Environmental Impact Assessment (EIA) Ordinance, Cap. 499

Application for Permission to Apply Directly for an Environmental Permit

Application No.: DIR-210/2010

 

Project Title : Yau Tong Bay – Decommissioning of Shipyard Sites

 

Conditions Imposed under Section 5(12) of the EIA Ordinance

for Permission to Apply Directly for Environmental Permit

 

1.      All measures described in the Project Profile (No. PP-427/2010) submitted by the Applicant on 10 November 2010 shall be fully implemented;

 

2.      All the mitigation measures, submissions and Environmental Monitoring and Audit (EM&A) programme as proposed in the Yau Tong Bay Development - Reclamation of Yau Tong Bay EIA Report (Register No. AEIAR – 053/2002) that are relevant to this project shall be fully implemented;

 

3.      At least one month before the commencement of the project, the Applicant shall submit to the Director for approval of an updated EM&A manual for the Project; and

 

4.      For those lots that were inaccessible during the EIA stage, the submission of the Contamination Assessment Plan (CAP), Contamination Assessment Report (CAR) and Remediation Action Plan (RAP) shall be prepared in accordance with the procedures and requirements stipulated in the EPD’s “Guidance Note for Contaminated Land Assessment and Remediation (dated 15 August 2007)” and “Guidance Manual for use of Risk-Based Remediation Goals (RGRBs) for Contaminated Land Management (dated December 2007)”..

 

 

 

 

 

Note

Under Section 17 of the EIA Ordinance, the Applicant may appeal to the Appeal Board against any of the above conditions within 30 days of the receipt of this notice of the Director’s decision.

 

 

Environmental Protection Department