Agreement No. CE 67/2015 (HY)  
Cycle Tracks from Tuen Mun to Sheung Shui Remaining Works Design and  
Construction  
Appendix J Summary of environmental complaint, warning, summon and notification of  
successful prosecution  
Reporting Month: December 2018  
Contract No. YL/2015/01  
Cycle Tracks from Tuen Mun to Sheung Shui Remaining Works  
Details of  
Complaint/warning/summon  
and prosecution  
Log  
Ref.  
Received  
Date  
Investigation/Mitigation  
Action  
Location  
Status  
Increase the  
frequency of water  
spraying on the paved  
roads to minimize the  
dust generation; and  
The complaint is filed against  
extensive dust nuisance by  
construction activities  
Mai Po  
San  
th  
20  
CIR was  
submitted  
1
Tsuen  
Portion  
D)  
December generated sand and dust, and  
Cover the  
(
2018  
may have caused the nearby  
village roads to look dusty and  
unclean.  
temporary cut slopes by  
tarpaulin before any  
excavation works  
commence.  
Mai Po  
San  
Tsuen  
The complaint is filed against  
site effluent being pumped  
December and discharge into the nearby  
surface channel from the same  
construction site.  
st  
21  
Will be updated in the  
next monthly report.  
Under  
Investigation  
2
(Portion  
2018  
D)  
Remarks: Two environmental complaints were received in the reporting period. Both complaints are considered to be  
project related.  