Environmental Permit No. : EP-007/1998
環境許可證編號 : EP-007/1998
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
Section 10
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE A DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
PART A (MAIN PERMIT)
A部(許可證主要部分)
Pursuant to Section 10 of the Environmental Impact Assessment Ordinance, the Director of Environmental Protection (the Director) grants this environmental permit to the MASS TRANSIT RAILWAY CORPORATION (the "Permit Holder") to construct and operate the designated project described in Part B subject to the conditions described in or attached to Part C. The issue of this environmental permit is based on the documents, approvals or permissions described below:
根據環境影響評估條例第10條的規定﹐環境保護署署長(署長)將本環境許可證批予香港地下鐵路公司(許可證持有人)以建造及營辦 B部 所說明的指定工程項目﹐但須遵守 C部 所說明或附載的條件。本環境許可證的發出﹐乃以下表所列的文件、批准或許可作為根據:-
Application No.
|
AEP 006/1998
|
Document in the Register :
|
(1) Feasibility Study and Preliminary Design for Tseung Kwan O Extension Quarry Bay Congestion Relief Works Detailed Environmental Impact Assessment Report R9T, Volumes I to III (Register No. EIA-120/BC). [Hereinafter referred to as the Phase I EIA Report]
(2) Tseung Kwan O Extension Phase II: Environmental Impact Assessment (Register No. EIA-132/BC). [Hereinafter referred to as the Phase II EIA Report]
|
____________________________________
|
____________________________________
|
PART B (DESCRIPTIONS OF DESIGNATED PROJECT)
B部(指定工程項目的說明)
Hereunder is the description of the designated project mentioned in Part A of this environmental permit :
下列為本環境許可證A部所提及的指定工程項目的說明:
Title of Designated Project
|
MTR Tseung Kwan O Extension-Phases I & II. [This designated project is hereinafter referred to as "the Project"]
| |
Nature of Designated Project
指定工程項目的性質 |
A railway, its associated stations and a railway depot.
鐵路、其相聯車站及鐵路車廠。 |
|
Location of Designated Project
|
Figures TKE/K/00/CIP/P02/001-003 as submitted by the Application and attached to this permit show the locations of the railway alignment, its six associated stations, ancillary buildings, the railway depot and construction sites (including temporary work sites)
|
|
Scale and Scope of Designated Project
|
MTRC Tseung Kwan O Extension-Phases I & II include the construction and operation of:
(a) A new Tseung Kwan O Line by means of a junction east of Tseung Kwan O Station providing two services; one from Po Lam Station and one from Area 86 Station in the south of Tseung Kwan O New Town (Area 86), to Tseung Kwan O Station. The Tseung Kwan O Line will run in tunnel, westward through Tiu Keng Leng and Yau Tong Stations to connect with the existing Eastern Harbour Crossing.
(b) A diversion of the existing Kwun Tong Line from the existing Lam Tin Station, to the Yau Tong and Tiu Keng Leng Stations, where cross platform interchanges will be provided with the Tseung Kwan O Line services.
(c) Interchange facilities between the Tseung Kwan O Line and the diverted Kwun Tong Line at Yau Tong and Tiu Keng Leng Stations, with appropriate tunnel configurations in the Black Hill Tunnels.
(d) Six new stations along the railway alignment, ie. Yau Tong Station, Tiu Keng Leng Station, Tseung Kwan O Station, Hang Hau Station, Po Lam Station and the Station in Area 86.
(e) A railway depot, to be provided in Area 86, for stabling trains and maintenance required for the operation of the Tseung Kwan O Line.
(f) Ancillary buildings including traction substations and ventilation buildings.
(Other descriptions of the scale and scope of the Project are given in section 1.2.2 of the Phase I EIA Report, Volume II and section 1.2.2 of the Phase II EIA Report mentioned in Part A of this permit.)
|
PART C (PERMIT CONDITIONS) / C 部 (許 可 證 條 件) 及 附 件 A