Environmental Impact Assessment (EIA) Ordinance, Cap. 499

Application for Permission to Apply Directly for Environmental Permit

Application No.: DIR-084/2003

 

Project Title: Stanley Waterfront Improvement Project – Construction of Boardwalk

 

Conditions Imposed under Section 5(12) of the Ordinance

for Permission to Apply Directly for Environmental Permit

 

 

1.            All measures described in the Project Profile submitted by the Applicant on 2 July 2003 shall be fully implemented.

 

2.            Water quality monitoring and audit described in the Project Profile shall be carried out during construction stage. The Applicant shall submit, prior to the application for Environmental Permit, the water quality monitoring and audit manual to the Director of Environmental Protection for approval.

 

3.            The placing of backfill material shall only be carried out after the vertical seawall is completed to the level of the high water mark or above.

 

 

 

 

 

Note

Under section 17 of the EIA Ordinance, the Applicant may appeal to the Appeal Board against any of the above conditions within 30 days of the receipt of this notice of the Director’s decision.

 

 

Environmental Protection Department

August 2003