Environmental Permit No.
EP-260/2006
環境許可證編號 EP-260/2006
ENVIRONMENTAL IMPACT ASSESSMENT
ORDINANCE
(CHAPTER 499)
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL
PERMIT TO CONSTRUCT AND OPERATE
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the
Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental
Protection (the Director) grants this environmental permit to the Television Broadcasts Limited (hereinafter
referred to as the "Permit Holder") to construct and operate the
designated project described in Part B subject to the conditions specified
in Part C. The issue of this environmental
permit is based on the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例)第10條的規定,環境保護署署長(署長)將本環境許可證批予電視廣播有限公司(下稱“許可證持有人”),以建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發:
Application No. 申請書編號 |
AEP-260/2006 |
|||
Document in the
Register: 登記冊上的文件: |
(1) Project Profile – “Hill-top Transposer Station
Expansion at Castle Peak, Kowloon Peak and Cloudy Hill and Lamma Island ” (Register
No.: PP-302/2006) 工程項目簡介 ― “青山、飛鵝山、九龍坑山及南丫島山頂轉播站擴建工程” (登記冊編號:PP-302/2006) (2)
Application documents including all
attachments submitted by the Permit Holder on 19 December 2006 (Application
No. AEP-260/2006) 申請文件包括許可證持有人於2006年12日19日提交的所有附件 (申請書編號:AEP-260/2006) |
|||
Director’s
Permission to Apply Directly for Environmental Permit 署長准許直接申請環境許可證 |
Letter Reference: (38) in
EP2/Q/144 信件檔號:(38)in EP2/Q/144 Date: 20 November 2006 日期: 2006年11月20 日 |
|||
|
January
2007 |
|
||
|
Date 日期 |
|
(Simon Y. M. HUI) Principal Environmental Protection Officer (Regional
Assessment) for Director of Environmental Protection 環境保護署署長 首席環境保護主任(區域評估) 許一鳴代行 |
|
PART B
(DESCRIPTION OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the designated project
mentioned in Part A of this environmental permit
(hereinafter referred to as “the Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明:
Title of Designated Project 指定工程項目的名稱 |
Hill-top
Transposer Station Expansion at Castle Peak, Kowloon Peak and Cloudy Hill (This
designated project is hereafter referred to as “the Project”) 青山、飛鵝山及九龍坑山山頂轉播站擴建工程 (本指定工程項目下稱“工程項目”) |
Nature of Designated Project 指定工程項目的性質 |
Earthworks
and building works wholly in Ma On Shan Country Park, Pak Sin Leng Country
Park, and the Castle Peak Site of Special Scientific Interest 於馬鞍山郊野公園、八仙嶺郊野公園及青山具有特別科學價值的地方內進行土木工事及建築工程 |
Location of Designated
Project 指定工程項目的地點 |
The
hill-top of Castle Peak at Tuen Mun, Kowloon Peak at Kowloon and Cloudy Hill
at Tai Po 屯門青山、九龍飛鵝嶺 及
大埔九龍坑山山頂 The
location of the Project is shown in Figure 1,2 & 3 of this Permit. 工程項目的地點展示於本許可證圖1,
2 及
3 內 |
Scale and Scope of
Designated Project |
The
project is to construct and operate three transposer stations including: (a) a
2-storey building with an area of about 157m2 and an antenna tower
about 34m in height on top of the building at Castle Peak; (b) a
2-storey building with an area of about 141m2 and an antenna tower
about 47m in height on top of the building at Kowloon Peak; and (c) a single
building with an area of about 130m2 and an antenna tower about
39m in height on top of the building at Cloudy Hill 工程項目涉及建造及營辦三座轉播站。包括: (a) 一座位於青山兩層高面積約157平方米的建築物,及一座在屋頂約34米高的天線塔; (b) 一座位於飛鵝山兩層高面積約141平方米的建築物,及一座在屋頂約47米高的天線塔;及 (c) 一座位於九龍坑山一層高面積約130平方米的建築物,及一座在屋頂約39米高的天線塔; |
1. General Conditions
1.1 The Permit Holder and any person working on
the Project shall comply with all conditions set out in this Permit. Any
non-compliance by any person may constitute a contravention of the
Environmental Impact Assessment Ordinance (Cap.499) and may become the subject
of appropriate action being taken under the Ordinance.
1.2 The Permit Holder shall ensure full
compliance with all legislation from time to time in force including, without
limitation to, the Noise Control Ordinance (Cap. 400), Air Pollution Control
Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), Waste
Disposal Ordinance (Cap. 354), Country Parks Ordinance (Cap.208) and Waterworks
Ordinance (Cap. 102). This Permit does not of itself constitute any ground of
defense against any proceedings instituted under any legislation or imply any
approval under any legislation.
1.3 The Permit Holder shall make
copies of this Permit together with all documents referred to in this Permit
and the documents referred to
in Part A of the Permit readily available at all times for inspection by the Director or his
authorized officers at all sites/offices covered by this Permit. Any reference
to the Permit shall include all documents referred to in the Permit and also
the relevant documents in the Register.
1.4 The Permit Holder shall give a
copy of this Permit to the person(s) in charge of the site(s) and ensure that
such person(s) fully understands all conditions and all requirements
incorporated by the Permit. The site(s) refers to site(s) of construction and
operation of the Project and shall mean the same hereafter.
1.5 The Permit Holder shall display
conspicuously a copy of this Permit on the Project site(s) at all vehicular
site entrances/exits or at a convenient location for public’s information at
all times. The Permit Holder shall ensure that the most updated information
about the Permit, including any amended Permit, is displayed at such locations.
If the Permit Holder surrenders a part or the whole of the Permit, the notice
he sends to the Director shall also be displayed at the same locations as the
original Permit. The suspended, varied or cancelled Permit shall be removed
from display at the Project site(s).
1.6 The Permit Holder shall
construct and operate the Project in accordance with the project description in Part B
of this Permit.
1.7 The Permit
Holder shall ensure that the Project is designed, constructed and operated in
accordance with the information and all recommendations described in the Project
Profile (Register No.: PP-302/2006), the application documents including all attachments
(Application No. AEP-260/2006), and the information or mitigation measures
described in this Permit. Where recommendations referred to in the documents of
the Register are not expressly referred to in this Permit, such recommendations
are nevertheless to be implemented unless expressly excluded or impliedly
amended in this Permit.
1.8 All
deposited submissions, as required under this Permit, shall be rectified and
resubmitted in accordance with the comments, if any, made by the Director,
within one month of the receipt of the Director’s comments or
otherwise specified by the Director.
1.9 All
submissions approved by the Director, all submissions deposited
without comments by the Director, or all submissions rectified in accordance
with comments by the Director under this Permit shall be construed as part of
the permit conditions described in Part C of this Permit. Any variation of the
submissions shall be approved by the Director in writing or as prescribed in the
relevant permit conditions. Any non-compliance with the submissions may
constitute a contravention of the Environmental Impact Assessment
Ordinance (Cap.499).
1.10 The
Permit Holder shall release all finalized submissions, as required under this
Permit, to the public by depositing copies in the Environmental Impact
Assessment Ordinance Register Office, or in any other places, or any internet
websites as specified by the Director, or by any other means as specified by
the Director for public inspection. For this purpose, the Permit Holder shall
provide sufficient copies of the submissions.
1.11 All submissions to the Director required under
this Permit shall be delivered either in person or by registered mail to the
Environmental Impact Assessment Ordinance Register Office (currently at 27/F,
Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of
all finalized submissions required under this Permit shall be prepared in Hyper
Text Markup Language (HTML) (version 4.0 or later) and in Portable Document
Format (PDF version 4.0 or later), unless otherwise agreed by the Director and
shall be submitted at the same time as the hard copies.
1.12 The Permit Holder shall notify the Director
in writing the commencement date of construction of the Project no later than two
weeks prior to the commencement of construction of the Project. The Permit
Holder shall notify the Director in writing immediately if there is any change
of the commencement date of the construction.
1.13 For the purpose
of this Permit, “commencement of construction” does not include works related
to site clearance and preparation, or other works as agreed by the Director.
2. Specific Conditions
2.1 The
Project shall only be constructed and operated at the locations as indicated in
Figure 1, 2 and 3 of this Permit.
2.2 No temporary access or haul road
shall be formed for construction of the Project. Construction materials,
equipments and surplus excavated materials for the Project shall be transported
to and away from the Project sites through the existing route(s) or by
helicopters.
2.3 No tree felling shall be
carried out for the Project.
2.4 Before commencement of
construction of the Project, field survey shall be conducted to ascertain any
presence of rare or protected plant species within and close to the Project
site. The Permit Holder shall, no later than two weeks after the completion of
field survey, deposit with the Director four hard copies and one soft copy of
the field survey report on the survey findings. If rare or protected plant
species that will be affected by the Project were identified, these plant
species shall be transplanted to suitable location(s) outside the Project
site(s) before commencement of construction of the Project. The Permit Holder
shall, no later than two weeks before commencement of transplantation, deposit
with the Director four hard copies and one soft copy of transplantation
proposal with the following details :
(a)
species and locations of
plants to be transplanted;
(b)
recipient site for the
transplanted plants;
(c)
methodology and
implementation programme of transplantation; and
(d)
post-transplanting
monitoring.
2.5 Chemical toilets shall be
provided during the construction stage.
2.6 Temporary drains
with silt traps shall be constructed at the boundaries of the Project sites to
direct all construction site run-off to sand/silt removal facilities before
discharges.
2.7 No earth, building
materials, fuel, oil or toxic materials and other materials which may cause
contamination shall be stockpiled on the Project sites. No waste, spoil,
excavated materials or materials alike arising from the Project shall be dumped
in any environmentally sensitive areas including any country park, site of special
scientific interest and conservation area.
2.8 Diesel storage in each
transposer station shall not be more than 2,500 litres. All diesel storage
tanks shall be housed in a fuel tight structure with holding capacity of not
less than 2,500 litres to fully retain any accidentally spilled diesel.
2.9 Grease trap and perimeter
drains shall be provided to retain any leakages of diesel/chemicals during both
construction and operation stages.
2.10 Visually
unobtrusive or sensitive architectural finishes and recessive chromatic
treatments shall be incorporated into the design of the Transposer Stations for
implementation. The Permit Holder shall, no later than three months after
completion of construction of the Project, deposit with the Director four hard
copies and one electronic copy of the as-built drawings and photo records
showing the completed visual and landscape mitigation works.
2.11 All temporary
works areas shall be reinstated and landscaped with vegetation within two
months after the completion of construction of the Project. Construction plants
and equipments which may cause pollution due to leakage of oil or fuel shall be
removed from the Project site immediately after completion of construction of
the Project.
Notes :
1. This
Permit consists of three parts, namely, Part A
(Main Permit), Part B (Description of
Designated Project) and Part C (Permit
Conditions). Any person relying on this permit should obtain independent
legal advice on the legal implications under the Ordinance, and the following
notes are for general information only.
2.
If there is a
breach of any conditions of this Permit, the Director or his authorized officer
may, with the consent of the Secretary for the Environment, Transport and
Works, order the cessation of associated work until the remedial action is
taken in respect of the resultant environmental damage, and in that case the
Permit Holder shall not carry out any associated works without the permission
of the Director or his authorized officer.
3.
The Permit Holder
may apply under Section 13 of the Environmental Impact Assessment Ordinance
(the “Ordinance”) to the Director for a variation of the conditions of this
Permit. The Permit Holder shall replace the original permit displayed on the
Project site by the amended permit.
4.
A person who
assumes the responsibility for the whole or a part of the Project may, before
he assumes responsibility of the Project, apply under Section 12 of the
Ordinance to the Director for a further environmental permit.
5.
Under Section 14 of the
Ordinance, the Director may with the consent of the Secretary for the
Environment, Transport and Works, suspend, vary or cancel this Permit. The
suspended, varied or cancelled Permit shall be removed from display at the
Project sites.
6.
If this
Permit is cancelled or surrendered during construction and operation of the
Project, another environmental permit must be obtained under the Ordinance
before the Project could be continued. It is an offence under Section 26 (1) of
the Ordinance to construct and operate a designated project listed in Schedule
2 of the Ordinance without a valid environmental permit.
7. Any person who constructs or
operates the Project contrary to the conditions in the Permit, and is convicted
of an offence under the Ordinance, is liable:
(i)
on a first conviction on indictment to a fine of $2 million and to
imprisonment for 6 months;
(ii)
on a second or subsequent conviction on indictment to a fine of $5
million and to imprisonment for 2 years;
(iii)
on a first summary conviction to a fine at level 6 and to
imprisonment for 6 months;
(iv)
on a second or subsequent summary conviction to a fine of $1
million and to imprisonment for 1 year; and
(v)
in any case where the offence is of a continuing nature, the court
or magistrate may impose a fine of $10,000 for each day on which he is
satisfied the offence continued.
8. The Permit Holder may appeal
against any condition of this Permit under Section 17 of the Ordinance within
30 days of receipt of this Permit.
9. The Notes are for general
reference only and that the Permit Holder should refer to the EIA Ordinance for
details and seek independent legal advice.
[ Back to First Page ] / [ Back to Main Index ]