Table of Contents
2......... Environmental
Monitoring and Audit
3......... implementation
status on the environmental protection requirements
List of
Tables
Table 1.1 Summary of Awarded Works Contracts
Table 2.1 Summary of Major Construction
Activities in the Reporting Period
Table 2.2 Summary of 24-Hour TSP Monitoring
Results in the Reporting Period
Table 2.3 Summary of Construction Noise Monitoring
Results in the Reporting Period
Table 3.1 Summary of Status of Required
Submissions for EP-438/2012/K
List of
Appendices
Appendix A 91st Monthly EM&A Report for Works Contract
1109 – Stations and Tunnels of Kowloon City Section
Appendix B 82nd
Monthly
EM&A Report for Works Contract 1112 – Hung Hom Station and Stabling Sidings
Tunnels
Table
1.1 Summary
of Awarded Works Contracts
Works
Contract |
Description |
Construction
Start Date |
Contractor |
Environmental
Team |
1101(1) |
Ma
On Shan Line Modification Works |
December 2012 |
Sun
Fook Kong Joint Venture (SFKJV) |
ANewR
Consulting Ltd. (ANewR) |
1102(6) |
Hin
Keng Station and Approach Structures |
October 2013 |
Penta-Ocean
Construction Co. Ltd. |
Wellab
Limited (Wellab) |
1103(7) |
Hin
Keng to Diamond Hill Tunnels |
February 2013 |
Vinci
Construction Grands Projets |
Ove
Arup & Partners Hong Kong Ltd. (Arup) |
October 2019 |
Wing
Ho Yuen Landscaping Co. Ltd. |
MTR Co. Limited |
||
1106(8) |
Diamond
Hill Station |
March 2013 |
Leader
Joint Venture |
Cinotech
Consultants Ltd. (Cinotech) |
1107(4) |
Diamond
Hill to Kai Tak Tunnels |
May 2013 |
Chun
Wo - SELI Joint Venture |
Cinotech
Consultants Ltd. (Cinotech) |
1108(5) |
Kai
Tak Station and Associated Tunnels |
June 2013 |
Kaden
-Chun Wo Joint Venture |
Environmental
Pioneers & Solutions Ltd. |
1108A(2) |
Kai
Tak Barging Point Facilities |
September 2012 |
Concentric
– Hong Kong River Joint Venture (CCL-HKR JV) |
Cinotech
Consultants Ltd. (Cinotech) |
1109 |
Stations
and Tunnels of Kowloon City Section |
September 2012 |
Samsung-Hsin
Chong JV (SSHCJV) |
ERM-Hong
Kong Limited (ERM) |
1111(9) |
Hung Hom North Approach Tunnels |
January 2013 |
Gammon-Kaden SCL1111 JV |
AECOM Asia Co. Ltd. |
1112 |
Hung
Hom Station and Stabling Sidings |
June 2013 |
Leighton
Contractors (Asia) Limited |
SMEC Asia Ltd., HK |
11240(3) |
Excavation,
Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site |
October 2017 |
Crown
Asia Engineering Limited (CAEL) |
MTR Co. Limited |
Notes:
(1)
All construction
works (works
areas at Tai Wai Mei Tin Road and the offsite temporary storage areas) under Works
Contract 1101 were completed on 29 February 2016.
(2)
All construction
works (Kai Tak
Barging Point Facilities) under Works Contract 1108A were completed on 29
September 2016.
(3)
All construction
works (Excavation,
Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site) under Works
Contract 11240 were completed on 3 January 2018.
(4)
All construction works (Diamond Hill to Kai Tak Tunnels) under Works
Contract 1107 were completed on 22 February 2018.
(5)
All construction works (Kai Tak Station and associated tunnels) under
Works Contract 1108 were completed in July 2018.
(6)
All construction works (Hin Keng Station and Approach Structures) under
Works Contract 1102 were completed in December 2018. The Environmental Team was
taken over by Wellab Limited starting from 1 January 2019.
(7)
All construction works (Hin Keng to
Diamond Hill Tunnels) under Works Contract 1103 were completed in June 2019.
Minor landscaping works at Fung Tak had been commenced in mid Oct and all the
works were completed at the end of Oct 2019.
(8)
All construction works (Diamond Hill
Station) under Works Contract 1106 with significant environmental impacts were
substantially completed by 25 Jun 2019.
(9)
All major construction works (Hung Hom North
Approach Tunnels) under Works Contract 1111 have been substantially completed
since 18 Nov 2018 with only minor works remaining.
Works Contract |
Contract Title |
Works Covered in Environmental Permit No. |
1101 |
Ma On
Shan Modification Works |
|
1102 |
Hin Keng Station and Approach
Structures |
|
1103 |
Hin
Keng to Diamond Hill Tunnels |
|
1106 |
Diamond
Hill Station |
|
1107 |
Diamond
Hill to Kai Tak Tunnels |
|
1108 |
Kai
Tak Station and Associated Tunnels |
|
1108A |
Kai
Tak Barging Point Facilities |
|
1109 |
Stations and Tunnels of Kowloon
City Section |
|
1111 |
Hung
Hom North Approach Tunnels |
|
1112 |
Hung
Hom Station and Stabling Sidings |
|
11240 |
Excavation,
Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site |
EP-438/2012/K |
Table 2.1 Summary of Major Construction
Activities in the Reporting Period
Works Contract |
Site |
Construction Activities |
1109 |
Works
in To Kwa Wan (TKW) (formerly named as Ma Tau Wai (MTW)) |
· To Kwa
Wan Station – ABWF works; · Ma Tau
Wai Road – Removal of D-wall, construction of carriageway panel near Chi
Kiang Street, and footpath reinstatement works at northbound footpath between
Kiang Su Street and Chi Kiang Street; · Ventilation
Shaft and Entrance A – Reinstatement of Lok Shan Road Playground and To Kwa
Wan Complex Playground; · Junction
of Ma Tau Wai Road and Chi Kiang Street – Construction of small garden; · Entrance
D – Reinstatement of Ma Tau Wai Road/ To Kwa Wan Road Garden; and · All
Work Areas – Maintenance, repairing, rectification and protection improvement
works for the structure within 1109 Contract Boundary due to social
activities. |
Works
in Sung Wong Toi (SUW) (formerly named as To Kwa Wan (TKW)) |
· Sung Wong
Toi Station – ABWF works; and · All
Works Areas – Maintenance, repairing, rectification and protection
improvement works for the structure within 1109 Contract Boundary due to
social activities. |
|
1112 |
Hung
Hom Station (HUH) |
· Minor
services connection at G.L J of HUH; · Platform
ABWF and E&M works; · Remedial
works at HUH |
SAT
Ventilation Shaft |
· Landscape
preparation works |
|
Concourse
level & Mid-level walkway |
· Modification
works |
Table 2.2 Summary of 24-Hour TSP Monitoring Results in the
Reporting Period
Monitoring Station ID |
Location |
TSP Concentration (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
Exceedance due to the Project
Construction (Yes/ No/ N/A) |
Works
Contracts 1102 and 1103 |
|
|
|
|
|
DMS-1(11) |
C.U.H.K.A.A.
Thomas Cheung School |
N/A |
148.7 |
260 |
N/A |
Works
Contract 1103 |
|
|
|
|
|
DMS-2(12) |
Price
Memorial Catholic Primary School |
N/A |
167.4 |
260 |
No |
Works
Contracts 1103 and 1106 |
|
|
|
|
|
DMS-3(13) |
Hong
Kong S.K.H Nursing Home (1) |
N/A |
159.1 |
260 |
No |
Works
Contract 1106(10) |
|
|
|
|
|
DMS-4(13) |
Block
1, Rhythm Garden |
N/A |
160.4 |
260 |
No |
Works
Contract 1108 (5) |
|
|
|
|
|
Works
Contract 1109 |
|
|
|
|
|
DMS-6 |
Katherine Building (2) |
36 – 65 |
156.8 |
260 |
No |
DMS-7 |
Parc
22 (3) |
28 – 56 |
166.7 |
260 |
No |
DMS-8 |
SKH
Good Shepherd Primary School |
32 – 68 |
152.2 |
260 |
No |
DMS-9 |
No.
12 Pau Chung Street (4)(9) |
46 – 93 |
160.9 |
260 |
No |
DMS-10 |
Chat
Ma Mansion |
37 – 88 |
170.4 |
260 |
No |
Works Contract 1111 |
|
|
|
|
|
AM1(6)(14) |
No.
234 – 238 Chatham Road North (7) |
N/A |
183.9 |
260 |
No |
Works Contract 1112 |
|
|
|
|
|
AM2 |
Site
Boundary of Finger Pier Adjacent
To
Harbourfront Horizon (8) |
44.0 – 51.4 |
182 |
260 |
No |
Works
Contract 11240 (5) |
|
|
|
|
Notes:
(1)
Alternative monitoring location to Shek On
House
(2)
Alternative monitoring location to
Prosperity House
(3)
Alternative monitoring location to Skytower Tower 2
(4)
Alternative
monitoring location to Lucky Building
(5)
No TSP monitoring is required under this
contract
(6)
AM1 named as HUH-1-3 in SCL(TAW-HUH) and
SCL(HHS) EIA Reports.
(7)
Alternative monitoring location to Wing
Fung Building
(8)
Alternative monitoring location to
Harbourfront Horizon
(9)
Alternative monitoring
location of No. 26 Kowloon City Road
(10)
The 24-hour TSP monitoring works would be taken
up by Works Contract 1106 since the completion of Works Contract 1107 in Feb
2018.
(11)
The cessation
of monitoring works at DMS-1 was approved by EPD and the last monitoring was
conducted on 16 Jul 2018.
(12)
The temporary
cessation of monitoring works at DMS-2 was approved by EPD in end-June 2019.
The last monitoring date was 27 June 2019.
(13)
The cessation of monitoring works at DMS-3
and DMS-4 was
approved by EPD on 31 Jul 2019. The last monitoring was conducted on 30 Jul 2019.
(14)
The cessation of monitoring works at AM1
was proposed on 25 Jul 2019 and EPD expressed no objection on 31 Jul 2019.
Table 2.3 Summary of Construction Noise
Monitoring Results in the Reporting Period
Monitoring Station ID |
Location |
Noise Level (LAeq,30mins, dB(A)) |
Limit Level (dB(A)) |
Exceedance due to the Project
Construction (Yes/No) |
|||
Measured |
Baseline |
Corrected (7) |
|||||
Works Contracts
1102 and 1103 |
|
|
|
|
|
||
NMS-CA-1(12) |
C.U.H.K.A.A.
Thomas Cheung School |
N/A |
57.0 |
N/A |
70 (65
during examination period) |
No |
|
Works Contract
1103 |
|
|
|
|
|
||
NMS-CA-2(13) |
Price
Memorial Catholic Primary
School |
N/A |
66.0 |
N/A |
70 (65
during examination period) |
No |
|
Works Contracts
1103 and 1106 |
|
|
|
|
|
||
NMS-CA-3(14) |
Hong
Kong S.K.H Nursing
Home (1) |
N/A |
73.0 |
N/A |
70 |
No |
|
Works Contracts
1106(11) |
|
|
|
|
|
||
NMS-CA-4(14) |
Block
1, Rhythm Garden (north-eastern façade) |
N/A |
71.0 |
N/A |
75 |
No |
|
NMS-CA-5(14) |
Block
1, Rhythm Garden (northern façade)(2) |
N/A |
74.0 |
N/A |
70 (65 during examination period) |
No |
|
Works Contract
1108 (6) |
|
|
|
|
|
||
Works Contract
1109 |
|
|
|
|
|
||
NMS-CA-6 |
No. 16-23 Nam Kok Road (3) |
61.9 –
62.3 |
76.1 |
<
Baseline |
75 |
No |
|
NMS-CA-7 |
Skytower
Tower 2 |
65.6 –
66.9 |
70.0 |
<
Baseline |
75 |
No |
|
NMS-CA-8 |
SKH Good
Shepherd Primary
School |
72.4 –
73.4 |
75.4 |
<
Baseline |
70 (65
during examination period) (79
during the period of conducting the continuous noise monitoring) (8) |
No |
|
NMS-CA-9 |
Kong
Yiu Mansion (4) |
69.2 –
70.2 |
69.2 |
<
Baseline – 63.3 |
75 |
No |
|
NMS-CA-10 |
Chat Ma Mansion |
75.7 – 76.1 |
76.6 |
< Baseline |
75 |
No |
|
Works Contract
1111 |
|
|
|
|
|
||
NM1(15) |
Carmel
Secondary School (South
Block) |
N/A |
68.0 |
N/A |
70 (65
during examination period) (68 during the period of conducting the
continuous noise monitoring) (9) |
No |
|
NM2(15) |
No.
234 – 238 Chatham Road North (5) |
N/A |
79.0 |
N/A |
75 (77) (10) |
No |
|
Works Contract
1112 (6) |
|
|
|
|
|
||
Works Contract
11240 (6) |
|
|
|
|
|
||
Notes:
(1)
Alternative monitoring location to Shek On
House.
(2)
Alternative monitoring location to Canossa
Primary School (San Po Kong).
(3)
Alternative monitoring location to
Prosperity House.
(4)
Alternative monitoring location to Lucky
Building.
(5)
Alternative monitoring location to Wing
Fung Building.
(6)
No construction noise monitoring is
required under this contract.
(7)
The measured noise levels are corrected
against the corresponding baseline noise levels.
(8)
The Limit Level of 79 dB(A) was updated on
22 Aug 2013 as per the latest Construction Noise Mitigation Measures Plan
(CNMMP) and Continuous Noise Monitoring Plan (CNMP) which were approved by EPD.
(9)
The Limit of 68
dB(A) was updated on 20 Jan 2014 as per the latest CNMMP and CNMP which were
approved by EPD.
(10)
Daytime noise
Limit Level of 77 dB(A) applies during the continuous noise monitoring period.
(11)
The
construction noise monitoring works would be taken up by Works Contract 1106
since the completion of Works Contract 1107 in Feb 2018.
(12)
The cessation
of monitoring works at NMS-CA-1 was approved by EPD and the last monitoring was
conducted on 17 Jul 2018.
(13)
The temporary
cessation of monitoring works at NMS-CA-2 was approved by EPD in end-June 2019.
The last monitoring date was 24 Jun 2019.
(14)
The cessation
of monitoring works at NMS-CA-3, NMS-CA-4 and NMS-CA-5 was approved by EPD on
31 Jul 2019. The
last monitoring proposed on 31 Jul 2019 was
rescheduled to 1 Aug 2019 due to adverse weather and the hoist of
Typhoon Signal No.8 (Typhoon “Wipha”).
(15)
The cessation of monitoring works at NM1
and NM2 were proposed on 25 Jul 2019 and EPD expressed no objection on 31 Jul
2019.
Table 2.4 Log for Environmental Complaints,
Notification of Summons and Successful Prosecutions
for the Reporting Month
Works Contract |
Environmental Complaints |
Notification of Summons |
Successful Prosecutions |
1109 |
0 |
0 |
0 |
1112 |
0 |
0 |
0 |
Table 3.1 Summary
of Status of Required Submissions for EP-438/2012/K
EP Condition |
Submission |
Submission date |
Condition 1.12 |
Notification of
Commencement Date of Construction of the Project |
1 Aug 2012 |
Condition 2.3 |
Notification of
Information of Community Liaison Groups |
13 Jul 2012 (1st
submission) 31 Aug 2012 (2nd
submission) 30 Nov 2012 (3rd
submission) |
Condition 2.7 |
Management Organisation
of Main Construction Companies |
27 Jul 2012 (1st
submission) 21 Aug 2012 (2nd
submission) 19 Dec 2012 (3rd
submission) 22 Jan 2013 (4th
submission) 30 Apr 2013 (5th
submission) 21 May 2013 (6th
submission) |
Condition 2.8 |
Construction
Programme and EP Submission Schedule |
27 Jul 2012 |
Condition 2.9 |
Construction
Noise Mitigation Measures Plan (CNMMP) |
1 Aug 2012 (1st
submission) 28 Sep 2012 (2nd
submission) 30 Nov 2012 (3rd
submission) 11 Jan 2013 (4th
submission) 8 Feb 2013 (Approved) 26 Apr 2013 (6th
submission) 11 Jun 2013 (7th
submission) 12 Jul 2013
(Approved) 26 Jul 2013 (8th
submission) 22 Aug 2013
(Approved) 23 Aug 2013 (9th
submission) 13 Sep 2013
(Approved) 20 Jan 2014 (10th
submission) 26 Feb 2014 (Approved) 31 Mar 2015 (Contract 1106 submission only) 13 Apr 2015 (Contract 1106 submission only) 15 Apr 2015 (Approved) |
Condition 2.10 |
Continuous Noise
Monitoring Plan (CNMP) |
1 Aug 2012 (1st
submission) 28 Sep 2012 (2nd
submission) 30 Nov 2012 (3rd
submission) 11 Jan 2013 (4th
submission) 8 Feb 2013
(Approved) 8 Feb 2013 (5th
submission) 26 Apr 2013 (6th
submission) 12 Jul 2013
(Approved) 26 Jul 2013 (8th
submission) 22 Aug 2013
(Approved) 23 Aug 2013 (9th
submission) 13 Sep 2013
(Approved) 20 Jan 2014 (10th
submission) 26 Feb 2014 (Approved) 7 Oct 2014 (11th
submission) 23 Oct 2014 (Approved) |
Condition 2.11 |
Construction and Demolition
Materials Management Plan (C&DMMP) |
6 Jul 2012 (1st
submission) 12 Sep 2012 (2nd
submission) 10 Oct 2012
(Approved) |
Condition 2.12 |
Sediment
Management Plan |
6 Jul 2012 (1st
submission) 12 Sep 2012 (2nd
submission) 5 Oct 2012 (3rd
submission) 10 Oct 2012
(Approved) 4 Mar 2013 (4th
submission) 9 May 2013 (5th
submission) 24 Jul 2013 (6th
submission) 26 Jul 2013
(Approved) |
Condition 2.13 |
Visual,
Landscape, Tree Planting & Tree Protection Plan |
6 Jul 2012 (1st
submission) 30 Aug 2012 (2nd
submission) 3 Oct 2012 (3rd
submission) 13 Nov 2013
(Approved) 14 Nov 2012 (4th
submission) 8 Feb 2013 (5th
submission) 18 Mar 2013 (6th
submission) 18 Jun 2013 (7th
submission) 12 Jul 2013
(Approved) 23 Mar 2017 (8th submission) 7 Mar 2018 (9th submission) 30 Jul 2018 (10th submission) 28 Feb 2019 (11th submission) 5 Mar 2019 (12th submission) 29 May 2019 (13th submission) 19 Jul 2019 (Approved) |
Condition 2.14 |
Transplantation
Proposal for Plant Species of Conservation Importance |
22 Aug 2012 (1st
submission) 5 Oct 2012 (2nd
submission) 26 Nov 2012 (3rd
submission) 4 Dec 2012
(Approved) |
Condition 2.15 |
Conservation Plan |
31 Jan 2013 (1st
submission) 18 Mar 2013 (2nd
submission) 24 Apr 2013
(Approved) |
Condition 2.16 |
Archaeological
Action Plan(s) (AAP(s)) for Works Contract 1109 |
10 Aug 2012 (1st
submission) 3 Sep 2012 (2nd
submission) 21 Sep 2012
(Approved) 11
Oct 2013
(3rd submission) 1 Nov 2013
(Approved) |
Condition 2.16 |
Archaeological
Action Plan(s) (AAP(s)) for Works Contract 1106 |
29 Jan 2013 (1st
submission) 19 Mar 2013 (2nd
submission) 8 Apr 2013
(Approved) |
Condition 2.23 |
Supplementary
Contamination Assessment Report for New Territories South Animal Centre |
28 Sep 2012 25 Oct 2012
(Approved) |
Condition 2.27 |
Operational
Ground-borne Noise Mitigation Measures Plan |
18 Mar 2016 (Batch 1 Version A submission) 28 Apr 2016 (Batch 1 Version B submission) 28 Apr 2016 (Batch 2 Version A submission) 1 Jun 2016 (Batch 1 Version C submission) 1 Jun 2016 (Batch 2 Version B submission) 23 Jun 2016 (Batch 1 Version D submission) 23 Jun 2016 (Batch 2 Version C submission) 15 Jul 2016 (Batch 1 Version D approved) 15 Jul 2016 (Batch 2 Version C approved) 15 Sep 2016 (Batch 3 Version A submission) 4 Oct 2016 (Batch 3 Version A approved) 8 Mar 2017 (Batch 4 Version A) 7 Apr 2017 (Batch 4 Version A approved) 7 Jun 2017 (Final) 20 Jul 2017 (Approved) |
Condition 2.28 |
As-built Drawings for Operational Ground-borne Noise Mitigation
Measures |
10
Aug 2017 (1st
submission) |
Condition 2.30 |
As-built Drawings for Operational Air-borne Noise Mitigation Measures |
4 Dec 2015 (1st submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) 20 Mar 2018 (3rd submission) 18 Jul 2018 (Approved) 4 May 2018 (4th submission) 23 Jul 2018 (Approved) 20 Feb 2020 (5th submission) |
Condition 2.31 |
Performance Test
Report for Train Noise – Operational Airborne Railway and Ground-borne Noise |
15 Nov 2018
(Batch 1 Version A submission) 30 Jan 2019
(Batch 2 Version A submission) 29 Mar 2019
(Batch 1 Version A & Batch 2 Version B submission) 15 April 2019 (Approved) |
Condition 2.32 |
Proposal for
Updating Maximum Allowable Sound Power Levels of Fixed Plant Sources |
30 Jan 2019 (Batch
1 Version A submission) 27 Feb 2019
(Batch 1 Version B submission) 13 Mar 2019
(Batch 1 Version B approved) 15 Mar 2019
(Batch 2 Version A submission) 8 Apr 2019 (Batch
2 Version A approved) 24 April 2019
(Batch 3 & 4 Version A submission) 21 May 2019
(Batch 3 Version B submission) 11 Jun 2019
(Batch 3 Version B & Batch 4 Version A approved) 21 Jun 2019
(Batch 5 Version A submission) 17 Jul 2019
(Batch 5 Version A approved) 19 Jul 2019
(Batch 6 Version A submission) 26 Jul 2019 (Batch
7 Version A submission) 29 Jul 2019
(Batch 6 Version A approved) 14
Aug 2019 (Batch 7 Version
A approved) |
Condition 2.32 |
Fixed Plant Noise
Audit Report |
30 Jan 2019
(Batch 1 Version A submission) 15 Mar 2019
(Batch 1 Version B submission) 4 Apr 2019 (Batch
1 Version B approved) 16 Apr 2019
(Batch 2 Version A submission) 7 May 2019 (Batch
2 Version A approved) 24 Jun 2019
(Batch 3 Version A and Batch 4 Version A submission) 6 Jul 2019 (Batch
3 Version A and Batch 4 Version A approved) 2 Aug 2019 (Batch
5 Version A submission) 27 Aug 2019
(Batch 6 Version A submission) 29 Aug 2019
(Batch 7 Version A submission) 3 Sep 2019 (Batch
5 Version A approved) 13 Sep 2019
(Batch 6 Version B approved) 23 Sep 2019
(Batch 7 Version B submission) 11 Oct 2019 (Batch
7 Version B approved) |
Condition 2.33 |
As-built Drawings for Landscape and Visual Mitigation Measures |
4 Dec 2015 (1st submission) 28 Dec 2015 (2nd submission) 4 Feb 2016 (Approved) 22 Aug 2018 (3rd submission) 5 Nov 2018 (4th submission) 6 Sep 2019 (5th submission) 27 Sep 2019 (6th submission) 21 Feb 2020 (7th submission) |
Condition 2.36 |
Contamination Assessment Plan (CAP) for the Temporary Magazine Site at
TKO Area 137 |
23 Mar 2016 (1st submission) 20 Apr 2016 (2nd submission) 22 Apr 2016 (Approved) |
Condition 2.36 |
Contamination Assessment Report (CAR) for the Temporary Magazine Site
at TKO Area 137 |
19 May 2016 (1st submission) 3 Jun 2016 (2nd submission) 15 Jun 2016 (Approved) |
Condition 3.1 |
Proposal for Termination of Environmental Monitoring and Audit
(EM&A) Programme for Kai Tak Barging Point Facilities |
7 Oct 2016 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Works at Hin Keng |
9 May 2018 (1st submission) 16 July 2018 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Diamond Hill Station |
25 July 2019 (1st submission) 31 July 2019 (Approved) |
Condition 3.1 |
Proposal for Cessation of EM&A Programme at Hung Hom North
Approach Tunnels |
25 July 2019 (1st submission) 31 July 2019 (Approved) |
Condition 3.3 |
Baseline
Monitoring Report (Works Contract 1109 - Stations and Tunnels of Kowloon City
Section ) |
27 Jul 2012 |
Condition 3.3 |
Baseline
Monitoring Report (Works Contract 1108A – Kai Tak Barging Point Facilities) |
31 Jul 2012 |
Condition 3.3 |
Baseline
Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin Keng to Diamond
Hill Tunnels, Diamond Hill Station, and Hung Hom North Approach Tunnels) |
19 Oct 2012 |
Condition 3.4 |
Monthly EM&A
Reports No. 1-89 Monthly EM&A Report
No. 90 |
Reported in previous Monthly EM&A Reports 13 Mar 2020 |