Environmental Impact Assessment (EIA) Ordinance, Cap.499
Application for Permission to Apply Directly for Environmental Permit
(Application No.: DIR-184/2009)
Project Title: Improvement Works of Seabed at
the Northwest of Tung Wan, Peng Chau
Conditions Imposed under Section 5(12) of the
EIA Ordinance
for Permission to Apply Directly for
Environmental Permit
1. All
measures described in the Project Profile submitted by the Applicant on 25 June
2009 shall be fully implemented.
2. Standing
type silt curtain should be employed and maintained at all time throughout
the excavation and sand filling operation to minimize the water quality impact.
3. No
more than two backhoes, one bulldozer and 5 village vehicles shall be employed
for the excavation operation.
4. No
more than two backhoes, one bulldozer and 1 conveyor belt barge shall be
employed for the sand filling operation.
5. The
excavation rate shall not exceed 100 cubic metre per day at all time throughout
the excavation operation.
6. No
construction works of the project shall be carried out between 1900 to 0700
hours and any time on a general holiday including Sunday.
7. The
water quality monitoring programme described in Section
Note
Under Section 17 of the EIA Ordinance, the Applicant may
appeal to the Appeal Board against the above conditions within 30 days of the
receipt of this notice of the Director’s decision.
Environmental Protection Department
August 2009