Table of Contents

 

1......... Introduction. 1

1.1          Background. 1

1.2          Project Programme. 1

1.3          Purpose of the Report 2

2......... Environmental Monitoring and Audit. 2

3......... implementation status on the environmental protection requirements. 10

 

List of Tables

Table 1.1             Summary of Awarded Works Contracts

Table 2.1             Summary of Major Construction Activities in the Reporting Period

Table 2.2             Summary of 24-Hour TSP Monitoring Results in the Reporting Period

Table 2.3             Summary of Construction Noise Monitoring Results in the Reporting Period

Table 2.4             Log for Environmental Complaints, Notification of Summons and Successful Prosecutions for the Reporting Month

Table 3.1             Summary of Status of Required Submissions for EP-438/2012/K

 

 

 

List of Appendices

Appendix A         91st Monthly EM&A Report for Works Contract 1109 – Stations and Tunnels of Kowloon City Section

Appendix B         82nd Monthly EM&A Report for Works Contract 1112 – Hung Hom Station and Stabling Sidings Tunnels

 

 

                               


1                    Introduction

1.1               Background

1.1.1         The Shatin to Central Link (SCL) is a 17km extension of the existing Ma On Shan Line (MOL) and East Rail Line (EAL) comprising (i) The East-West Corridor which extends the MOL from Tai Wai to Hung Hom via East Kowloon to connect with the West Rail Line (WRL) at Hung Hom Station (HUH) and Stabling Sidings at Hung Hom Freight Yard (HHS); and (ii) The North-South Corridor which is an extension of the East Rail Line (EAL) at Hung Hom across the harbour to Admiralty Station (ADM).

1.1.2         Shatin to Central Link – Tai Wai to Hung Hom Section [SCL (TAW-HUH)] (hereafter referred to as “the Project”) is part of the SCL. Shatin to Central Link – Stabling Sidings at Hung Hom Freight Yard [SCL (HHS)] is a proposed stabling sidings option for SCL (TAW – HUH) at the former freight yard in Hung Hom.

1.1.3         The Environmental Impact Assessment (EIA) Reports for SCL (TAW-HUH) (Register No.: AEIAR-167/2012) and SCL (HHS) (Register No.: AEIAR-164/2012) were approved on 17 February 2012 under the Environmental Impact Assessment Ordinance (EIAO). Following the approval of the EIA Reports, an Environmental Permit (EP) was granted on 22 March 2012 covering SCL (TAW-HUH) and SCL (HHS) (EP No: EP-438/2012) for their construction and operation. Variations of environmental permit (VEP) were subsequently applied for EP-438/2012. The latest Environmental Permit (EP No.: EP-438/2012/K) was issued by Director of Environmental Protection (DEP) on 4 October 2016.

 

1.2       Project Programme

1.2.1         Eleven civil construction works contracts of the Project have been awarded since July 2012. The construction of the Project commenced in September 2012 and is expected to complete in 2019 tentatively. Table 1.1 summarises the information of the awarded Works Contracts.

Table 1.1             Summary of Awarded Works Contracts

Works Contract

Description

Construction Start Date

Contractor

Environmental Team

1101(1)

Ma On Shan Line Modification Works

December 2012

Sun Fook Kong Joint Venture

(SFKJV)

ANewR Consulting Ltd. (ANewR)

1102(6)

Hin Keng Station and Approach Structures

October 2013

Penta-Ocean Construction Co. Ltd.

Wellab Limited (Wellab)

1103(7)

Hin Keng to Diamond Hill Tunnels

February 2013

Vinci Construction Grands Projets

Ove Arup & Partners Hong Kong Ltd. (Arup)

October 2019

Wing Ho Yuen Landscaping Co. Ltd.

MTR Co. Limited

1106(8)

Diamond Hill Station

March 2013

Leader Joint Venture

Cinotech Consultants Ltd. (Cinotech)

1107(4)

Diamond Hill to Kai Tak Tunnels

May 2013

Chun Wo - SELI Joint Venture

Cinotech Consultants Ltd. (Cinotech)

1108(5)

Kai Tak Station and Associated Tunnels

June 2013

Kaden -Chun Wo Joint Venture

Environmental Pioneers & Solutions Ltd.

1108A(2)

Kai Tak Barging Point Facilities

September 2012

Concentric – Hong Kong River Joint Venture (CCL-HKR JV)

Cinotech Consultants Ltd. (Cinotech)

1109

Stations and Tunnels of Kowloon City Section

September 2012

Samsung-Hsin Chong JV (SSHCJV)

ERM-Hong Kong Limited (ERM)

1111(9)

Hung Hom North Approach Tunnels

January 2013

Gammon-Kaden SCL1111 JV

AECOM Asia Co. Ltd.

1112

Hung Hom Station and Stabling Sidings

June 2013

Leighton Contractors (Asia) Limited

SMEC Asia Ltd., HK

11240(3)

Excavation, Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site

October 2017

Crown Asia Engineering Limited (CAEL)

MTR Co. Limited

Notes:

(1)         All construction works (works areas at Tai Wai Mei Tin Road and the offsite temporary storage areas) under Works Contract 1101 were completed on 29 February 2016.

(2)         All construction works (Kai Tak Barging Point Facilities) under Works Contract 1108A were completed on 29 September 2016.

(3)         All construction works (Excavation, Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site) under Works Contract 11240 were completed on 3 January 2018.

(4)         All construction works (Diamond Hill to Kai Tak Tunnels) under Works Contract 1107 were completed on 22 February 2018.

(5)         All construction works (Kai Tak Station and associated tunnels) under Works Contract 1108 were completed in July 2018.

(6)         All construction works (Hin Keng Station and Approach Structures) under Works Contract 1102 were completed in December 2018. The Environmental Team was taken over by Wellab Limited starting from 1 January 2019.

(7)         All construction works (Hin Keng to Diamond Hill Tunnels) under Works Contract 1103 were completed in June 2019. Minor landscaping works at Fung Tak had been commenced in mid Oct and all the works were completed at the end of Oct 2019.

(8)         All construction works (Diamond Hill Station) under Works Contract 1106 with significant environmental impacts were substantially completed by 25 Jun 2019.

(9)         All major construction works (Hung Hom North Approach Tunnels) under Works Contract 1111 have been substantially completed since 18 Nov 2018 with only minor works remaining.

 

1.3       Purpose of the Report

1.3.1 The Environmental Monitoring and Audit (EM&A) programme for the Project commenced in September 2012. This is the ninety-first EM&A Report for the Project which summarises the EM&A works undertaken by the respective ETs during the period from 1 to 31 March 2020.

 

2                    Environmental Monitoring and Audit

2.1.1         The construction of SCL has been divided into different civil construction works contracts which are covered by EP No. EP-438/2012/K. As per the EP Conditions, EM&A Reports for the works contracts as shown in the table below have been prepared by the respective ETs.

Works Contract

Contract Title

Works Covered in Environmental Permit No.

1101

Ma On Shan Modification Works

EP-438/2012/K

1102

Hin Keng Station and Approach Structures

EP-438/2012/K

1103

Hin Keng to Diamond Hill Tunnels

EP-438/2012/K

1106

Diamond Hill Station

EP-438/2012/K

1107

Diamond Hill to Kai Tak Tunnels

EP-438/2012/K

1108

Kai Tak Station and Associated Tunnels

EP-438/2012/K

1108A

Kai Tak Barging Point Facilities

EP-438/2012/K

1109

Stations and Tunnels of Kowloon City Section

EP-438/2012/K

1111

Hung Hom North Approach Tunnels

EP-438/2012/K

1112

Hung Hom Station and Stabling Sidings

EP-438/2012/K

11240

Excavation, Sorting and Disposal of Stockpiled Spoils to Approved Receptor Site

EP-438/2012/K

 

2.1.2 The EM&A Reports for Works Contracts 1109 and 1112 prepared by the respective ETs are provided in Appendices A to B respectively. The EM&A Reports provide details of the project information, EM&A requirements, impact monitoring and audit results for the corresponding Contracts.

2.1.3 A summary of the major construction activities undertaken by the respective Contractors of various Works Contracts during the reporting period are presented in Table 2.1.

 

Table 2.1             Summary of Major Construction Activities in the Reporting Period

Works Contract

Site

Construction Activities

 

 

1109

 

Works in To Kwa Wan (TKW) (formerly named as Ma Tau Wai (MTW))

·     To Kwa Wan Station – ABWF works;

·     Ma Tau Wai Road – Removal of D-wall, construction of carriageway panel near Chi Kiang Street, and footpath reinstatement works at northbound footpath between Kiang Su Street and Chi Kiang Street;

·     Ventilation Shaft and Entrance A – Reinstatement of Lok Shan Road Playground and To Kwa Wan Complex Playground;

·     Junction of Ma Tau Wai Road and Chi Kiang Street – Construction of small garden;

·     Entrance D – Reinstatement of Ma Tau Wai Road/ To Kwa Wan Road Garden; and

·     All Work Areas – Maintenance, repairing, rectification and protection improvement works for the structure within 1109 Contract Boundary due to social activities.

Works in Sung Wong Toi (SUW) (formerly named as To Kwa Wan (TKW))

·     Sung Wong Toi Station – ABWF works; and

·     All Works Areas – Maintenance, repairing, rectification and protection improvement works for the structure within 1109 Contract Boundary due to social activities.

1112

Hung Hom Station (HUH)

·     Minor services connection at G.L J of HUH;

·     Platform ABWF and E&M works;

·     Remedial works at HUH

SAT Ventilation Shaft

·     Landscape preparation works

Concourse level & Mid-level walkway

·     Modification works

 

2.1.4         Impact monitoring for air quality and construction noise were conducted in accordance with the EM&A Manual in the reporting period. Continuous noise monitoring was not required in the reporting period for all Works Contracts according to the Continuous Noise Monitoring Plan (CNMP). The air quality and construction noise for this reporting month are summarised in Tables 2.2 and 2.3. Details of the monitoring requirements, locations, equipment, methodology and QA/QC procedures are presented in the EM&A Reports as provided in Appendices A to B.

2.1.5         Water quality monitoring was not carried out during this reporting period since no dredging activity was conducted in the reporting month.

2.1.6 No environmental complaint, exceedance of limit level, notification of summons or successful prosecutions was received during the reporting period. Log for environmental complaints, notification of summons and successful prosecutions are provided in Table 2.4.

2.1.7 Regular site inspections were conducted by the respective ETs on a weekly basis to check the implementation of environmental pollution control and mitigation measures for the Project. No non-conformance was identified in the reporting period.

Table 2.2             Summary of 24-Hour TSP Monitoring Results in the Reporting Period

Monitoring Station ID

Location

TSP Concentration (mg/m3)

Action Level

(mg/m3)

Limit Level (mg/m3)

Exceedance due to the Project Construction

(Yes/ No/ N/A)

Works Contracts 1102 and 1103

 

 

 

 

DMS-1(11)

C.U.H.K.A.A. Thomas Cheung School

N/A

148.7

260

N/A

Works Contract 1103

 

 

 

 

DMS-2(12)

Price Memorial Catholic Primary School

N/A

167.4

260

No

Works Contracts 1103 and 1106

 

 

 

 

DMS-3(13)

Hong Kong S.K.H Nursing Home (1)

N/A

159.1

260

No

Works Contract 1106(10)

 

 

 

 

DMS-4(13)

Block 1, Rhythm Garden

N/A

160.4

260

No

Works Contract 1108 (5)

 

 

 

 

Works Contract 1109

 

 

 

 

DMS-6

Katherine Building (2)

36 – 65

156.8

260

No

DMS-7

Parc 22 (3)

28 – 56

166.7

260

No

DMS-8

SKH Good Shepherd Primary School

32 – 68

152.2

260

No

DMS-9

No. 12 Pau Chung Street (4)(9)

46 – 93

160.9

260

No

DMS-10

Chat Ma Mansion

37 – 88

170.4

260

No

Works Contract 1111

 

 

 

 

AM1(6)(14)

No. 234 – 238 Chatham Road North (7)

N/A

183.9

260

No

Works Contract 1112

 

 

 

 

AM2

Site Boundary of Finger Pier Adjacent To Harbourfront Horizon (8)

44.0 – 51.4

182

260

No

Works Contract 11240 (5)

 

 

 

 

Notes:

(1)         Alternative monitoring location to Shek On House

(2)         Alternative monitoring location to Prosperity House

(3)         Alternative monitoring location to Skytower Tower 2

(4)         Alternative monitoring location to Lucky Building

(5)         No TSP monitoring is required under this contract

(6)         AM1 named as HUH-1-3 in SCL(TAW-HUH) and SCL(HHS) EIA Reports.

(7)         Alternative monitoring location to Wing Fung Building

(8)         Alternative monitoring location to Harbourfront Horizon

(9)         Alternative monitoring location of No. 26 Kowloon City Road

(10)     The 24-hour TSP monitoring works would be taken up by Works Contract 1106 since the completion of Works Contract 1107 in Feb 2018. 

(11)     The cessation of monitoring works at DMS-1 was approved by EPD and the last monitoring was conducted on 16 Jul 2018.

(12)     The temporary cessation of monitoring works at DMS-2 was approved by EPD in end-June 2019. The last monitoring date was 27 June 2019.

(13)     The cessation of monitoring works at DMS-3 and DMS-4 was approved by EPD on 31 Jul 2019. The last monitoring was conducted on 30 Jul 2019.

(14)     The cessation of monitoring works at AM1 was proposed on 25 Jul 2019 and EPD expressed no objection on 31 Jul 2019.

 


Table 2.3             Summary of Construction Noise Monitoring Results in the Reporting Period

Monitoring Station ID

Location

Noise Level (LAeq,30mins, dB(A))

Limit Level

(dB(A))

Exceedance due to the Project Construction

(Yes/No)

Measured

Baseline

Corrected (7)

Works Contracts 1102 and 1103

 

 

 

 

 

NMS-CA-1(12)

C.U.H.K.A.A. Thomas Cheung School

N/A

57.0

N/A

70

(65 during examination period)

No

Works Contract 1103

 

 

 

 

 

NMS-CA-2(13)

Price Memorial Catholic

Primary School

N/A

66.0

N/A

70

(65 during examination period)

No

Works Contracts 1103 and 1106

 

 

 

 

 

NMS-CA-3(14)

Hong Kong S.K.H

Nursing Home (1)

N/A

73.0

N/A

70

No

Works Contracts 1106(11)

 

 

 

 

 

NMS-CA-4(14)

Block 1, Rhythm Garden (north-eastern façade)

N/A

71.0

N/A

75

No

NMS-CA-5(14)

Block 1, Rhythm Garden (northern façade)(2)

N/A

74.0

N/A

70

(65 during examination period)

No

Works Contract 1108 (6)

 

 

 

 

 

Works Contract 1109

 

 

 

 

 

NMS-CA-6

No. 16-23 Nam Kok Road (3)

61.9 – 62.3

76.1

< Baseline

75

No

NMS-CA-7

Skytower Tower 2

65.6 – 66.9

70.0

< Baseline

75

No

NMS-CA-8

SKH Good Shepherd

Primary School

72.4 – 73.4

75.4

< Baseline

70

(65 during examination period)

(79 during the period of conducting the continuous noise monitoring) (8)

No

NMS-CA-9

Kong Yiu Mansion (4)

69.2 – 70.2

69.2

< Baseline – 63.3

75

No

NMS-CA-10

Chat Ma Mansion

75.776.1

76.6

< Baseline

75

No

Works Contract 1111

 

 

 

 

 

NM1(15)

Carmel Secondary School

(South Block)

N/A

68.0

N/A

70

(65 during examination period)

(68 during the period of conducting the continuous noise monitoring) (9)

No

NM2(15)

No. 234 – 238 Chatham Road North (5)

N/A

79.0

N/A

75 (77) (10)

No

Works Contract 1112 (6)

 

 

 

 

 

Works Contract 11240 (6)

 

 

 

 

 

Notes:

(1)         Alternative monitoring location to Shek On House.

(2)         Alternative monitoring location to Canossa Primary School (San Po Kong).

(3)         Alternative monitoring location to Prosperity House.

(4)         Alternative monitoring location to Lucky Building.

(5)         Alternative monitoring location to Wing Fung Building.

(6)         No construction noise monitoring is required under this contract.

(7)         The measured noise levels are corrected against the corresponding baseline noise levels.

(8)        The Limit Level of 79 dB(A) was updated on 22 Aug 2013 as per the latest Construction Noise Mitigation Measures Plan (CNMMP) and Continuous Noise Monitoring Plan (CNMP) which were approved by EPD.

(9)        The Limit of 68 dB(A) was updated on 20 Jan 2014 as per the latest CNMMP and CNMP which were approved by EPD.

(10)     Daytime noise Limit Level of 77 dB(A) applies during the continuous noise monitoring period.

(11)     The construction noise monitoring works would be taken up by Works Contract 1106 since the completion of Works Contract 1107 in Feb 2018.

(12)     The cessation of monitoring works at NMS-CA-1 was approved by EPD and the last monitoring was conducted on 17 Jul 2018.

(13)     The temporary cessation of monitoring works at NMS-CA-2 was approved by EPD in end-June 2019. The last monitoring date was 24 Jun 2019.

(14)     The cessation of monitoring works at NMS-CA-3, NMS-CA-4 and NMS-CA-5 was approved by EPD on 31 Jul 2019. The last monitoring proposed on 31 Jul 2019 was rescheduled to 1 Aug 2019 due to adverse weather and the hoist of Typhoon Signal No.8 (Typhoon “Wipha”).

(15)     The cessation of monitoring works at NM1 and NM2 were proposed on 25 Jul 2019 and EPD expressed no objection on 31 Jul 2019.

 

 

 


Table 2.4             Log for Environmental Complaints, Notification of Summons and Successful Prosecutions for the Reporting Month

 

Works Contract

Environmental Complaints

Notification of Summons

Successful Prosecutions

1109

0

0

0

1112

0

0

0

 

 

 


 

3                    implementation status on the environmental protection requirements

 

3.1.1         The respective Contractors have implemented all mitigation measures and requirements as stated in the EIA Reports, EM&A Manuals and EP (EP-438/2012/K). The status of required submissions under the EP as of the reporting period are summarised in Tables 3.1.

Table 3.1             Summary of Status of Required Submissions for EP-438/2012/K

EP Condition

(EP-438/2012/K)

Submission

Submission date

Condition 1.12

Notification of Commencement Date of Construction of the Project

1 Aug 2012

Condition 2.3

Notification of Information of Community Liaison Groups

13 Jul 2012 (1st submission)

31 Aug 2012 (2nd submission)

30 Nov 2012 (3rd submission)

Condition 2.7

Management Organisation of Main Construction Companies

27 Jul 2012 (1st submission)

21 Aug 2012 (2nd submission)

19 Dec 2012 (3rd submission)

22 Jan 2013 (4th submission)

30 Apr 2013 (5th submission)

21 May 2013 (6th submission)

Condition 2.8

Construction Programme and EP Submission Schedule

27 Jul 2012

Condition 2.9

Construction Noise Mitigation Measures Plan (CNMMP)

1 Aug 2012 (1st submission)

28 Sep 2012 (2nd submission)

30 Nov 2012 (3rd submission)

11 Jan 2013 (4th submission)

8 Feb 2013 (Approved)
8 Feb 2013 (5th submission)

26 Apr 2013 (6th submission)

11 Jun 2013 (7th submission)

12 Jul 2013 (Approved)

26 Jul 2013 (8th submission)

22 Aug 2013 (Approved)

23 Aug 2013 (9th submission)

13 Sep 2013 (Approved)

20 Jan 2014 (10th submission)

26 Feb 2014 (Approved)

31 Mar 2015 (Contract 1106 submission only)

13 Apr 2015 (Contract 1106 submission only)

15 Apr 2015 (Approved)

Condition 2.10

Continuous Noise Monitoring Plan (CNMP)

1 Aug 2012 (1st submission)

28 Sep 2012 (2nd submission)

30 Nov 2012 (3rd submission)

11 Jan 2013 (4th submission)

8 Feb 2013 (Approved)

8 Feb 2013 (5th submission)

26 Apr 2013 (6th submission)

11 Jun 2013 (7th submission)

12 Jul 2013 (Approved)

26 Jul 2013 (8th submission)

22 Aug 2013 (Approved)

23 Aug 2013 (9th submission)

13 Sep 2013 (Approved)

20 Jan 2014 (10th submission)

26 Feb 2014 (Approved)

7 Oct 2014 (11th submission)

23 Oct 2014 (Approved)

Condition 2.11

Construction and Demolition Materials Management Plan (C&DMMP)

6 Jul 2012 (1st submission)

12 Sep 2012 (2nd submission)

10 Oct 2012 (Approved)

Condition 2.12

Sediment Management Plan

6 Jul 2012 (1st submission)

12 Sep 2012 (2nd submission)

5 Oct 2012 (3rd submission)

10 Oct 2012 (Approved)

4 Mar 2013 (4th submission)

9 May 2013 (5th submission)

24 Jul 2013 (6th submission)

26 Jul 2013 (Approved)

Condition 2.13

Visual, Landscape, Tree Planting & Tree Protection Plan

6 Jul 2012 (1st submission)

30 Aug 2012 (2nd submission)

3 Oct 2012 (3rd submission)

13 Nov 2013 (Approved)

14 Nov 2012 (4th submission)

8 Feb 2013 (5th submission)

18 Mar 2013 (6th submission)

18 Jun 2013 (7th submission)

12 Jul 2013 (Approved)

23 Mar 2017 (8th submission)

7 Mar 2018 (9th submission)

30 Jul 2018 (10th submission)

28 Feb 2019 (11th submission)

5 Mar 2019 (12th submission)

29 May 2019 (13th submission)

19 Jul 2019 (Approved)

Condition 2.14

Transplantation Proposal for Plant Species of Conservation Importance

22 Aug 2012 (1st submission)

5 Oct 2012 (2nd submission)

26 Nov 2012 (3rd submission)

4 Dec 2012 (Approved)

Condition 2.15

Conservation Plan

31 Jan 2013 (1st submission)

18 Mar 2013 (2nd submission)

24 Apr 2013 (Approved)

Condition 2.16

Archaeological Action Plan(s) (AAP(s)) for Works Contract 1109

10 Aug 2012 (1st submission)

3 Sep 2012 (2nd submission)

21 Sep 2012 (Approved)

11 Oct 2013 (3rd submission)

1 Nov 2013 (Approved)

Condition 2.16

Archaeological Action Plan(s) (AAP(s)) for Works Contract 1106

29 Jan 2013 (1st submission)

19 Mar 2013 (2nd submission)

8 Apr 2013 (Approved)

Condition 2.23

Supplementary Contamination Assessment Report for New Territories South Animal Centre

28 Sep 2012

25 Oct 2012 (Approved)

Condition 2.27

Operational Ground-borne Noise Mitigation Measures Plan

18 Mar 2016 (Batch 1 Version A submission)

28 Apr 2016 (Batch 1 Version B submission)

28 Apr 2016 (Batch 2 Version A submission)

1 Jun 2016 (Batch 1 Version C submission)

1 Jun 2016 (Batch 2 Version B submission)

23 Jun 2016 (Batch 1 Version D submission)

23 Jun 2016 (Batch 2 Version C submission)

15 Jul 2016 (Batch 1 Version D approved)

15 Jul 2016 (Batch 2 Version C approved)

15 Sep 2016 (Batch 3 Version A submission)

4 Oct 2016 (Batch 3 Version A approved)

8 Mar 2017 (Batch 4 Version A)

7 Apr 2017 (Batch 4 Version A approved)

7 Jun 2017 (Final)

20 Jul 2017 (Approved)

Condition 2.28

As-built Drawings for Operational Ground-borne Noise Mitigation Measures

10 Aug 2017 (1st submission)

Condition 2.30

As-built Drawings for Operational Air-borne Noise Mitigation Measures

4 Dec 2015 (1st submission)

28 Dec 2015 (2nd submission)

4 Feb 2016 (Approved)

20 Mar 2018 (3rd submission)

18 Jul 2018 (Approved)

4 May 2018 (4th submission)

23 Jul 2018 (Approved)

20 Feb 2020 (5th submission)

Condition 2.31

Performance Test Report for Train Noise – Operational Airborne Railway and Ground-borne Noise

15 Nov 2018 (Batch 1 Version A submission)

30 Jan 2019 (Batch 2 Version A submission)

29 Mar 2019 (Batch 1 Version A & Batch 2 Version B submission)

15 April 2019 (Approved)

Condition 2.32

Proposal for Updating Maximum Allowable Sound Power Levels of Fixed Plant Sources

30 Jan 2019 (Batch 1 Version A submission)

27 Feb 2019 (Batch 1 Version B submission)

13 Mar 2019 (Batch 1 Version B approved)

15 Mar 2019 (Batch 2 Version A submission)

8 Apr 2019 (Batch 2 Version A approved)

24 April 2019 (Batch 3 & 4 Version A submission)

21 May 2019 (Batch 3 Version B submission)

11 Jun 2019 (Batch 3 Version B & Batch 4 Version A approved)

21 Jun 2019 (Batch 5 Version A submission)

17 Jul 2019 (Batch 5 Version A approved)

19 Jul 2019 (Batch 6 Version A submission)

26 Jul 2019 (Batch 7 Version A submission)

29 Jul 2019 (Batch 6 Version A approved)

14 Aug 2019 (Batch 7 Version A approved)

Condition 2.32

Fixed Plant Noise Audit Report

30 Jan 2019 (Batch 1 Version A submission)

15 Mar 2019 (Batch 1 Version B submission)

4 Apr 2019 (Batch 1 Version B approved)

16 Apr 2019 (Batch 2 Version A submission)

7 May 2019 (Batch 2 Version A approved)

24 Jun 2019 (Batch 3 Version A and Batch 4 Version A submission)

6 Jul 2019 (Batch 3 Version A and Batch 4 Version A approved)

2 Aug 2019 (Batch 5 Version A submission)

27 Aug 2019 (Batch 6 Version A submission)

29 Aug 2019 (Batch 7 Version A submission)

3 Sep 2019 (Batch 5 Version A approved)

13 Sep 2019 (Batch 6 Version B approved)

23 Sep 2019 (Batch 7 Version B submission)

11 Oct 2019 (Batch 7 Version B approved)

Condition 2.33

As-built Drawings for Landscape and Visual Mitigation Measures

4 Dec 2015 (1st submission)

28 Dec 2015 (2nd submission)

4 Feb 2016 (Approved)

22 Aug 2018 (3rd submission)

5 Nov 2018 (4th submission)

6 Sep 2019 (5th submission)

27 Sep 2019 (6th submission)

21 Feb 2020 (7th submission)

Condition 2.36

Contamination Assessment Plan (CAP) for the Temporary Magazine Site at TKO Area 137

23 Mar 2016 (1st submission)

20 Apr 2016 (2nd submission)

22 Apr 2016 (Approved)

Condition 2.36

Contamination Assessment Report (CAR) for the Temporary Magazine Site at TKO Area 137

19 May 2016 (1st submission)

3 Jun 2016 (2nd submission)

15 Jun 2016 (Approved)

 

Condition 3.1

Proposal for Termination of Environmental Monitoring and Audit (EM&A) Programme for Kai Tak Barging Point Facilities

7 Oct 2016 (Approved)

Condition 3.1

Proposal for Cessation of EM&A Works at Hin Keng

9 May 2018 (1st submission)

16 July 2018 (Approved)

Condition 3.1

Proposal for Cessation of EM&A Programme at Diamond Hill Station

25 July 2019 (1st submission)

31 July 2019 (Approved)

Condition 3.1

Proposal for Cessation of EM&A Programme at Hung Hom North Approach Tunnels

25 July 2019 (1st submission)

31 July 2019 (Approved)

Condition 3.3

Baseline Monitoring Report (Works Contract 1109 - Stations and Tunnels of Kowloon City Section )

27 Jul 2012

Condition 3.3

Baseline Monitoring Report (Works Contract 1108A – Kai Tak Barging Point Facilities)

31 Jul 2012

Condition 3.3

Baseline Monitoring Report (Works Contracts 1103, 1106 and 1111 – Hin Keng to Diamond Hill Tunnels, Diamond Hill Station, and Hung Hom North Approach Tunnels)

19 Oct 2012

Condition 3.4

Monthly EM&A Reports No. 1-89

 

 

Monthly EM&A Report No. 90

Reported in previous Monthly EM&A Reports

 

13 Mar 2020