Environmental Impact Assessment (EIA) Ordinance, Cap. 499

Application for Permission to Apply Directly for Environmental Permit

Application No.: DIR-082/2003

 

Project Title: Design and Construction of Causeway Bay Flyover

 

Conditions Imposed under Section 5(12) of the Ordinance

for Permission to Apply Directly for Environmental Permit

 

 

1.          Transplantation shall be carried out as described in the Project Profile submited by the applicant on 23 April 2003, before the commencement of construction.

 

2.          All measures described in the Project Profile shall be fully implemented.

 

 

Note:

Under Section 17 of the EIA Ordinance, the applicant may appeal to the Appeal Board against any of the above conditions within 30 days of the receipt of this notice of the Director’s decision.

 

 

Environmental Protection Department

May 2003