Application No.: DIR-195/2009

 

Project Title: Hill-top Transposer Station Expansion at Hill 374, Lam Tsuen Country Park,

Short Term Tenancy No. 1985, DD 104

 

 

Conditions Imposed under Section 5(12) of the Ordinance

for Permission to Apply Directly for Environmental Permit

 

 

1.          All measures proposed in the Project Profile (No. PP-405/2009) submitted by the Applicant on 17 December 2009 shall be fully implemented.

 

 

 

 

 

 

Note

 

Under section 17 of the EIA Ordinance, the Applicant may appeal to the Appeal Board against the above condition within 30 days of the receipt of this notice of the Director’s decision.

 

 