Environmental Permit No. EP-140/2002

環境許可證編號EP-140/2002

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE

(CHAPTER 499)

Section 10

 

環境影響評估條例

(499)

10

 

ENVIRONMENTAL PERMIT TO CONSTRUCT A PART OF THE

DESIGNATED PROJECT

 

建造及營辦指定工程項目的環境許可證

 

PART A (MAIN PERMIT)

A (許可證主要部分)

 

Pursuant to Sections 10 of the Environmental Impact Assessment Ordinance (the EIAO), the Director of Environmental Protection (the Director) grants this Environmental Permit to Civil Engineering Department (hereinafter referred to as the “Permit Holder”) to construct the designated project described in Part B subject to the conditions specified in Part C.  The issue of this Environmental Permit is based on the documents, approvals or permissions described below:

 

根據環境影響評估條例第10條的規定,環境保護署署長(署長)將本環境許可證批予 土木工程署 (下稱許可證持有人) 以建造B部所說明的指定工程項目,但須遵守C部所列明的條件本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據

 

 

Application No.

申請書編號:

 

 

 AEP-140/2002

 

 

Document in the Register:

登記冊上的文件:

 

 

(1) Planning and Engineering Feasibility Study for Development at Anderson Road

(Register No. AEIAR-005/1999)

安達臣道發展計劃的規劃及程可行性研究

(登記冊編號:AEIAR-005/1999)

 

- Environmental Impact Assessment Report (September 1998) [hereinafter referred to as the "EIA Report"]

- 環境影響評估報告 (19989) [下稱 「環評報告」]

 

- Environmental Monitoring and Audit Manual

- 環境監察審核手冊  (19989)

 

- Executive Summary

- 摘要  (19989)

 

(2) The Director’s letter approval of the EIA Report dated 2.3.1999 in (28) in EP2/K14/P/09 Ax(1) Part 4

      署長已於199932日發出該環評報告的批准信,檔案編號(28) in EP2/K14/P/09 Ax(1) Part 4

 

 

 

(3) Application documents including all attachments submitted by the Permit Holder on 21.5.2002 (Application No. AEP-140/2002)

      申請文件包括許可證持有人於2002521日提交的所有附件 (申請書編號 AEP-140/2002) [下稱 申請書]

 

 

  

 

 

 

 

18 June 2002

 

 

 

Date

日期

 

(Shirley S.L. Lee)

Acting Assistant Director of Environmental Protection

(Environmental Assessment and Noise)

for Director of Environmental Protection

環境保護署署長

(署理助 ( ) 李韓琇玲代 )

 

 

 


PART B (DESCRIPTIONS OF DESIGNATED PROJECT)

B (指定工程項目的說明)

 

Hereunder is the description of the designated project mentioned in Part A of this environmental permit:

(hereinafter referred to as the Permit)

下列為本環境許可證(下稱許可證)A部所提述的指定工程項目的說明:

 

 

Title of Designated Project

指定工程項目的名稱

 

 

Po Lam Road – road widening [This designated project is hereinafter referred to as “the Project”]

寶琳路–道路擴闊工程 [本指定工程項目下稱「工程項目」]

 

 

 

Nature of Designated Project
指定工程項目的性質

 

 

Improvement works to existing roads

改善現有道路工程

 

 

Location of Designated Project

指定工程項目的地點

 

Po Lam Road, Kwun Tong.  The location of the project is shown in Figure 1 attached to this Permit.

觀塘寶琳路。圖 1 顯示工程項目的位置。

 

 

 

Scale and Scope of Designated Project(s)

指定工程項目的規模和範圍

 

 

Widening of a section of Po Lam Road

擴闊寶琳路的

 

 

PART C (PERMIT CONDITIONS)

 

1.    General Conditions

 

1.1              The Permit Holder and any person working on the Project shall comply with all conditions set out in this Permit. Any non-compliance by any person may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap.499) and may become the subject of appropriate action being taken under the Ordinance.

 

1.2              The Permit Holder shall ensure full compliance with all legislation from time to time in force including without limitation to the Noise Control Ordinance (Cap.400), Air Pollution Control Ordinance (Cap.311), Water Pollution Control Ordinance (Cap.358), Dumping at Sea Ordinance (Cap.466), the Waste Disposal Ordinance (Cap.354). This Permit does not of itself (a) constitute any ground of defense against any proceedings instituted under any legislation or (b) imply any approval under any legislation.

 

1.3              The Permit Holder shall make copies of this Permit together with all documents referred to in this Permit or the documents referred to in Part A of the Permit readily available at all times for inspection by the Director or his authorized officers at all sites/offices covered by this Permit. Any reference to the Permit shall include all documents referred to in the Permit and also the relevant documents in the Register.

 

1.4              The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understands all conditions and all requirements incorporated by the Permit. The site(s) refers to site(s) of construction and/or operation of the Project(s) and shall mean the same hereinafter.

 

1.5              The Permit Holder shall display conspicuously a copy of this Permit on the construction site(s) at all vehicular site entrances/exits or at a convenient location for public information at all times. The Permit Holder shall ensure that the most updated information about the Permit, including any amended permit, is displayed at such locations. If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit. The suspended, varied or cancelled Permit shall be removed from display at the construction site(s).

 

1.6              The Permit Holder shall construct the Project as described in Part B of this Permit.

 

1.7              The Permit Holder shall ensure that the Project is designed and constructed in accordance with the information and recommendations described in the EIA report (Register No. AEIAR-005/1999); other relevant documents in the Register; and the information or mitigation measures described in this Permit, or mitigation measures to be recommended in submissions that shall be deposited with or approved by the Director as a result of permit conditions contained in this Permit, or mitigation measures to be recommended under on-going surveillance and monitoring activities during all stages of the Project. Where recommendations referred to in the documents of the Register are not expressly referred to in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded or impliedly amended in this Permit.

 

 

1.8              All submissions, as required under this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by the Director within one month of the receipt of the Director's comments or otherwise as specified by the Director.

 

1.9              All submissions approved by the Director, all submissions deposited without comments by the Director, or all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions. All submissions or any variation of the submissions shall be certified by the Environmental Team (ET) Leader and verified by the Independent Environmental Checker (IEC) referred to in Conditions 2.1 and 2.2 below, before submitting to the Director under the Permit.

 

1.10          The Permit Holder shall release all finalized submissions, as required under this Permit, to the public by depositing copies in the Environmental Impact Assessment Ordinance Register Office, or in any other places, or any internet websites as specified by the Director, or by any other means as specified by the Director for public inspection. For this purpose, the Permit Holder shall provide sufficient copies of the submissions.

 

1.11          The Permit Holder shall notify the Director in writing the commencement date of construction of the Project no later than one month prior to the commencement of construction of the Project. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the construction.

 

1.12          All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to the Environmental Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalized submissions required under this Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies.

 

1.13          For the purpose of this Permit, "commencement of construction" does not include works related to site clearance and preparation, or other works as agreed by the Director.

 

 

 

 

 

 

 

 

 

 

 

 

 

2.         Special Conditions

 

2.1              An Environmental Team (ET) shall be established by the Permit Holder no later than one month before the commencement of the Project. The ET shall be headed by an ET Leader.  The ET Leader shall be a person who has at least 7 years’ experience in environmental monitoring and auditing (EM&A) or environmental management. The ET and the ET Leader shall be responsible for the implementation of the EM&A programme in accordance with the EM&A requirements as contained in the EM&A Manual.  The ET Leader shall keep a contemporaneous log-book of each and every instance or circumstance or change of circumstances which may affect the environmental impact assessment and each and every non-compliance with the recommendations of the EIA Report (Register No. AEIAR-005/1999) or this Permit.  This log-book shall be kept readily available for inspection by all persons assisting in supervision of the implementation of the EIA Report recommendations and this Permit or by the Director or his authorized officers.  Failure to maintain records in the log-book, failure to discharge the duties of the ET Leader as defined in the EM&A Manual or failure to comply with this Condition would entitle the Director to require the Permit Holder by notice in writing to replace the ET Leader.  Failure by the Permit Holder to make replacement, or further failure to keep contemporaneous records in the log-book despite the employment of a new ET Leader may render the Permit liable to suspension, cancellation or variation.  The ET shall not be in any way an associated body of the Independent Environmental Checker (IEC) for the Project.

 

2.2              An Independent Environmental Checker (IEC) shall be employed by the Permit Holder no later than one month before the commencement of the Project. The IEC shall be a person who has at least 7 years’ experience in environmental monitoring and audit (EM&A) or environmental management.  The IEC shall be responsible for duties defined in the EM&A Manual and shall audit the overall EM&A programme, including the implementation of all environmental mitigation measures, submissions required in the EM&A Manual, and any other submissions required under this Permit. In addition, the IEC shall be responsible for verifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions under this Permit.  The IEC shall verify the log-book(s) mentioned in Condition 2.1 of this Permit.  The IEC shall notify the Director by fax, within 24 hours of each and every occurrence, change of circumstances or non-compliance with the EIA Report (Register No. AEIAR-005/1999) or this Permit, which might affect the monitoring or control of adverse environmental impact.  Where the IEC fails to so notify the Director of the same, fails to discharge the duties of the IEC as defined the EM&A Manual or fails to comply with this Condition, the Director may require the Permit Holder by notice in writing to replace the IEC.  Failure to replace the IEC as directed or further failure to so notify the Director despite employment of a new IEC may render the Permit liable to suspension, cancellation or variation.  Notification by the Permit Holder is the same as notification by the IEC for the purpose of this Condition.  The IEC shall not be in any way an associated body of the Contractor or the Environmental Team for the Project.

 

2.3              All submissions for approval and deposition under Sections 2 and 3 of this Permit shall be certified by the ET Leader and verified by the IEC as conforming to the information and recommendation contained in the EIA Report before submission to the Director.

 

 

2.4              The Permit Holder shall, within 4 weeks after the commencement of construction of the Project, inform the Director in writing the management organization of the main construction companies and/or any form of joint ventures associated with the construction of the Project.  The submitted information shall include at least an organization chart, names of responsible persons and their contact details.

 

 

            Measures to Mitigate Noise Impacts

 

2.5              Two weeks before commencement of construction of the Project, the Permit Holder shall deposit with the Director 3 copies of a construction phase noise mitigation plan which shall consist of a layout plan (at least 1:1000 scale) and explanatory statement showing the exact locations and details of the construction plant to be used and the noise mitigation measures to be adopted during different stages of construction of the Project. The construction phase noise mitigation plan shall conform to the requirements set out in section 12.3 of the EIA Report (attached as Appendix A). During construction of the Project, the noise mitigation measures as stipulated in the construction phase noise mitigation plan shall be implemented.

 

2.6              The Permit Holder shall construct a 7 m high cantilevered noise barrier wall (6 m vertical barrier with 1.4 m cantilever length at 45 degree to the horizontal) as a traffic noise mitigation measure along the footpath of the widened Po Lam Road to replace the existing noise barrier which will be removed by the road widening works. The locations of both the existing and reprovisioned noise barriers are indicated in Figure 1 attached to this Permit. The reprovisioned cantilevered noise barrier shall be a continuous structure with no gaps or openings. Upon completion of construction of the reprovisioned cantilevered noise barrier, the Permit Holder shall deposit with the Director 3 copies of as-built drawings, certified by the ET Leader and verified by the IEC, demonstrating the satisfactory completion of the noise barrier.

 

 

3.    Environmental Monitoring and Audit (EM&A)

 

3.1      The EM&A programme shall be implemented in accordance with the procedures and requirements in the EM&A Manual of the EIA report.  Any changes to the EM&A programme shall be justified by the ET Leader and verified by the IEC as conforming to the requirements set out in the EM&A Manual and shall be submitted to the Director for approval.

 

3.2      The Permit Holder shall submit two hard copies and one electronic copy of the Baseline Monitoring Report to the Director at least 2 weeks before the commencement of construction of the project.  The submissions shall be certified by the ET Leader and verified by the IEC.  Additional copies of the submission shall be provided upon request from the Director.

 

3.3      The Permit Holder shall submit two hard copies and one electronic copy of monthly EM&A Report to the Director within 2 weeks after the end of the reporting month.  The submissions shall be certified by the ET Leader and verified by the IEC.  Additional copies of the submission shall be provided upon request from the Director.

 

3.4     Samples and measurement shall be taken in accordance with the requirements of the EM&A Manual by:

          

(a)                conducting baseline monitoring as set out in the EM&A Manual; and

(b)                conducting impact monitoring as set out in the EM&A Manual.

 

3.5      The actions described in the Event /Action Plans of the EM&A Manual shall be fully and properly carried out, in accordance with the time frame as set out in the Event/Action Plans, or as agreed by the Director.

 

3.6     Records of measurements and remedial actions taken under Conditions 3.4 and 3.5 of this Permit shall be logged and kept, within 3 working days of the collection of data or completion of remedial action, for the purpose of preparing and submitting the EM&A Reports and making the information available for inspection on site or as required by the Director.

 

3.7      All environmental monitoring and audit data submitted under this Permit shall be true, valid and correct.

 

 

4.    Electronic Reporting of EM&A Information

 

4.1       To facilitate public inspection of the Baseline Monitoring Report and monthly EM&A Reports via the EIAO Internet Website and at the EIAO Register Office, electronic copies of these Reports, prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies as described in Conditions 3.2 and 3.3 above.  For the HTML version, a content page capable of providing hyperlink to each section and sub-section of these Reports shall be included in the beginning of the document.  Hyperlinks to all figures, drawings and tables in these Reports shall be provided in the main text from where the respective references are made.  All graphics in these Reports shall be in interlaced GIF format unless otherwise agreed by the Director.  The content of the electronic copies of these Reports must be the same as the hard copies.

 

4.2       The Permit Holder shall, set up a dedicated web site and notify the Director in writing the internet address where the environmental monitoring and project data is to be placed, within six weeks after the commencement of construction of the Project. All environmental monitoring data described in Condition 4.1 above shall be made available to the public via a dedicated web site to be set up by the Permit Holder in the shortest possible time and in no event later than 2 weeks after the relevant environmental monitoring data are collected or become available, unless otherwise agreed with the Director.

 

 

 

 

 

 

 

4.3       The internet website as described in Condition 4.2 above shall enable user-friendly public access to the monitoring data with features capable of:

 

(a) providing access to all environmental monitoring data collected since the commencement of works;

 

(b) searching by date;

 

(c) searching by types of monitoring data (air quality and construction waste); and

 

(d) hyperlinking to relevant monitoring data after searching;

 

            or otherwise as agreed by the Director.

 


 

Notes:

 

1.         This Environmental Permit consists of three parts, namely, PART A (Main Permit), PART B (Description of Designated Project) and PART C (Permit Conditions). Any person relying on this permit should obtain independent legal advice on the legal implications under the Ordinance, and the following notes are for general information only.

 

2.         If there is a breach of any condition of this Permit, the Director or its authorized officer may, with the consent of the Secretary, order the cessation of associated work until the remedial action is taken in respect of the resultant environmental damage, and in that case the Permit Holder shall not carry out any associated works without the permission of the Director or his authorized officer.

 

3.         The Permit Holder may apply under Section 13 of the Ordinance to the Director for a variation of the conditions of this Permit. The Permit Holder shall replace the original permit displayed on the construction site by the amended permit.

 

4.         A person who assumes the responsibility for the whole or a part of the designated project may, before he assumes responsibility of the designated project, apply under Section 12 of the Ordinance to the Director for a further environmental permit.

 

5.         Under Section 14 of the Ordinance, the Director may with the consent of the Secretary for the Environment and Food, suspend, vary or cancel this Permit.  The suspended, varied or cancelled Permit shall be removed from display at the construction site.

 

6.         If this Permit is cancelled or surrendered during construction or operation of the Project, another environmental permit must be obtained under the Ordinance before the Project could be continued. It is an offence under Section 26(1) of the Ordinance to construct or operate a designated project listed in Part I of Schedule 2 of the Ordinance without a valid environmental permit.

 

7.         Any person who constructs or operates the Project contrary to the conditions in the Permit, and is convicted of an offence under the Ordinance, is liable: -

 

(i)                 on a first conviction on indictment to a fine of $ 2 million and to imprisonment for 6 months;

 

(ii)                on a second or subsequent conviction on indictment to a fine of $ 5 million and to imprisonment for 2 years;

 

(iii)              on a first summary conviction to a fine at level 6 and to imprisonment for 6 months;

 

(iv)              on a second or subsequent summary conviction to a fine of $1 million and to imprisonment for 1 year; and

 

(v)               in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $ 10,000 for each day on which he is satisfied the offence continued.

 

8.         The Permit Holder may appeal against any condition of this Permit under Section 17 of the Ordinance within 30 days of receipt of this Permit.

 

9.         The Notes are for general reference only and that the Permit Holder should refer to the EIA Ordinance for details and seek independent legal advice.

 

Figure 1


[ Back to First Page ] / [ Back to Main Index ]