Environmental Permit No. EP-273 /2007

    環境許可證編號 EP-273/2007

 

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE

(CHAPTER 499)

Section 10

 

環境影響評估條例

(499)

10

 

ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE A DESIGNATED PROJECT 

建造及營辦指定工程項目的環境許可證

 

PART A (MAIN PERMIT)

A (許可證主要部分)

 

Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (the EIAO), the Director of Environmental Protection (the Director) grants this Environmental Permit to Water Supplies Department (hereinafter referred to as the “Permit Holder”) to construct and operate the designated project described in Part B subject to the conditions specified in Part C.  The issue of this Environmental Permit is based on the documents, approvals or permissions described below:

 

根據環境影響評估條例第10條的規定,環境保護署署長(署長)將本環境許可證批予 水務署 (下稱許可證持有人) 建造及營B所說明指定工程項目但須遵守C部所列明的條件本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據

 

 

Application No.

申請書編號: 

 

 AEP-273/2007

 

Document in the Register:

登記冊上的文件:

 

(1)     Laying of Western Cross Harbour Main and Associated Land Mains from West Kowloon to Sai Ying Pun

-          Environmental Impact Assessment Report

-          Environmental Monitoring and Audit Manual

-          Executive Summary

Hereinafter referred to as the “EIA Report” (Register No.: AEIAR-109/2007)

敷設由西九龍至西營盤之西區過海海底水管及與其相關的地下喉管

-          環境影響評估報告

-          環境監察與審核手冊

-          行政摘要

     下稱“環評報告”(登記冊編號AEIAR-109/2007

 

(2)     The Director’s letter of approval of the EIA Report dated 31 July 2007 referenced  ( 10 ) in EP2/G/E/141 Pt.2

署長於2007 7 31 發出批環評報告的信件檔案編號  (11) in EP2/G/E/141 Pt.2

 

(3)     Application for Environmental Permit received on 4 April 2007 (Application No.: AEP-273/2007) 

許可證持有人於2007年4月4日提交的許可証申請文件 (申請書編號 AEP-273/2007) [下稱 「申請書」]

 

 

 

 

 

31 July 2007

 

 

 

Date

日期

 

(Mrs. Shirley LEE)

Principal Environmental Protection Officer

for Director of Environmental Protection

環境保護署署長

(首席環境保護主任 李韓琇玲女士代行)

 

 

 

 

 

 

 

PART B (DESCRIPTIONS OF DESIGNATED PROJECTS)

B (指定工程項目的說明)

 

Hereunder is the description of the designated projects mentioned in Part A of this environmental permit:

(hereinafter referred to as the Permit)

下列為本環境許可證(下稱「許可證」)A所提述的指定工程項目的說明:

 

 

Title of Designated Projects

指定工程項目的名稱

 

 

Laying of Western Cross Harbour Main and Associated Land Mains from West Kowloon to Sai Ying Pun [This designated project is referred hereafter as “the Project”]

敷設由西九龍至西營盤之西區過海海底水管及與其相關的地下喉管

[本指定工程項目下稱「工程項目」]

  

 

Nature of Designated Projects
指定工程項目的性質

 

Construction and operation of a submarine water supply pipeline with a diameter of 1200 mm and a length of 2.1 km.

建造和營運一條直徑 1200 毫米和長度2.1公里海底供水管道

 

 

Location of Designated Project

指定工程項目的地點

 

The submarine water main is to laid across the Victoria Harbour from West Kowloon to Sai Ying Pun . See Figure 1 attached to this Permit.

海底供水管道橫越維多利亞港, 由西九龍敷設至西營盤。參看圖1。

 

 

Scale and Scope of Designated Project(s)

指定工程項目的規模和範圍

 

 

Trench excavation by grab dredger and install a submarine water main of 1200 mm diameter and a length of 2.1 km. The total dredged volume of marine sediment is about 362,000 m3. 

工程主要涉及以抓斗挖掘管槽,敷設一條直徑 1200 毫米和長度2.1公里海底供水管道 。挖出的沉積物總體積估計約達 362,000立方米

 

 

 

PART C (PERMIT CONDITIONS)

1.         General Conditions

 

1.1               The Permit Holder and any person working on the Project shall comply with all conditions set out in this Permit. Any non-compliance by any person may constitute a contravention of the Environmental Impact Assessment (EIA) Ordinance (Cap.499) and may become the subject of appropriate action being taken under the Ordinance.

 

1.2               The Permit Holder shall ensure full compliance with all legislation from time to time in force including without limitation to the Noise Control Ordinance (Cap.400), Air Pollution Control Ordinance (Cap.311), Water Pollution Control Ordinance (Cap.358), and Waste Disposal Ordinance (Cap.354). This Permit does not of itself (a) constitute any ground of defence against any proceedings instituted under any legislation or (b) imply any approval under any legislation.

 

1.3               The Permit Holder shall make copies of this Permit together with all documents referred to in this Permit or the documents referred to in Part A of the Permit readily available at all times for inspection by the Director or his authorized officers at all sites/offices covered by this Permit. Any reference to the Permit shall include all documents referred to in the Permit and also the relevant documents in the EIA Ordinance Register Office.

 

1.4               The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understands all conditions and all requirements incorporated by the Permit. The site(s) refers to site(s) of construction and / or operation of the Project and shall mean the same hereafter. 

 

1.5               The Permit Holder shall display conspicuously a copy of this Permit on the Project site(s) at all vehicular site entrances/exits or at a convenient location for public information at all times.  The Permit Holder shall ensure that the most updated information about the Permit, including any amended permit, is displayed at such locations. If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit. The suspended, varied or cancelled Permit shall be removed from display at the Project site(s).

 

1.6               The Permit Holder shall construct and operate the Project in accordance with the project description in Part B of this Permit.

 

1.7         The Permit Holder shall ensure that the Project is designed, constructed and operated in accordance with the information and all recommendations described in the EIA Report (EIAO Register No. AEIAR-109/2007); other relevant documents in the Register; and the information or mitigation measures described in this Permit, and mitigation measures to be recommended in submissions that shall be deposited with or approved by the Director as a result of permit conditions contained in this Permit, and mitigation measures to be recommended under on going surveillance and monitoring activities during all stages of the Project. Where recommendations referred to in the documents of the Register are not expressly referred to in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded or impliedly amended in this Permit.

 

1.8               All submissions, as required under this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by the Director within one month of the receipt of the Director’s comments or otherwise as specified by the Director.

 

1.9               All submissions approved by the Director, all submissions deposited without comments by the Director, and all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions. Any non-compliance with the submissions may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap. 499).  All submissions or any variation of the submissions shall be certified by the Environmental Team (ET) Leader and verified by the Independent Environmental Checker (IEC) referred to in Conditions 2.1 and 2.2 below, before submitting to the Director under this Permit.

 

1.10            The Permit Holder shall release all finalised submissions as required under this Permit, to the public by depositing copies in the Environmental Impact Assessment Ordinance Register Office, or in any other places, or any internet websites as specified by the Director, or by any means as specified by the Director, for public inspection. For this purpose, the Permit Holder shall provide sufficient copies of the submissions.

 

1.11            The Permit Holder shall notify the Director in writing the commencement date of construction of the Project no later than one week prior to the commencement of construction of the Project. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the construction.

 

1.12            All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to the Environmental Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalised submissions required under this Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hardcopies.

 

1.13            For the purpose of this Permit, “commencement of construction” does not include works related to site clearance and preparation or other works as agreed by the Director.

 

2.       Specific Conditions

 

Employment of Environmental Monitoring and Audit (EM&A) Personnel

 

2.1      An Environmental Team (ET) shall be established by the Permit Holder no later than two weeks before commencement of construction of the Project. The ET shall not be in any way an associated body of the Contractor or the Independent Environmental Checker (IEC) for the Project. The ET shall be headed by an ET Leader.  The ET leader shall be a person who has at least 7 years of experience in environmental monitoring and auditing (EM&A) or environmental management. The ET and the ET Leader shall be responsible for the implementation of the EM&A programme in accordance with the requirements as contained in the EM&A Manual (Register No. AEIAR-109/2007) of the Project.  In addition, the ET Leader shall be responsible for certifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions under this Permit.  The ET Leader shall keep a contemporaneous log-book of each and every instance or circumstance or change of circumstances which may affect the environmental impact assessment and each and every non-compliance with the recommendations of the approved EIA Report (Register No. AEIAR-109/2007) or this Permit. The ET Leader shall notify the IEC within one working day of the occurrence of any such instance or circumstance or change of circumstances. The ET Leader’s log-book shall be kept readily available for inspection by all persons assisting in supervision of the implementation of the recommendations of the approved EIA Report (Register No. AEIAR-109/2007) or this Permit or by the Director or his authorized officers.  Failure to maintain records in the log-book, failure to discharge the duties of the ET Leader as defined in the EM&A Manual or failure to comply with this Condition would entitle the Director to require the Permit Holder by notice in writing to replace the ET Leader. Failure by the Permit Holder to make replacement, or further failure to keep contemporaneous records in the log-book despite the employment of a new ET Leader may render the Permit liable to suspension, cancellation or variation.

 

2.2        An Independent Environmental Checker (IEC) shall be employed by the Permit Holder no later than two weeks before commencement of construction of the Project. The IEC shall not be in any way an associated body of the Contractor or the ET for the Project. The IEC shall be a person who has at least 7 years of experience in EM&A or environmental management. The IEC shall be responsible for duties defined in the EM&A Manual (Register No. AEIAR-109/2007) of the Project and shall audit the overall EM&A programme, including the implementation of all environmental mitigation measures, submissions required in the EM&A Manual, and any other submissions required under this Permit. In addition, the IEC shall be responsible for verifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions under this Permit. The IEC shall verify the log-book(s) mentioned in Condition 2.1 of this Permit. The IEC shall notify the Director by fax, within one working day of receipt of notification from the ET Leader of each and every occurrence, change of circumstances or non-compliance with the approved EIA Report (Register No. AEIAR-109/2007) or this Permit, which might affect the monitoring or control of adverse environmental impacts from the Project.  In the case where the IEC fails to so notify the Director of the same, fails to discharge the duties of the IEC as defined in the EM&A Manual or fails to comply with this Condition, the Director may require the Permit Holder by notice in writing to replace the IEC. Failure to replace the IEC as directed or further failure to so notify the Director despite employment of a new IEC may render the Permit liable to suspension, cancellation or variation. Notification by the Permit Holder is the same as notification by the IEC for the purpose of this Condition. 

 

2.3       The Permit Holder shall, no later than one week before the commencement of construction of the Project, inform the Director in writing the management organization of the main construction companies and/ or any form of joint ventures associated with the construction of the Project.  The submitted information shall include at least an organization chart, names of responsible persons and their contact details.

 

2.4       The Permit Holder shall set up and operate a Community Liaison Office throughout the construction of the Project to receive and respond to complaints or enquires on environmental nuisances or pollution caused by the Project and to implement remedial mitigation measures.

 

            Measures for Mitigating Water Quality Impact

 

2.5       Dredging work shall be undertaken by no more than one grab dredger and the dredging rate shall not exceed 4,000 cubic metre per day at all time throughout the dredging work. 

 

2.6        Frame type silt curtain with typical configuration as shown in Figure 2 of this Permit shall be deployed to fully enclose the grab at all time when dredging work is in progress. This frame type silt curtain shall be designed to enclose local sources of water pollution caused by the grab dredger. The silt curtain shall be suspended by a steel frame mounted on the grab dredger and be floating on water. The silt curtain shall be fabricated from permeable, durable, abrasive resistance membrane like geo-textiles and mounted on a floating boom structure. The frame type silt curtain shall also extend to the seabed to cover the entire water column.  Steel chain or ballast shall be attached to the bottom of the silt curtain.   

 

2.7        The Permit Holder shall liaise with the owner and the operator of the Kowloon South Salt Water Pumping Station as shown in Figure 1 of this Permit to install a silt screen at the seawater intake. The silt screen shall be installed with typical configuration as shown in Figure 2 of this Permit. The silt screen shall be installed before the commencement of any dredging work and be properly maintained at all time throughout the dredging work.

 

 

3.         Environmental Monitoring and Audit (EM&A) Requirements

3.1       The EM&A programme of the Project shall be implemented in accordance with the procedures and requirements as set out in the EM&A Manual (Register No. AEIAR-109/2007) of the Project. Any change to the EM&A requirements or programme shall be justified by the ET Leader and verified by the IEC as conforming to the requirements set out in the EM&A Manual and shall seek the prior approval from the Director before implementation.

3.2       Four hard copies and one electronic copy of the Baseline Monitoring Report shall be submitted to the Director at least one week before the commencement of construction. The submissions shall be certified by the ET Leader and verified by the IEC as complying with the requirements as set out in the EM&A Manual before submission to the Director. Additional copies of the submission shall be provided upon request by the Director.

3.3       Four hard copies and one electronic copy of the monthly EM&A Reports for the construction stage shall be submitted to the Director within two weeks after the end of the reporting month. The monthly EM&A Reports shall include a summary of all non-compliance with the recommendations in the EIA Report or this Permit. The submissions shall be certified by the ET Leader and verified by the IEC as complying with the requirements as set out in the EM&A Manual before submission to the Director. Additional copies of the submission shall be provided upon request by the Director.

3.4       All environmental monitoring and audit results submitted under this Permit shall be true, valid and correct.

3.5       Any necessary remedial measures and actions as described in the EM&A Manual shall be fully and properly carried out, in accordance with the time frame(s) set out in the EM&A Manual, or as agreed by the Director.

4.       Electronic Reporting of EM&A Information

 

4.1       To facilitate public inspection of the Baseline Monitoring Report and the monthly EM&A Reports via the EIAO Internet Website and at the EIAO Register Office, electronic copies of these Reports shall be prepared in the Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies as described in Conditions 3.2 and 3.3 of this Permit. For the HTML version, a content page capable of providing hyperlink to each section and sub-section of these Reports shall be included in the beginning of the document.  Hyperlinks to all figures, drawings and tables in these Reports shall be provided in the main text from where the respective references are made.  All graphics in these Reports shall be in interlaced GIF format unless otherwise agreed by the Director. The content of the electronic copies of these Reports must be the same as the hard copies.

 

 

Notes:

 

1.         This Permit consists of three parts, namely, PART A (Main Permit), PART B (Description of Designated Project) and PART C (Permit Conditions). Any person relying on this permit should obtain independent legal advice on the legal implications under the Ordinance, and the following notes are for general information only.

 

2.         If there is a breach of any conditions of this Permit, the Director or his authorized officer may, with the consent of the Secretary for the Environment, Transport and Works, order the cessation of associated work until the remedial action is taken in respect of the resultant environmental damage, and in that case the Permit Holder shall not carry out any associated works without the permission of the Director or his authorized officer.

 

3.         The Permit Holder may apply under Section 13 of the Environmental Impact Assessment Ordinance (the “Ordinance”) to the Director for a variation of the conditions of this Permit. The Permit Holder shall replace the original permit displayed on the Project site by the amended permit.

 

 4.        A person who assumes the responsibility for the whole or a part of the Project may, before he assumes responsibility of the Project, apply under Section 12 of the Ordinance to the Director for a further environmental permit.

 

5.         Under Section 14 of the Ordinance, the Director may with the consent of the Secretary for the Environment, Transport and Works, suspend, vary or cancel this Permit.  The suspended, varied or cancelled Permit shall be removed from display at the Project site.

 

6.         If this Permit is cancelled or surrendered during construction of the Project, another environmental permit must be obtained under the Ordinance before the Project could be continued. It is an offence under Section 26(1) of the Ordinance to construct a designated project listed in Schedule 2 of the Ordinance without a valid environmental permit.

 

 

7.         Any person who constructs the Project contrary to the conditions in the Permit, and is convicted of an offence under the Ordinance, is liable: -

 

(i)                  on a first conviction on indictment to a fine of $ 2 million and to imprisonment for 6 months;

(ii)                on a second or subsequent conviction on indictment to a fine of $ 5 million and to imprisonment for 2 years;

(iii)               on a first summary conviction to a fine at level 6 and to imprisonment for 6 months;

(iv)              on a second or subsequent summary conviction to a fine of $1 million and to imprisonment for 1 year; and

(v)        in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $ 10,000 for each day on which he is satisfied the offence continued.

 

 8.        The Permit Holder may appeal against any condition of this Permit under Section 17 of the Ordinance within 30 days of receipt of this Permit.

 

9.         The Notes are for general reference only and that the Permit Holder should refer to the EIA Ordinance for details and seek independent legal advice.

 

 

Environmental Permit No. EP-273/2007

環境許可證編號EP-273/2007

 

Figure 1Figure 2

[ Back to First Page ] / [ Back to Main Index ]