Environmental Permit No. EP-429/2012
環境許可證編號 EP-429/2012
ENVIRONMENTAL
IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
SECTION 10
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE
A DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental Impact
Assessment Ordinance (EIAO), the Director of Environmental Protection (the
Director) grants this environmental permit to the DIRECTOR of ENVIRONMENTAL PROTECTION (hereinafter referred
to as the “Permit Holder”) to construct and operate the designated project
described in Part B subject to the conditions specified
in Part C. The issue of this environmental permit is based
on the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例) 第10條的規定,環境保護署署長(署長)將本環境許可證批予環境保護署署長 (下稱“許可證持有人”)以建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發﹕
Application No. 申請書編號 |
AEP-429/2011 |
|
Document in
the Register: 登記冊上的文件: |
(1) (2) (3) |
Engineering Investigation and Environmental Studies
for Integrated Waste Management Facilities Phase 1 – Feasibility Study
(October 2011) Environmental
Impact Assessment Report [Hereinafter
referred to as the “EIA Report”] EIA
Executive Summary [Hereinafter
referred to as the “EIA Executive Summary”] Environmental
Monitoring and Audit Manual [Hereinafter
referred to as the “EM&A Manual”] (Register
No. AEIAR-163/2012) 綜合廢物管理設施第一期工程及環境研究─可行性研究(2011年10月) 環境影響評估報告 [下稱“環評報告”] 環境影響評估報告行政摘要 [下稱“環評摘要”] 環境監察及審核手冊 [下稱 “環監手冊”] (登記冊檔號:AEIAR-163/2012) The Director’s letter of approval of the EIA
report dated 17 January 2012 (Reference: (5) in Ax (1) to EP2/G/G/ 署長於 Application for environmental permit submitted
by the Permit Holder on 24 October 2011 (Application No.: AEP-429/2011) 許可證持有人於 |
19
January 2012
Date 日期 |
|
(WONG Hon-meng) Principal Environmental Protection Officer for Director of Environmental Protection 環境保護署署長 (首席環境保護主任黃漢明代行) |
PART B (DESCRIPTION OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the designated
project mentioned in Part A of this environmental
permit (hereinafter referred to as the “Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明﹕
Title
of Designated Project 指定工程項目的名稱 |
Development of the Integrated Waste Management
Facilities Phase 1 [This designated project is hereinafter referred to as
“the Project”] 發展綜合廢物管理設施第一期 [本指定工程項目下稱 “工程項目”] |
Nature of Designated Project |
(i)
An incinerator with an
installed capacity of more than 50 tonnes per day (ii)
A waste disposal facility for
refuse (iii)
A waste disposal facility for
pulverized fuel ash or furnace bottom ash (iv)
Public utility electricity
power facility (v)
Reclamation works (including
associated dredging works) of more than (vi)
An activity for the reuse of
treated sewage effluent from a treatment plant (i)
裝置的垃圾焚化能力超過每天50公噸的垃圾焚化爐 (ii)
垃圾處置設施 (iii)
處置粉狀的燃料灰或爐底灰的廢物處置設施 (iv)
公用事業電力廠 (v)
面積超過 (vi) 對從處理廠流出並經處理的污水進行再使用的活動 |
Location
of Designated Project 指定工程項目的地點 |
Located near the south-western
coast of 毗鄰介乎於長洲西南和大嶼山芝麻灣半島以南的石鼓洲西南海岸。工程項目的位置載於本許可證夾附的圖1。 |
Scale and Scope of Designated Project 指定工程項目的規模和範圍 |
The Project is mainly to: 工程主要包括: (i)
reclaim 15.9 hectares of land; 填海供地15.9公頃; (ii)
construct and operate an incinerator with
design capacity of 3,000 tonnes per day for treating municipal solid wastes; 建造及營辦一所設計處理能力達每日3,000公噸的焚化爐以供處理都市固體廢物; (iii)
construct and operate a mechanical sorting
and recycling plant with design capacity of 200 tonnes per day; 建造及營辦一所設計處理能力達每日200公噸的機械式分類及回收廠; (iv)
construct and operate an on-site wastewater
treatment plant for the reuse of treated sewage effluent; 建造及營辦一所污水處理廠以供重新使用經過處理的污水; (v)
construct and operate an on-site
desalination plant; 建造及營辦一所海水化淡廠; (vi)
construct and operate an electricity power
plant for the heat recovered from the incineration process; 建造及營辦一所電廠以供回收焚化過程中所產生的熱能; (vii)
construct submarine cables for exporting
surplus electricity to the power grid; 建造海底電纜以供輸送剩餘的電力至電網; (viii)
construct and operate a berthing area; and 建造及營辦碼頭區; 及 (ix)
construct and operate an environmental
education centre, supporting and community facilities. 建造及營辦一所環境教育中心、支援及社區設施。 |
C部 (許可證條件)
1. General
Conditions
一般條件
1.1 The Permit
Holder and any person working on the Project shall comply with all conditions
set out in this Permit. Any non-compliance by any person may constitute a
contravention of the Environmental Impact Assessment Ordinance (EIAO) (Cap.
499) and may become the subject of appropriate action being taken under the
EIAO.
許可證持有人及任何從事工程項目的人士必須符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反環境影響評估條例 (「環評條例」)
(第499章) 的規定,而當局可根據條例採取適當行動。
1.2 The Permit Holder shall ensure full
compliance with all legislation from time to time in force including, without
limitation to, the Noise Control Ordinance (Cap. 400), Air Pollution Control
Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), and Waste
Disposal Ordinance (Cap. 354). This Permit does not of itself constitute any
ground of defence against any proceedings instituted under any legislation or
imply any approval under any legislation.
許可證持有人須經常確保完全符合現行法例的規定,包括但不限於噪音管制條例(第400章);空氣污染管制條例(第311章);水污染管制條例(第358章);以及廢物處置條例(第354章)。本許可證本身不會就根據任何法例提起的法律程式構成任何抗辯理由,或根據任何法例默示任何批准。
1.3 The Permit Holder shall make
copies of this Permit together with all documents referred to in this Permit
and the documents referred to in Part A of the Permit
readily available at all times for inspection by the Director or his authorised
officers at all sites/offices covered by this Permit. Any reference to the
Permit shall include all documents referred to in the Permit and also the
relevant documents in the Register.
許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件及本許可證A部所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地 / 辦事處查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。
1.4 The Permit Holder shall give a
copy of this Permit to the person(s) in charge of the site(s) and ensure that
such person(s) fully understands all conditions and all requirements
incorporated in the Permit. The site(s) refers to site(s) of construction and
operation of the Project and shall mean the same hereafter.
許可證持有人須把本許可證的複本交予有關工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指建造及營辦工程項目的工地,下文所提及的工地亦屬同一意思。
1.5 The Permit Holder shall display
conspicuously a copy of this Permit on the Project site(s) at all vehicular
site entrances/exits or at a convenient location for public’s information at all
times. The Permit Holder shall ensure that the most updated information about
the Permit, including any amended Permit, is displayed at such locations.
If the Permit Holder surrenders a part or the whole of the Permit, the notice
he sends to the Director shall also be displayed at the same locations as the
original Permit. The suspended, varied or cancelled Permit shall be
removed from display at the Project site(s).
許可證持有人須在工程項目的工地的所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證 (包括任何經修訂的許可證) 的最新資料。許可證持有人如交回許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的相同地點展示。遭暫時吊銷、更改或取消的許可證必須從工程項目的工地除下,不再展示。
1.6 The Permit Holder shall
construct and operate the Project in accordance with the project description in
Part B of this Permit.
許可證持有人須依據本許可證B部的工程項目說明,建造及營辦工程項目。
1.7 The Permit
Holder shall ensure that the Project is designed, constructed and operated in
accordance with the information and all recommendations described in the EIA
Report (Register No.: AEIAR-163/2012), the application documents including all
attachments (Application No. AEP-429/2011), other relevant documents in the
Register; and the information or mitigation measures described in this Permit,
and mitigation measures to be recommended in submissions that shall be
deposited with or approved by the Director as a result of permit conditions
contained in this Permit, and mitigation measures to be recommended under on
going surveillance and monitoring activities during all stages of the Project.
Where recommendations referred to in the documents of the Register are not
expressly referred to in this Permit, such recommendations are nevertheless to
be implemented unless expressly excluded or impliedly amended in this Permit.
許可證持有人須確保工程項目的設計、建造及營辦,按照下述資料及措施辦理:環評報告(登記冊編號:AEIAR-163/2012) 所說明的資料及各項建議、申請文件包括所有附件(申請書編號: AEP-429/2011);登記冊內的其他相關文件;本許可證所說明的資料及緩解措施;根據本許可證內載的條件須向署長存放或獲署長批准的提交文件所建議的緩解措施;以及在工程項目各階段進行的持續監察及監測工作所建議的緩解措施。登記冊文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或默示修訂。
1.8 All deposited submissions, as
required under this Permit, shall be rectified and resubmitted in accordance
with the comments, if any, made by the Director within one month of the receipt
of the Director’s comments or otherwise as specified by the Director.
所有按本許可證規定存放的文件,須在接獲署長的意見 (如有者) 後1個月內
(除非署長另行指定),根據署長的意見加以修正並再向署長提交。
1.9 All submissions approved by the
Director, all submissions deposited without comments by the Director, or all
submissions rectified in accordance with comments by the Director under this Permit
shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions
shall be approved by the Director in writing or as prescribed in the relevant
permit conditions. Any non-compliance with the submissions may constitute a
contravention of the Environmental Impact Assessment Ordinance (Cap. 499). All submissions
or any variation of the submissions shall be certified by the Environmental
Team (ET) Leader and verified by the Independent Environmental Checker (IEC)
referred to Conditions 2.1 and 2.2 below, before submitting to the Director
under the Permit.
署長批准的所有提交文件、署長沒有給予意見的所有存放文件及根據本許可證規定由署長給予意見修正的所有提交文件,均須詮釋為本許可證C部 說明的許可證條件的一部分。提交文件如有任何修訂,均須獲署長的書面批准,或符合有關許可證條件訂明的規定。如有不符合提交文件的情況,則可能違反環境影響評估條例 (第499章) 的規定。所有提交文件或提交文件的任何修訂本,均須按下文條件第2.1及2.2項所述由環境小組組長核證及獨立環境查核人核實,然後才按本許可證規定向署長提交。
1.10 The Permit Holder shall release all
finalized submissions as required under this Permit, to the public by depositing
copies in the EIAO Register Office, or in any other places, or any internet
websites as specified by the Director, or by any other means as specified by
the Director for public inspection. For this purpose, the Permit Holder shall
provide sufficient copies of the submissions.
許可證持有人須把所有按本許可證規定提交的文件定稿公開給公眾人士知道,方法是把有關文件複本存放於環境影響評估條例登記冊辦事處,或署長指定的任何其他地方,或署長指定的任何互聯網網站,或採取署長指定的任何其他方法,以供公眾查閱。因此,許可證持有人須提供足夠數量的複本。
1.11 All submissions to the Director required under
this Permit shall be delivered either in person or by registered mail to the
EIAO Register Office (currently at 27/F, Southorn Centre,
本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環境影響評估條例登記冊辦事處
(現址為:香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子版本,均須以超文本標示語言 (HTML) (第4.0或較後版本) 和便攜式文件格式 (PDF) (第4.0或較後版本) 製作,除非另獲署長同意,並須與硬複本同時提交。
1.12 The Permit Holder shall notify the Director
in writing the commencement date of construction of the Project at least 1
month prior to the commencement of construction of the Project. The Permit
Holder shall notify the Director in writing immediately if there is any change
of the commencement date of the construction.
許可證持有人須在工程項目的建造工程展開前,至少提早1個月以書面方式把建造工程的施工日期通知署長。建造工程的施工日期如有任何更改,許可證持有人必須立即以書面方式通知署長。
1.13 For the purpose of this Permit, “commencement of
construction” does not include works related to site clearance and preparation,
or other works as agreed by the Director.
為執行本許可證,「建造工程的展開」不包括有關工地清理和預備的工程,或署長同意的其他工程。
2 Specific Conditions
特定條件
Submissions or Measures before Commencement of
Construction
施工前須提交的文件或採取的措施
Employment of Environmental Monitoring
and Audit (EM&A) Personnel
聘用環境監察及審核(環監)人員
2.1
An Environmental Team (ET) shall be established by the
Permit Holder no later than 1 month before the commencement of construction of
the Project. The ET shall not be in any way an associated body of the
Contractor or the Independent Environmental Checker (IEC) for the Project.
The ET shall be headed by an ET Leader. The ET Leader shall be a person who has
at least 7 years of experience in environmental monitoring and auditing
(EM&A) or environmental management. The ET and the ET Leader shall be
responsible for the implementation of the EM&A programme in accordance with
the EM&A requirements as contained in the EM&A Manual of the
Project. The ET Leader shall keep a contemporaneous log-book of each and
every instance or circumstance or change of circumstances, which may affect the
compliance with the recommendations of the EIA Report (Register
No.: AEIAR-163/2012) and this Permit. The ET Leader shall notify
the IEC within one working day of the occurrence of any such instance or
circumstance or change of circumstances. The ET Leader’s log-book shall
be kept readily available for inspection by all persons assisting in
supervision of the implementation of the recommendations of the EIA Report (Register No.: AEIAR-163/2012) and this Permit or by
the Director or his authorized officers. Failure to maintain records in
the log-book, failure to discharge the duties of the ET Leader as defined in
the EM&A Manual or failure to comply with this Condition would entitle the
Director to require the Permit Holder by notice in writing to replace the ET
Leader. Failure by the Permit Holder to make replacement, or further
failure to keep contemporaneous records in the log-book despite the employment
of a new ET Leader may
render the Permit liable to suspension, cancellation or variation.
在工程項目的建造工程展開前,許可證持有人須至少提早1個月成立一個環境小組。環境小組不得與工程項目的承辦商或獨立環境查核人有任何聯繫。環境小組須由一名環境小組組長帶領。環境小組組長須在環境監察及審核 (「環監」)
或環境管理方面至少有7年經驗。環境小組及環境小組組長須按工程項目的環監手冊內載的環監規定,執行環監計劃。環境小組組長須保存一本記錄冊,同時記載可能會影響環評報告 (登記冊編號:AEIAR-163/2012)
的建議及本許可證的符合情況的每宗事件、每種情況或每次情況變化。環境小組組長須在發生任何類似事件、情況或情況變化後1個工作天內通知獨立環境查核人。存放環境小組組長的記錄冊的地方,須可供協助督導執行環評報告 (登記冊編號:AEIAR-163/2012)
的建議及本許可證的所有人士、署長或獲授權人員隨時查閱。環境小組組長如未能在記錄冊保存記錄、未能執行環監手冊所列明的環境小組組長職務或未能符合本條件的規定,署長有權以書面要求許可證持有人撤換環境小組組長。許可證持有人如未能安排人選替補,或在聘用新環境小組組長後仍未能在記錄冊保存同期的記錄,或會導致許可證遭暫時吊銷、取消或更改。
2.2
An IEC shall
be employed by the Permit Holder no later than 1 month before the commencement
of construction of the Project. The IEC shall not be in any way an
associated body of the Contractor or the ET for the Project. The IEC
shall be a person who has at least 7 years of experience in EM&A or
environmental management. The IEC shall be responsible for duties defined
in the EM&A Manual and shall audit the overall EM&A performance,
including the implementation of all environmental mitigation measures, submissions
required in the EM&A Manual, and any other submissions required under this
Permit. In addition, the IEC shall be responsible for verifying the
environmental acceptability of permanent and temporary works, relevant design
plans and submissions under this Permit. The IEC shall verify the
log-book(s) mentioned in Condition 2.1 of this Permit. The IEC shall
notify the Director by fax, within one working day of receipt of notification
from the ET Leader of each and every change of circumstances or non-compliance
with the recommendations of the EIA Report (Register
No.: AEIAR- 163/2012) and
this Permit, which might affect the monitoring or control of adverse
environmental impacts from the Project. In case the IEC fails to so
notify the Director of the same, fails to discharge the duties of the IEC as
defined in the EM&A Manual or fails to comply with this Condition, the
Director may require the Permit Holder by notice in writing to replace the
IEC. Failure to replace the IEC as directed or further failure to so
notify the Director despite employment of a new IEC may render the Permit
liable to suspension, cancellation or variation. Notification by the
Permit Holder is the same as notification by the IEC for the purpose of this
Condition.
在工程項目的建造工程展開前,許可證持有人須至少提早1個月聘用一名獨立環境查核人。獨立環境查核人不得與工程項目的承辦商或環境小組有任何聯繫。獨立環境查核人須在環監或環境管理方面至少有7年經驗。獨立環境查核人須執行環監手冊所列明的職務,以及審核整體環監工作的表現,包括實施所有環境緩解措施、提交環監手冊規定的文件,以及提交本許可證所要求的其他文件。此外,獨立環境查核人須核實永久及臨時工程在環境上的可接受程度、相關的設計圖則和根據本許可證提交的文件,並須核實本許可證條件第2.1項所述的記錄冊。在每次出現事故、情況變化或不符合環評報告 (登記冊編號:AEIAR- 163/2012)的建議及本許可證的情況,而可能會妨礙工程項目所造成不良環境影響的監察或控制工作時,獨立環境查核人須在接獲環境小組組長通知後1個工作天內以傳真方式通知署長。獨立環境查核人如未能通知署長有關情況、未能執行環監手冊所列明的獨立環境查核人職務或未能符合本條件的規定,署長可以書面要求許可證持有人撤換獨立環境查核人。如未能按指示撤換獨立環境查核人,或在聘用新獨立環境查核人後仍未能通知署長有關情況,則或會導致許可證遭暫時吊銷、取消或更改。為執行本條件,許可證持有人的通知等同獨立環境查核人的通知。
Management Organization of Main
Construction Companies
主要建造公司的管理架構
2.3
The Permit
Holder shall, no later than 2 weeks before the commencement of construction of
the Project, inform the Director in writing the management organization of the
main construction companies and/or any form of joint ventures associated with
the construction of the Project. The submitted information shall include
at least an organization chart, names of responsible persons and their contact
details.
許可證持有人在工程項目的建造工程展開前,須至少提早2個星期把主要建造公司及 / 或以任何形式與建造工程相關的合營企業的管理架構,以書面通知署長。提交的資料須至少包括一份組織圖、負責人的姓名及聯絡資料。
Setting up of Community Liaison Group
成立社區聯絡小組
2.4
To enhance
transparency and communication with the public, the Permit Holder shall, at
least 3 months before the commencement of construction of the Project, set up a
Community Liaison Group comprising representatives of
concerned and affected parties, including the fishery sector, to facilitate
communications, enquires and complaints handling on all environmental issues.
The Community Liaison Group shall take a proactive approach to
disseminate information to the local community, promote community cooperation
and participation and implement suitable local environmental enhancement
works. All relevant information of
the project including the detailed design, the progress of construction and
operation and environmental monitoring and audit results shall be provided to
the Community Liaison Group. The
Permit Holder shall inform the Director in writing the membership and terms of
reference of the Community Liaison Group.
The Permit Holder shall make the minutes of the Community Liaison Group
meetings and all papers and documents available to the public through a
website.
為提高透明度和加強與公眾溝通,在工程項目的建造工程展開前至少提早3個月,許可證持有人須成立一個由相關及受影響團體代表,包括漁業界組成的社區聯絡小組,以方便有關人士就所有環境問題進行溝通、查詢及處理投訴。社區聯絡小組須採取積極主動的做法,向當地社區傳遞信息、推廣社區合作和參與,並進行適當的地區環境改善工程。工程項目的所有相關資料,包括詳細設計、建造及營辦進度、環境監察及審核結果,均須提供予社區聯絡小組。許可證持有人須將社區聯絡小組的成員名單及職權範圍以書面通知署長,並須把社區聯絡小組的所有會議記錄及相關文件,上載至網站供公眾閱覽。
Submission of
Works Schedule and Location Plan
提交施工時間表及位置圖
2.5 The dredging and filling works together with seawall construction of the Project shall be carried out in stages. At least 1 month before the commencement of the above marine works of the Project, 3 hard copies and 1 electronic copy of works schedule and location plan in the scale of 1:1000 or other appropriate scales shall be deposited with the Director. The works schedule and location plan shall include an update works programme with dates of commencement of construction activities, dredging and filling works together with seawall construction with reference to the sequence and locations as shown in Figure 2 of this Permit.
工程項目的挖泥和填土工程,以及海堤建造工程須分期進行。須在以上的海事工程展開前,至少提早1個月向署長存放施工時間表及用1:1 000或其他合適比例繪製的位置圖的3份複本及1份電子版本。施工時間表及位置圖須包括最新的工程計劃,並參照本許可證圖2所示的施工次序及位置,顯示建造工程、挖泥及填土工程,以及海堤建造工程分別的施工日期。
Before submission to the Director,
the works schedule and location plan shall be certified by the ET Leader and
verified by the IEC as conforming to the recommendations contained in the
approved EIA report (Register No.: AEIAR-163/2012).
施工時間表及位置圖在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告(登記冊編號:AEIAR-163/2012)內載的有關建議。
The
recommendations in the works schedule and location plan shall be fully and
properly implemented for the Project.
施工時間表及位置圖內載的有關建議均須在工程項目徹底及妥善執行。
Any subsequent changes to
the construction sequences and/or arrangements shall be deposited with the
Director at least two weeks before implementation of such changes. Before submission to the Director,
the proposed changes shall be certified by the ET Leader and verified by the
IEC as conforming to the requirements set out in the “Technical Memorandum on
Environmental Impact Assessment Process”.
施工次序及/或安排其後如有任何修改,許可證持有人須在實施有關修改前,至少提早2個星期向署長存放修改詳情。建議的修改在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合環境影響評估程序技術備忘錄訂明的要求。
Submission of
Silt Curtain Deployment Plan
提交隔泥幕設置計劃
2.6 At least 1 month before the commencement of the marine works of the Project, 3 hard copies and 1 electronic copy of a silt curtain deployment plan shall be deposited with the Director. The silt curtain deployment plan shall include the construction programme and details on the design, operation and maintenance of silt curtain(s) for dredging and filling works.
在工程項目的海事工程展開前,須至少提早1個月向署長存放隔泥幕設置計劃的3份複本及1份電子版本。隔泥幕設置計劃須包括就挖泥及填土工程設置隔泥幕的施工計劃,以及隔泥幕的設計、營辦和保養詳情。
Before submission to the
Director, the silt curtain deployment plan shall be certified by the ET Leader
and verified by the IEC as conforming to the recommendations contained in the
approved EIA report (Register No.: AEIAR-163/2012).
隔泥幕設置計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告(登記冊編號:AEIAR-163/2012)內載的有關建議。
All measures recommended
in the deposited silt curtain deployment plan shall be fully and properly
implemented for the Project.
已存放的隔泥幕設置計劃建議的所有措施均須在工程項目徹底及妥善執行。
Submission of
Detailed Proposal on Enhancement of Air Quality Monitoring in Cheung Chau
提交在長洲加強進行空氣質素監測的詳細建議
2.7
At least 3
months before the commencement of construction of the Project, 3 hard copies
and 1 electronic copy of detailed proposal on enhancement of air quality
monitoring in Cheung Chau shall be submitted to the Director for approval. The proposal shall include setting up of
air quality monitoring station(s) and devising air quality monitoring
programme(s) to keep track of the air quality baseline and impacts of the
Project and their respective frequencies.
The monitoring shall cover various air quality parameters including, but
not be limited to, dioxins, Air Quality Objectives parameters and heavy
metals. The monitoring station(s)
shall be in operation at least 1 month before the commencement of construction
of the Project. The air quality
monitoring results shall be made available to the public through a dedicated
web site as required in Condition 3.6 below.
在工程項目的建造工程展開前,須至少提早3個月就在長洲加強進行空氣質素監測向署長提交詳細建議的3份複本及1份電子版本,以供審批。建議須包括設立空氣質素監測站、採用空氣質素監測計劃以記錄空氣質素的基線數據和工程項目的影響,以及各項監測的密度。有關監測須涵蓋各項空氣質素參數,包括但不限於二噁英、空氣質素指標參數和重金屬。監測站須至少提早1個月在工程項目建造工程展開前投入運作。空氣質素監測結果須按下文條件第3.6項所規定,上載至指定網站供公眾閱覽。
Before submission to the Director, the detailed
proposal shall be certified by the ET Leader and verified by the IEC as
conforming to the recommendations contained in the approved EIA report
(Register No.: AEIAR-163/2012).
詳細建議在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告(登記冊編號:AEIAR-163/2012)內載的有關建議。
All measures recommended in the approved proposal
shall be fully and properly implemented for the Project.
核准建議的所有措施均須在工程項目徹底及妥善執行。
Submission of Detailed Design of
提交海岸公園的詳細設計
2.8 At least 1 month before the commencement of construction of the Project, 3 hard copies and 1 electronic copy of detailed design of the marine park shall be submitted to the Director for approval. The detailed design shall include at least the following information/specifications:
在工程項目的建造工程展開前,須至少提早1個月向署長提交海岸公園詳細設計的3份複本及1份電子版本,以供審批。詳細設計須至少包括以下資料/規格:
(i)
a marine park with an area of
at least 700 hectares in the waters between
在索罟群島及石鼓洲之間的水域劃定一個面積至少達
(ii) details of the marine park including proposed location and size, deployment of artificial reefs, release of fish fry, management plan and construction programme;
海岸公園的詳細資料,包括建議的位置及面積、敷設人工魚礁和投放魚苗的詳情、管理計劃及施工計劃;
(iii)
The
designation of the marine park shall immediately follow the completion of
construction works of the Project.
當工程項目的建造工程竣工後,須即時劃出建議地點為海岸公園。
In preparing the detailed design of the marine park, the
relevant stakeholders, including the fishery sector, and the Director of
Agriculture, Fisheries and Conservation shall be consulted.
在擬備海岸公園的詳細設計時,須徵詢相關人士包括漁業界及漁農自然護理署署長的意見。
Before
submission to the Director, the detailed design of marine park shall be certified by
the ET Leader and verified by the IEC as conforming to the recommendations
contained in the approved EIA report (Register No.: AEIAR-163/2012).
海岸公園的詳細設計在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告(登記冊編號:AEIAR-163/2012)內載的有關建議。
All measures recommended
in the approved detailed design of the marine park shall
be fully and properly implemented for the Project.
核准的海岸公園詳細設計建議的所有措施均須在工程項目徹底及妥善執行。
Submission of Detailed Monitoring Programme on Finless
Porpoise
提交江豚詳細監察計劃
2.9
At least 1
month before the commencement of construction of the Project, 3 hard copies and
1 electronic copy of a detailed monitoring programme on Finless Porpoise during
construction and operation phases shall be submitted to the Director for
approval. The detailed monitoring
plan shall include monitoring frequency and mitigation measures to be taken to
avoid disturbance to Finless Porpoise.
在工程項目的建造工程展開前,須至少提早1個月向署長提交在工程建造及營辦期間的江豚詳細監察計劃的3份複本及1份電子版本,以供審批。詳細的監察計劃須包括監察密度,以及避免對江豚造成滋擾採取的緩解措施。
In preparing the detailed monitoring programme, the
Director of Agriculture, Fisheries and Conservation shall be consulted.
在擬備詳細監察計劃時,須徵詢漁農自然護理署署長的意見。
Before
submission to the Director, the detailed monitoring programme shall be
certified by the ET Leader and verified by the IEC as conforming to the
recommendations contained in the approved EIA report (Register No.:
AEIAR-163/2012).
詳細監察計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告(登記冊編號:AEIAR-163/2012)內載的有關建議。
All measures recommended in the
approved detailed monitoring programme shall be fully and properly implemented
for the Project.
核准的詳細監察計劃建議的所有措施均須在工程項目徹底及妥善執行。
Submission of Fisheries Enhancement Programme
提交漁業強化計劃
2.10
At least 1
month before the commencement of construction of the Project, 3 hard copies and
1 electronic copy of a fisheries enhancement programme shall be submitted to
the Director for approval. The
fisheries enhancement programme shall include mitigation measures to be taken
to enhance fisheries resources in the vicinity of the Project area.
在工程項目的建造工程展開前,須至少提早1個月向署長提交漁業強化計劃的3份複本及1份電子版本,以供審批。漁業強化計劃須包括增加工程項目鄰近範圍的漁業資源所採取的緩解措施。
In preparing the enhancement programme, the Director of
Agriculture, Fisheries and Conservation shall be consulted.
在擬備強化計劃時,須徵詢漁農自然護理署署長的意見。
Before
submission to the Director, the enhancement programme shall be certified by the
ET Leader and verified by the IEC as conforming to the recommendations
contained in the approved EIA report (Register No.: AEIAR-163/2012).
強化計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告(登記冊編號:AEIAR-163/2012)內載的有關建議。
All measures
recommended in the approved enhancement programme shall be fully and properly
implemented for the Project.
核准的強化計劃建議的所有措施均須在工程項目徹底及妥善執行。
Submission of
Landscape and Visual Plan
提交景觀及視覺美化計劃
2.11 At least 1 month before the commencement of construction of the Project, 3 hard copies and 1 electronic copy of landscape and visual plan shall be submitted to the Director for approval. The landscape and visual plan, with drawings in the scale of 1:1000 or other appropriate scales showing the landscape and visual mitigation measures of the Project, shall include at least the following information:
在工程項目的建造工程展開前,須至少提早1個月向署長提交景觀及視覺美化計劃的3份複本及1份電子版本,以供審批。景觀及視覺美化計劃須用1:1 000或其他合適比例繪製圖則,顯示工程項目的景觀及視覺緩解措施,還須至少包括以下資料:
(i) aesthetic architectural designs for building structures, chimney and breakwater;
建築物、煙囪及防波堤具美感的建築設計;
(ii) locations, size, number and plant species of trees to be transplanted and their final transplanting locations;
計劃移植樹木的位置、大小、數量和品種,以及樹木的最終移植地點;
(iii) locations, size, number and plant species to be felled;
計劃砍伐的植物位置、大小、數量和品種;
(iv) locations, size, number and plant species to be provided or compensated; and
計劃栽種或補償的植物位置、大小、數量和品種;以及
(v) implementation programme, maintenance and management schedules.
實施計劃、保養和管理時間表。
In preparing the landscape and visual plan, the Director of
Planning shall be consulted.
在擬備景觀及視覺美化計劃時,須徵詢規劃署署長的意見。
Before
submission to the Director, the landscape and visual plan shall be certified by
the ET Leader and verified by the IEC as conforming to the recommendations
contained in the approved EIA report (Register No.: AEIAR-163/2012).
景觀及視覺美化計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告(登記冊編號:AEIAR-163/2012)內載的有關建議。
All measures recommended
in the approved landscape and visual plan shall be fully and properly
implemented and maintained for the Project.
核准的景觀及視覺美化計劃建議的所有措施均須在工程項目徹底執行及妥善維持。
Submission of
Coral Translocation Plan
提交珊瑚移植計劃
2.12 At least 1 month before the commencement of construction at works areas with potentially affected coral colonies, 3 hard copies and 1 electronic copy of coral translocation plan shall be deposited with the Director. The coral translocation plan shall include at least the following information/specifications:
在珊瑚群落可能受影響的工地範圍展開建造工程前,須至少提早1個月向署長存放珊瑚移植計劃的3份複本及1份電子版本。珊瑚移植計劃須至少包括以下資料/規格:
(i) a detailed baseline survey to be carried out before the commencement of the construction to further confirm the exact number and locations of coral colonies within the potentially affected areas; and
在建造工程展開前,於可能受影響的範圍進行詳細的基線調查,以進一步確定珊瑚群落的確實數量和位置;
(ii) translocation details including information of coral colonies to be translocated, recipient area, translocation methodology and monitoring of transplanted corals.
移植詳情,包括準備移植的珊瑚群落資料、接收地點、移植方法及珊瑚移植後的監察。
In preparing the coral translocation plan, the Director of Agriculture, Fisheries and Conservation shall be consulted.
在擬備珊瑚移植計劃時,須徵詢漁農自然護理署署長的意見。
Before submission to the
Director, the coral translocation plan shall be certified by the ET Leader and
verified by the IEC as conforming to the recommendations contained in the
approved EIA report (Register No.: AEIAR-163/2012).
珊瑚移植計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告(登記冊編號:AEIAR-163/2012)內載的有關建議。
All measures recommended
in the deposited coral translocation plan shall be fully and properly
implemented for the Project.
已存放的珊瑚移植計劃建議的所有措施均須在工程項目徹底及妥善執行。
Submission of Marine Mammal Watching Plan
提交海洋哺乳動物觀察計劃
2.13 At least 1 month before the commencement of marine works of the Project, 3 hard copies and 1 electronic copy of Marine Mammal Watching Plan shall be deposited with the Director. The Plan shall include regular inspection of silt curtains, visual inspection of the waters surrounded by silt curtains, and an action plan shall be devised to cope with any unpredicted incidents such a the case that any marine mammal including, but not limited to, Finless Porpoise is found within the waters surrounded by silt curtains.
在工程項目的海事工程展開前,須至少提早1個月向署長存放海洋哺乳動物觀察計劃的3份複本及1份電子版本。計劃須包括定期檢查隔泥幕、目視檢查隔泥幕包圍的水域,以及制訂行動計劃以應付任何突發事件,例如在隔泥幕包圍的水域內發現海洋哺乳動物(包括但不限於江豚)等情況。
In preparing the Marine Mammal Watching Plan, the Director of Agriculture, Fisheries and Conservation shall be consulted.
在擬備海洋哺乳動物觀察計劃時,須徵詢漁農自然護理署署長的意見。
Before submission to the
Director, the Marine Mammal Watching Plan shall be certified by the ET Leader
and verified by the IEC as conforming to the recommendations contained in the
approved EIA report (Register No.: AEIAR-163/2012).
海洋哺乳動物觀察計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告(登記冊編號:AEIAR-163/2012)內載的有關建議。
All measures recommended
in the deposited Marine Mammal Watching Plan shall be fully and properly
implemented for the Project.
已存放的海洋哺乳動物觀察計劃建議的所有措施均須在工程項目徹底及妥善執行。
Submission of
Vessel Travel Details
提交船隻航行資料
2.14
To minimize the chance of
vessel collision and disturbance to the Finless Porpoise and White-bellied Sea
Eagle arising from frequent vessel traffic, at least 1 month before the
commencement of construction of the Project, 3 hard copies and 1 electronic
copy of regular marine travel routes of vessels moving to and from the Project
site during construction and operation stages shall be deposited with the
Director. Any subsequent changes to
the regular routes shall be certified by the ET Leader and verified by the IEC
as conforming to the requirements in the approved EIA report
(Register No.: AEIAR-163/2012) and deposited with the Director at least 2 weeks
before changing the routes.
為盡量減低船隻碰撞的機會及船隻頻繁的交通對江豚及白腹海鵰造成的滋擾,在工程項目的建造工程展開前,須至少提早1個月向署長存放船隻慣常航行路線的3份複本及1份電子版本,顯示在施工及營辦期期間往返工程項目工地船隻的慣常航行路線。慣常航行路線其後如有任何更改,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告(登記冊編號:AEIAR-163/2012)的規定,並須在更改路線前,至少提早2個星期向署長存放有關文件。
Submission of Detailed
Plan on Wastewater Treatment Plant
提交廢水處理裝置的詳細計劃
2.15
At least 1 month
before the commencement of construction of the Project, 3 hard copies and 1
electronic copy of a detailed plan on the wastewater treatment plant shall be
submitted to the Director for approval.
The detailed plan shall be based on realistic assessment of various
sources of sewage, including those generated from the sanitary facilities of
the proposed Education Centre and potential surface runoff. The plan shall also include schematic
drawing(s) showing the treatment process and deodourisation system.
在工程項目的建造工程展開前,須至少提早1個月向署長提交廢水處理裝置詳細計劃的3份複本及1份電子版本,以供審批。詳細計劃須根據各種污水來源的實際評估作參考,包括擬建教育中心衞生設施所產生的污水,以及可能出現的地面徑流。計劃亦須包括示意圖,顯示廢水處理裝置的處理程序和消臭系統。
Before submission to the
Director, the detailed plan shall be certified by the ET Leader and verified by
the IEC as conforming to the recommendations contained in the approved EIA
report (Register No.: AEIAR-163/2012).
詳細計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告(登記冊編號:AEIAR-163/2012)內載的有關建議。
All measures recommended
in the detailed plan shall be fully and properly implemented for the Project.
詳細計劃建議的所有措施均須在工程項目徹底及妥善執行。
Submission of
Waste Management Plan
提交廢物管理計劃
2.16
At least 1 month before the
commencement of construction of the Project, 3 hard copies and 1 electronic
copy of a waste management plan (WMP) for the construction stage of the Project
shall be deposited with the Director. The WMP shall describe the arrangements for
avoidance, reuse, recovery and recycling, storage, collection, treatment and
disposal of different categories of waste to be generated from the construction
activities and shall include the recommended mitigation measures on waste
management in the EIA Report. The WMP shall indicate the disposal
location(s) of all surplus excavated spoil and other wastes. A trip
ticket system shall be included in the WMP. Surplus excavated spoil and
other wastes shall only be disposed of at designated disposal locations unless
otherwise approved by the Director.
在工程項目的建造工程展開前,須至少提早1個月向署長存放工程項目施工階段的廢物管理計劃的3份複本及1份電子版本。廢物管理計劃須說明建造活動所產生的各類廢物的避免產生、再使用、回收、循環再造、貯存、收集、處理和棄置安排,並須包括環評報告所建議的廢物管理緩解措施。廢物管理計劃須顯示所有過剩的掘出廢土及其他廢物的棄置地點。廢物管理計劃須包括一套運載記錄制度。過剩的掘出廢土及其他廢物只可棄置在指定的棄置地點,除非另獲署長批准。
Before submission to the
Director, the WMP shall be certified by the ET Leader and verified by the IEC
as conforming to the recommendations contained in the approved EIA report
(Register No.: AEIAR-163/2012).
廢物管理計劃在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明其符合核准環評報告(登記冊編號:AEIAR-163/2012)內載的有關建議。
All measures recommended
in the deposited WMP shall be fully and properly implemented for the Project.
已存放的廢物管理計劃建議的所有措施均須在工程項目徹底及妥善執行。
Measures to be Implemented during Construction of the Project
工程項目施工期間須採取的措施
Measures to
Mitigate Water Quality Impacts during Construction of the Project
工程項目施工期間的水質影響緩解措施
2.17 Dredging shall only be carried out at breakwaters and seawalls as shown in Figure 3.
挖泥工程只可在圖3所示的防波堤及海堤範圍進行。
2.18
Dredging shall only be carried
out by closed grab dredger(s), each with grab size of not more than
挖泥工程只可採用密封式抓斗挖泥機進行,每部挖泥機的抓斗容量不得超過
2.19 Each grab shall be enclosed by a frame-type silt curtain as shown in Figure 4 of this Permit.
每個抓斗須如本許可證圖4所示,用框架式隔泥幕圍封。
2.20
No dredging shall be carried
out within
在不可移植的珊瑚群落附近
2.21 All barges for transporting dredged/waste materials shall be fitted with tight bottom seals to prevent leakage of materials during loading and transportation.
所有運載挖出物料/廢料的躉船均須在船底加上緊密的封邊,以避免在裝卸和運載期間洩漏物料。
2.22 To minimize loss of sediment affecting the water quality due to filling works:
為盡量減低填土工程造成沉積物流失而影響水質:
(i) the filling works for seawall construction shall be carried out behind silt curtain(s); and
建造海堤的填土工程須於隔泥幕後進行;以及
(ii) any seawall gap that needs to be provided for marine access shall be sealed by silt curtain(s) as detailed in the finalized silt curtain deployment plan deposited under Condition 2.6 of this Permit.
任何需提供作海上通道的海堤間隙,須圍上隔泥幕,詳情載於按本許可證條件第2.6項存放的隔泥幕設置計劃的最終定稿。
2.23
The filling
materials shall only consist of public fill, rock and sand. To reduce the elevation in suspended
solids, the filling works shall be carried out in accordance with the filling
composition and filling rates shown in Table 1 and Figure 5 of this Permit.
填土物料只可由公眾填料、石和沙組成。為減少懸浮固體上升,填土工程須按本許可證表1及圖5所示的填土成分和填土速度進行。
2.24
The dredging/reclamation works
shall not be carried out simultaneously with the laying of submarine cables
within the same location. For works
close to each other, the construction programme shall be arranged in such a way
that the dredging/reclamation works within areas bounded by the breakwaters and
the laying of submarine cables shall not be carried out within a distance of
不得在同一地點同時進行挖泥/填海工程和海底電纜敷設工程。如工程地點互相靠近,施工計劃須作適當安排,以令在防波堤圍封範圍內進行的挖泥/填海工程,與海底電纜敷設工程之間,相距不少於80 米的距離,從而避免對環境造成累積影響。
Measures to Minimize Disturbance to Marine Mammals
減低對海洋哺乳動物造成滋擾的措施
2.25
A marine mammal exclusion zone
of
在安裝、重置或遷移浮動式隔泥幕工程期間,須在四周
2.26 Once the floating silt curtain(s) as mentioned in Condition 2.6 above are installed/re-installed/relocated, the Marine Mammal Watching Plan as required to be deposited under Condition 2.13 of this Permit shall be implemented as part of the EM&A programme.
當上文條件第2.6項所述的浮動式隔泥幕完成安裝/重置/遷移後,須實施本許可證條件第2.13項規定存放的海洋哺乳動物觀察計劃,作為環監計劃的一部分。
2.27 To minimize the acoustic disturbance to marine mammals:
為減低對海洋哺乳動物造成的聲音滋擾:
(i) construction works that may produce underwater acoustic disturbance shall be restricted within June to November to avoid peak season of Finless Porpoise occurrence;
可能產生水底聲音滋擾的建造工程,須禁止在6月至11月期間進行,以避開江豚出沒的高峰期;
(ii) silence piling equipment such as vibratory or hydraulic impact hammers shall be used for the installation of sheet piling into the seabed; and
在海床安裝板樁時須採用低噪音打樁設備,例如震動式打樁機或油壓錘; 以及
(iii) no underwater percussive piling shall be used for the Project.
工程項目不得在水底進行撞擊式打樁。
2.28 All vessels within the works areas shall not travel at a speed higher than 10 knots.
工地範圍內所有船隻的航行速度不得超過10海里。
Implementation of Surface Water Drainage System
設置地面排水系統
2.29 A surface water drainage system shall be provided to manage runoff during the construction and operation stages. The system shall consist of the following features:
在建造及營辦階段期間,須安裝地面排水系統以管理調控徑流。系統須包括以下特點:
(i) Channels shall be constructed around the perimeter of the site area to direct surface water to silt removal facilities such as sand/silt traps and sediment basins to remove sand/silt particles from runoff before discharge; and
在地盤周邊建造排水道,引導地面徑流至淤泥清除設施,例如隔沙/隔泥池和沉澱池,以清除徑流的沙泥後才排放;以及
(ii) Oil interceptors shall be provided in the drainage
system of any potentially contaminated areas (such as truck parking area and
maintenance workshop) and regularly cleaned to prevent the release of oil
products into the storm water drainage system in case of accidental spillages.
任何可能受到污染的地方(如貨車停車場和維修工場),其排水系統須設置截油器,並定期進行清理,以便一旦發生油類產品意外溢漏時,防止油污流入雨水渠系統。
Measures to be
Implemented during Operation of the Project
工程項目營辦期間須實施的措施
Restriction on Treatment Capacity during Operation of the Project
工程項目營辦期間處理量的限制
2.30
The Project
shall treat:
工程項目須處理:
(i) a maximum
of 3,000 tonnes of municipal solid waste daily by the incinerator; and
焚化爐每日處理的都市固體廢物量最多為3,000公噸;以及
(ii) a maximum of 200
tonnes of municipal solid waste daily by the mechanical sorting and recycling plant.
機械式分類及回收廠每日處理的都市固體廢物量最多為200公噸。
Restriction on Reception of Wastes
接收廢物的限制
2.31
Reception
of wastes on site shall only be limited from 8:00am to 8:00pm daily.
設施接收廢物的時間只限於每日上午8時至晚上8時。
Measures to Mitigate Air Quality Impact during Operation of the Project
工程項目營辦期間的空氣質素影響緩解措施
2.32
To minimize air quality impacts
during operation of the Project:
為減低工程項目營辦期間對空氣質素的影響:
(i) an advanced air pollution control system, including selective catalytic reduction for removal of nitrogen oxides, activated carbon for removal of dioxins and a continuous emission monitoring system, shall be installed; and
須安裝先進的空氣污染控制系統,包括清除氮氧化物的選擇性催化還原器、清除二噁英的活性碳,以及排放物持續監察系統;以及
(ii)
the chimney height shall be
煙囪的地面高度須為
Measures to Mitigate Odour Emissions
氣味排放緩解措施
2.33 The wastewater treatment plant, waste reception halls, waste storage areas and mechanical sorting and recycling plant shall be maintained at a negative pressure.
污水處理廠、廢物接收大堂、廢物存放區和機械式分類及回收廠均須維持在負氣壓下運作。
2.34 The wastewater treatment plant, waste reception halls and waste storage areas shall be fully enclosed and odorous air shall be incinerated.
污水處理廠、廢物接收大堂和廢物存放區須採用全封閉的設計,而有味空氣須予以焚化。
2.35 A deodorizing unit
with odour removal efficiency of at least 95%, or otherwise agreed by the
Director, shall be installed for the mechanical
sorting and recycling plant before commencement of operation of the Project.
在工程項目展開營辦前,機械式分類及回收廠須安裝除臭效率達95%(或署長同意的除臭效率)的除臭系統。
2.36 All wastes shall be stored in
enclosed containers during transportation to and from the Project boundary.
所有進入及離開工程項目範圍的廢物在運送期間須存放於密封的貨櫃。
Measures to Mitigate Water Quality Impacts
during Operation of the Project
工程項目營辦期間的水質影響緩解措施
2.37 No wastewater effluent, except the
saline water from desalination plant, arising from the Project shall be
discharged to the coastal waters of southern water control zone.
除海水化淡廠的鹽水外,工程項目產生的污水,不得排入南區水質管制區的近岸海域。
2.38 The treated effluent from the
wastewater treatment plant shall be reused.
經污水處理廠處理過的水,須予重新使用。
2.39 Maintenance dredging shall only be
carried out within the area shown in Figure
6 of this Permit to avoid dredging too close to coral communities.
維修挖泥只可在本許可證圖6所示範圍內進行,以避免挖泥工程太接近珊瑚群落。
2.40 Maintenance dredging shall only be
carried out by closed grab dredger(s), each with grab size of not more than
維修挖泥只可採用密封式抓斗挖泥機進行,每部挖泥機的抓斗容量不得超過
2.41
Each grab
to be used for maintenance dredging shall be enclosed by as frame-type curtain
as shown in Figure 4 of this Permit.
每個用作維修挖泥的抓斗須如本許可證圖4所示,用框架式隔泥幕圍封。
2.42
No
maintenance dredging shall be carried out within
在不可移植的珊瑚群落附近
2.43
All barges
for transporting dredged materials from maintenance dredging shall be fitted
with tight bottom seals to prevent leakage of materials during loading and
transportation.
所有運載維修挖泥挖出物料的躉船,均須在船底加上緊密的封邊,以避免在裝卸和運載期間洩漏物料。
2.44 Floating refuse shall be collected and removed at regular intervals on a daily basis to keep the water within the Project site boundary and the neighbouring waters free from floating refuse.
須每日定時收集及清除漂浮垃圾,以確保工程項目工地範圍內的水域及鄰近水域沒有漂浮垃圾。
Measures to Mitigate Noise Impacts
噪音影響緩解措施
2.45 The stack of the incinerator and the ventilation system shall be equipped with silencer or other acoustic treatment equipment.
焚化爐的煙囪和通風系統均須裝設滅聲器或其他隔音設備。
2.46 The exhaust of the ventilation system and any opening of the building shall be located away from noise sensitive receivers.
通風系統的排氣口及樓宇的開口須設於遠離噪音敏感受體。
Handling of Incineration By-product
處理焚化過程的副產品
2.47 The fly ash and air pollution control residues generated from incineration shall be treated by cement solidification or chemical stabilization prior to disposal to designated landfill sites.
焚化過程產生的飛灰和空氣污染控制殘渣,在運往指定的堆填區棄置前,須進行水泥固化或化學穩定化等處理程序。
2.48
The treated
fly ash and air pollution control residues shall be tested to conform to the
Incineration Residue Pollution Control Limits and leachability criteria shown
in Table 2 of this Permit before disposal to designated landfill sites.
經處理的飛灰和空氣污染控制殘渣須進行測試,確認符合本許可證表 2所示的焚化殘渣污染控制上限和滲濾污水標準後,方可運往指定的堆填區棄置。
2.49 The incineration by-product including fly ash, air pollution control residues and bottom ash arising from the Project shall be:
工程項目焚化過程產生的副產品,包括飛灰、空氣污染控制殘渣及爐底灰,均須:
(i) handled in closed systems fully segregated from the ambient environment; and
於封閉系統內處理,與外圍環境完全隔離;以及
(ii) transported in covered trucks or containers to the designated landfill sites.
使用有蓋貨車或貨櫃運往指定的堆填區。
3
Environmental
Monitoring and Audit Requirements
環境監察及審核規定
3.1 The EM&A programme shall be
implemented in accordance with the procedures and requirements as set out in
the approved EM&A Manual or as approved by the Director. Any changes to the
programme shall be justified by the ET Leader and verified by the IEC as
conforming to the information and requirements contained in the EM&A Manual
before submission to the Director for approval.
環監計劃須按照核准的環監手冊或署長同意的程序及規定執行。計劃如有更改,須由環境小組組長提出充分理由,並由獨立環境查核人核實,證明其符合環監手冊內載的資料及規定,然後才提交署長批准。
3.2 Samples,
measurements and necessary remedial actions shall be taken in accordance with
the requirements of the EM&A Manual by:
(i)
conducting
baseline environmental monitoring;
(ii)
conducting
impact monitoring;
(iii)
carrying
out remedial actions described in the Event/Action Plans of the EM&A Manual
in accordance with the time frame set out in the Event/Action Plans, or as
agreed by the Director, in case where specified criteria in the EM&A Manual
are exceeded; and
(iv)
logging
and keeping records of the details of (i) to (iii) above for all parameters
within 3 working days of the collection of data or completion of remedial
action(s), for the purpose of preparing and submitting the monthly EM&A Reports and to make available
the information for inspection on site.
取樣、測量及採取必要的補救行動時,均須按照環監手冊的規定進行:
(i) 進行環境基線監測;
(ii) 進行影響監測;
(iii) 如超逾環監手冊內指定的標準,則按照環監手冊內的事件 / 行動計劃所訂明的時限或署長所同意的時限,執行事件 / 行動計劃所說明的補救行動;以及
(iv) 在收集數據或完成補救行動3個工作天內,須記錄及備存上文(i)至(iii)項各參數的詳情,用作擬備並提交每月環監報告,並備妥有關資料以供在工地查閱。
3.3 3 hard copies
and 1 electronic copy of Baseline Monitoring Report shall be submitted to the
Director at least 2 weeks before the commencement of construction of the
Project. The submissions shall be certified by the ET Leader and verified
by the IEC as having complied with the requirements as set out in the EM&A
Manual before submission to the Director. Additional copies of the
Baseline Monitoring Report shall be provided upon request by the Director.
在工程項目建造工程展開前,須至少提早2個星期向署長提交基線監測報告的3份硬複本及1份電子版本。文件在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明符合環監手冊所載的規定。如署長要求,則須提交基線監測報告的額外複本。
3.4 3 hard
copies and 1 electronic copy of Monthly EM&A Reports for the construction
stage of the Project shall be submitted to the Director, within 2 weeks after
the end of the reporting month. The monthly EM&A Reports shall
include a summary of all non-compliance (exceedances) of the environmental
quality performance limits (Action and Limit Levels). The submissions
shall be certified by the ET Leader and verified by the IEC as having complied
with the requirements as set out in the EM&A Manual
before submission to the Director. Additional copies of the
Monthly EM&A Reports shall be provided upon request by the Director.
在規定提交報告的月份結束後2個星期內,須向署長提交工程項目建造階段的每月環監報告的3份硬複本及1份電子版本。每月環監報告須包括各種不符合(超出)環境質素表現規限(行動及極限水平)情況的摘要。文件在提交署長前,須由環境小組組長核證及獨立環境查核人核實,證明符合環監手冊所載的規定。如署長要求,則須提交每月環監報告的額外複本。
3.5 All environmental monitoring and audit
data submitted under this Permit shall be true, valid and correct.
根據本許可證提交的所有環監數據,均須有效及真實無誤。
3.6 To ensure a high degree of transparency
regarding the monitoring data and results in view of the public concern about
the Project, all environmental monitoring and audit data and results and all
submissions and all performance test data and results required by this Permit
shall be made available by the Permit Holder to the public through a dedicated
web site to be set up by the Permit Holder under Condition 4.2 below, in the
shortest practicable time and in no event later than 2 weeks after such
information is available.
基於公眾對工程項目的關注,為確保監察數據和結果具高透明度,許可證持有人須盡快把各項環境監察及審核數據和結果、本許可證規定的所有提交文件及各項表現測試數據和結果,透過按下文條件第4.2項由許可證持有人設立的特定網站供公眾閱覽,在任何情況下均不得遲於這些資料可供閱覽後的2個星期。
4
Electronic
Reporting of EM&A Information
環監資料的電子匯報
4.1 To facilitate public
inspection of the Baseline Monitoring Report and Monthly EM&A Reports via
the EIAO Internet Website and at the EIAO Register Office, electronic copies of
these Reports shall be prepared in Hyper Text Markup Language (HTML) (version
4.0 or later) and in Portable Document Format (PDF version 1.3 or later),
unless otherwise agreed by the Director and shall be submitted at the same time
as the hard copies as described in Conditions 3.3 and 3.4 above of this
Permit. For the HTML version, a content page capable of providing
hyperlink to each section and sub-section of these Reports shall be included in
the beginning of the document. Hyperlinks to all figures, drawings and tables
in these Reports shall be provided in the main text from where the respective references
are made. All graphics in these Reports shall be in interlaced GIF format
unless otherwise agreed by the Director. The content of the electronic
copies of these Reports must be the same as the hard copies.
為方便公眾透過環評條例互聯網網站及在環評條例登記冊辦事處查閱基線監測報告及每月環監報告,以超文本標示語言(HTML)(第4.0或較後版本)及便攜式文件格式(PDF)(第1.3或較後版本)製作的報告的電子版本,除非另獲署長同意,須與本許可證條件第3.3及3.4項所說明的硬複本同時提交。關於HTML的版本方面,可與報告各節及小節作出超文本連結的目錄須在文件開端加入。報告內各類圖表須在載有相關資料的正文內作出超文本連結。除非另獲署長同意,報告內所有圖形均須以交錯存取的GIF格式制定。報告的電子版本內容,必須與硬複本的內容一致。
4.2 The
Permit Holder shall, within 6 weeks after the commencement of construction of
the Project, set up a dedicated Internet web site and notify the Director in
writing the Internet address where the environmental monitoring data and
project information is to be placed. All environmental monitoring data
described in Condition 4.1 above shall be made available to the public via the
abovementioned dedicated Internet web site in the shortest possible time and in
any event no later than 2 weeks after the relevant environmental monitoring
data are collected or become available, unless otherwise agreed with the
Director.
許可證持有人須在工程項目的建造工程展開後6個星期內,設立特定網站存放環境監察數據及工程項目資料,並以書面通知署長互聯網網址所在。除非另獲署長同意,上文條件第4.1項說明的所有環境監察數據及報告,均須盡快透過由許可證持有人設立的特定網站供公眾閱覽,在任何情況下均不得遲於有關資料在收集或可供發放後的2個星期內上載至該特定網站。
4.3
The Internet web site as described in Condition 4.2 above
shall enable user-friendly public access to the environmental monitoring data
and project information including the Project Profile and this Environmental
Permit. The Internet web site shall have features capable of:
(i)
providing access to all environmental monitoring data of this Project
collected since the
commencement of construction;
(ii)
searching by date;
(iii) searching by types of
monitoring data (air and water quality); and
(iv)
hyperlinking to relevant monitoring data after searching;
or otherwise as agreed by the Director.
上文條件第4.2項說明的互聯網網站,必須方便用戶使用,讓公眾容易接達環境監察數據及工程項目資料,當中包括工程項目簡介及本環境許可證。除非另獲署長同意,互聯網網站須具備部件,提供下述功能:
(i) 接達建造工程展開後所收集的全部環境監察數據;
(ii) 按日期搜尋;
(iii) 按監察數據類別 (空氣質素及水質) 搜尋;以及
(iv) 在搜尋後與相關的監察數據作出超文本連結。
Notes:
註:
1. This
Permit consists of three parts, namely, Part A (Main
Permit), Part B (Description of Designated Project)
and Part C (Permit Conditions). Any person relying on this permit should
obtain independent legal advice on the legal implications under the EIAO, and
the following notes are for general information only.
本許可證共有3部,即A部
(許可證主要部分);B部
(指定工程項目的說明) 及C部
(許可證條件)。任何援引本許可證的人士須就環評條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。
2. If
there is a breach of any condition of this Permit, the Director or his
authorized officer may, with the consent of the Secretary for the Environment,
order the cessation of associated work until the remedial action is taken in
respect of the resultant environmental damage, and in that case the Permit
Holder shall not carry out any associated works without the permission of the
Director or his authorized officer.
如違反本許可證的任何條件,署長或獲授權人員徵得環境局局長的同意後勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。
3. The
Permit Holder may apply under Section 13 of the EIAO to the Director for a
variation of the conditions of this Permit. The Permit Holder shall replace the
original permit displayed on the Project site by the amended permit.
許可證持有人可根據環評條例第13條的規定向署長申請更改本環境許可證的條件。許可證持有人須將經修改的許可證替換在建造工地內展示的原有許可證。
4. A
person who assumes the responsibility for the whole or a part of the Project
may, before he assumes responsibility of the Project, apply under Section 12 of
the EIAO to the Director for a further environmental permit.
承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據環評條例第12條的規定向署長申請新的環境許可證。
5. Under
Section 14 of the EIAO, the Director may with the consent of the Secretary for
the Environment, suspend, vary or cancel this Permit. The suspended, varied or cancelled
Permit shall be removed from display at the Project site.
根據環評條例第14條的規定,署長可在環境局局長的同意下暫時吊銷、更改或取消環境許可證。遭暫時吊銷、更改或取消的環境許可證必須從工程項目工地除下,不再展示。
6. If
this Permit is cancelled or surrendered during construction or operation of the
Project, another environmental permit must be obtained under the EIAO before
the Project could be continued. It
is an offence under Section 26(1) of the EIAO to construct or operate a
designated project listed in Part 1 and 2 of Schedule 2 of the EIAO without a
valid environmental permit.
如果本許可證在工程項目建造或營辦期間取消或交回,則在繼續營辦工程項目之前,必須先根據環評條例規定取得另一份環境許可證。根據環評條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造或營辦環評條例附表2第1及2部所列明的指定工程項目,即屬犯罪。
7. Any
person who constructs or operates the Project contrary to the conditions in the
Permit, and is convicted of an offence under the EIAO, is liable:
(i)
on a first conviction on indictment to a fine of $2
million and to imprisonment
for 6 months;
(ii)
on a second or subsequent conviction on indictment to
a fine of $5 million and to imprisonment for 2 years;
(iii)
on a first summary conviction to a fine at level 6 and
to imprisonment for 6 months;
(iv)
on a second or subsequent summary conviction to a fine
of $1 million and to imprisonment for 1 year; and
(v)
in any case where the offence is of a continuing
nature, the court or magistrate may impose a fine of $10,000 for each day on
which he is satisfied the offence continued.
如任何人在違反本許可證的條件下建造或營辦工程項目,根據環評條例,即屬犯罪—
(i)
一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;
(ii)
一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;
(iii)
一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;
(iv)
一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;及
(v)
在任何情況下如該罪行屬持續性質,則法院或裁判官可就其信納該罪行持續的每天另處罰款10,000元。
8. The
Permit Holder may appeal against any condition of this Permit under Section 17
of the EIAO within 30 days of receipt of this Permit.
許可證持有人可在接獲本許可證後30天內,根據環評條例第17條就本許可證的任何條件提出上訴。
9. The
Notes are for general reference only and that the Permit Holder should refer to
the EIAO for details and seek independent legal advice.
上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。
Environmental
Permit No. EP-429/2012
環境許可證編號EP-429/2012
| Figure
1 | Figure 2 | Figure 3 | Figure 4 | Figure 5 | Figure 6 |
[ Back to First Page ] / [ Back to Main Index ]
Table
1 Composition of Filling Materials and Filling Rates at Different Locations
表1 不同地點的填土材料成份及填土速度
Area 區域 |
Area Code 區域 編號 |
Filling Rate (m3/day) 填土速度(立方米/每日) |
||
Public
Fill 公眾填料 |
Sand 沙 |
Rock 石 |
||
Filling of reclamation area between 距離最接近的珊瑚群落 |
A |
300 @ |
4,000 @ |
2,700@@ |
Filling of reclamation area more than 距離最接近的珊瑚群落超過 |
B |
1,000 @ |
3,300 @ |
2,700@@ |
Filling of completely confined reclamation area with closure of opening for marine access** 在完全圍封及已封閉的海上通道出口之填海區域進行的填土作業** |
- |
7,000 @ |
0 |
0 |
Notes:
註:
*: Composition of filling materials shall be restricted to public fill, sand and rock only.
填土材料的成份只限於公眾填料、沙和石。
@: Maximum filling rate below +2.5mPD
主水平基準
@@: Minimum filling rate below +2.5mPD
主水平基準
**: Composition of filling materials shall be restricted to public fill only.
填土材料的成份只限於公眾填料。
Table
2 Incineration Residue Pollution Control Limits
表2 焚化殘渣的污染控制上限
Pollutant
Parameter 污染物參數 |
Pollution Control Limit 污染控制上限 |
Each Skip Load Prior to Transportation to Disposal Site 按運往棄置地點前每程吊斗車載物量計 |
|
Residue Itself: 剩餘殘渣本身: |
|
Total organic carbons 總有機碳量 |
3% by wt 按重量計佔3% |
Dioxins/Furans 二噁英/呋喃 |
1 ppb (or 1 µg/kg) 1 ppb(或 1微克/千克) |
Leachate Derived from the Residue: 剩餘殘渣得出的滲濾污水: |
|
pH 酸鹼度 |
>8 |
Heavy Metals * 重金屬* |
|
Cd 鎘 |
10 ppm (or mg/kg) 10 ppm(或毫克/千克) |
Cr 鉻 |
50 ppm (or mg/kg) 50 ppm(或毫克/千克) |
Cu 銅 |
250 ppm (or mg/kg) 250 ppm(或毫克/千克) |
Ni 鎳 |
250 ppm (or mg/kg) 250 ppm(或毫克/千克) |
Pb 鉛 |
50 ppm (or mg/kg) 50 ppm(或毫克/千克) |
Zn 鋅 |
250 ppm (or mg/kg) 250 ppm(或毫克/千克) |
Hg 汞 |
1 ppm (or mg/kg) 1 ppm(或毫克/千克) |
Sn 錫 |
250 ppm (or mg/kg) 250 ppm(或毫克/千克) |
Ag 銀 |
50 ppm (or mg/kg) 50 ppm(或毫克/千克) |
Sb 銻 |
150 ppm (or mg/kg) 150 ppm(或毫克/千克) |
As 砷 |
50 ppm (or mg/kg) 50 ppm(或毫克/千克) |
Be 鈹 |
10 ppm (or mg/kg) 10 ppm(或毫克/千克) |
Tl 鉈 |
50 ppm (or mg/kg) 50 ppm(或毫克/千克) |
V 釩 |
250 ppm (or mg/kg) 250 ppm(或毫克/千克) |
Se 硒 |
1 ppm (or mg/kg) 1 ppm(或毫克/千克) |
Ba 鋇 |
1,000 ppm (or mg/kg) 1,000 ppm(或毫克/千克) |
Notes:
註:
*: Toxicity Characteristic Leaching Procedure (TCLP) limits for landfill disposal
堆填區棄置廢物的毒性滲濾測試限值
ID:
IWMFep(5)