Contents
Executive Summary
1.1 Purpose of the Report
1.2 Structure of the Report
2.1 Background
2.2 Site Description
2.3 Construction Activities
2.4 CONSTRUCTION PROGRAMME
2.5 Project Organisation and Management Structure
2.6 Status of Environmental Approval Documents
3 environmental
monitoring REQUIREMENTS
3.1 Noise Monitoring
3.2 Cultural Heritage
3.3 Landscape and Visual Monitoring
3.4 Environmental Requirements in
Contract Documents
4 Implementation
Status on Environmental MITIGATION MEASURES
5.1 Noise
5.2 Landscape and Visual Monitoring
5.3 Cultural Heritage
5.4 Waste Management
5.5 Effectiveness of Mitigation Measures and Monitoring
6 Environmental
Site Inspection
7 Environmental
Non-conformance
8 REVIEW
OF THE EM&A DATA AND EIA PREDICTIONS
8.1 NOISE
8.2 Waste Management
8.3 Summary of Review
LIST
OF TABLES
Table 2.1 Summary
of Construction Activities undertaken in this Reporting Period
Table 2.2 Summary
of Environmental Licensing, Notification and Permit Status
Table 3.1 Construction
Phase Noise Monitoring Locations
Table 3.2 Noise
Monitoring Equipment
Table 3.3 Action
and Limit Levels for Construction Noise Monitoring
Table 3.4 Alert,
Alarm and Action (AAA) Levels for Vibration Monitoring
Table 3.5 Event and Action Plan for vibration monitoring
Table 4.1 Status of Required Submissions
Table 5.1 Findings
of Monthly Tree Inspection in the Reporting Period
Table 5.2 Summary
of Vibration Monitoring for Other Construction Works
Table 5.3 Quantities
of Waste Generated from the Project
Table 8.1 Comparison
of Construction Noise Standard and Noise Monitoring Results
LIST
OF ANNEXES
Annex
A |
Locations
of Works Areas and the Surroundings |
Annex A1 |
|
Annex A2 |
|
Annex
B |
|
Annex
C |
Locations
of Noise Monitoring Stations and Noise Sensitive Receivers |
Annex
D |
|
Annex
E |
|
Annex
F |
|
Annex
G |
|
Annex
H |
|
Annex
I |
|
Annex
J |
Cumulative
Environmental Complaint, Environmental Summons, Prosecution Log and
Investigation Report for Environmental Enquiry |
Annex J1 |
Cumulative
Environmental Complaint and Summons/Prosecutions Log |
Annex J2 |
|
Annex
K |
Not
Used |
Annex
L |
Records
of Vibration Monitoring for Other Construction Works |
Annex
M |
Summary
of Key Findings of Monthly Cultural Heritage Site Audits, Non-compliance
Reports and Condition of Character Defining Elements, Historic Buildings and
Structures |
Annex M1 |
A Summary of Key Findings
of Monthly Cultural Heritage Site Audits |
Annex M2 |
|
Annex M3 |
A Summary of Condition of
Character Defining Elements, Historic Buildings and Structures |
EXECUTIVE
SUMMARY
The
construction works of Central Police
Station Conservation and Revitalisation Project commenced on 24 October 2011. This is the 6th annual
Environmental Monitoring and Audit (EM&A) review report summarising the
EM&A works carried out during the period from 1 November 2016 and 31 October
2017 in accordance with the EM&A Manual.
Environmental
Monitoring and Audit Progress
A
summary of the monitoring activities undertaken in this reporting period is
listed below:
¡P Construction Noise Monitoring during normal weekdays at
each monitoring station |
66 times |
¡P Joint Environmental Site Inspection |
12 times |
¡P Heritage Site Inspection |
292 times |
¡P Landscape & Visual Monitoring / tree inspection ([1]) |
12 times |
¡P Vibration monitoring for other
construction works
|
292 times |
Noise
66
sets of 30-minute construction noise measurements were carried
out at each of the monitoring stations (NM2 and NM6) during normal weekdays of
the reporting period. No exceedance of the Action
or Limit Level of construction noise was recorded.
Cultural
Heritage
No vibration monitoring was carried out for demolition
works, trial piling or pile/bored piling works as the aforementioned works were
not conducted during the reporting period.
Vibration monitoring carried out for other
construction works during the reporting period are listed below:
¡P
292
vibration monitoring measurements for the structural addition and alteration
works at Block 11.
No exceedance of Alert, Alarm and Action Levels of
vibration was recorded during the reporting period.
292 heritage site inspections were conducted and the
Contractor has generally implemented the necessary protection measures as
recommended.
Landscape
& Visual
Landscape and visual monitoring has commenced
since October 2011 on a monthly basis.
Twelve monthly tree inspections have been conducted by the arborist
during the reporting period. An
ad-hoc joint tree inspection for Tree 6 and Tree 7 was carried out by the
representatives of the arborist, Contractor, IEC, ET, HKJC, EPD and relevant
parties on 8 August 2017. Most
recommended actions have been performed by the Contractor as advised in the
reporting period.
Waste Management
Wastes
generated from this Project include inert construction and demolition (C&D)
materials and non-inert C&D materials.
883.74 tonnes of inert C&D materials and 862.89 tonnes of non-inert
C&D materials were generated during the reporting period. 1,314 kg of paper/cardboard packaging
waste were produced and sent to recyclers for recycling. No metals or plastics waste was recycled during
the reporting period. No chemical
waste was generated and collected by licenced chemical waste collector during
the reporting period.
Environmental Site Inspection
Twelve joint environmental site inspections were
carried out by the representatives of the Contractor, the IEC and the ET during
the reporting period. The
Contractor has generally implemented the mitigation measures as
recommended.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
No
exceedance of the Action or Limit Level of construction noise was recorded at
designated monitoring stations during the reporting period.
No exceedance of the Alert, Alarm and Action Levels
of vibration was recorded during the reporting period.
One enquiry was received during the reporting
period.
No environmental non-compliance
event was recorded during the reporting period. 6 non-compliance events
related to the
character defining elements, historic buildings and structures were recorded
during the reporting period.
No
complaint was received during the reporting period.
No
summons/prosecutions were received in this reporting period.
ERM-Hong Kong, Limited (ERM) was
appointed by the Jockey Club
This is the 6th annual EM&A
review report, which summarises the impact monitoring results and audit
findings for the EM&A programme during the first year of the construction
period from 1 November 2016 to 31 October 2017.
The structure of the report is as
follows:
Section 1 : Introduction
details the scope and
structure of the report.
Section
2 : Project Information
summarises
background and scope of the Project, site description, project organization and
contract details, construction programme, the construction works undertaken and
the status of Environmental Permit(s)/License(s) during the reporting period.
Section 3 : Environmental Monitoring Requirements
summarises
the monitoring parameters, monitoring programmes, monitoring methodologies,
monitoring frequency, monitoring locations, Action and Limit Levels,
Event/Action Plans, environmental mitigation measures as recommended in the EIA
report, and relevant environmental requirements.
Section 4 : Implementation
Status on Environmental Mitigation Measures
summarises
the implementation of environmental protection measures during the reporting
period.
Section 5 : Monitoring
Results
summarises
the monitoring and waste management results obtained in the reporting period.
Section 6 : Environmental
Site Inspection
summarises
the audit findings of the monthly site inspections undertaken within the
reporting period.
Section 7 : Environmental
Non-conformance
summarises
any monitoring exceedance, environmental complaints and environmental summons
received within the reporting period.
Section 8 : Review of the
EM&A Data and EIA Predictions
compares
the monitoring data and waste quantity against predictions in the approved
Project EIA report.
Section
9 : Conclusions
The Chief Executive (CE)¡¦s 2007-2008 Policy Address
highlighted revitalisation as the guiding principle of heritage conservation
and the Project was among one of the specific proposals put forward by the CE
in the same Policy Address. At the
meeting of the Executive Council (ExCo) on 15 July 2008, the ExCo advised and
the CE ordered that Government should enter into a partnership with the Hong
Kong Jockey Club (HKJC) in the form of an agreement (or agreements) to take
forward the conservation and revitalisation of the CPS project based on various
guiding parameters. The Project is now being
undertaken in partnership with the Development Bureau of the HKSAR
Government. The
HKJC has taken on board the decision at the ExCo meeting and further
investigated the design and implementation of the Project. The Project is now implemented by the Jockey
Club CPS Limited.
The location of the Project Site is
shown in Annex A1. The Site is bounded by Hollywood Road to
the north, Arbuthnot Road to the east, Chancery Lane to the south and Old
Bailey Street to the west.
The
Site comprises three Declared Monuments designated under the Antiquities and Monuments Ordinance in
1995. They are:
¡P
Central
Police Station;
¡P
Former
Central Magistracy; and
¡P
Victoria
Prison Compound.
They
are collectively named the Central Police Station (CPS). Annex A2 shows the location of the
Declared Monuments within CPS and the buildings within the CPS.
A
summary of the major construction activities undertaken in this reporting
period is shown in Table 2.1.
Table
2.1 Summary
of Construction Activities undertaken in this Reporting Period
Construction Activities Undertaken |
1st
Quarter |
¡P
Resumption
of works for Block 19 and open ground; ¡P
Hard
landscape construction; ¡P
Timber
elements repair and replacement at Blocks, 1, 2, 3, 6, 7, 9, 14 and 19; ¡P
Metal
works installation at Blocks 8, 9 and 11; ¡P
External
façade repair at Blocks 3, 8, 10, 13, 14 and 17; ¡P
Fitting
out works at Blocks 1, 2, 15, 19, Arbuthnot Wing and Old Bailey Wing; ¡P
E&M
fixing at Blocks 6, 7, 9, 11, 12, 15, Arbuthnot Wing and Old Bailey Wing; and ¡P
Footbridge
construction. |
2nd
Quarter |
¡P
Hard
landscape construction; ¡P
Timber
elements repair and replacement at Blocks 1, 3, 6, 7, 8, 9, 10 and 14; ¡P
Fitting
out works at Blocks 1, 3, 6, 7, 9, 11, 12, 13, 14, 15, 17, Arbuthnot Wing and
Old Bailey Wing; ¡P
Metal
works installation and repair at Blocks 1, 3, 8, 9, 15, 17 and 19; ¡P
External
façade repair at Blocks 3, 8, 9, 10, 11, 13, 14 and 17; ¡P
E&M
fixing at Blocks 1, 2, 3, 6, 7, 8, 9, 12, 13, 14, 15, Arbuthnot Wing and Old
Bailey Wing; ¡P
Footbridge
construction; ¡P
External
staircase construction; and ¡P
Old
Bailey Street staircase construction. |
3rd Quarter |
¡P
Sitewide
hard landscape construction; ¡P
Timber
elements repair and replacement at Blocks 1, 3, 6, 7, 9, 13 and 14; ¡P
Fitting
out works at Blocks 1, 3, 6, 7, 9, 11, 14, 15, 17, Arbuthnot Wing and Old
Bailey Wing; ¡P
Metal
works repair at Blocks 1, 3, 8, 9, 14 and 17; ¡P
External
façade repair at Blocks 3, 9, 10, 11, 12, 13, 14 and 17; ¡P
E&M
fixing at Blocks 1, 3, 6, 7, 9, 12, 13, 14, 15, Arbuthnot Wing and Old Bailey
Wing; ¡P
Footbridge
construction; ¡P
Old
Bailey Street staircase construction; and ¡P
Enhancement
works at Blocks 6 and 7. |
4th Quarter |
¡P
Sitewide
hard landscape construction; ¡P
Timber
elements repair and replacement at Blocks 1, 3, 6, 7, 9, 10 and 14; ¡P
Fitting
out works at Blocks 1, 3, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 17, Arbuthnot
Wing and Old Bailey Wing; ¡P
Metal
works repair at Blocks 1, 3, 8, 9, 10, 12 and 14; ¡P
External
façade repair at Blocks 1, 3, 9, 10, 12, 13, 14, 17 and 19; ¡P
E&M
fixing at Blocks 1, 3, 6, 7, 9, 12, 13, 14, 15, Arbuthnot Wing and Old Bailey
Wing; ¡P
Footbridge
construction; ¡P
Guard
house works construction; and ¡P
Enhancement
works at Blocks 3, 8, 9, 10 and 14. |
The
most updated construction programme for the Project is presented in Annex H.
The Project organization
chart, hotline number and contact details are shown in Annex B.
A
summary of the valid permits, licences, and/or notifications on environmental
protection for this Project within the reporting period is presented in Table 2.2.
Table 2.2 Summary of Environmental
Licensing, Notification and Permit Status
Permit/
Licences/ Notification |
Reference |
Validity
Period |
Remarks |
Environmental Permit (EP) |
EP-408/2011/B |
- |
superseded by EP-408/2011/C |
|
EP-408/2011/C |
Throughout the
Contract |
Permit granted on 29
April 2016 |
Notification of Construction Works as
required under Air Pollution Control
(Construction Dust) Regulation |
Ref. No. 332920 |
Throughout the Contract |
- |
Registration of Chemical Waste Producer under
Waste Disposal Ordinance |
Chemical Waste Producer No.:
5213-122-G2347-25 |
Throughout the Contract |
- |
Disposal of C&D
material/waste |
Billing Account
Number: 7013338 |
Throughout the
Contract |
- |
Effluent Discharge License under Water Pollution Control Ordinance |
License No. WT00010633-2011 |
21 Oct 2011 - 31 Oct 2016 |
- |
Notification of Commencement of Asbestos
Abatement Work under Air Pollution
Control Ordinance |
- |
Throughout the Contract |
EPD¡¦s letter (EPD¡¦s ref.: (5) in EPAC/A/4/000/233
II) dated 2 December 2011 satisfied that the content of the asbestos
abatement plan (Report No.: 0210/11/ED/0078A) is in accordance with the APCO |
Approval of Asbestos Abatement Work (Phase 2) |
- |
Earliest commencement date on 26 January
2012. |
EPD¡¦s letter (EPD¡¦s ref:() in
EPAC/A/4/000/233) dated 18 January 2012. |
Construction Noise Permit (CNP) |
GW-RS0445-16 |
30 May 2016 at 0000
hours to 28 November 2016 at 2400 hours |
- |
|
GW-RS1270-16 |
15 December 2016 at
0000 hours to 11 June 2017 at 2400 hours |
- |
|
GW-RS0443-17 |
12 June 2017 at 1900
hours to 10 December 2017 at 1800 hours |
This CNP was
cancelled and superseded by GW-RS0599-17 at 1900 hours on 17 July 2017. |
|
GW-RS0599-17 |
17 July 2017 at 1900
hours to 16 January 2018 at 2300 hours |
- |
|
GW-RS0662-17 |
4 September 2017 at
2300 hours to 3 November 2017 at 0600 hours |
- |
The
construction noise monitoring locations are given in Table 3.1 and shown in Annex C.
Table
3.1 Construction Phase Noise
Monitoring Locations
Monitoring
Location |
Proposed Construction Noise Monitoring Station |
|||
|
ID in EM&A Manual |
ID |
Type of Measurement |
Remark |
Rooftop of Ho |
N2 |
NM2 |
Façade |
- |
Rooftop of |
--- |
NM6 |
Façade |
Accesses to the original
proposed monitoring location in the EM&A Manual, Chancery House (N5),
were rejected; alternative location of Chancery Mansion (N6), were therefore
proposed and approved by the Authorised Person (AP), the Independent
Environmental Checker (IEC) and EPD. |
The noise sensitive receivers
are also shown in Annex
C.
Weekly
construction noise monitoring was conducted in accordance with the requirements
stipulated in the EM&A Manual.
The
construction noise levels were measured in terms of A-weighted equivalent
continuous sound pressure level (Leq) in decibels dB(A). Leq (30min) were used as the
monitoring parameter for the time period in between 0700 ¡V 1900 hours on normal
weekdays. Supplementary information
for data auditing, two statistical sound levels L10 and L90;
the levels exceeded for 10 and 90 percent of the time respectively, were also
recorded during the monitoring for reference. The measured noise levels were logged in
every 5 minutes throughout the impact monitoring period.
Construction
noise measurements were conducted in accordance with the calibration and
measurement procedures as stated in Annex
¡V General Calibration and Measurement Procedures of Technical Memorandum on Noise from Construction Work other than
Percussive Piling (GW-TM) issued
under the Noise Control Ordinance (NCO) (Cap 400).
The
sound level meters and calibrator used for the noise measurement, as listed in Table
3.2, complies with IEC 651: 1979 and 804:1985 (Type 1) specification. The calibration certificates of the
sound level meters are included in Annex D.
Table 3.2 Noise
Monitoring Equipment
Monitoring Stations |
Monitoring Equipment (Sound
Level Meter and Calibrator) |
NM2,
NM6 |
Calibrator Sound
Level Meter |
Immediately prior to and following the noise
measurements, the accuracy of the measurement
equipment was checked using an acoustic calibrator generating a known sound
pressure level at a known frequency.
Measurements were accepted as the calibration level
from before and after the noise measurement agree to within 1.0 dB.
Table 3.3 Action and Limit Levels for Construction Noise
Monitoring
Noise Monitoring Location |
Action Level |
Limit Level, Leq(30mins),
dB(A) |
Remark |
NM2,
NM6 |
When
one documented complaint is received from any one of the sensitive receivers |
75 (note) |
Applicable
during 0700 ¡V 1900 hours on normal weekdays. |
Notes: a) Acceptable
Noise Levels for Area Sensitivity Rating of A/B/C. Limit Level is reduced to 70dB(A) for
schools and 65dB(A) during school examination periods. b) If
works are to be carried out during restricted hours, the conditions
stipulated in the CNP issued by the NCA have to be followed. |
The
Event / Action Plan (EAP) for noise monitoring is presented in Annex E.
The mitigation measures in accordance with the EP, EIA
and EM&A Manual and their implementation status are presented in Annex
F.
In accordance with the
EM&A Manual, vibration monitoring is required and the vibration control
limits and vibration monitoring proposal are defined by a specialist for AMO¡¦s
approval.
Baseline
vibration monitoring was not conducted during the reporting period.
As no
demolition works were carried out, vibration monitoring for demolition works
was not conducted during the reporting period.
As no
trial piling or pipe/bored piling works were carried out, vibration monitoring for
trial piling and pipe/bored piling works was not conducted during the reporting
period.
Vibration Monitoring for Other Construction Works
Vibration
monitoring for specific construction works other than demolition works, trial
piling works and pipe/bored piling works is also required in accordance with
Building Department¡¦s requirement.
The monitoring location is shown in Annex L. The
number and location of monitoring location will depend on the location of the
specific construction works. The
vibration monitoring should be conducted for duration of 5 minutes on a daily
basis (working day) at each vibration monitoring location.
Alert, Alarm and Action Levels
The Alert, Alarm and Action
(AAA) Levels are to be implemented during the vibration monitoring and shown in
Table 3.4.
Table 3.4 Alert, Alarm and Action
(AAA) Levels for Vibration Monitoring
Instrument Type |
Item Monitored |
Alert Level |
Alarm Level |
Action Level |
Vibration
Monitoring |
Horizontal
Movement |
2.0
mm/s |
2.5
mm/s |
3.0
mm/s |
The Event / Action Plan (EAP)
for vibration monitoring is shown in Table
3.5.
Table 3.5 Event
and Action Plan for Vibration Monitoring
Events |
Action |
Exceedance
of Alert Level |
Notify
Management Contractor |
Exceedance
of Alarm Level |
Notify
Authorised Person/ Resident Engineer |
Exceedance
of Action Level |
Cease
Works and submit mitigation |
Cultural heritage mitigation measures in accordance
with the EP, EIA and EM&A Manual were implemented by the Contractor and the
implementation status is given in Annex
F.
In
accordance with the EM&A Manual, inspections of affected trees were
conducted by an experienced and appropriately trained arborist. All irregularities that deviate from the
recommended tree protection measures or could impose deleterious impacts on the
protected trees were reported.
Besides, implementation of mitigation measures for landscape and visual
resources recommended in the EIA Report were also monitored during the site
inspection.
Landscape and visual mitigation measures in accordance with the
EP, EIA and EM&A Manual were implemented by the Contractor and the
implementation status is given in Annex F.
The
environmental requirements as specified in the contract documents were reviewed
and were covered in the EIA¡¦s requirements.
The Contractor has generally implemented
the environmental mitigation measures and requirements as stated in the EIA
Report, EM&A Manual, EP and the contract documents. The implementation status during the
reporting period is summarised in Annex F.
Status of required submissions under the
EP during the reporting period is presented in Table 4.1.
Table 4.1 Status of
Required Submissions
|
Submission |
Submission Date |
EP
Condition |
|
|
Conditions
3.4 |
¡P
60th
Monthly EM&A Report |
14
November 2016 |
|
¡P
61st
Monthly EM&A Report |
14
December 2016 |
|
¡P
62nd
Monthly EM&A Report |
13
January 2017 |
|
¡P
63rd
Monthly EM&A Report |
14
February 2017 |
|
¡P
64th
Monthly EM&A Report |
14
March 2017 |
|
¡P
65th
Monthly EM&A Report |
13
April 2017 |
|
¡P
66th
Monthly EM&A Report |
12
May 2017 |
|
¡P
67th
Monthly EM&A Report |
14
June 2017 |
|
¡P
68th
Monthly EM&A Report |
14
July 2017 |
|
¡P
69th
Monthly EM&A Report |
14
August 2017 |
|
¡P
70th
Monthly EM&A Report |
14
September 2017 |
|
¡P
71st
Monthly EM&A Report |
13
October 2017 |
EM&A Manual |
|
|
Section
10.4 |
¡P 17th
Quarterly EM&A Report |
30 November 2016 |
|
¡P 18th
Quarterly EM&A Report |
30 November 2016 |
|
¡P
19th Quarterly EM&A Report |
30 November 2016 |
|
¡P
20th Quarterly EM&A Report |
2 February 2017 |
|
¡P
21st Quarterly EM&A Report |
31 March 2017 |
|
¡P
22nd Quarterly EM&A Report |
4 July 2017 |
|
¡P
23rd Quarterly EM&A Report |
24 October 2017 |
A
total of 66 sets of 30-minute construction noise measurements were carried out
at each monitoring station, NM2 and NM6, during normal weekdays of the
reporting period. The monitoring
results together with graphical presentations are presented in Annex G. The local impacts observed near the
monitoring stations of NM2 and NM6 were summarised below:
¡P
NM2:
construction noise from activities in the Project Site and traffic noise from
¡P
NM6:
construction noise from activities in the Project Site and traffic noise from
No
exceedance of the Action or Limit level of construction noise was recorded
during the reporting period.
Monthly
tree inspections were conducted by the arborist during the reporting period and
key findings and recommendations are summarised in Table 5.1.
Table
5.1 Findings of Monthly Tree
Inspections in the Reporting Period
Tree No. |
Botanical Name |
Overall Health Condition |
Arborist¡¦s Observation /
Recommendations |
1st
Quarter (2 Nov 2016, 6 Dec 2016 and 4 Jan 2017) |
|||
Tree
-5 |
Mangifera
indica |
Fair |
¡P
The
new planter has been built and was ready for backfilling of topsoil. ¡P
Before
backfilling of topsoil, the topsoil supplier should provide the Topsoil Test
Reports to the Contractor for inspection and ensure that the topsoil is
qualified and not infected by Phellinus
noxius. The Contractor should
closely monitor the topsoil backfilling work. ¡P
The
Contractor did not inspect the Topsoil Test Report prepared by the soil
suppliers before backfilling of the topsoil. It was understood that the soil
suppliers may have filled unqualified topsoil to the new planter. ¡P
The
Contractor should closely monitor the growth of tree in coming months. |
Tree
-6 |
Aleurites
moluccana |
Fair |
¡P
No
further action required. |
Tree-7 |
Aleurites
moluccana |
Fair |
¡P
No
further action required. |
Tree-8 |
Plumeria
rubra |
Fair |
¡P
To
remove litter from the planter. |
Tree-9 |
Araucaria
cunninghamia |
Fair |
¡P
No
further action required. |
Tree-11 |
Dracaena
marginata |
Fair |
¡P
Many
withered leaves were observed on the tree and at the planter; ¡P
Renovation
works were observed being carried out near the tree with working platform set
up adjacent to the tree. The
Contractor was recommended to remove the working platform which may affect
the growth of the tree; ¡P
To
provide further protection measures (e.g. erect temporary shelter) to the
tree during the nearby renovation works; ¡P
The
Contractor should ensure that the nearby renovation works would not cause
damage to the tree. |
2nd
Quarter (8 Feb, 15 Mar and 7 Apr 2017) |
|||
Tree
-5 |
Mangifera indica |
Fair |
¡P
The
Contractor should closely monitor the growth of tree in coming months due to
backfilling of unqualified topsoil. |
Tree
-6 |
Aleurites moluccana |
Fair |
¡P
No
further action required. |
Tree-7 |
Aleurites moluccana |
Fair |
¡P
No
further action required. |
Tree-8 |
Plumeria rubra |
Fair |
¡P
No
further action required. |
Tree-9 |
Araucaria cunninghamia |
Fair |
¡P
No
further action required. |
Tree-11 |
Dracaena marginata |
Fair |
¡P
Withered
leaves were observed on the tree and at the planter; ¡P
Renovation
works were observed being carried out near the tree with working platform set
up adjacent to the tree; ¡P
A
temporary shelter has been erected for protection of the tree; ¡P
Construction
debris was observed at the planter and the Contractor was reminded to remove
them; ¡P
The
Contractor should closely monitor the growth of the tree. |
3rd
Quarter (5 May, 8 Jun and 10 Jul 2017) |
|||
Tree
-5 |
Mangifera indica |
Fair |
¡P
The
Contractor should erect a Tree Protection Zone at the planter as repairing of
the planter is nearly completed. |
Tree
-6 |
Aleurites moluccana |
Fair |
¡P
The
Contractor should add more mulch and erect a Tree Protection Zone at the
planter. ¡P
Signs
of pest (Trialeurodes vaporariorum)
have been observed on the faded leaves. ¡P
Application
of pesticides to the tree should be carried out as soon as possible. |
Tree-7 |
Aleurites moluccana |
Fair |
¡P
The
Contractor should add more mulch and erect a Tree Protection Zone at the
planter. ¡P
A
decayed log has been observed on the upper branches. ¡P
Signs
of pest (Trialeurodes vaporariorum)
have been observed on the faded leaves. ¡P
Application
of pesticides to the tree and puning of the decayed log should be carried out
as soon as possible. |
Tree-8 |
Plumeria rubra |
Fair/Good |
¡P
The
Contractor should add more mulch and erect a Tree Protection Zone at the
planter. |
Tree-9 |
Araucaria cunninghamia |
Fair/Good |
¡P
The
Contractor should add more mulch and erect a Tree Protection Zone at the
planter. |
Tree-11 |
Dracaena marginata |
Fair |
¡P
Remove
construction debris away from the planter ¡P
Remove
construction debris away from the planter ¡P
The
planter was observed to be covered with construction dust. ¡P
To
wrap the trunk with hessian cloth and to add more hessian cloth to cover the
planter. ¡P
Withered
leaves were observed on the tree. ¡P
The
Contractor should closely monitor the growth of the tree. |
4th
Quarter (4 Aug, 5 Sep and 9 Oct 2017) |
|||
Tree
-5 |
Mangifera indica |
Fair |
¡P
Signs
of pests (Mealy Bugs) were observed on the tree. ¡P
Application
of pesticides should be carried out as soon as possible. ¡P
Application
of pesticides and pruning of decayed logs were conducted on 26 September 2017 |
Tree
-6 |
Aleurites moluccana |
Fair |
¡P
Signs
of pest (Trialeurodes vaporariorum)
apparently reduced due to pesticide application on 3 and 4 August 2017. ¡P
Leaves
on the crown are rather sparse. ¡P
Four
pits near the planter were created for ventilation purpose for the tree ¡P
Keep
monitoring on the growth of the tree. |
Tree-7 |
Aleurites moluccana |
Fair |
¡P
Signs
of pest (Trialeurodes vaporariorum)
apparently reduced due to pesticide application on 3 and 4 August 2017. ¡P
Leaves
on the crown are rather sparse. ¡P
Four
pits near the planter were created for ventilation purpose for the tree ¡P
Keep
monitoring on the growth of the tree. |
Tree-8 |
Plumeria rubra |
Good |
¡P
No
further action required. |
Tree-9 |
Araucaria cunninghamia |
Good |
¡P
No
further action required. |
Tree-11 |
Dracaena marginata |
Fair |
¡P
Remove
construction debris away from the planter. ¡P
Construction
debris observed in the last inspection has been removed from the planter. ¡P
Withered
leaves were observed on the tree. ¡P
The
Contractor should closely monitor the growth of the tree. |
Follow-up
actions needed to be implemented were recommended to the Contractor and the
status of the follow-up actions was reviewed during the subsequent monthly site
inspections. Recommendations have generally
been implemented by the Contractor during the reporting period.
An article on 31 July 2017 and a follow-up article on
5 August 2017 concerning Tree 6 and Tree 7 were published by Ming Pao. An investigation has been carried out to
address the Ming Pao reports. The
31 July 2017 article indicated that pests were found on Tree 6 and 7 and the
current amount of leaves on Tree 6 and Tree
7 have seemingly reduced in comparison with the photo of the trees which was
said to be taken in December 2015, suggesting
that the health of Tree 6 and Tree 7 may have deteriorated. The report enquired if the construction
work has been carried out in compliance with the requirements in the
Environmental Permit and potential measures to rectify the condition of Tree
6 and Tree 7. The 5 August 2017
article reported that the contractor has applied pesticides to the trees but
queried if the contractor did not rectify the problem in a timely
manner. An ad-hoc joint tree
inspection for Tree 6 and Tree 7 was carried out by the representatives of the
arborist, Contractor, IEC, ET, HKJC, EPD and relevant parties on 8 August
2017. An investigation has been
carried out to address the Ming Pao reports and the investigation report is
provided in Annex J. The recommended follow-up actions have
been implemented.
No vibration monitoring was carried out for demolition
works, trial piling or pile/bored piling works as the aforementioned works were
not conducted during the reporting period.
Other construction works
A summary of vibration
monitoring for underpinning,
strengthening and structural alteration works at Blocks 11 in the reporting
period is presented in Table 5.2.
Table 5.2 Summary
of Vibration
Monitoring for Other Construction Works
Month/
Date |
Works
Locations |
Number
of monitoring at monitoring station |
Nov 2016 |
Block 11 |
26 |
Dec 2016 |
Block 11 |
25 |
Jan 2017 |
Block 11 |
21 |
Feb 2017 |
Block 11 |
22 |
Mar 2017 |
Block 11 |
27 |
Apr 2017 |
Block 11 |
21 |
May 2017 |
Block 11 |
24 |
Jun 2017 |
Block 11 |
26 |
Jul 2017 |
Block 11 |
25 |
Aug 2017 |
Block 11 |
26 |
Sep 2017 |
Block 11 |
26 |
Oct 2017 |
Block 11 |
23 |
The monitoring results for other construction works are
presented in Annex L.
All monitoring results
were below the Alert/Alarm/ Action Levels throughout during the reporting
period.
Heritage site audits were
conducted by the Heritage Checker on every working weekday during the reporting
period. Key site audit findings and
recommendations for each month are summarised in Annex M. Observations
and recommendations were made to the Contractor during the site audits and
follow-up actions were
generally undertaken in the subsequent site audits.
A
total of 6 non-compliance reports related to the character defining elements, historic buildings
and structures were issued during the reporting period. The non-compliance reports are provided
in Annex M.
A summary of condition
of the character defining elements, historic buildings and structures is
contained in Annex
M.
Wastes
generated from this Project include inert construction and demolition (C&D)
materials and non-inert C&D materials. Non-inert C&D materials were made up
of wastes such as general refuse and mixed construction waste. With reference to relevant handling
records and trip tickets of this Project, the quantities of different types of
waste generated in the reporting period are summarised in Table 5.3. The summary
of Waste Flow Table prepared by the Contractor is shown in
Annex I.
Table 5.3 Quantities
of Waste Generated from the Project
Month / Year |
Quantity |
|
||||||
C&D Materials (inert) (tonnes) (a) |
C&D Materials (non-inert) (tonnes) (b) |
Chemical Waste |
Recycled materials |
|
||||
Liquid (L) |
Solid (kg) |
Paper/cardboard (kg) |
Plastics (kg) |
Metals (kg) |
|
|||
November 2016 |
14.21 |
105.39 |
0 |
0 |
0 |
0 |
0 |
|
December 2016 |
29.61 |
69.45 |
0 |
0 |
260 |
0 |
0 |
|
January 2017 |
27.51 |
51.97 |
0 |
0 |
190 |
0 |
0 |
|
February 2017 |
60.97 |
43.89 |
0 |
0 |
210 |
0 |
0 |
|
March 2017 |
135.47 |
93.05 |
0 |
0 |
160 |
0 |
0 |
|
April 2017 |
32.19 |
103.21 |
0 |
0 |
0 |
0 |
0 |
|
May 2017 |
54.34 |
87.19 |
0 |
0 |
228 (c) |
0 |
0 |
|
June 2017 |
134.59 |
80.65 |
0 |
0 |
266
(c) |
0 |
0 |
|
July 2017 |
12.61 |
57.54 |
0 |
0 |
0 |
0 |
0 |
|
August 2017 |
79.39 |
58.03 |
0 |
0 |
0 |
0 |
0 |
|
September 2017 |
199.78 |
62.43 |
0 |
0 |
0 |
0 |
0 |
|
October 2017 |
103.07 |
50.09 |
0 |
0 |
0 |
0 |
0 |
|
Total |
883.74 |
862.89 |
0 |
0 |
1,314 |
0 |
0 |
|
Notes: (a)
Inert
C&D materials include bricks, concrete, building debris, rubble and
excavated soil, which were disposed of at Chai
Wan Public Fill Barging Point, Tseung Kwan O Area 137 Fill Bank and Tuen Mun
38 Fill Bank. (b)
Non-inert
C&D materials include general refuse and mixed construction waste, which
were disposed of at SENT
Landfill, Tseung Kwan O Area 137 Sorting Facility, Tuen Mun Area 38 Sorting
Facility and NENT Landfill. |
The
mitigation measures recommended in the EIA report and required by the EP are
considered effective in minimising environmental impacts.
The
EM&A for the Project was conducted as scheduled during the sixth construction
year. No exceedance of Action Level
of construction noise was recorded during the reporting period. No exceedance of limit level of
construction noise was recorded and no environmental non-compliance events were
observed during site inspections. 6
non-compliance reports related to the character defining elements, historic buildings
and structures were issued during the reporting period. No complaint was recorded during the
reporting period. One enquiry was
recorded during the reporting period.
The
follow up mitigation measures for the enquiry and the 6 non-compliance events related
to cultural heritage were carried out accordingly. The mitigation measures taken were
considered efficient and effective.
The EM&A programme is considered effective.
Monthly
environmental site inspections were conducted by the representatives of the
Contractor, IEC and the ET. There
was no environmental non-compliance event recorded during site inspections for
the sixth year of the construction period.
Key site audit findings and recommendations are summarised below. Monthly recommendations were implemented
and observations were rectified by the Contractor in the subsequent monthly
site inspections.
17 November 2016
¡P
Nil.
16 December 2016
¡P
Nil.
19 January 2017
¡P Nil.
16 February 2017
¡P
Nil.
16
March 2017
¡P
Nil.
20 April 2017
¡P Nil.
25 May 2017
¡P
It was observed that over 20 bags of cement were
stored near Block 3, some of them opened without covered by impervious
sheet. The Contractor was reminded
to provide impervious sheet to the cement bags after use.
15 June
2017
¡P
Noise label for the air compressor located near Block
14 was observed missing. The
Contractor was reminded to provide and attach appropriate noise label for the
air compressor.
18 July 2017
¡P Nil.
24 August 2017
¡P
Nil.
An ad-hoc joint tree inspection for Tree 6 and Tree 7
was carried out by the representatives of the arborist, Contractor, IEC, ET,
HKJC, EPD and relevant parties on 8 August 2017.
18 September
2017
¡P
Nil.
26 October 2017
¡P
Nil.
No exceedance of the Action
or Limit Level of construction noise or Alert, Alarm and Action Level of
vibration was recorded during the reporting period.
One
enquiry was received during the reporting period. Please refer to Section 5.2 for the details of the enquiry.
No environmental non-compliance
event was recorded during the reporting period. 6 non-compliance events related to the
character defining elements, historic buildings and structures were recorded
during the reporting period. The
non-compliance reports are contained in Annex M.
No complaint was received
during the reporting period. The cumulative
number of complaints is presented in Annex
J.
No summons was received
during the reporting period. The
cumulative summons/prosecution log is shown in Annex
J.
A comparison was made between
the monitoring results in this reporting period and the Noise Standard for
general construction works during 0700 ¡V 1900 hrs on normal weekdays (Table 8.1).
Table
8.1 Comparison of Construction Noise Standard and Noise
Monitoring Results
Reporting Month
|
Monitoring Stations
|
Corresponding NSR in EIA
|
Noise Limit Level |
Predicted
Construction Noise Level (With Mitigation) in EIA |
Measured Construction
Noise Level |
|
|
|
Leq, 30 min
dB(A) |
Leq, 30 min
dB(A) |
Leq, 30 min
dB(A) |
Nov
2016 |
NM2 |
N2 |
75 |
67
- 72 |
69.4
¡V 72.1 |
NM6 |
N6 |
75 |
73
- 75 |
64.2
¡V 68.4 |
|
Dec
2016 |
NM2 |
N2 |
75 |
67
- 72 |
68.2
¡V 73.1 |
NM6 |
N6 |
75 |
73
- 75 |
65.1
¡V 69.0 |
|
Jan
2017 |
NM2 |
N2 |
75 |
67
- 72 |
64.3 ¡V 71.0 |
|
NM6 |
N6 |
75 |
73
- 75 |
60.6
¡V 66.0 |
Feb
2017 |
NM2 |
N2 |
75 |
67
- 72 |
67.6
¡V 71.5 |
NM6 |
N6 |
75 |
73
- 75 |
61.9
¡V 66.1 |
|
Mar
2017 |
NM2 |
N2 |
75 |
67
- 72 |
65.2
¡V 69.1 |
NM6 |
N6 |
75 |
73
- 75 |
63.5
¡V 65.0 |
|
Apr
2017 |
NM2 |
N2 |
75 |
67
- 72 |
67.8
¡V 69.5 |
|
NM6 |
N6 |
75 |
73
- 75 |
63.7
¡V 68.0 |
May
2017 |
NM2 |
N2 |
75 |
67
- 72 |
67.5
¡V 70.6 |
NM6 |
N6 |
75 |
73
- 75 |
64.3
¡V 67.5 |
|
June
2017 |
NM2 |
N2 |
75 |
67
- 72 |
66.3
¡V 71.0 |
NM6 |
N6 |
75 |
73
- 75 |
62.7
¡V 66.7 |
|
July
2017 |
NM2 |
N2 |
75 |
67
- 72 |
64.0
¡V 67.5 |
|
NM6 |
N6 |
75 |
73
- 75 |
63.3
¡V 68.3 |
August
2017 |
NM2 |
N2 |
75 |
67
- 72 |
65.5
¡V 69.1 |
NM6 |
N6 |
75 |
73
- 75 |
62.1
¡V 66.3 |
|
Sep
2017 |
NM2 |
N2 |
75 |
67
- 72 |
67.0
¡V 69.8 |
NM6 |
N6 |
75 |
73
- 75 |
63.6
¡V 65.4 |
|
Oct
2017 |
NM2 |
N2 |
75 |
67
- 72 |
65.9
¡V 69.1 |
|
NM6 |
N6 |
75 |
73
- 75 |
62.6
¡V 65.3 |
The monitoring results
recorded during the reporting period have been below the Limit Level and
comparable to the predicted construction noise level in the approved EIA. Recommended mitigation measures in Section 5.9.1 of EIA will continue to be implemented
throughout the construction stage.
The estimated amount of waste generated in the approved EIA and the
accumulated quantities of waste generated up to this reporting period are
presented in Table 8.2.
The accumulated amount of inert and non-inert C&D materials is higher
than the estimated amount in EIA. The major chemical waste generated on
site was primarily asbestos which was not estimated in the approved EIA and
hence no data is available for comparison. Recommended mitigation measures in Section 8.5.1 of the EIA will continue to be implemented throughout the
construction stage.
Table
8.2 Quantity of Actual Amount
of C&D Materials, General Wastes and Chemical Wastes Generated and EIA
Estimation
Type
of Material |
Estimated
Amount of Waste in EIA |
Accumulated
Actual Amount of Waste Recorded (a) (b) |
Amount
of C&D Materials (Inert) Arising |
16,440
m3 |
37,898.25
m3 |
Amount
of C&D Materials (Non-inert) Arising |
890
m3 |
15,634.13
m3 |
General
Refuse |
130
kg per day |
-
(c) |
Chemical
Waste |
Less
than 100L per month |
-
57
L -
395
kg -
7,000
kg of asbestos generated |
Notes: (a) The accumulated actual amount of C&D Materials and
chemical waste were recorded since the commencement of construction works. (b) The volume of waste materials are provided by the
Contractor based on the updated waste record in October 2017. (c) The amount of general refuse generated was not
recorded. |
The EIA predictions and the monitoring results since the commencement of
construction works have been reviewed.
The EIA concluded that the
Project would not cause adverse impacts to the environment and the monitoring
results have also indicated the same so far. Mitigation measures recommended in the
EP, EIA and EM&A Manual were implemented by the Contractor as far as
practicable and were considered effective.
The recommended mitigation measures will continue to be implemented
throughout the construction phase of the Project.
The effectiveness of the
monitoring programme has been exhibited therefore change to the programme is
not considered to be necessary.
This 6th
Annual EM&A review Report presents the EM&A works undertaken during the
reporting period from 1 November 2016 to 31 October 2017 in accordance with
EM&A Manual.
No
exceedance of Action or Limit Level of construction noise was recorded at the
monitoring stations during the reporting period.
Tree inspections were conducted in this reporting
period. Most of the necessary
landscape and visual mitigation measures recommended in the EIA Report were
implemented by the Contractor.
No exceedance of the Alert, Alarm and Action Levels of vibration was
recorded during the reporting period.
One enquiry was received during the
reporting period.
No environmental non-compliance event was
recorded during the reporting period. 6 non-compliance events related to the character defining elements, historic buildings
and structures were recorded during the reporting period.
No complaint
was received during the reporting period.
No
summons/prosecution was received during the reporting period.
The monitoring
programme was considered effective in reflecting the environmental conditions
at the designated representative sensitive receivers. The monitoring results also indicate
that the Project have not caused adverse impacts on the environment with
implementation of appropriate mitigation measures. Change to the monitoring programme is
not considered to be necessary. The
ET will keep track on the EM&A programme to ensure compliance of
environmental requirements and the proper implementation of all necessary
mitigation measures in the coming periods.