Environmental
Permit No. EP-452/2013
環境許可證編號 EP-452/2013
ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER
499)
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL
PERMIT TO CONSTRUCT AND OPERATE
A
DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant
to Section 10 of the Environmental Impact Assessment Ordinance (EIAO), the
Director of Environmental Protection (the Director) grants this environmental
permit to Hong Kong Housing Authority (hereinafter referred to as the
"Permit Holder") to construct and operate the designated project described
in Part B subject to the conditions specified in Part C. The issue of this
environmental permit is based on the documents, approvals or permissions
described below:
根據《環境影響評估條例》(環評條例)第10條的規定,環境保護署署長(署長)將本環境許可證批予香港房屋委員會(下稱 “ 許可證持有人”),以建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發:
Application No. 申請書編號 |
AEP-452/2013 |
|||
Document in the Register : 登記冊上的文件: |
1.
Project
Profile – Temporary Sewage Pumping Station Ancillary to Tung Chung Area 56
Public Housing Development (Register No.: PP-481/2013) 工程項目簡介–東涌56區公共房屋發展計劃附屬臨時污水泵房 (登記冊編號:PP- 481/2013) 2.
The
Director’s letter of Permission to Apply Directly for Environmental Permit
dated 18 March 2013 (Ref.: (15) in EP2/N9/F/148) 署長於 3.
Application
for Environmental Permit submitted by the Permit Holder on 16 May 2013 (Application
No.: AEP-452/2013) 許可證持有人於 |
|||
|
6 June 2013 |
|
||
|
Date 日期 |
|
(Mr. Louis P.L. CHAN) Ag. Principal Environmental Protection Officer (Regional Assessment) for Director of Environmental Protection 環境保護署署長 (署理首席環境保護主任(區域評估) 陳檳林 代行) |
|
PART
B (DESCRIPTION OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the
description of the designated project mentioned in Part A of
this environmental permit (hereinafter referred to as “the Permit”):
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明:
Title of Designated Project 指定工程項目的名稱 |
Temporary
Sewage Pumping Station Ancillary to Tung Chung Area 56 Public Housing
Development. (This
designated project is hereinafter referred to as “the Project”) 東涌56區公共房屋發展計劃附屬臨時污水泵房 (本指定工程項目下稱“工程項目”) |
Nature of Designated Project 指定工程項目的性質 |
A sewage
pumping station with an installed capacity of more than 污水泵水站,其裝置的泵水能力超過每天 |
Location of Designated Project 指定工程項目的地點 |
At the
western side of Tung Chung Area 56.
The location of the Project is shown in Figure 1 attached to this Permit. 位於大嶼山東涌56區西側。工程項目的位置展示於本許可證圖1內。 |
Scale
and Scope of Designated Project |
The Project is to
construct and operate a temporary sewage pumping station with an installed
capacity (average dry weather flow) of about 工程項目為建造及營辦一座安裝流量(平均旱季流量)約為 |
PART C (PERMIT
CONDITIONS)
C部 (許可證條件)
1. General
Conditions
一般條件
1.1
The Permit Holder and any person working on the
Project shall comply with all conditions set out in this Permit. Any
non-compliance by any person may constitute a contravention of the
Environmental Impact Assessment Ordinance (Cap.499) and may become the subject
of appropriate action being taken under the Ordinance.
許可證持有人及任何從事工程項目的人士必須完全符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反《環境影響評估條例》(第499章)的規定,而當局可根據條例採取適當行動。
1.2
The Permit Holder shall ensure full compliance with
all legislation from time to time in force including, without limitation to,
the Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap.
311), Water Pollution Control Ordinance (Cap. 358) and Waste Disposal Ordinance
(Cap. 354). This Permit does not of itself constitute any ground of defense
against any proceedings instituted under any legislation or imply any approval
under any legislation.
許可證持有人須經常確保完全符合現行法例的規定,包括但不限於《噪音管制條例》(第400章)、《空氣污染管制條例 》(第311章)、《水污染管制條例》(第358章)、《廢物處置條例》(第354章)。本許可證本身不會就根據任何法例提起的法律程序構成任何抗辯理由,或根據任何法例默示任何批准。
1.3
The Permit Holder shall make copies of this Permit
together with all documents referred to in this Permit and the documents
referred to in Part A of the Permit readily
available at all times for inspection by the Director or his authorized
officers at all sites/offices covered by this Permit. Any reference to the
Permit shall include all documents referred to in the Permit and also the
relevant documents in the Register.
許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件及本許可證A部所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地 / 辦事處查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。
1.4
The Permit Holder shall give a copy of this Permit
to the person(s) in charge of the site(s) and ensure that such person(s) fully
understands all conditions and all requirements incorporated in the Permit. The
site(s) refers to site(s) of construction and operation of the Project and
shall mean the same hereafter.
許可證持有人須把本許可證的複本交予有關工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指建造及營辦工程項目的工地,下文所提及的工地亦屬同一意思。
1.5
The Permit Holder shall display conspicuously a copy
of this Permit on the Project site(s) at all vehicle site entrances/exits or at
a convenient location for public’s information at all times. The Permit Holder
shall ensure that the most updated information about the Permit, including any
amended Permit, is displayed at such locations. If the Permit Holder surrenders
a part or the whole of the Permit, the notice he sends to the Director shall
also be displayed at the same locations as the original Permit. The suspended,
varied or cancelled Permit shall be removed from display at the Project
site(s).
許可證持有人須在工程項目的工地的所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證(包括任何經修訂的許可證)的最新資料。許可證持有人如交回許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的相同地點展示。遭暫時吊銷、更改或取消的許可證必須從工程項目的工地除下,不再展示。
1.6
The Permit Holder shall construct and operate the
Project in accordance with the project description in Part
B of this Permit.
許可證持有人須依據本許可證B部的工程項目說明,建造及營辦工程項目。
1.7
The Permit Holder shall ensure that the Project is
designed, constructed and operated in accordance with the information and
recommendations described in the Project Profile (Register No. PP-481/2013),
the Application for Environmental Permit (Application No. AEP-452/2013), and
the information and mitigation measures described in this Permit. Where recommendations referred to in the
documents of the Register are not expressly referred to in this Permit, such
recommendations are nevertheless to be implemented unless expressly excluded or
amended in this Permit.
許可證持有人須確保工程項目的設計、建造及營辦是按照工程項目簡介(登記冊編號:PP-481/2013)所說明的資料及建議;環境許可證申請文件(申請書編號:AEP-452/2013);以及本許可證所說明的資料及緩解措施辦理。登記冊文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或修訂。
1.8
All
deposited submissions, as required under this Permit, shall be rectified and
resubmitted in accordance with the comments, if any, made by the Director
within one month of the receipt of the Director’s comments or otherwise
specified by the Director.
所有按本許可證規定提交的文件,須在接獲署長的意見(如有者)後1個月內(除非署長另行指定),根據署長的意見加以修正並再向署長提交。
1.9
All
submissions approved by the Director, all submissions deposited without
comments by the Director, or all submissions rectified in accordance with
comments by the Director under this Permit shall be construed as part of the
permit conditions described in Part C of this
Permit. Any variation of the submissions shall be approved by the Director in
writing or as prescribed in the relevant permit conditions. Any non-compliance
with the submissions may constitute a contravention of the Environmental Impact
Assessment Ordinance (Cap.499).
署長批准的所有提交文件、署長沒有給予意見的所有存放文件、或根據本許可證規定由署長給予意見修正的所有提交文件,均須詮釋為本許可證C部說明的許可證條件的一部分。提交文件如有任何修訂,均須獲署長的書面批准,或符合有關許可證條件訂明的規定。如有不符合提交文件的情況,可能違反環境影響評估條例(第499章)的規定。
1.10
The Permit Holder
shall release all finalized submissions, as required under this Permit, to the
public by depositing copies in the Environmental Impact Assessment Ordinance
Register Office, or in any other places, or any internet websites as specified
by the Director, or by any other means as specified by the Director for public
inspection. For this purpose, the Permit Holder shall provide sufficient copies
of the submissions.
許可證持有人須把所有按本許可證規定提交的文件定稿公開給公眾知道,方法是把有關文件複本存放於環評條例登記冊辦事處、署長指定的任何其他地方、署長指定的任何互聯網網站或採取署長指定的任何方法,以供公眾查閱。因此,許可證持有人須提供足夠數量的複本。
1.11
All submissions to the
Director required under this Permit shall be delivered either in person or by
registered mail to the Environmental Impact Assessment Ordinance Register
Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong
Kong). Electronic copies of all finalized submissions required under this
Permit shall be prepared in Hyper Text Markup Language (HTML) (version 4.0 or
later) and in Portable Document Format (PDF version 1.3 or later), unless
otherwise agreed by the Director and shall be submitted at the same time as the
hard copies.
本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環評條例登記冊辦事處(現址為:香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子版本,均須以超文本標示語言(HTML)(第4.0或較後版本)及便攜式文件格式(PDF)(第1.3或較後版本)製作,除非另獲署長同意,並須與硬複本同時提交。
1.12
The Permit Holder shall notify the Director in
writing the commencement date of construction of the Project no later than two
weeks before the commencement of construction of the Project. The Permit Holder
shall notify the Director in writing immediately if there is any change of the
commencement date of the construction.
許可證持有人須在工程項目的建造工程展開前至少兩個星期,以書面方式把工程項目建造工程的施工日期通知署長。施工日期如有任何更改,許可證持有人必須立即以書面方式通知署長。
1.13 For
the purpose of this Permit, “commencement of construction” does not include
works related to site clearance and preparation or other works as agreed by the
Director.
為執行本許可證,「建造工程的展開」不包括有關工地清理和預備的工程,或署長同意的其他工程。
2.
Specific Conditions
特定條件
2.1.
The Permit Holder shall employ an independent
checker to audit the implementation of all mitigation measures recommended in
the Project Profile (Register No. PP-481/2013) and to confirm with the Director
in writing in the monthly audit report full implementation of the mitigation
measures during and upon completion of the construction works.
許可證持有人須聘請一名獨立的審核人,以審核及書面方式通知署長在每月的審核報告中認證已執行於工程項目簡介(登記冊編號:PP-481/2013)中建議的所有在施工及項目建設完成期間的緩解措施。
2.2.
To minimize odour impact
during operation of the Project, the inlet chamber, wet well and screening
facilities shall be enclosed by a reinforced concrete structure.
為盡量減低工程項目營辦期間的氣味影響,入水漕、濕井及隔篩須設於以鋼筋混凝土結構的建築物內。
2.3.
To minimize odour impact
during operation of the Project, a deodorizer with forced ventilation and odour
removal rate of at least 99.5% shall be installed, operated and properly
maintained. The exhaust of the deodorizer shall be oriented away from sensitive
receivers.
為盡量減低工程項目營辦期間的氣味影響,須安裝附有壓力通風系統及具備消除至少99.5%除臭功能的除臭器,並予以妥善保養維修。除臭器排口的排氣方向,必需遠離易受空氣污染影響的地方。
2.4.
To minimize noise impact
during operation of the Project, the pump sets and the mechanically raked
screens shall be located in a reinforced concrete structure with a soundproof
door. All exits of the ventilation exhaust fans shall be installed with
acoustic louvers and silencers.
為盡量減低工程項目營辦期間的噪音影響,泵房的水泵組及機械式隔篩設施均須設於鋼筋混凝土結構連隔音門的建築物內。所有抽氣扇必須附有隔音百葉簾及滅聲器裝設。
2.5.
To minimize the chance
of emergency sewage bypass during operation of the Project, a standby pump,
dual power supply and a wet well with 2-hour storage capacity of average dry
weather flow shall be installed and properly maintained. The Supervisory
Control and Data Acquisition System shall be installed and properly maintained
to allow for remote monitoring of the sewage pumping station and immediate
actions to the Siu Ho Wan Sewage Treatment Works in case of emergency or
operational problems.
為盡量減低工程項目營辦期間緊急排放污水的機會,泵房須設有一個備用水泵、雙重電力供應量及可預留兩小時平均旱季流量的污水貯存濕井,並予以妥善保養維修。亦須裝設遙測警報系統,以便泵房一旦有異常情況或操作出現問題時可把信號傳送至小壕灣污水處理廠,並予以妥善保養維修。
2.6.
To minimize landscape
and visual impacts during operation of the Project, roof greening and vertical
greening as proposed in the Project Profile (Register No. PP-481/2013) and
shown in Figure 2 of the
permit shall be implemented and properly maintained.
為盡量減低工程項目對景觀及視覺造成的影響,須如工程項目簡介(登記冊編號:PP-481/2013)中建議及本許可證夾附的圖2所示,在工程項目營辦期間採用綠化屋頂及垂直綠化設計,並予以妥善保養。
Notes :
註:
1. This Permit consists of three parts, namely, PART A
(Main Permit), PART B (Descriptions of
Designated Project) and PART C (Permit
Conditions). Any person relying on this Permit shall obtain
independent legal advice on the legal implications under the EIAO, and the following
notes are for general information only.
本許可證共有3部,即A部(許可證主要部分);B部(指定工程項目的說明)及C部(許可證條件)。任何援引本許可證的人士須就環評條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。
2. If there is a breach of any condition of this Permit, the Director or
his authorized officer may, with the consent of the Secretary for the
Environment, order the cessation of associated work until the remedial action
is taken in respect of the resultant environmental damage, and in that case the
Permit Holder shall not carry out any associated works without the permission
of the Director or his authorized officer.
如違反本許可證的任何條件,署長或獲授權人員徵得環境局局長的同意後可勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。
3. The Permit Holder may apply under Section 13 of the EIAO to the Director
for a variation of the conditions of this Permit. The Permit Holder shall
replace the original permit displayed on the Project site by the amended
permit.
許可證持有人可根據環評條例第13條的規定向署長申請更改本環境許可證的條件。許可證持有人須把經修改的許可證替換在工地內展示的原有許可證。
4. A person who assumes responsibility for the whole or a part of the
Project may, before he assumes responsibility of the Project, apply under
Section 12 of the EIAO to the Director for a further environmental permit.
承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據環評條例第12條的規定向署長申請新的環境許可證。
5. Under Section 14 of the EIAO, the Director may with the consent of the
Secretary for the Environment, suspend, vary or cancel this Permit. The
suspended, varied or cancelled Permit shall be removed from display at the
site.
根據環評條例第14條的規定,署長可在環境局局長的同意下暫時吊銷、更改或取消環境許可證。遭暫時吊銷、更改或取消的環境許可證必須從建造工地除下,不再展示。
6. If this Permit is cancelled or surrendered during construction or
operation of the Project, another environmental permit must be obtained under
the EIAO before the Project could be continued. It is an offence under Section
26(1) of the EIAO to construct or operate a designated project listed in Part I
of Schedule 2 of the EIAO without a valid environmental permit.
如果本許可證在工程項目建造或營辦期間取消或交回,則在繼續進行工程項目之前,必須先根據環評條例規定取得另一份環境許可證。根據環評條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下建造或營辦條例附表2第I部所列明的指定工程項目,即屬犯罪。
7. Any person who constructs or operates the Project contrary to the
conditions in the Permit, and is convicted of an offence under the EIAO, is
liable: -
如任何人在違反本許可證的條件下建造或營辦工程項目,根據環評條例,即屬犯罪:
(i)
on a first conviction on
indictment to a fine of $2 million and to imprisonment for 6 months;
一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;
(ii)
on a second or
subsequent conviction on indictment to a fine of $5 million and to imprisonment
for 2 years;
一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;
(iii)
on a
first summary conviction to a fine at level 6 and to imprisonment for 6 months;
一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;
(iv)
on a
second or subsequent summary conviction to a fine of $1 million and to
imprisonment for 1 year; and
一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;及
(v)
in
any case where the offence is of a continuing nature, the court or magistrate may
impose a fine of $10,000 for each day on which he is satisfied the offence
continued.
在任何情況下如該罪行屬連續性質,法院或裁判官可就其信納該罪行連續的每一天另處罰款10,000元。
8. The Permit Holder may appeal against any condition of this Permit under
Section 17 of the EIAO within 30 days of receipt of this Permit.
許可證持有人可在接獲本許可證後30天內,根據環評條例第17條就本許可證的任何條件提出上訴。
9. The Notes are for general reference only and that the Permit Holder shall
refer to the EIAO for details and seek independent legal advice.
上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。
Environmental Permit
No. EP-452/2013
環境許可證編號EP-452/2013
[ Back to First Page ] / [ Back to Main Index ]