Environmental Impact Assessment (EIA) Ordinance, Cap. 499

Application for Permission to Apply Directly for Environmental Permit

Application No.: DIR-072/2002

 

Project Title : Decommissioning of Gas Turbine Units (GT3 – GT6) inside

Castle Peak Power Station

 

Conditions Imposed under Section 5(12) of the Ordinance

for Permission to Apply Directly for Environmental Permit

 

 

1.      All measures described in the Project Profile PP-178/2002 submitted by the applicant on 27 November 2002, together with the requirement mentioned in the following condition, shall be fully implemented.

 

2.      No excavation work shall be permitted.

 

 

 

 

Note:

 

Under section 17 of the EIA Ordinance, the applicant may appeal to the Appeal Board against any of the above conditions within 30 days of the receipt of this notice of the Director’s decision.

 

 

 

 

Environmental Protection Department