Environmental
Permit No. EP-292/2007
環境許可證編號
EP-292/2007
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE
A DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (the EIAO), the Director of Environmental Protection (the Director) grants this environmental permit to the Environmental Infrastructure Division of Environmental Protection Department (hereinafter referred to as the “Permit Holder”) to construct and operate the designated project described in Part B subject to the conditions specified in Part C. The issue of this environmental permit is based on the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例)第10條的規定,環境保護署署長 (署長) 將本環境許可證批予環境保護署環境基建科(下稱 “許可證持有人”),以建造及營辦B部所說明的指定工程項目,但須遵守C部所說明的條件。本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據:-
Application No. 申請書編號: |
AEP-277/2007 |
|||
Document in the
Register : 登記冊上的文件:: |
(1) North East New
Territories (NENT) Landfill Extension : –
Environmental Impact Assessment Report –
Environmental Monitoring and Audit Manual –
Environmental Impact Assessment Executive Summary (Register No.
AEIAR-111/2007) [Hereinafter referred to as the “EIA Report”] (1) 新界東北堆填區擴建計劃: –
環境影響評估報告 –
環境監察及審核手冊 –
環境影響評估行政摘要 (登記冊編號 : AEIAR-111/2007) [下稱 “環評報告”] (2) The Director’s letter of approval of the EIA Report dated 20
September 2007, ref.: (16) in Ax(1) to EP2/N7/G/36 VI. (2) 署長於二零零七年九月二十日發出批准環評報告的信件,檔案編號:(16) in
Ax(1) to
EP2/N7/G/36 VI。 |
|||
|
26 November 2007 |
|
|
|
|
Date 日期 |
|
(Maurice YEUNG) Principal Environmental
Protection Officer (Assessment and Noise) for the Director of
Environmental Protection 環境保護署署長 (首席環境保護主任(評估及噪音)楊國良代行) |
|
PART B (DESCRIPTIONS OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is
the description of the designated project mentioned in Part A
of this environmental permit (hereinafter referred to as the “Permit”):
下列為本環境許可證(下稱 “許可證”) A部所提述的指定工程項目的說明:
Title of Designated
Project 指定工程項目的名稱 |
North East New Territories (NENT) Landfill Extension 新界東北堆填區擴建計劃 [This designated project is hereinafter referred to as “the Project”] [本指定工程項目下稱 “工程項目”] |
Nature of Designated
Project |
Construction and operation of a landfill for waste as defined in the
“Waste Disposal Ordinance” (Cap. 354) 建造及營辦一個<<廢物處置條例>>(第354章)所界定的廢物堆填區 |
Location of Designated
Project 指定工程項目的地點 |
Ta Kwu Ling, North East New Territories 新界東北打鼓嶺 The location of the Project is shown in Figure 1 of this Permit. 指定工程項目的位置載於本許可證圖1。 |
Scale
and Scope of Designated Project 指定工程項目的規模和範圍 |
The Project mainly consists of the followings:- 工程項目主要範圍包括以下各項:- Construction and
operation of a landfill extension of about 70 hectares with a target void
space of at least 19 million cubic metres on the eastern side of the existing
NENT Landfill, including the followings:- (i)
Site formation and preparation; (ii)
Installation of liner system; (iii)
Installation of leachate collection, treatment and disposal facilities; (iv)
Installation of gas collection, utilization and management facilities; (v)
Utilities provisions and drainage diversion; (vi)
Landfilling operation; (vii)
Restoration and aftercare in subsequent stages; and (viii)
Measures to mitigate environmental impacts as well as environmental
monitoring and auditing to be implemented. 在現有新界東北堆填區的東面建造及營辦目標容量約1900萬立方米、佔地約70公頃的堆填區擴建工程,包括:- (i)
工地平整及預備工程; (ii)
裝設防滲漏層系統; (iii)
裝設滲濾污水收集、處理及排放設施; (iv)
裝設堆填氣體收集、應用及管理設施; (v)
提供公用設施及排水渠改道; (vi)
堆填區的營運; (vii)
繼後的修復及修復後的護理工程;以及 (viii) 環境影響緩解措施及執行環境監察及審核。 |
1 General Conditions
1.1 The permit holder and any person working on the Project shall comply with all conditions of this Permit. Any non-compliance by any person may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap. 499) and may become the subject of appropriate action being taken under the Ordinance.
1.2 The Permit Holder shall ensure full compliance with all legislation from time to time in force including without limitation to the Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358) and Waste Disposal Ordinance (Cap.354). This Permit does not of itself constitute any ground of defence against any proceedings instituted under any legislation or imply any approval under any legislation.
1.3
The Permit Holder
shall make copies of this Permit together with
all documents referred to in this Permit or the documents referred to in Part A of the Permit readily available at all times for
inspection by the Director or his authorised officers at all sites/offices
covered by this Permit. Any
reference to the Permit shall include all documents referred to in the Permit
and also the relevant documents in the Register.
1.4
The Permit Holder shall give
a copy of this Permit to the person(s) in charge of the site(s) and ensure that
such person(s) fully understands all conditions and all requirements
incorporated by the Permit. The
site(s) refers to site(s) of construction and operation of the Project and
shall mean the same hereafter.
1.5 The Permit Holder shall display conspicuously a copy of this Permit on the Project site(s) at all vehicular entrances/exits or at a convenient location for public information at all times. The Permit Holder shall ensure that the most updated information about the Permit, including any amended permit, is displayed at such locations. If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit. The suspended, varied or cancelled Permit shall be removed from display at the Project site(s).
1.6 The permit holder shall construct and operate the Project in accordance with the project descriptions in Part B of this Permit.
1.7 The Permit Holder shall ensure that the Project is designed, constructed and operated in accordance with the information and all recommendations described in the EIA Report, other relevant documents in the Register; and the information or mitigation measures described in this Permit, and mitigation measures to be recommended in submissions that shall be deposited with or approved by the Director as a result of permit conditions contained in this Permit, and mitigation measures to be recommended under on going surveillance and monitoring activities during all stages of the Project. Where recommendations referred to in the documents of the Register are not expressly referred to in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded or impliedly amended in this Permit.
1.8 All submissions, as required under this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by the Director within one month of the receipt of the Director’s comments or otherwise specified by the Director.
1.9 All submissions approved by the Director, all submissions deposited without comments by the Director, or all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions. Any non-compliance with the submissions may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap. 499). All submissions or any variation of the submissions shall be certified by the Environmental Team (ET) Leader and verified by the Independent Environmental Checker (IEC) referred to in Conditions 2.1 and 2.2 below before submitting to the Director under this Permit.
1.10 The Permit Holder shall release all finalized submissions, as required under this Permit, to the public by depositing copies in the Environmental Impact Assessment Ordinance Register Office, or in any other places, or any internet websites as specified by the Director, or by any other means as specified by the Director for public inspection. For this purpose, the Permit Holder shall provide sufficient copies of the submissions.
1.11 All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to the Environmental Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalized submissions required under this Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies.
1.12 The Permit Holder shall notify the Director in writing the commencement date of construction of the Project no later than one month prior to the commencement of construction of the Project. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the construction.
1.13 For the purpose of this Permit, “commencement of construction” does not include works related to site clearance and preparation or other works as agreed by the Director.
2 Special Conditions
Submissions or Measures before Commencement of Construction
Employment of Environmental Monitoring and Audit (EM&A)
Personnel
2.1 An ET shall be established by the Permit Holder no later than one month before the commencement of construction of the Project. The ET shall not be in any way an associated body of the Contractor or the IEC for the Project. The ET shall be headed by an ET Leader. The ET Leader shall be a person who has at least 7 years of experience in environmental monitoring and auditing (EM&A) or environmental management. The ET and the ET Leader shall be responsible for the implementation of the EM&A programme in accordance with the EM&A requirements as contained in the EM&A Manual of the Project. The ET Leader shall keep a contemporaneous log-book of each and every instance or circumstance or change of circumstances, which may affect the compliance with the recommendations of the EIA Report and this Permit. The ET Leader shall notify the IEC within one working day of the occurrence of any such instance or circumstance or change of circumstances. The ET Leader’s log-book shall be kept readily available for inspection by all persons assisting in supervision of the implementation of the recommendations of the EIA Report and this Permit or by the Director or his authorized officers. Failure to maintain records in the log-book, failure to discharge the duties of the ET Leader as defined in the EM&A Manual or failure to comply with this Condition would entitle the Director to require the Permit Holder by notice in writing to replace the ET Leader. Failure by the Permit Holder to make replacement, or further failure to keep contemporaneous records in the log-book despite the employment of a new ET Leader may render the Permit liable to suspension, cancellation or variation.
2.2
An IEC shall be employed by the Permit
Holder no later than one month before commencement of construction of the
Project. The IEC shall not be in
any way an associated body of the Contractor or the ET for the Project. The IEC shall be a person who has at
least 7 years of experience in EM&A or environmental management. The IEC shall be responsible for duties
defined in the EM&A Manual and shall audit the overall EM&A
performance, including the implementation of all environmental mitigation
measures, submissions required in the EM&A Manual, and any other
submissions required under this Permit.
In addition, the IEC shall be responsible for verifying the environmental
acceptability of permanent and temporary works, relevant design plans and
submissions under this Permit. The
IEC shall verify the log-book(s) mentioned in Condition 2.1 of this
Permit. The IEC shall notify the
Director by fax, within one working day of receipt of notification from the ET
Leader of each and every occurrence, change of circumstances or non-compliance
with the EIA Report and this Permit, which might affect the monitoring or
control of adverse environmental impacts from the Project. In the case where the IEC fails to so
notify the Director of the same, fails to discharge the duties of the IEC as
defined in the EM&A Manual or fails to comply with this Condition, the
Director may require the Permit Holder by notice in writing to replace the IEC. Failure to replace the IEC as directed
or further failure to so notify the Director despite employment of a new IEC
may render the Permit liable to suspension, cancellation or variation. Notification by the Permit Holder is
the same as notification by the IEC for the purpose of this Condition.
Management Organization of Main
Construction Companies
2.3 The Permit Holder shall, no later than two weeks before the commencement of construction of the Project, inform the Director in writing the management organization of the main construction companies and/or any form of joint ventures associated with the construction of the Project. The submitted information shall include at least an organization chart, names of responsible persons and their contact details.
Setting up of Community Liaison Group
2.4
To enhance transparency and
communication with the public, the Permit Holder shall, within 3 months before
commencement of construction of the Project, set up a Community Liaison Group
involving relevant stakeholders and shall take a proactive approach to disseminate
information to the local community, promote community cooperation and
participation and implement suitable local environmental enhancement
works. All relevant information of
the project including the detailed design, the progress of construction and
operation and environmental monitoring and audit results shall be provided to
the Community Liaison Group. The
Permit Holder shall inform the Director in writing the membership and terms of
reference of the Community Liaison Group.
The Permit Holder shall make the minutes of the Community Liaison Group
meetings and all papers and documents available to the public through a
website.
Submission of EM&A Manual
2.5
The Permit Holder shall, no later than
one month before the commencement of construction of the Project, submit to the
Director for approval four hard copies and one electronic copy of an updated
EM&A Manual for the Project.
Before submission to the Director, the EM&A Manual shall be
certified by the ET and verified by the IEC as conforming to the information
and recommendations contained in the EIA Report. The EM&A Manual shall
include the latest information on the EM&A requirements for ecological,
landscape, water and landfill gas hazard.
All measures recommended in the approved EM&A Manual shall be fully
and properly implemented according to the requirements and time schedule(s) set
out in the EM&A Manual.
Preservation of Cultural Landscape
Features
2.6 The Permit Holder shall, no later than four weeks before commencement of construction of the Project, deposit a report documenting the implementation of the following mitigation measures for preservation of the cultural landscape features located within the Project area. The report shall be certified by the ET Leader and verified by the IEC as conforming to the information and recommendations contained in the approved EIA Report :-
(a)
Carry
out survey and mapping works to identify sections of boulder path BP1 and BP2
as shown in Figure 2 attached to the
Permit that fall within the Project area, and preservation by detailed record
for sections of boulder paths that fall within the Project area; and
(b)
Preservation
by detailed record for graves G2, G4, G5, G6, G7, G8, G14, G15, G25, G26, G27
as shown in Figure 2 attached to the
Permit.
Ecological Mitigation Measures
2.7 The Permit Holder shall, no later than one month before the commencement of construction of the Project, submit to the Director for approval four hard copies and one electronic copy of a detailed vegetation survey covering the affected habitats located within the Project area for the purpose of updating, identifying and recording the location and number, health condition and suitability for transportation of the affected individual plant species in order to provide details for the transplantation scheme. The survey shall cover the four plant species of conservation importance including the Aquilaria sinensis, Rhododendron simsii, Endospermum chinense, and Arundina graminifolia at the locations shown in the attached Figure 3. The detailed vegetation survey shall be prepared by a qualified botanist or ecologist and shall be certified by the ET Leader and verified by the IEC as conforming to the information and recommendations contained in the approved EIA Report.
2.8 The Permit Holder shall, no later than six month before the commencement of construction of the Project, submit to the Director for approval four hard copies and one electronic copy of a detailed methodology for capture surveys and translocation on the endemic freshwater crab Somanniathelphusa zanklon affected by the Project area and monitoring requirements on the establishment of the Somanniathelphusa zanklon community in the translocated site. The submission shall be prepared by a qualified botanist or ecologist and shall be certified by the ET Leader and verified by the IEC as conforming to the information and recommendations contained in the approved EIA Report.
2.9 The transplantation shall be carried out according to the transplantation scheme approved under Condition 2.7 before commencement of construction of the Project.
2.10
The capture surveys, translocation and
monitoring on the endemic freshwater crab Somanniathelphusa zanklon
shall be carried out according to the submission approved under Condition 2.8
before commencement of construction of the Project.
Submission of Detailed Landfill Gas
Hazard Assessment Report
2.11 The Permit Holder shall, within one month before the commencement of construction of the Project, submit to the Director for approval four hard copies and one electronic copy of a detailed landfill gas hazard assessment, which shall include a review of the preliminary qualitative risk assessment in the approved EIA report, preparation of a detailed qualitative risk assessment, preparation of detailed design of gas protection measures and the establishment of maintenance and monitoring programmes to ensure the continued performance of the proposed control measures. The submissions shall be certified by the ET Leader and verified by the IEC. Additional copies of the submission shall be provided upon request by the Director.
Measures and Submissions to be Implemented during Construction of
the Project
Submission of Waste Management Plan
2.12
The Permit Holder shall, within one
month after the commencement of construction of the Project, deposit with the
Director four hard copies and one electronic copy of a Waste Management Plan
(WMP) for the construction stage of the Project. The WMP shall be certified by the ET Leader and verified by
the IEC as conforming to the information and recommendations contained in the
approved EIA Report. The WMP shall
describe the arrangements for avoidance, reuse, recovery and recycling,
storage, collection, treatment and disposal of different categories of waste to
be generated from the construction activities and shall include the recommended
mitigation measures on waste management in the approved EIA Report. The WMP shall indicate the disposal
location(s) of all surplus excavated spoil and other waste. A trip ticket
system shall be included in the WMP.
Surplus excavated spoil and other wastes shall only be disposed of at
designated disposal locations unless otherwise approved by the Director. All measures recommended in the
approved WMP shall be fully and properly implemented by the Permit Holder and
any person working on the Project throughout the construction period.
Submission of Landscape Plan
2.13
The Permit Holder shall, within six
months after the commencement of construction of the Project, submit to the
Director for approval four hard copies and one electronic copy of a landscape
plan(s) showing details of landscape measures including phased plantation of
26.83 hectares of woodland, 19 hectares of shrubland and 17.55ha grassland
during construction, operation and restoration stages of the Project. The
plan(s), of scale 1 to 1000 or other appropriate scale as agreed by the
Director, shall include details on locations, size, number and species of
planting, fire prevention measures including provision of firebreak and
plantation of fire tolerant species, implementation programme, maintenance and
management schedules. The
submission shall be certified by the ET Leader and verified by the IEC as
conforming to the information, requirements and recommendations set out in the
approved EIA Report. All measures recommended in the approved landscape plan(s)
shall be fully and properly implemented in accordance with the details and
programme set out in the submission.
Submission of Contingency Plan on
Accidental Leakage of Leachate
2.14 The Permit Holder shall, within four weeks before the commencement of operation of the Project, submit to the Director for approval four hard copies and one electronic copy of a contingency plan on accidental leakage of leachate. The contingency plan shall cover design contingency plan for both groundwater contamination and surface water contamination. The submission shall be verified by the IEC as conforming to the information and recommendations contained in the approved EIA Report. All design features and measures recommended in the approved plan shall be fully and properly implemented.
Implementation of Surface Water Drainage System
2.15 A temporary surface water drainage system shall be provided to manage runoff during the construction and operational stages. The system shall consist of the following features:-
(a) channels constructed around the perimeter of the site area to collect surface water from the areas of higher elevations to those of lower elevations and ultimately to the point of discharge.
(b)
use of a silt
fence around the soil stockpile areas to prevent sediment from entering the
system. Regular cleaning will be carried out to prevent blockage of the passage
of water flow in silt fence.
(c) Intermediate drainage system will be installed for filled cell/phase to prevent the clean surface water run-off from the filled phases coming into contact with the waste mass in active cell and to prevent excessive surface water infiltration through the intermediate cover, thus contribute to increasing volume of leachate. The intermediate drainage system will collect the clean surface water run-off and divert it to the permanent discharge channels connected to the public drainage system.
(d)
In addition, surface flow from the
haul road (especially near the wheel washing facility) shall be collected to a
dry weather flow interceptor and conveyed to the on-site leachate treatment
plant for further treatment.
Measures and Submissions to be
Implemented during Operation of the Project
Measures to Minimize
Surface Gas and Odour Emissions
2.16 To minimize surface gas emissions, the inactive tipping areas shall be covered with impermeable plastic sheet and a landfill gas extraction system shall be in operation.
2.17 To minimize odour emissions, the exposed area of the leachate storage lagoons and tanks at the on-site leachate treatment plant shall be installed with covers and deodourizers. The covers shall be air tight to prevent release of odour from the facilities into atmosphere. Foul air underneath the covers shall be drawn through deodourizers and be discharged after treatment. The deodourizers shall be designed for odour removal efficiency of 99% or otherwise agreed by the Director.
2.18 Site walk to Tong To Shan Tsuen shall be conducted once every three months and if resident is identified, the following additional measures shall be undertaken to further reduce odour emissions from the Project area : -
(a) thicker daily cover and alternative daily cover shall be applied at active tipping area during Phase 3 of the Project;
(b)
early morning odour patrol at Tong To
Shan Tsuen shall be arranged to ensure the effectiveness of the measures.
Liner
System to Control Seepage of Leachate
2.19
A composite liner system consisting of
a layer of at least 2.0 mm thick high density polyethylene (HDPE) with a
hydraulic conductivity of at least 1xE-9 meters per second and a layer of at
least 6.0 mm thick bentonite matting with a hydraulic conductivity of at least
1xE-11 meters per second shall be provided over the entire area of the Project.
Measures for Controlling
Contamination to Surface and Ground Water
2.20
Hydroseeding shall be applied on the
surface of stockpiled soil and on temporary soil covers for inactive tipping
areas to prevent soil erosion during rainy season.
Measures to Mitigate the Potential
Loss of Groundwater Yields to Ping Yeung and Wo Keng Shan areas
2.21
The Permit Holder shall implement the
following measures as necessary in the event circumstances arise when
significant changes in groundwater yields are identified by the monitoring
programme at Ping Yeung and Wo Keng Shan areas as specified in the EM&A Manual
during implementation of the Project : -
(a)
Provision of adequate water supply for
irrigation purposes for the operational lifetime of the landfill extension;
(b)
Installation of a network of monitoring
stations to keep track of the stream flow volumes. Should monitoring of stream flow indicate insufficient
quantities to provide sufficient water for irrigation downstream, water shall
be supplied from an external source;
(c)
Diversion of flow from other catchments
shall be considered: the surface runoff generated in the catchments with
abandoned agricultural lands could be collected and conveyed to the active
agricultural lands;
(d)
Formation of new extraction wells that
extend deeper down within the aquifer;
(e)
Provision of Piped Water Supply; and
(f)
Artificial recharge by surface
spreading, spray irrigation or pumping water directly into the ground via
vertical shafts.
Provision of Landfill Gas (LFG)
Collection and Management System
2.22 A LFG collection and management system shall be implemented to eliminate any off-site migration of LFG.
2.23
Landfill gas protection measures shall
be implemented at all new buildings on site to prevent the ingress of landfill
gas and mitigate any potential risks posed by landfill gas migration in
accordance with the recommendations of the approved detailed landfill gas
hazard assessment submitted under Condition 2.11.
Measures and Submissions to be Implemented
during Restoration Stage of the Project
2.24 The Permit Holder shall, within two months after the commencement of the restoration stage the Project, deposit with the Director four hard copies and one electronic copy of as-built drawings of scale 1 to 1000 with an explanatory statement showing the location, size, number, and species of planting in the Project area. The submissions shall be certified by the ET Leader and verified by the IEC. Additional copies of the submission shall be provided upon request by the Director.
3 Environmental Monitoring and Audit (EM&A) Requirements
3.1 The EM&A programme shall be implemented in accordance with the procedures and requirements as set out in the EM&A Manual of the Project. Any changes to the EM&A programme shall be justified by the ET Leader and verified by the IEC as conforming to the requirements set out in the EM&A Manual and shall seek the prior approval from the Director before implementation.
3.2 Four hard copies and one electronic copy of Baseline Monitoring Report shall be submitted to the Director at least two weeks before the commencement of construction. The submissions shall be certified by the ET Leader and verified by the IEC. Additional copies of the Baseline Monitoring Report shall be provided upon request by the Director.
3.3 Four hard copies and one electronic copy of Monthly EM&A Reports for the construction stage shall be submitted to the Director, within 2 weeks after the end of the reporting month. The submission shall be certified by the ET Leader and verified by the IEC before submission to the Director. Additional copies of the Monthly EM&A Reports shall be provided upon request by the Director.
3.4 The actions described in the Event/Action Plans of the EM&A Manual shall be fully and properly carried out, in accordance with the time frame(s) as set out in the Event/Action Plan, or as agreed by the Director.
3.5 All environmental monitoring and audit data submitted under this Permit shall be true, valid and correct.
3.6 To ensure a high degree of transparency regarding the monitoring data and results, all environmental monitoring and audit data and results and all submissions and all performance test data and results required by this Permit shall be made available by the Permit Holder to the public through a dedicated web site to be set up by the Permit Holder under Condition 4.2 below, in the shortest practicable time and in no event later than 2 weeks after such information is available.
3.7 Records of measurements and remedial actions taken under Condition 3.4 of this Permit shall be logged and kept within 3 working days of the collection of data or completion of remedial action, shall be included in the EM&A Reports and shall be available for inspection on site or as requested by the Director.
4 Electronic Reporting of EM&A Information
4.1 To facilitate public inspection of the EM&A Manual, Baseline Monitoring Report and the Monthly EM&A Reports via the EIAO Internet Website and at the EIAO Register Office, electronic copies of these Reports shall be prepared in the Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies as described in Conditions 3.2 and 3.3 of this Permit. For the HTML version, a content page capable of providing hyperlink of each section and sub-section of these Reports shall be included in the beginning of the document. Hyperlinks to all figures, drawings and tables in these Reports shall be provided in the main text from where the respective references are made. All graphics in these Reports shall be interlaced Graphics Interchange Format (GIF) unless otherwise agreed by the Director. The content of the electronic copies of these Reports must be the same as the hard copies.
4.2 The Permit Holder shall set up a dedicated web site and notify the Director in writing the internet address where the environmental monitoring and project data is to be placed within six weeks after the commencement of construction of the Project. All environmental monitoring results described in Condition 4.1 above, all submissions and all performance test data and results required by this Permit and all minutes of meetings, documents and papers for the Community Liaison Group as described in Condition 2.4 shall be made available to the public via this dedicated web site to be set up by the Permit Holder in the shortest time practicable and in no event later than 2 weeks after the relevant environmental monitoring data are collected or become available, unless otherwise agreed with the Director.
4.3 The internet website as described in Condition 4.2 above shall enable user-friendly public access to the monitoring data and project data including the EIA report, the environmental permit(s) and project profile of the Project. The internet website shall have features capable of : -
(a)
providing access to all
environmental monitoring data collected since the commencement of work and all
submissions under this permit;
(b)
searching by date;
(c)
searching by types of
monitoring data; and
(d)
hyperlinks to relevant monitoring
data after searching;
or
otherwise as agreed by the Director.
Notes :
1.
This Permit consists of three parts, namely, PART A (Main Permit), PART B
(Description of Designated Project) and PART C (Permit
Conditions). Any person relying on
this permit should obtain independent legal advice on the legal implications
under the Ordinance, and the following notes are for general information only.
2.
If there is a breach of any conditions of this Permit,
the Director or his authorized officer may, with the consent of the Secretary
for the Environment, order the cessation of associated work until the remedial
action is taken in respect of the resultant environmental damage, and in that
case the Permit Holder shall not carry out any associated works without the
permission of the Director or his authorized officer.
3.
The Permit Holder may apply under Section 13 of the
Ordinance to the Director for a variation of the conditions of this
Permit. The Permit Holder shall
replace the original permit displayed on the construction site by the amended
permit.
4.
A person who assumes the responsibility for the whole
or a part of the designated project may, before he assumes responsibility of
the designated project, apply under Section 12 of the Ordinance to the Director
for a further environmental permit.
5.
Under Section 14 of the Ordinance, the Director may
with the consent of the Secretary for the Environment, suspend, vary or cancel
this Permit. The suspended, varied
or cancelled Permit shall be removed from display at the construction site.
6.
If this Permit is cancelled or surrendered during
construction or operation of the Project, another environmental permit must be
obtained under the Ordinance before the Project could be continued. It is an offence under section 26(1) of
the Ordinance to construct or operate a designated project listed in Part I of
schedule 2 of the Ordinance without a valid environmental permit.
7.
Any person who constructs or operates the Project
contrary to the conditions in the Permit, and is convicted of an offence under
the Ordinance, is liable:-
(i)
on a first conviction on indictment to a fine of $ 2
million and to imprisonment for 6 months;
(ii)
on a second or subsequent conviction on indictment to
a fine of $ 5 million and to imprisonment for 2 years;
(iii)
on a first summary conviction to a fine at level 6 and
to imprisonment for 6 months;
(iv)
on a second or subsequent summary conviction to a fine
of $1 million and to imprisonment for 1 year; and
(v)
in any case where the offence is of a continuing
nature, the court or magistrate may impose a fine of $ 10,000 for each day on
which he is satisfied the offence continued.
8.
The Permit Holder may appeal against any condition of
this Permit under Section 17 of the Ordinance within 30 days of receipt of this
Permit.
9.
The Notes are for general reference only and that the
Permit Holder should refer to the EIA Ordinance for details and seek
independent legal advice.
Environmental Permit No. EP-292/2007
環境許可證編號 EP-292/2007
|
Figure 1 | Figure 2 | Figure 3 |