Environmental Permit No. EP-296/2007
環境許可證編號EP-296/2007

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE

(CHAPTER 499)

SECTION 10

環境影響評估條例

(499)

10

 

ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE

A DESIGNATED PROJECT

建造及營辦指定工程項目的環境許可證

 

 

 

PART A (MAIN PERMIT)

A (許可證主要部分)

 

Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (EIAO), the Director of Environmental Protection (the Director) grants this environmental permit to the Architectural Services Department (hereinafter referred to as the “Permit Holder”) to construct and operate the designated project described in Part B subject to the conditions specified in Part C. The issue of this environmental permit is based on the documents, approvals or permissions described below:

根據環境影響評估條例(環評條例) 10條的規定,環境保護署署長(署長)將本環境許可證批予建築署 (下稱許可證持有人”) 以建造營辦B所說明的指定工程項目,但須遵守C列明的條件。本環境許可證是依據下列文件、批准或許可而簽發﹕

 

 

Application No.

申請書編號

AEP-296/2007

 

Documents in the Register:

登記冊上的文件:

 

(1)    Proposed Joint User Complex and Wholesale Fish Market at Area 44, Tuen Mun: Environmental Impact Assessment (EIA) Report, Environmental Monitoring and Audit (EM&A) Manual and Executive Summary

(Register No.: AEIAR-070/2003) [Hereinafter referred to as the “EIA Report”]

(1)    擬建之屯門44綜合社區設施及魚類批發市場:環境影響評估報告環境監察及審核手冊及行政摘要

(登記冊編號:AEIAR-070/2003) [下稱環評報告”]

 

(2)    The Director’s letter of approval of the EIA Report dated 14 March 2003 (Reference: (9) in Ax(1) to EP2/N4/N/14 X)

(2)    署長於2003314日發出批准環評報告的信件 (檔案編號(9) in Ax(1) to EP2/N4/N/14 X)

 

 

Documents in the Register:

登記冊上的文件:

(3)    Application for Environmental Permit submitted on 14 November 2007 (Application No. AEP-296/2007)

(3)    20071114日提交的環境許可證申請 (申請書編號:AEP-296/2007)

 

 

 

 

 

 

 

 

 

            December 2007

        200712  

Date

日期

 

(WONG Hon-meng)

Principal Environmental Protection Officer

for Director of Environmental Protection

環境保護署署長

(首席環境保護主任黃漢明代行)


PART B (DESCRIPTIONS OF DESIGNATED PROJECT)

B (指定工程項目的說明)

 

Hereunder is the description of the designated project mentioned in Part A of this environmental permit:

下列為本環境許可證A所提及的指定工程項目的說明:

 

Title of Designated Project

指定工程項目的名稱

Proposed Joint User Complex and Wholesale Fish Market at Area 44, Tuen Mun

[This designated project is hereinafter referred to as “the Project”]

擬建之屯門44綜合社區設施及魚類批發市場

[本指定工程項目下稱 工程項目”]

 

Nature of Designated Project
指定工程項目的性質

Construction and operation of a wholesale fish market.

建造及營辦魚類批發市場

 

Location of Designated Project

指定工程項目的地點

Tuen Mun Area 44.  The location of the Project is shown in Figure 1 attached to this Permit.

屯門第44工程項目的位置載於本許可證夾附的圖1

 

Scale and Scope of Designated Project

指定工程項目的規模和範圍

Construction and operation of a wholesale fish market with gross floor area of approximately 4,700 m2.

建造及營辦一個建築樓面面積4,700平方米魚類批發市場

 


PART C (PERMIT CONDITIONS)

 

1.         General Conditions

 

1.1       The Permit Holder and any person working on the Project shall comply with all conditions set out in this Permit.  Any non-compliance by any person may constitute a contravention of the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and may become the subject of appropriate action being taken under the EIAO.

 

1.2       The Permit Holder shall ensure full compliance with all legislation from time to time in force including without limitation to the Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358) and Waste Disposal Ordinance (Cap. 354).  This Permit does not of itself constitute any ground of defence against any proceedings instituted under any legislation or imply any approval under any legislation.

 

1.3       The Permit Holder shall make copies of this Permit together with all documents referred to in this Permit or the documents referred to in Part A of the Permit readily available at all times for inspection by the Director or his authorised officers at all sites/offices covered by this Permit. Any reference to the Permit shall include all documents referred to in the Permit and also the relevant documents in the Register.

 

1.4       The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understands all conditions and all requirements incorporated by the Permit. The site(s) refers to site(s) of construction and operation of the Project and shall mean the same hereafter.

 

1.5       The Permit Holder shall display conspicuously a copy of this Permit on the Project site(s) at all vehicular site entrances/exits or at a convenient location for public information at all times. The Permit Holder shall ensure that the most updated information about the Permit, including any amended Permit, is displayed at such locations.  If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit.  The suspended, varied or cancelled Permit shall be removed from display at the construction site(s).

 

1.6       The Permit Holder shall construct and operate the Project in accordance with the project descriptions in Part B of this Permit.

 

1.7       The Permit Holder shall ensure that the Project is designed, constructed and operated in accordance with the information and all recommendations described in the EIA Report (Register No.: AEIAR-070/2003), the Application for Environmental Permit (Application No. AEP-296/2007), other relevant documents in the Register, the information and mitigation measures described in this Permit, mitigation measures to be recommended in submissions that shall be deposited with or approved by the Director as a result of permit conditions contained in this Permit, and mitigation measures to be recommended under on going surveillance and monitoring activities during all stages of the Project. Where recommendations referred to in the documents of the Register are not expressly referred to in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded or impliedly amended in this Permit.

1.8       All submissions, as required under this Permit, shall be rectified and resubmitted in accordance with the comments, if any, made by the Director within one month of the receipt of the Director’s comments or otherwise as specified by the Director.

 

1.9       All submissions approved by the Director, all submissions deposited without comments by the Director, or all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions. Any non-compliance with the submissions may constitute a contravention of the Environmental Impact Assessment Ordinance (Cap. 499). All submissions or any variation of the submissions shall be certified by the Environmental Team Leader and verified by the Independent Environmental Checker referred to in Conditions 2.1 and 2.2 below before submitting to the Director under the Permit.

 

1.10     The Permit Holder shall release all finalized submissions, as required under this Permit, to the public by depositing copies in the EIAO Register Office, or in any other places, or any internet websites as specified by the Director, or by any other means as specified by the Director for public inspection. For this purpose, the Permit Holder shall provide sufficient copies of the submissions.

 

1.11     All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to the EIAO Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalized submissions required under this Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies.

 

1.12     The Permit Holder shall notify the Director in writing the commencement date of construction of the Project at least two weeks before the commencement of construction of the Project. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the construction.

 

1.13     For the purpose of this Permit, “commencement of construction” does not include works related to site clearance and preparation, or other works as agreed by the Director.

 

1.14     The Permit Holder shall notify the Director in writing the commencement date of operation of the Project at least two weeks before the commencement of operation of the Project. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the operation.

 

 

2.         Submissions and Measures before Commencement of Construction of the Project

 

Employment of Environmental Monitoring and Audit (EM&A) Personnel

 

2.1       An Environmental Team (ET) shall be established by the Permit Holder no later than one month before the commencement of construction of the Project. The ET shall not be in any way an associated body of the Contractor or the Independent Environmental Checker (IEC) for the Project. The ET shall be headed by an ET Leader. The ET Leader shall be a person who has at least 7 years of experience in environmental monitoring and audit (EM&A) or environmental management. The ET and the ET Leader shall be responsible for the implementation of the EM&A programme in accordance with the EM&A requirements as contained in the EM&A Manual. The ET Leader shall keep a contemporaneous log-book of each and every instance or circumstance or change of circumstances which may affect the environmental impact assessment and each and every non-compliance with the recommendations of the EIA Report (Register No.: AEIAR-070/2003) or this Permit. The ET Leader shall notify the IEC within one working day of the occurrence of any such instance or circumstance or change of circumstances. The ET Leader’s log-book shall be kept readily available for inspection by all persons assisting in supervision of the implementation of the recommendations of the EIA Report (Register No.: AEIAR-070/2003) and this Permit or by the Director or his authorized officers. Failure to maintain records in the log-book, failure to discharge the duties of the ET Leader as defined in the EM&A Manual or failure to comply with this Condition would entitle the Director to require the Permit Holder by notice in writing to replace the ET Leader. Failure by the Permit Holder to make replacement, or further failure to keep contemporaneous records in the log-book despite the employment of a new ET Leader may render the Permit liable to suspension, cancellation or variation.

 

2.2       An IEC shall be employed by the Permit Holder no later than one month before the commencement of construction of the Project. The IEC shall not be in any way an associated body of the Contractor or the ET for the Project. The IEC shall be a person who has at least 7 years of experience in EM&A or environmental management. The IEC shall be responsible for the duties defined in the EM&A Manual and shall audit the overall EM&A programme, including the implementation of all environmental mitigation measures, submissions required in the EM&A Manual, and any other submissions required under this Permit. In addition, the IEC shall be responsible for verifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions under this Permit. The IEC shall verify the log-book(s) mentioned in Condition 2.1 of this Permit. The IEC shall notify the Director by fax, within one working day of receipt of notification from the ET Leader of each and every occurrence, change of circumstances or non-compliance with the EIA Report (Register No.: AEIAR-070/2003) and this Permit, which might affect the monitoring or control of adverse environmental impacts from the Project. In the case where the IEC fails to so notify the Director of the same, fails to discharge the duties of the IEC as defined in the EM&A Manual or fails to comply with this Condition, the Director may require the Permit Holder by notice in writing to replace the IEC. Failure to replace the IEC as directed or further failure to so notify the Director despite employment of a new IEC may render the Permit liable to suspension, cancellation or variation. Notification by the Permit Holder is the same as notification by the IEC for the purpose of this Condition.

 

Set up of an Environmental Committee for the Construction Phase

 

2.3       To monitor environmental impacts of the construction of the Wholesale Fish Market, the Permit Holder shall set up an Environmental Committee (EC) including representatives from the nearby residents before the commencement of construction of the Project to closely supervise the construction of the Wholesale Fish Market.  The EC shall advise on and monitor the proper design and construction of the Wholesale Fish Market according to the EIA Report (Register No.: AEIAR-070/2003) and this Permit, and to follow-up on environmental complaints about the construction of the Wholesale Fish Market.

 

2.4       The Permit Holder shall place all minutes of meeting, the relevant documents and the associated papers of the EC on the dedicated website set up by the Permit Holder under Condition 6.2, within one month of the day of the meeting.

 

Management Organization of Main Construction Companies

           

2.5       The Permit Holder shall, before the commencement of construction of the Project, inform the Director in writing the management organization of the main construction companies and/or any form of joint ventures associated with the construction of the Project.  The submitted information shall include at least an organization chart, names of responsible persons and their contact details.

 

 

3.         Measures for the Construction of the Project

           

Design of the Wholesale Fish Market

 

3.1       To minimise noise and odour impacts, the building of the Wholesale Fish Market shall be a fully-enclosed design with openings only along the waterfront to allow for loading of fish stocks from marine vessels and associated activities.

 

3.2       To minimise noise and odour impacts, the external wall of the Wholesale Fish Market along Wu Shan Road shall be a blank façade with no opening.  Pedestrian entrance at street level along Wu Shan Road, if any, shall be designed with double doors and a lobby. 

 

3.3       To minimise noise and air quality impacts, a minimum of 40 lorry parking spaces shall be provided inside the Wholesale Fish Market with access from the northern side of the building to allow for parking, loading and unloading activities to take place inside the building of the Wholesale Fish Market as shown in Figure 2. 

 

3.4       To minimise road traffic noise impact, the junction at Wu Shan Road for vehicle access to the Wholesale Fish Market shall be designed to prohibit traffic entering and leaving the building from the south of Wu Shan Road as shown in Figure 3.

 

3.5       To minimise noise impact, the Wholesale Fish Market building shall be constructed with a noise canopy of at least 5 m wide and 90 m long projected from the façade of the Wholesale Fish Market along the waterfront to screen off the noise emitted from loading and unloading activities and berthed vessels as shown in Figure 2.

 

3.6       To minimise noise impact, acoustic louvers and silencers with a minimum insertion loss of 15dB(A) shall be installed at plantroom ventilation openings and mechanical ventilation systems respectively. 

 

3.7       To minimise odour impact, an induced draft ventilation system with extraction points located at the fish handling areas and lorry parking area shall be installed.  The exhausts of the ventilation system shall be vented from the waterfront side of the building of the Wholesale Fish Market as shown in Figure 4.  The induced draft ventilation system shall be operated at a rate of no less than 10 air changes per hour throughout the peak operating hours of the Wholesale Fish Market from 3:00 am to 6:30 am.

 

3.8       To minimise odour impact, a de-odorised scrubber system or equivalent de-odorising system shall be installed for the Wholesale Fish Market on mezzanine floor as shown in Figure 4 to remove odour prior to discharging outside the Wholesale Fish Market.

 

3.9       To minimise odour impact, fresh air intakes of the mechanical ventilation system provided to the community hall shall be located at level above 15mPD and fitted with odour removal systems such as carbon filters to remove odour.

 

3.10     To minimise odour impact, building materials used associated with the operation of the Wholesale Fish Market shall be impervious, durable and easy to clean to avoid build-up of odour from organic material carried in washing water.

 

            Measures to Mitigate Environmental Impacts during Construction

 

3.11     To minimise air quality impact, solid hoarding of at least 2.4 m high shall be erected along the site boundary, except at the site entrance and exit, during construction of the Project.

 

3.12     To minimise air quality impact, any stockpile of dusty materials shall be covered entirely by impervious sheeting; placed in an area sheltered on the top and the three sides; or sprayed with water or a dust suppression chemical so as to maintain the entire surface wet.

 

3.13     To minimise air quality impact, vehicle washing facilities including a high pressure water jet shall be provided at vehicle exit points and vehicles immediately before leaving the construction site shall be washed to remove any dust material from their wheels and bodies.

 

3.14     To minimise noise impact, no percussive piling shall be used for the construction of the Project.

 

3.15     To minimise noise impact, silencers or mufflers on construction equipment shall be utilised and shall be properly maintained during construction of the Project.

 

3.16     To minimise water quality impact, surface run-off from the construction site shall be directed to silt traps or sedimentation basins before reuse or discharge with the help of channels, earth bunds or sand bag barriers for removal of suspended solids prior to discharging into stormwater drainage system.  No discharge of surface runoff into foul sewers shall be allowed.

 

3.17     To minimise air and water quality impacts, main haul roads, vehicle washing areas and the sections of roads between the washing facilities and the vehicle exit points shall be paved with concrete, bituminous materials, hardcore or metal plates.

 

 

 

4.         Submissions and Measures for the Operation of the Project

 

Set up of an Environmental Management Committee for the Operational Phase

 

4.1       To monitor environmental impacts of the operation of the Wholesale Fish Market, the Permit Holder shall set up an Environmental Management Committee (EMC) including representatives from the market management, market users and the nearby residents before the commencement of operation of the Project to closely supervise the operation of the Wholesale Fish Market.  The EMC shall advise on and monitor the effectiveness of the proposed mitigation measures and the environmental performance of the Wholesale Fish Market according to the EIA Report (Register No.: AEIAR-070/2003) and this Permit, and to follow-up on environmental complaints about the operation of the Wholesale Fish Market.

 

4.2       The Permit Holder shall place all minutes of meeting, the relevant documents and the associated papers of the EMC on the dedicated website set up by the Permit Holder under Condition 6.2, within one month of the day of the meeting.

 

          Submission on Routing Arrangement of Marine Vessels

 

4.3       To further minimise and monitor noise impact during operational stage, a routing arrangement of marine vessels associated with the operation of the Wholesale Fish Market shall be submitted to and approved by the Director before the commencement of operation of the Wholesale Fish Market.  All recommendations of the approved submission shall be followed and implemented.

 

Maintenance of the Design of the Wholesale Fish Market

 

4.4       To minimise the environmental impacts, the design of the Wholesale Fish Market specified in Conditions 3.1 to 3.10 shall be properly implemented and maintained throughout the operation of the Project:

 

            (i)                   the building of the Wholesale Fish Market shall be fully-enclosed with openings only along the waterfront to allow for loading of fish stocks from marine vessels.

            (ii)                 the external wall of the Wholesale Fish Market along Wu Shan Road shall be a blank façade with no opening.  Pedestrian entrance at street level along Wu Shan Road, if any, shall be designed with double doors and a lobby.

            (iii)                a minimum of 40 lorry parking spaces shall be provided inside the Wholesale Fish Market with access from the northern side of the building to allow for parking, loading and unloading activities to take place inside the building of the Wholesale Fish Market as shown in Figure 2.

            (iv)               the junction at Wu Shan Road for vehicle access to the Wholesale Fish Market shall be designed to prohibit traffic entering and leaving the building from the south of Wu Shan Road as shown in Figure 3.

            (v)                 the Wholesale Fish Market building shall be constructed with a noise canopy of at least 5 m wide and 90 m long projected from the façade of the Wholesale Fish Market along the waterfront to provide screening for the noise emitted from loading and unloading activities and berthed vessels as shown in Figure 2.

            (vi)               acoustic louvers and silencers with a minimum insertion loss of 15dB(A) shall be installed at plantroom ventilation openings and mechanical ventilation systems respectively.

            (vii)              an induced draft ventilation system with extraction points located at the fish handling areas and lorry parking area shall be installed.  The exhausts of the ventilation system shall be vented from the waterfront side of the building of the Wholesale Fish Market as shown in Figure 4.  The induced draft ventilation system shall be operated at a rate of no less than 10 air changes per hour throughout the peak operating hours of the Wholesale Fish Market from 3:00 am to 6:30 am.

            (viii)            a de-odorised scrubber system or equivalent de-odorising system shall be installed for the Wholesale Fish Market on mezzanine floor as shown in Figure 4 to remove odour prior to discharge outside the Wholesale Fish Market.

            (ix)               fresh air intakes of the mechanical ventilation system provided to the community hall shall be located at level above 15mPD and fitted with odour removal systems such as carbon filters to remove odour.

            (x)                 construction materials for the Wholesale Fish Market shall be impervious, durable and easy to clean to avoid build-up of odour from organic material carried in washing water.

 

            Measures to Mitigate Environmental Impacts during Operation

 

4.5       To minimise marine traffic noise impact, the Permit Holder shall require marine vessels associated with the operation of the Wholesale Fish Market to use the eastern entrance of the Tuen Mun Typhoon Shelter when they approach and leave the Wholesale Fish Market.

 

4.6       To minimise marine traffic noise impact, no more than nine fishing vessels and two sampans shall be allowed to approach and leave the Wholesale Fish Market per hour.

 

4.7       To minimise noise impact, no loudhailer shall be used by fish traders and market users within the Wholesale Fish Market.

 

4.8       To minimise noise impact, the Permit Holder shall require marine vessels visiting the Wholesale Fish Market not to use any loudhailer and horn, except under emergency.

 

4.9       To minimise road traffic noise and air quality impacts, vehicles/lorries associated with the operation of the Wholesale Fish Market shall only be parked inside the carpark of the Wholesale Fish Market with access from the northern side of the building as shown in Figure 2.  The Permit Holder shall ensure no on-street parking and on-street loading and unloading activities associated with the operation of the Wholesale Fish Market.

 

4.10     To minimise road traffic noise impact, no traffic shall be allowed to enter and leave the Wholesale Fish Market from the south of Wu Shan Road as shown in Figure 3.

 

 

4.11    To minimise odour impact, the fish market areas shall be cleaned at least daily.  Organic waste from the Wholesale Fish Market shall be sealed in collection bags or containers for daily disposal out of the Wholesale Fish Market.

5.         Environmental Monitoring and Audit (EM&A) Requirements

           

5.1       The EM&A programme shall be implemented in accordance with the procedures and requirements as set out in the EM&A Manual.  Any changes to the EM&A programme shall be justified by the ET Leader and verified by the IEC as conforming to the requirements set out in the EM&A Manual before submission to the Director for approval.

 

5.2       Samples, surveys, measurements and necessary remedial actions shall be taken in accordance with the EM&A Manual by:

 

(i)         conducting baseline environmental monitoring on air quality and noise for the construction of the Project;

(ii)        conducting impact monitoring on air quality and noise for the construction of the Project;

(iii)       conducting odour, operational noise and marine traffic noise monitoring at least during the peak operating hours from 3:00 am to 6:30 am at a frequency of no less than once a week throughout the first 12 months of the operation of the Wholesale Fish Market;

(iv)        carrying out remedial actions described in the Event/Action Plans of the EM&A Manual fully and properly in accordance with the time frames set out in the Event/Action Plans, or as agreed by the Director; and

(v)        logging and keeping records of details of (i) to (iv) above for all parameters within 3 working days of the collection of data or completion of remedial action(s), for the purpose of preparing and submitting the monthly EM&A reports and to make available the information for inspection on site.

 

5.3       Four hard copies and one electronic copy of the Baseline Monitoring Report shall be submitted to the Director at least two weeks before the commencement of construction of the Project.  The submission shall be certified by the ET leader and verified by the IEC before submission to the Director.  Additional copies of the submission shall be provided upon request by the Director.

 

5.4       Four hard copies and one electronic copy of the monthly EM&A Report shall be submitted to the Director within two weeks after the end of the reporting month.  The EM&A Reports shall include a summary of all non-compliances (exceedances) of the environmental quality performance limits (Action and Limit Levels). The submission shall be certified by the ET leader and verified by the IEC before submission to the Director.  Additional copies of the submission shall be provided upon request by the Director.

 

5.5       All environmental monitoring and audit results submitted under this Permit shall be true, valid and correct.

 

5.6       To ensure high degree of transparency regarding the monitoring data and results of the Project, all environmental monitoring and audit data and results and all submissions and all performance test data and results required by this Permit shall be made available by the Permit Holder to the public through a dedicated web site to be set up by the Permit Holder under Condition 6.2 below, in the shortest practicable time and in no event later than two weeks after such information is available.

 

Visual Monitoring by Web Cameras

 

5.7       Within three months of the commencement of construction of the Wholesale Fish Market, the Permit Holder shall install and thereafter maintain a system of web cameras covering the construction works areas at the Project site.  The system shall provide real time visual monitoring of the site condition during construction and shall be accessible by public through the dedicated web site set up by the Permit Holder under Condition 6.2 below.

 

5.8       Before the commencement of operation of the Wholesale Fish Market, the Permit Holder shall install and thereafter maintain a system of web cameras covering the Project site for the first 12 months of the operation of the Wholesale Fish Market.  The system shall provide real time visual monitoring of the site condition covering at least the peak operating hours of the Wholesale Fish Market from 3:00 am to 6:30 am each day and shall be accessible by public through the dedicated web site set up by the Permit Holder under Condition 6.2 below.  The Permit Holder shall review and consult the Environmental Management Committee before seeking the agreement from the Director on the need to continue to maintain the system of web cameras covering the Project site after the first 12 months of the operation of the Project.

 

 

6.         Electronic Reporting of EM&A Information

 

6.1       To facilitate public inspection of the Baseline Monitoring Report and the monthly EM&A Reports via the EIAO Internet Website and at the EIAO Register Office, electronic copies of these Reports shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF version 4.0 or later), unless otherwise agreed by the Director and shall be submitted at the same time as the hard copies as described in Conditions 5.3 and 5.4 of this Permit.  For the HTML version, a content page capable of providing hyperlink to each section and sub-section of these Reports shall be included in the beginning of the document. Hyperlinks to all figures, drawings and tables in these Reports shall be provided in the main text from where the respective references are made. All graphics in these Reports shall be in interlaced GIF format unless otherwise agreed by the Director. The content of the electronic copies of these Reports must be the same as the hard copies.

 

6.2      The Permit Holder shall set up a dedicated website and notify the Director in writing the Internet address where the environmental monitoring and project data is to be placed, within six weeks after the commencement of construction of the Project. All environmental monitoring data described in Condition 6.1 above shall be made available to the public via a dedicated website to be set up by the Permit Holder in the shortest possible time and in no event later than two weeks after the relevant environmental monitoring data are collected or become available, unless otherwise agreed with the Director.

 

 

6.3       The Internet website as described in Condition 6.2 above shall enable user-friendly public access to the monitoring and project data including the EIA Report and the environmental permit(s) and the project profile of the Project. The Internet website shall have features capable of:

 

(i)                  providing access to all environmental monitoring data collected since the commencement of works and all submissions under this Permit;

(ii)                searching by date;

(iii)               searching by types of monitoring data; and

(iv)              hyperlinks to relevant monitoring data after searching;

            or otherwise as agreed by the Director.

Notes:

 

1.         This Permit consists of three parts, namely, Part A (Main Permit), Part B (Description of Designated Project) and Part C (Permit Conditions).  Any person relying on this permit should obtain independent legal advice on the legal implications under the EIAO, and the following notes are for general information only.

 

2.         If there is a breach of any condition of this Permit, the Director or his authorized officer may, with the consent of the Secretary for the Environment, Transport and Works, order the cessation of associated work until the remedial action is taken in respect of the resultant environmental damage, and in that case the Permit Holder shall not carry out any associated works without the permission of the Director or his authorized officer.

 

3.         The Permit Holder may apply under Section 13 of the EIAO to the Director for a variation of the conditions of this Permit. The Permit Holder shall replace the original permit displayed on the Project site by the amended permit.

 

4.         A person who assumes responsibility for the whole or a part of the Project may, before he assumes responsibility of the Project, apply under Section 12 of the EIAO to the Director for a further environmental permit.

 

5.         Under Section 14 of the EIAO, the Director may with the consent of the Secretary for the Environment, Transport and Works, suspend, vary or cancel this Permit.  The suspended, varied or cancelled Permit shall be removed from display at the Project site.

 

6.         If this Permit is cancelled or surrendered during operation of the Project, another environmental permit must be obtained under the EIAO before the Project could be continued.  It is an offence under Section 26(1) of the EIAO to operate a designated project listed in Part I of Schedule 2 of the EIAO without a valid environmental permit.

 

7.         Any person who operates the Project contrary to the conditions in the Permit, and is convicted of an offence under the EIAO, is liable:

(i)                  on a first conviction on indictment to a fine of $2 million and to   imprisonment for 6 months;

(ii)                on a second or subsequent conviction on indictment to a fine of $5 million and to imprisonment for 2 years;

 

(iii)               on a first summary conviction to a fine at level 6 and to imprisonment for 6 months;

(iv)              on a second or subsequent summary conviction to a fine of $1 million and to imprisonment for 1 year; and

 

(v)                in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $10,000 for each day on which he is satisfied the offence continued.

 

8.         The Permit Holder may appeal against any condition of this Permit under Section 17 of the EIAO within 30 days of receipt of this Permit.

 

9.         The Notes are for general reference only and that the Permit Holder should refer to the EIAO for details and seek independent legal advice.

 

 

Environmental Permit No. EP-296/2007

 

| Figure 1 | Figure 2 | Figure 3 | Figure 4 |