Environmental Impact Assessment
(EIA) Ordinance, Cap.499
Application No.: DIR-142/2006
Protect Title: Natural Terrain
Hazard Mitigation Works in Luk Keng Wong
Conditions Imposed under Section 5(12) of the EIA Ordinance
For Permission to Apply Directly for Environmental Permit
1.
All measures described in the
Project Profile submitted by the Applicant on 2 June 2006 shall be fully
implemented.
2.
The applicant shall submit to the
Director for approval, at least 4 weeks before commencement of construction, 3
sets of layout drawing showing the locations of the plant species of
conservation importance including Aquilaria sinensis, Artocarpus
stracifoilus and Cibotium barometz and a proposal to protect all
trees recommended to be retained on site, in particular the species of
conservation importance, before the commencement of works.
3.
Tree losses of common species arising from the Project shall be
compensated and the loss to compensation ratio shall be at least 1:1.5.
4.
An ecologist/plant specialist shall be employed to station on site
during construction to supervise the selection of the locations of the works
and the avoidance of trees and concerned plants. He shall also supervise and
advise during replanting.
Note
Under Section 17 of the
EIA Ordinance, the applicant may appeal to the Appeal Board against any of the
above conditions within 30 days of the receipt of this notice of the Director’s
decision.
Environmental
Protection Department
July
2006