has been
temporarily fine-tuned to alternative station SR10B(N2) (Coordinate: 823689E,
823159N) since 11 September 2017. Proposal for permanently relocating the
aforementioned stations was approved by EPD on 8 January 2018.
¡P
The future key issues
include potential noise, air quality, water quality and ecological impacts and
waste management arising from the following construction activities to be
undertaken in the upcoming month:Removal
of toe loading at Portion X
¡P
Works for Diversion of
Airport Road;
¡P
Finishing Works for
Highway Operation and Maintenance Area Building at Portion X; and
¡P
Finishing Works for
Scenic Hill Tunnel West Portal Ventilation building at West Portal.
¡P
New reclamation along
the east coast of the approximately 23 hectares.
¡P
Tunnel of Scenic Hill
(Tunnel SHT) from Scenic Hill to the new reclamation, of approximately 1km in
length with three (3) lanes for the east bound carriageway heading to the HKBCF
and four (4) lanes for the westbound carriageway heading to the HZMB Main
Bridge.
¡P
An abutment of the
viaduct portion of the HKLR at the west portal of Tunnel SHT and associated
road works at the west portal of Tunnel SHT.
¡P
An at grade road on
the new reclamation along the east coast of the HKIA to connect with the HKBCF,
of approximately 1.6 km along dual 3-lane carriageway with hard shoulder for
each bound.
¡P
Road links between
the HKBCF and the HKIA including new roads and the modification of existing
roads at the HKIA, involving viaducts, at grade roads and a Tunnel HAT.
¡P
A highway operation and
maintenance area (HMA) located on the new reclamation, south of the Dragonair
Headquarters Building, including the construction of buildings, connection
roads and other associated facilities.
¡P
Associated civil,
structural, building, geotechnical, marine, environmental protection,
landscaping, drainage and sewerage, tunnel and highway electrical and
mechanical works, together with the installation of street lightings, traffic
aids and sign gantries, water mains and fire hydrants, provision of facilities
for installation of traffic control and surveillance system (TCSS),
reprovisioning works of affected existing facilities, implementation of
transplanting, compensatory planting and protection of existing trees, and
implementation of an environmental monitoring and audit (EM&A) program.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
Supervising
Officer¡¦s Representative |
(Chief Resident Engineer, CRE) |
Robert Antony Evans |
3968 0801 |
2109 1882 |
Environmental Project Office / Independent Environmental Checker |
Environmental Project Office Leader |
Y. H. Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor |
Project Manager |
S. Y. Tse |
3968 7002 |
2109 2588 |
Environmental Officer |
Federick Wong |
3968 7117 |
2109 2588 |
|
Environmental Team |
Environmental Team Leader |
Claudine Lee |
2241 9847 |
2815 3377 |
Environmental Team |
Deputy Environmental Team Leader |
Willie Wong |
2241 9821 |
2815 3377 |
24 hours complaint
hotline |
--- |
--- |
5699 5730 |
--- |
Remark: 1) Ramboll Environ Hong
Kong Limited has
been re-branded as Ramboll Hong Kong Limited
since January 2018. |
Table 1.2 Construction
Activities During Reporting Month
Description of Activities |
Site Area |
Removal
of Stockpiling |
WA7 |
Dismantling/trimming
of temporary 40mm stone platform for construction of seawall |
Portion X |
Construction
of seawall |
Portion X |
Loading
and unloading of filling materials |
Portion X |
Backfilling
at Scenic Hill Tunnel (Cut & Cover Tunnel) |
Portion X |
E&M/ Backfilling/ Bitumen works for HKBCF
to Airport Tunnel (Mined Tunnel) |
Portion X |
Works for diversion |
Airport Road |
Utilities detection |
Airport Road/ Airport
Express Line/ East Coast Road |
Establishment of site access |
Airport Road/ Airport
Express Line/ East Coast Road |
E&M/ Backfilling/ Bitumen works for HKBCF
to Airport Tunnel West (Cut & Cover Tunnel) |
Airport Road |
E&M/ Backfilling/ Bitumen works for HKBCF
to Airport Tunnel East ( Cut & Cover Tunnel) |
Portion X |
Finishing
works for Highway Operation and Maintenance Area Building |
Portion X |
Finishing
works for Scenic Hill Tunnel West Portal Ventilation building |
West Portal |
Table 2.1 Action
and Limit Levels for 1-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS 5 ¡V Ma Wan Chung Village (Tung Chung) |
352 |
500 |
AMS 6 ¡V Dragonair / CNAC (Group) Building (HKIA) |
360 |
Table 2.2 Action and
Limit Levels for 24-hour TSP
Monitoring Station |
Action Level, µg/m3 |
Limit Level, µg/m3 |
AMS 5 ¡V Ma Wan Chung Village (Tung Chung) |
164 |
260 |
AMS 6 ¡V Dragonair / CNAC (Group) Building (HKIA) |
173 |
260 |
Table 2.3 Air
Quality Monitoring Equipment
Equipment |
Brand and Model |
Portable direct reading dust meter (1-hour
TSP) |
Sibata Digital Dust Monitor (Model No.
LD-3B) |
High Volume Sampler |
Tisch Environmental Mass Flow Controlled
Total Suspended Particulate (TSP) High Volume Air Sampler (Model No. TE-5170) |
Table 2.4 Locations
of Impact Air Quality Monitoring Stations
Monitoring
Station |
Location |
AMS5 |
Ma Wan Chung Village (Tung Chung) |
AMS6 |
Dragonair / CNAC (Group) Building (HKIA) |
Table 2.5 Air
Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency
and Duration |
1-hour TSP |
Three times every 6 days while the highest dust impact was expected |
24-hour TSP |
Once every 6 days |
(a) The HVS was installed in the vicinity of the air sensitive receivers.
The following criteria were considered in the installation of the HVS.
(i) A horizontal platform with appropriate support to secure the sampler
against gusty wind was provided.
(ii) The distance between the HVS and any obstacles, such as buildings, was at
least twice the height that the obstacle protrudes above the HVS.
(iii) A minimum of 2 meters separation from walls, parapets and penthouse for
rooftop sampler was provided.
(iv) No furnace or incinerator flues are nearby.
(v) Airflow around the sampler was unrestricted.
(vi) Permission was obtained to set up the samplers and access to the
monitoring stations.
(vii) A secured supply of electricity was obtained to operate the samplers.
(viii) The sampler was located more than 20 meters from any dripline.
(ix) Any wire fence and gate, required to protect the sampler, did not
obstruct the monitoring process.
(x) Flow control accuracy was kept within ¡Ó2.5% deviation over 24-hour
sampling period.
(b)
Preparation of Filter Papers
(i)
Glass fibre filters, G810 were labelled and sufficient filters that were
clean and without pinholes were selected.
(ii)
All filters were equilibrated in the conditioning environment for 24
hours before weighing. The conditioning environment temperature was around
(iii)
All filter papers were prepared and analysed by ALS Technichem (HK) Pty
Ltd., which is a HOKLAS accredited laboratory and has comprehensive quality
assurance and quality control programmes.
(c)
Field Monitoring
(i) The power supply was checked to ensure the HVS works properly.
(ii) The filter holder and the area surrounding the filter were cleaned.
(iii) The filter holder was removed by loosening the four bolts and a new
filter, with stamped number upward, on a supporting screen was aligned
carefully.
(iv) The filter was properly aligned on the screen so that the gasket formed
an airtight seal on the outer edges of the filter.
(v)
The swing bolts were fastened to hold the filter holder down to the
frame. The pressure applied was
sufficient to avoid air leakage at the edges.
(vi) Then the shelter lid was closed and was secured with the aluminium
strip.
(vii) The HVS was warmed-up for about 5 minutes to establish run-temperature
conditions.
(viii) A new flow rate record sheet was set into the flow recorder.
(ix)
On site temperature and atmospheric pressure readings were taken and the
flow rate of the HVS was checked and adjusted at around 1.1 m3/min,
and complied with the range specified in the Updated EM&A Manual for HKLR
(Version 1.0) (i.e. 0.6-1.7 m3/min).
(x) The programmable digital timer was set for a sampling period of 24
hours, and the starting time, weather condition and the filter number were
recorded.
(xi) The initial elapsed time was recorded.
(xii) At the end of sampling, on site temperature and atmospheric pressure
readings were taken and the final flow rate of the HVS was checked and
recorded.
(xiii)
The final elapsed time was recorded.
(xiv)
The sampled filter was removed carefully and folded in half length so
that only surfaces with collected particulate matter were in contact.
(xv)
It was then placed in a clean plastic envelope and sealed.
(xvi) All monitoring information was recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.
(d)
Maintenance and Calibration
(i) The HVS and its accessories were maintained in good working condition,
such as replacing motor brushes routinely and checking electrical wiring to
ensure a continuous power supply.
(ii) 5-point calibration of the HVS was conducted using TE
(iii) Calibration certificate of the HVSs are provided in Appendix C.
(a) Measuring Procedures
The measuring procedures of
the 1-hour dust meter were in accordance with the Manufacturer¡¦s Instruction
Manual as follows:-
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the ¡§TIME SETTING¡¨ switch to [BG].
(iv)
Push ¡§START/STOP¡¨ switch to perform background measurement for 6
seconds.
(v)
Turn the knob at SENSI ADJ position to insert the light scattering
plate.
(vi)
Leave the equipment for 1 minute upon ¡§SPAN CHECK¡¨ is indicated in the
display.
(vii)
Push ¡§START/STOP¡¨ switch to perform automatic sensitivity adjustment.
This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE position.
(ix)
Push the ¡§TIME SETTING¡¨ switch the time set in the display to 3 hours.
(x)
Lower down the air collection opening cover.
(xi)
Push ¡§START/STOP¡¨ switch to start measurement.
(b) Maintenance
and Calibration
(i) The 1-hour TSP meter
was calibrated at 1-year intervals against a Tisch Environmental Mass Flow
Controlled Total Suspended Particulate (TSP) High Volume Air Sampler.
Calibration certificates of the Laser Dust Monitors are provided in Appendix C.
Table 2.6 Summary
of 1-hour TSP Monitoring Results During the Reporting Month
Monitoring Station |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AMS5 |
108 |
16 ¡V 398 |
352 |
500 |
AMS6 |
117 |
15 ¡V 412 |
360 |
500 |
Table 2.7 Summary of 24-hour TSP Monitoring Results During the
Reporting Month
Monitoring Station |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AMS5 |
54 |
44 ¡V 67 |
164 |
260 |
AMS6 |
77 |
62 ¡V 100 |
173 |
260 |
Table 3.1 Action
and Limit Levels for Noise during Construction Period
Monitoring Station |
Time Period |
Action Level |
Limit Level |
NMS5 ¡V Ma Wan Chung
Village (Ma Wan Chung Resident Association) (Tung Chung) |
0700-1900 hours on normal
weekdays |
When one documented
complaint is received |
75 dB(A) |
Table 3.2 Noise
Monitoring Equipment
Equipment |
Brand and Model |
Integrated Sound Level
Meter |
B&K 2238 |
Acoustic Calibrator |
B&K 4231 |
Table 3.3 Locations
of Impact Noise Monitoring Stations
Monitoring Station |
Location |
NMS5 |
Ma Wan Chung Village (Ma
Wan Chung Resident Association) (Tung Chung) |
Table 3.4 Noise
Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
30-mins measurement at each
monitoring station between 0700 and 1900 on normal weekdays (Monday to
Saturday). Leq, L10 and L90 would be
recorded. |
At least once per week |
(a) The sound level meter was
set on a tripod at a height of
(b)
The battery condition was
checked to ensure the correct functioning of the meter.
(c)
Parameters such as
frequency weighting, the time weighting and the measurement time were set as
follows:-
(i) frequency weighting:
A
(ii) time weighting: Fast
(iii) time
measurement: Leq(30-minutes) during non-restricted hours i.e. 07:00
¡V 1900 on normal weekdays
(d)
Prior to and after each
noise measurement, the meter was calibrated using the acoustic calibrator for
94.0 dB(A) at 1000 Hz. If the
difference in the calibration level before and after measurement was more than
1.0 dB(A), the measurement would be considered invalid and repeat of noise
measurement would be required after re-calibration or repair of the equipment.
(e)
During the monitoring
period, the Leq, L10 and L90 were
recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
(f)
Noise measurement was
paused during periods of high intrusive noise (e.g. dog barking, helicopter
noise) if possible. Observations were recorded when intrusive noise was
unavoidable.
(g)
Noise monitoring was
cancelled in the presence of fog, rain, wind with a steady speed exceeding
(a) The microphone head of the sound level
meter was cleaned with soft cloth at regular intervals.
(b) The meter and calibrator
were sent to the supplier or HOKLAS laboratory to check and calibrate at yearly
intervals.
(c) Calibration certificates
of the sound level meters and acoustic calibrators are provided in Appendix C.
Table 3.5 Summary
of Construction Noise Monitoring Results During the Reporting Month
Monitoring Station |
Average Leq (30 mins), dB(A) |
Range of Leq (30 mins), dB(A) |
Limit Level Leq (30 mins), dB(A) |
NMS5 |
58 |
57 ¡V 60 |
75 |
Table 4.1 Action
and Limit Levels for Water Quality
Parameter (unit) |
Water Depth |
Action Level |
Limit Level |
Dissolved Oxygen (mg/L)
(surface, middle and bottom) |
Surface and Middle |
5.0 |
4.2 except 5 for Fish
Culture Zone |
Bottom |
4.7 |
3.6 |
|
Turbidity (NTU) |
Depth average |
27.5 or 120% of upstream
control station¡¦s turbidity at the same tide of the same day; The action level has been
amended to ¡§27.5 and 120% of upstream control station¡¦s turbidity at the same
tide of the same day¡¨ since 25 March 2013. |
47.0 or 130% of turbidity
at the upstream control station at the same tide of same day; The limit level has been
amended to ¡§47.0 and 130% of turbidity at the upstream control station at the
same tide of same day¡¨ since 25 March 2013. |
Suspended Solid (SS)
(mg/L) |
Depth average |
23.5 or 120% of upstream
control station¡¦s SS at the same tide of the same day; The action level has been
amended to ¡§23.5 and 120% of upstream control station¡¦s SS at the same tide of
the same day¡¨ since 25 March 2013. |
34.4 or 130% of SS at the
upstream control station at the same tide of same day and 10mg/L for Water
Services Department Seawater Intakes; The limit level has been
amended to ¡§34.4 and 130% of SS at the upstream control station at the same tide
of same day and 10mg/L for Water Services Department Seawater Intakes¡¨ since
25 March 2013 |
Notes:
(1) Depth-averaged
is calculated by taking the arithmetic means of reading of all three depths.
(2) For DO,
non-compliance of the water quality limit occurs when monitoring result is
lower that the limit.
(3) For SS &
turbidity non-compliance of the water quality limits occur when monitoring
result is higher than the limits.
(4) The change to
the Action and limit Levels for Water Quality Monitoring for the EM&A works
was approved by EPD on 25 March 2013.
Table 4.2 Water
Quality Monitoring Equipment
Equipment |
Brand and Model |
DO and Temperature Meter,
Salinity Meter, Turbidimeter and pH Meter |
YSI Model 6820 |
Positioning Equipment |
JRC DGPS 224 Model
JLR-4341 with J-NAV 500 Model NWZ4551 |
Water Depth Detector |
Eagle Cuda-168 and
Lowrance x-4 |
Water Sampler |
Kahlsio Water Sampler
(Vertical) 2.2 L with messenger |
Table 4.3 Impact
Water Quality Monitoring Parameters and Frequency
Monitoring Stations |
Parameter, unit |
Frequency |
No. of depth |
Impact Stations: Control/Far Field
Stations: Sensitive Receiver
Stations: |
¡P
Depth, m ¡P
Temperature, oC ¡P
Salinity, ppt ¡P
Dissolved Oxygen
(DO), mg/L ¡P
DO Saturation, % ¡P
Turbidity, NTU ¡P
pH ¡P Suspended Solids (SS), mg/L |
Three times per week
during mid-ebb and mid-flood tides (within ¡Ó 1.75 hour of the predicted time) |
3 (1 m below water surface,
mid-depth and 1 m above sea bed, except where the water depth is less than 6
m, in which case the mid-depth station may be omitted. Should the water depth
be less than 3 m, only the mid-depth station will be monitored). |
Table 4.4 Impact
Water Quality Monitoring Stations
Monitoring Stations |
Description |
Coordinates |
|
Easting |
Northing |
||
IS5 |
Impact Station (Close to
HKLR construction site) |
811579 |
817106 |
IS(Mf)6 |
Impact Station (Close to
HKLR construction site) |
812101 |
817873 |
IS7 |
Impact Station (Close to
HKBCF construction site) |
812244 |
818777 |
IS8 |
Impact Station (Close to
HKBCF construction site) |
814251 |
818412 |
IS(Mf)9 |
Impact Station (Close to
HKBCF construction site) |
813273 |
818850 |
IS10(N) |
Impact Station (Close to HKBCF
construction site) |
812942 |
820881 |
SR3 |
Sensitive Receivers (San
Tau SSSI) |
810525 |
816456 |
SR3(N) |
Sensitive receivers (San
Tau SSSI) |
810689 |
816591 |
SR4 |
Sensitive Receivers (Tai
Ho Inlet) |
814760 |
817867 |
SR4(N) |
Sensitive receivers (Tai
Ho Inlet) |
814705 |
817859 |
SR5(N) |
Sensitive Receivers
(Artificial Reef in NE Airport) |
812569 |
821475 |
SR10A |
Sensitive Receivers (Ma
Wan Fish Culture Zone) |
823741 |
823495 |
SR10A(N) |
Sensitive receivers (Ma
Wan Fish Culture Zone) |
823644 |
823484 |
SR10B |
Sensitive Receivers (Ma Wan
Fish Culture Zone) |
823686 |
823213 |
SR10B(N2) |
Sensitive receivers (Ma
Wan Fish Culture Zone) |
823689 |
823159 |
CS2(A) |
Control Station (Mid-Ebb) |
805232 |
818606 |
CS(Mf)5 |
Control Station
(Mid-Flood) |
817990 |
821129 |
Remark: 1) The topographical
condition of four monitoring stations -SR3 (Coordinate: 810525E, 816456N),
SR4 (Coordinate: 814760E, 817867N, SR10A(823741E, 823495N) and
SR10B(Coordinate: 823686E, 823213N ) cannot be accessed safely for
undertaking water quality monitoring. Water quality monitoring has been
conducted at alternative stations, namely SR3(N) (Coordinate: 810689E,
816591N), SR4(N) (Coordinate: 814705E, 817859N), SR10A(N) (Coordinate:
823644E, 823484N) and SR10B(N2) (Coordinate: 823689E, 823159N). Proposal for permanently relocating
the aforementioned stations was approved by EPD on 8 January 2018. 2) Due to rough sea
condition on 31 January 2018, the water quality monitoring at Station IS10(N)
was temporarily conducted at coordinate: 812886E, 820855N during mid flood tide
while the water quality monitoring at Station SR5(N) was temporarily
conducted at coordinate: 812557E, 821522N during mid flood tide. |
(a) The in-situ
water quality parameters including dissolved oxygen, temperature, salinity and
turbidity, pH were measured by multi-parameter meters.
(a) Digital Differential Global Positioning Systems
(DGPS) were used to ensure that the correct location was selected prior to
sample collection.
(b) Portable, battery-operated echo sounders were used
for the determination of water depth at each designated monitoring station.
(c) All in-situ measurements were taken at 3 water
depths, 1 m below water surface, mid-depth and 1 m above sea bed, except where
the water depth was less than 6 m, in which case the mid-depth station was
omitted. Should the water depth be less than 3 m, only the mid-depth station
was monitored.
(d) At each measurement/sampling depth, two consecutive
in-situ monitoring (DO concentration and saturation, temperature, turbidity,
pH, salinity) and water sample for SS. The probes were retrieved out of the
water after the first measurement and then re-deployed for the second
measurement. Where the difference in the value between the first and second
readings of DO or turbidity parameters was more than 25% of the value of the
first reading, the reading was discarded and further readings were taken.
(e) Duplicate samples from each independent sampling
event were collected for SS measurement. Water samples were collected using the
water samplers and the samples were stored in high-density polythene bottles.
Water samples collected were well-mixed in the water sampler prior to
pre-rinsing and transferring to sample bottles. Sample bottles were pre-rinsed
with the same water samples. The sample bottles were then be packed in
cool-boxes (cooled at 4oC without being frozen), and delivered to
ALS Technichem (HK) Pty Ltd. for the analysis of suspended solids
concentrations. The laboratory determination work would be started within 24
hours after collection of the water samples. ALS Technichem (HK) Pty Ltd. is a
HOKLAS accredited laboratory and has comprehensive quality assurance and
quality control programmes.
(f) The analysis method and detection limit for SS is
shown in Table 4.5.
Table 4.5 Laboratory Analysis for Suspended
Solids
Parameters |
Instrumentation |
Analytical Method |
Detection Limit |
Suspended Solid (SS) |
Weighting |
APHA 2540-D |
0.5mg/L |
(g) Other relevant data were recorded, including
monitoring location / position, time, water depth, tidal stages, weather
conditions and any special phenomena or work underway at the construction site
in the field log sheet for information.
Station |
Exceedance Level |
DO (S&M) |
DO (Bottom) |
Turbidity |
SS |
Total number of exceedances |
|||||
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
Ebb |
Flood |
||
IS5 |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
IS(Mf)6 |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
IS7 |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
IS8 |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
8-1-2018 |
22-1-2018 24-1-2018 |
1 |
2 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
IS(Mf)9 |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
IS10(N) |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
SR3/ SR3(N) |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
SR4/ SR4(N) |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
SR5(N) |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
SR10A/ SR10A(N) |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
SR10B/ SR10B(N2) |
Action Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
Limit Level |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
-- |
0 |
0 |
|
Total |
Action |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
2 |
3** |
|
Limit |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0** |
Notes:
S: Surface;
M: Mid-depth;
** The
total number of
exceedances
1) The topographical condition
of four monitoring stations (SR3, SR4, SR10A and SR10B) cannot be accessed
safely for undertaking water quality monitoring. Water quality monitoring has
been conducted at alternative stations, namely SR3(N) (Coordinate: 810689E,
816591N), SR4(N) (Coordinate: 814705E, 817859N), SR10A(N) (Coordinate: 823644E,
823484N) and SR10B(N2) (Coordinate: 823689E, 823159N). Proposal for permanently
relocating the aforementioned stations was approved by EPD on 8 January 2018.
Table
5.1 Action
and Limit Levels for Dolphin Monitoring
|
North Lantau Social Cluster |
|
NEL |
NWL |
|
Action
Level |
STG < 4.2 & ANI < 15.5 |
STG < 6.9 & ANI <
31.3 |
Limit Level |
(STG < 2.4 & ANI
< 8.9) and (STG < 3.9 & ANI < 17.9) |
Remarks:
1. STG means quarterly encounter rate of number of dolphin sightings.
2. ANI means quarterly encounter rate of total number of dolphins.
3. For North Lantau Social Cluster, AL will be trigger if either NEL or NWL fall below the criteria; LL will
be triggered if both NEL and NWL
fall below the criteria.
Table 5.2 Co-ordinates
of Transect Lines
Line No. |
Easting |
Northing |
|
Line No. |
Easting |
Northing |
||
1 |
Start Point |
804671 |
815456 |
|
13 |
Start Point |
816506 |
819480 |
1 |
End Point |
804671 |
831404 |
|
13 |
End Point |
816506 |
824859 |
2 |
Start Point |
805476 |
820800* |
|
14 |
Start Point |
817537 |
820220 |
2 |
End Point |
805476 |
826654 |
|
14 |
End Point |
817537 |
824613 |
3 |
Start Point |
806464 |
821150* |
|
15 |
Start Point |
818568 |
820735 |
3 |
End Point |
806464 |
822911 |
|
15 |
End Point |
818568 |
824433 |
4 |
Start Point |
807518 |
821500* |
|
16 |
Start Point |
819532 |
821420 |
4 |
End Point |
807518 |
829230 |
|
16 |
End Point |
819532 |
824209 |
5 |
Start Point |
808504 |
821850* |
|
17 |
Start Point |
820451 |
822125 |
5 |
End Point |
808504 |
828602 |
|
17 |
End Point |
820451 |
823671 |
6 |
Start Point |
809490 |
822150* |
|
18 |
Start Point |
821504 |
822371 |
6 |
End Point |
809490 |
825352 |
|
18 |
End Point |
821504 |
823761 |
7 |
Start Point |
810499 |
822000* |
|
19 |
Start Point |
822513 |
823268 |
7 |
End Point |
810499 |
824613 |
|
19 |
End Point |
822513 |
824321 |
8 |
Start Point |
811508 |
821123 |
|
20 |
Start Point |
823477 |
823402 |
8 |
End Point |
811508 |
824254 |
|
20 |
End Point |
823477 |
824613 |
9 |
Start Point |
812516 |
821303 |
|
21 |
Start Point |
805476 |
827081 |
9 |
End Point |
812516 |
824254 |
|
21 |
End Point |
805476 |
830562 |
10 |
Start Point |
813525 |
821176 |
|
22 |
Start Point |
806464 |
824033 |
10 |
End Point |
813525 |
824657 |
|
22 |
End Point |
806464 |
829598 |
11 |
Start Point |
814556 |
818853 |
|
23 |
Start Point |
814559 |
821739 |
11 |
End Point |
814556 |
820992 |
|
23 |
End Point |
814559 |
824768 |
12 |
Start Point |
815542 |
818807 |
|
24* |
Start Point |
805476* |
815900* |
12 |
End Point |
815542 |
824882 |
|
24* |
End Point |
805476* |
819100* |
Note:
Co-ordinates in red and marked with asterisk are revised co-ordinates of transect
line.
Table 5.3 Individual
Survey Event Encounter Rates
|
Encounter
rate (STG) (no. of on-effort dolphin sightings per 100
km of survey effort) |
Encounter
rate (ANI) (no. of dolphins from all on-effort
sightings per 100 km of survey effort) |
|
Primary Lines Only |
Primary Lines Only |
||
NEL |
Set
1: January 2nd / 8th |
0.0 |
0.0 |
Set
2: January 16th / 25th |
0.0 |
0.0 |
|
NWL |
Set
1: January 2nd / 8th |
5.7 |
45.4 |
Set
2: January 16th / 25th |
3.4 |
3.4 |
Remark:
1. Dolphin Encounter Rates Deduced from the Two
Sets of Surveys (Two Surveys in Each Set) in January 2018 in Northeast Lantau
(NEL) and Northwest Lantau (NWL).
Table 5.4 Monthly
Average Encounter Rates
|
Encounter rate (STG) (no.
of on-effort dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI) (no.
of dolphins from all on-effort sightings per 100 km of survey effort) |
||
Primary Lines Only |
Both Primary and Secondary Lines |
Primary Lines Only |
Both Primary and Secondary Lines |
|
Northeast
Lantau |
0.0 |
0.0 |
0.0 |
0.0 |
Northwest
Lantau |
4.3 |
3.2 |
19.2 |
14.3 |
Remark:
1.
Monthly Average Dolphin Encounter Rates (Sightings Per 100 km of
Survey Effort) from All Four Surveys Conducted in January 2018 on Primary Lines only as well as Both Primary
Lines and Secondary Lines in Northeast Lantau (NEL) and Northwest Lantau (NWL).
Table 6.1 Summary
of Environmental Site Inspections
Date of Audit |
Observations |
Actions Taken by
Contractor / Recommendation |
Date of Observations
Closed |
30 Dec 2017 |
1. Drip tray was not provided for oil drum at Depressed Roundabout of S16. 2. Access road was appeared dry at N20A. 3. Wheel washing was
observed insufficient at N30. 4. Drip tray was not
provided for chemical containers at N30. 5.
Wheel washing was observed insufficient at S16. 6.
Stagnant water was observed at S16. 7.
No water spraying on stockpile during excavation at
S16. 8.
Waste was observed at S16. 9.
Waste was observed at S15. 10. Waste was observed at
Depressed Roundabout of S16. |
1. The oil drum was removed
from Depressed Roundabout at S16. 2. Water spraying was
provided to the access road at N20A. 3. Wheel washing facilities with high pressure water jet was provided to clean
the vehicles before leaving the work area at N30. 4. The chemical containers were
removed from N30. 5. Wheel washing facilities with high pressure water jet was provided to clean the
of vehicles before leaving the work area at S16. 6. The stagnant water was
removed at S16. 7. The stockpile was removed
at S16. 8. The waste was cleared at
S16. 9. The waste was removed at
S15. 10.
The waste was removed at Depressed Roundabout of
S16. |
3 Jan 2018 |
3 Jan 2018 |
1.
Dust emission was observed during vehicles movement
at N26. 2. Gap of silt curtains was
observed at Portion X. 3. Construction waste was
observed on the ground at N20. 4. Construction waste was
observed on the ground at S15. 5.
Chemical
drums were observed without drip tray at HAT. |
1. Water spraying was
provided at the road of N26 to reduce dust emission. 2. The silt curtains were
maintained at Portion X. 3. The construction waste
was removed from N20. 4. The construction waste
was removed from S15. 5. The chemical drums were
removed from HAT. |
10 Jan 2018 |
10 Jan 2018 |
1.
Wastewater
from the site was not controlled properly to prevent discharge entering into
marine water at S7. 2.
Construction
waste was accumulated on the ground at S15. 3.
Construction
waste was observed at Plant room of S15. 4.
Construction
waste was accumulated on the ground at S9. 5.
Chemical
containers were observed without drip tray at S7. |
1.
Proper bunding were set up to
prevent wastewater from the site entering into marine water at S7. 2.
The construction waste at was
removed from S15. 3.
The construction waste was
removed from Plant Room of S15. 4.
The construction waste was
removed from S9. 5. The chemical
containers were removed from S7. |
17Jan 2018 |
17 Jan 2018 |
1.
Mud
was observed on the paved haul road at N26. 2.
Construction
waste was observed at Plant Room of S15. 3.
Construction
waste was observed at HAT. |
1. Mud was cleared on the paved haul road at N26. 2. The construction waste was removed from Plant Room of S15. 3. The construction waste was removed from HAT. |
26 Jan 2018 |
26 Jan 2018 |
1.
Waste
was observed at HAT. 2.
No drip
tray was provided to chemical containers at HAT. 3.
No
drip tray was provided to chemical containers at S16. 4.
Waste
was observed at S16. 5.
Stagnant
water was observed inside the drip tray next to a generator at S16. 6.
Abandoned
cement bags was observed at S16. |
The Contractor was
recommended to: 1. remove the waste promptly at HAT. 2. provide drip tray for the
chemical containers at HAT. 3. provide drip tray for the
chemical containers at S16. 4. remove the waste promptly at S16. 5. remove stagnant water
from the drip tray next to the generator at S16. 6. remove the abandoned
cement bags at S16. |
Follow-up actions for the observations
issued for the last weekly site inspection of the
reporting month will be inspected during the next site inspection. |
Table 7.1 Construction
Activities for February 2018
Site Area |
Description of
Activities |
Portion X |
Removal of Toe Loading |
Portion X |
Dismantling/Trimming of
Temporary 40mm Stone Platform for Construction of Seawall |
Portion X |
Construction of Seawall |
Portion X |
Loading and Unloading of Filling Materials |
Portion X |
Backfilling at Scenic Hill Tunnel (Cut & Cover Tunnel) |
Portion X |
Excavation for HKBCF to Airport Tunnel & Construction of Tunnel
Box structure |
Airport Road |
Works for Diversion of
Airport Road |
Airport Road / Airport Express Line / East Coast Road |
Utilities Detection |
Airport Road / Airport Express Line/ East Coast Road |
Establishment of Site Access |
Airport Road |
E&M/ Backfilling/
Bitumen works for HKBCF to Airport Tunnel West (Cut & Cover Tunnel) |
Portion X |
E&M/ Backfilling/
Bitumen works for HKBCF to Airport Tunnel East (Cut & Cover Tunnel) |
Portion X |
Finishing works for Highway Operation and Maintenance Area Building |
West Portal |
Finishing Works for Scenic Hill Tunnel West Portal Ventilation
building |