Environmental
Impact Assessment (EIA) Ordinance, Cap.499
( Application
No. : DIR- 168/2008)
for
Permission to Apply Directly for Environmental Permit
1. The Applicant shall update the construction noise impact assessment and operational noise impact assessment at the detail design stage, taking into account of the change in site locations and planned land uses in the vicinity after the approval of the EIA report in the register (EIAO Register Ref : AEIAR - 044/2001).
2. The Application shall submit a landscape plan to the Director for approval before commencement of construction of the Project.
Under section 17 of the EIA Ordinance, the applicant
may appeal to the Appeal Board against the above conditions within 30 days of
receipt of the notice of the Director’s decision.
Environmental Protection Department
September 2008