Environmental Impact Assessment (EIA) Ordinance, Cap.499
Application for Permission to Apply Directly for Environmental Permit
(Application No.: DIR-108/2004)
Project Title : 10-Year Extended Landslip
Preventive Measures (LPM) Project,
Phase 3, Package D, Outlying Islands
Location: Along Keung Shan Road, Lantau
(Feature No. 13NW-B/C319)
Conditions Imposed under Section 5(12) of the
Ordinance
for Permission to Apply Directly for
Environmental Permit
1.
All
measures described in the Project Profile submitted by the Applicant on 22
September 2004, together with those requirements mentioned in the following
conditions, shall be fully implemented.
2.
A
detailed Landscape Proposal with sufficient quantity of plants and
justification for the use of particular plant species shall be submitted for
approval. The Landscape Proposal shall contain the following information:
(a)
proposed
slope treatment, including consideration of (i) sprayed concrete with colour
paint; (ii) masonry finish for the slope; (iii) planting of hardy tree species
instead of climbers on planter holes; (iv) more tree planting along the whole
slope toe; (v) berm planting; and (vi) tree preservation
(b)
quantity
of plants to be planted
(c)
justification
for the use of particular plant
(d)
the
design, works area and construction method of soil nails installation
(e)
overall
implementation of landscape and visual mitigation measures.
Note
Under Section 17 of the EIA Ordinance, the Applicant may
appeal to the Appeal Board against any of the above conditions within 30 days
of the receipt of this notice of the Director’s decision.
Environmental Protection Department
November 2004