Environmental Permit No. EP-465/2013
環境許可證編號EP-465/2013
ENVIRONMENTAL IMPACT
ASSESSMENT ORDINANCE
(CHAPTER 499)
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE
A DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant
to Section 10 of the Environmental Impact Assessment Ordinance (EIAO), the
Director of Environmental Protection (the Director) grants this environmental
permit to the Civil
Engineering and Development Department (hereinafter referred to as the "Permit
Holder") to construct and operate the designated project described in Part B subject to the conditions specified in Part C. The issue of this environmental permit is
based on the documents, approvals or permissions described below:
根據《環境影響評估條例》(環評條例)第10條的規定,環境保護署署長(署長)將本環境許可證批予土木工程拓展署 (下稱“許可證持有人”),以建造及營辦B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證是依據下列文件、批准或許可而簽發:
Application No. 申請書編號 |
AEP-465/2013
|
Document in the Register: 登記冊上的文件: |
(1) North East New
Territories New Development Areas (Register No.:
AEIAR-175/2013) - Environmental Impact
Assessment Report (April 2013) [hereinafter
referred to as the "EIA Report"] - Environmental Monitoring and Audit Manual (April 2013) [hereinafter referred to as the
“EM&A Manual”] 新界東北新發展區 (登記冊編號:AEIAR-175/2013)
- 環境監察及審核手冊 (2013年4月) [下稱 “環監手冊”] (2)
The Director’s letter of approval of the EIA Report dated 18 October 2013 (Reference: (45) in EP2/N7/S3/
署長於 (檔案編號: (45) in EP2/N7/S3/ (3) Documents
attached to the Application for Environmental Permit submitted by the Permit Holder on 23
October 2013 (Application No.: AEP-465/2013) [Hereinafter
referred to as the "Application"] 許可證持有人於 [下稱 “申請書”] |
21 November 2013
Date 日期 |
|
(Maurice K.L. YEUNG) Principal Environmental Protection Officer for Director of Environmental Protection 環境保護署署長 (首席環境保護主任楊國良代行) |
PART B (DESCRIPTION OF
DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder
is the description of the designated project mentioned in Part A of this environmental permit
(hereinafter referred to as “the Permit”):
下列為本環境許可證 (下稱“許可證”) A部 所提述的指定工程項目的說明:
Title of
Designated Project 指定工程項目的名稱 |
[Hereinafter
referred to as "the Project"] 新田公路及粉嶺公路古洞段擴闊 (新田交匯處至寶石湖路交匯處) [本指定工程項目下稱"工程項目" ] |
Nature of
Designated Project 指定工程項目的性質 |
Major extensions or improvements to an existing
expressway. 對現有快速公路作重大擴建或改善。 |
Location of
Designated Project 指定工程項目的地點 |
Kwu Tung North New Development Area. The location of the Project is shown in Figure
1 attached to this
Permit. 古洞北新發展區 工程項目的位置載於本許可證夾附的圖1。 |
Scale and
Scope of Designated Project 指定工程項目的規模和範圍 |
Widening an existing carriageway
from dual 3-lane to dual 4-lane configuration
and junction improvement. 擴闊現時行車線,由三線雙程道路改為四線雙程道路; 並改善其交滙處。 |
1
General
Conditions
1.1
The
Permit Holder and any person working on the Project shall comply with all
conditions set out in this Permit. Any non-compliance by any person may
constitute a contravention of the Environmental Impact Assessment Ordinance
(EIAO) (Cap. 499) and may become the subject of appropriate action being taken under the EIAO.
1.2
The
Permit Holder shall ensure full compliance with all legislation from time to
time in force including, without limitation to, the Air Pollution Control
Ordinance (Cap. 311), Waste Disposal Ordinance (Cap. 354), Water Pollution
Control Ordinance (Cap. 358), Noise Control Ordinance (Cap. 400) and Dumping at
Sea Ordinance (Cap. 466). This Permit does not of itself constitute
any ground of defence
against any proceedings instituted under any legislation or imply any approval
under any legislation.
1.3
The
Permit Holder shall make copies of this Permit together with all documents
referred to in this Permit and
the documents referred to in Part A of the Permit readily available at all times
for inspection by the Director or his authorized
officers at all sites/offices covered by this Permit. Any
reference to the Permit shall include all documents referred to in the Permit
and also the relevant documents in the Register.
1.4
The
Permit Holder shall give a copy of this Permit to the person(s) in charge of
the site(s) and ensure that such person(s) fully understands all conditions and
all requirements incorporated in the
Permit.
The site(s) refers to site(s) of
construction and operation of the Project and shall mean the same hereafter.
1.5
The
Permit Holder shall display conspicuously a copy of this Permit on the Project
site(s) at all vehicular site entrances/exits or at a convenient location for
public information at all times. The Permit Holder shall ensure that the most
updated information about the Permit, including any amended Permit, is
displayed at such locations. If the
Permit Holder surrenders a part or the whole of the Permit, the notice he sends
to the Director shall also be displayed at the same locations as the original
Permit. The
suspended, varied or cancelled Permit shall be removed from display at the
Project site(s).
1.6
The
Permit Holder shall construct and operate the Project in accordance with the
project descriptions in Part B of this Permit.
1.7
The Permit Holder shall ensure that the Project is
designed, constructed and operated in accordance with the information and all
recommendations described in the approved EIA Report (Register No. AEIAR-175/2013)
as described in Part A of this Permit; the
Director’s letter of approval of the EIA Report dated 18 October 2013
referenced (45) in EP2/N7/S3/
1.8
All deposited submissions, as required under this Permit,
shall be rectified and resubmitted in accordance with the comments, if any,
made by the Director within one month of the receipt of the Director’s comments
or otherwise as specified by the Director.
1.9
All
submissions, approved by the Director, all submissions deposited without
comments by the Director, or all submissions rectified in accordance with
comments by the Director under this Permit shall be construed as part of the
permit conditions described in Part C of this
Permit.
Any variation of the submissions shall be
approved by the Director in writing or as prescribed in the relevant permit
conditions. Any non-compliance with the submissions may constitute a
contravention of the Environmental Impact Assessment Ordinance (Cap. 499). All
submissions or any variation of the submissions shall be certified by the
Environmental Team (ET) Leader and verified by the Independent Environmental
Checker (IEC) referred to in Conditions 2.1 and 2.2 below, before submitting to
the Director under the Permit.
1.10
The
Permit Holder shall release all finalized submissions, as required under this
Permit, to the public by depositing copies in the EIAO Register Office, or in
any other places, or any internet websites as specified by the Director, or by
any other means as specified by the Director for public inspection. For this
purpose, the Permit Holder shall provide sufficient copies of the submissions.
1.11
All
submissions to the Director required under this Permit shall be delivered
either in person or by registered mail to the EIAO Register Office (currently
at 27/F, Southorn Centre,
1.12
The
Permit Holder shall notify the Director in writing the commencement date of
construction of the Project no later than 8 weeks prior to the commencement of construction of the
Project.
The Permit Holder shall notify the
Director in writing immediately if there is any change of the commencement date
of the construction.
1.13
For
the purpose of this Permit, “commencement of construction” does not include
works related to site clearance and preparation, or other works as agreed by
the Director.
2
Specific
Conditions
Submissions or Measures to be implemented before
Construction of the Project
Employment
of Environmental Monitoring and Audit (EM&A) Personnel
2.1
An
Environmental Team (ET) shall be established by the Permit Holder no later than
6 weeks before the commencement of
construction of the Project. The ET
shall not be in any way an associated body of the Contractor or the Independent
Environmental Checker (IEC) for the Project. The ET shall be headed by an ET Leader. The ET Leader shall be a person who has
at least 7 years of experience in environmental monitoring and auditing
(EM&A) or environmental management. The ET and the ET Leader shall be
responsible for the implementation of the EM&A programme in accordance with
the EM&A requirements as contained in the updated EM&A Manual submitted
and approved under Condition 2.3 of this Permit. The ET Leader shall keep a
contemporaneous log-book of each and every instance or circumstance or change
of circumstances, which may affect the compliance with the recommendations of
the EIA Report (Register No.: AEIAR-175/2013) and this Permit. The ET Leader shall notify the IEC within
one working day of the occurrence of any such instance or circumstance or
change of circumstances. The ET
Leader’s log-book shall be kept readily available for inspection by all persons
assisting in supervision of the implementation of the recommendations of the
EIA Report (Register No.: AEIAR-175/2013) and this Permit or by the Director or
his authorized officers. Failure to maintain records in the log-book, failure
to discharge the duties of the ET Leader as defined in the updated EM&A
Manual or failure to comply with this Condition would entitle the Director to
require the Permit Holder by notice in writing to replace the ET Leader. Failure by the Permit Holder to make
replacement, or further failure to keep contemporaneous records in the log-book
despite the employment of a new ET Leader may render the Permit liable to
suspension, cancellation or variation.
2.2
An
IEC shall be employed by the Permit Holder no later than 6 weeks before the commencement of
construction of the Project. The
IEC shall not be in any way an associated body of the Contractor or the ET for
the Project. The IEC shall be a
person who has at least 7 years of experience in EM&A or environmental
management. The IEC shall be
responsible for duties defined in the updated EM&A Manual submitted and
approved under Condition 2.3 of this Permit, and shall audit the overall
EM&A performance, including the implementation of all environmental
mitigation measures, submissions required in the updated EM&A Manual, and
any other submissions required under this Permit. In addition, the IEC shall be responsible
for verifying the environmental acceptability of permanent and temporary works,
relevant design plans and submissions under this Permit. The IEC shall verify the log-book(s)
mentioned in Condition 2.1 of this Permit. The IEC shall notify the Director, within
one working day of receipt of notification from the ET Leader of each and every
change of circumstances or non-compliance with the recommendations of the EIA
Report (Register No.: AEIAR-175/2013) and this Permit, which might affect the
monitoring or control of adverse environmental impacts from the Project. In
case the IEC fails to so notify the Director of the same, fails to discharge
the duties of the IEC as defined in the updated EM&A Manual or fails to
comply with this Condition, the Director may require the Permit Holder by notice
in writing to replace the IEC. Failure
to replace the IEC as directed or further failure to so notify the Director
despite employment of a new IEC may render the Permit liable to suspension,
cancellation or variation. Notification
by the Permit Holder is the same as notification by the IEC for the purpose of
this Condition.
Submission
of Updated Environmental Monitoring and Audit Manual
2.3
The
Permit Holder shall update the EM&A Manual to include the latest EM&A
requirements in accordance with the information and recommendations described
in the EIA Report and by taking into account any specific site conditions that
may be changed before the construction of the Project. The Permit Holder shall, at least 4 weeks before the commencement of construction of
the Project, deposit with the Director four hard copies and four electronic
copies of the updated EM&A Manual. Before submission to the Director, the
updated EM&A Manual shall be certified by the ET Leader and verified by the
IEC as conforming to the information and recommendations described in the EIA
Report (Register No. AEIAR-175/2013), and taking into account any specific
requirements with respect to the latest site conditions of the Project. All measures recommended in the updated
EM&A Manual approved under this Condition shall be fully and properly
implemented in accordance with the requirements and time schedule(s) set out in
the updated EM&A Manual. The
EM&A Manual deposited under this Condition shall hereinafter be referred to
as the “updated EM&A Manual”.
Management
Organization of Main Construction Companies
2.4
The
Permit Holder shall, no later than 2 weeks before the commencement of construction of the
Project, inform the Director in writing the management organization of the main
construction companies and/or any form of joint ventures associated with the
construction of the Project. The information shall include at least an
organization chart, names of responsible persons and their contact details.
Submission
of Location Plans
2.5
The Permit Holder shall, no later than 2 weeks
before the commencement of construction of the Project, deposit four hard
copies and one electronic copy of location plan(s) of the Project with a scale
of 1:1000 or other appropriate scale as agreed with the Director. The plans shall include the details the works boundaries,
works areas, vertical and horizontal alignments of the roads and any other major
facilities; and the locations of key environmental mitigation measures.
Measures
to mitigate Cultural Heritage
Impact
2.6
A baseline
condition survey and baseline vibration impact assessment shall be conducted by
a qualified building surveyor or a qualified structural engineer prior to the
commencement of construction of the Project to: (1) define
the vibration limit of identified built
heritage features
at G202 and HKT03 shown in Figures 2a and 2b; (2) determine
whether construction vibration
monitoring and/or structural strengthening measures are required during construction phase; and (3) maintain a record of the condition survey of graded historic buildings that may be affected by the Project. The baseline condition survey and baseline
vibration impact assessment shall be included in and form part of the Baseline
Monitoring Report to be submitted under Condition 3.3 of this Permit.
2.7
Photographic and cartographic
records of the directly impacted historical buildings at HKT08 and the entrance gate of HKT03 shown in Figures 3a and 3b shall be kept by the Permit Holder and a copy of the records shall be deposited with
the Director prior to the commencement
of the respective removal or relocation works. Proposals on
relocation of any built heritages, including the entrance gate of HKT03 as
shown in Figure 3b, shall be submitted for approval by the Director
prior to commencement of the respective relocation works.
Submissions or
Measures to be implemented during Construction of the Project
Submission
of Landscape Plan
2.8
The Permit Holder
shall, at least 6 weeks before the commencement of the corresponding parts of
landscape and visual mitigation measures of the Project, deposit with the
Director three hard copies and one electronic copy of landscape plan(s). The landscape plan(s) shall show the
design details, confirmation of the feasibility for proposed planting,
locations, implementation programme, maintenance and management schedules, and
drawings in the scale of 1:1,000 or other appropriate scale, as agreed with the
Director, of the landscape and visual mitigation measures of the Project. Before submission to the Director, the
landscape plan(s) shall be certified by the ET Leader and verified by the IEC
as conforming to the relevant information and recommendations, including those
described in the EIA Report (Register No. AEIAR-175/2013). All landscape and visual mitigation
measures shall be properly implemented and maintained for the Project in
accordance with the deposited landscape plan. The Permit Holder shall make
available additional copies to the Director upon request.
Measures
to mitigate Ecological Impacts
2.9
To minimise adverse impacts on habitats of ecological importance in the
vicinity of the Project,
Submissions or
Measures to be implemented during Operation of the Project
Measures
to Mitigate Traffic Noise Impact
2.10
To mitigate traffic noise impact
arising from the Project, the Permit
Holder shall implement all noise mitigation measures as shown in Figure 4 of this Permit before commencement of operation of
the Project. All noise mitigation measures implemented
shall be properly maintained during operation of the Project.
Measures
to mitigate Ecological Impacts
2.11
All noise barriers
shall be opaque, non-transparent and non-reflective to minimize mortality
impacts on birds, unless otherwise agreed with the Director.
3
Environmental
Monitoring and Audit Requirements
3.1
The EM&A programme
shall be implemented in accordance with the procedures and requirements as set
out in the updated EM&A Manual deposited under Condition 2.3 of this Permit. Any change to the EM&A requirements
or programme shall be justified by the ET Leader and verified by the IEC as
conforming to the relevant requirements set out in the updated EM&A Manual and shall seek prior approval from the Director before
implementation.
3.2
Samples,
measurements and necessary remedial actions shall be taken in accordance with
the requirements of the updated EM&A Manual by:-
(i)
conducting
baseline environmental monitoring;
(ii)
conducting
impact monitoring;
(iii)
carrying
out remedial actions described in the Event/Action Plans of the updated
EM&A Manual in
accordance with the time frames set out in the Event/Action Plans, or as agreed
by the Director, in case where specified criteria in the updated
EM&A Manual are
exceeded; and
(iv)
logging
and keeping records of details of all parameters within 3 working days of the
collection of data or completion of remedial action(s), for the purpose of
preparing and submitting the monthly EM&A Reports and to make available for
inspection on site.
3.3
Three hard copies and two electronic copy
of the Baseline Monitoring Report shall be submitted to the Director at least 2
weeks before the commencement of construction of the Project. The submissions
shall be certified by the ET Leader and verified by the IEC as complied with
the requirements as set out in the updated EM&A Manual before submission
to the Director. The ET Leader and IEC shall personally
inspect the site within each reporting cycle prior to certification and
verification of compliance of EM&A Reports. Additional copies of the submission shall be provided upon request by
the Director.
3.4 Three hard copies and two electronic copy of monthly EM&A Report shall be submitted to the
Director within 2 weeks after the end of each reporting month throughout the entire construction period. The EM&A Reports shall include a summary of all non-compliance. The submissions
shall be certified by the ET Leader and verified by the IEC as complying with
the requirements as set out in the updated EM&A Manual before submission
to the Director. Additional copies of the submission shall be provided to the Director
upon request by the Director.
3.5
All
EM&A data submitted under this Permit shall be true, valid and correct.
4
Electronic
Reporting of EM&A Information
4.1
To
facilitate public inspection of the Baseline Monitoring Report and Monthly
EM&A Reports via the EIAO Internet Website and at the EIAO Register Office,
electronic copies of these Reports shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and/or
in Portable Document Format (PDF version 1.3 or later), unless otherwise agreed
by the Director and shall be submitted at the same time as the hard copies as
described in Conditions 3.3 and
3.4 above of this Permit. For
the HTML version, a content page capable of providing hyperlink to each section
and sub-section of these Reports shall be included in the beginning of the
document. Hyperlinks to all figures, drawings and tables in these Reports shall
be provided in the main text from where the respective references are made. All
graphics in these Reports shall be in interlaced GIF/JEPG format unless
otherwise agreed by the Director. The content of the electronic copies of these
Reports must be the same as the hard copies.
(a)
providing access to all environmental monitoring data
collected since the commencement of construction and all submissions under this
permit;
(b)
searching by date;
(c)
searching by types of monitoring data; and
(d)
hyperlinks to relevant monitoring data after
searching.
or otherwise as agreed by the Director.
Notes :
1.
This Permit consists of three parts, namely, Part A
(Main Permit), Part B (Description of Designated
Project) and Part C (Permit Conditions). Any person
relying on this permit should obtain independent legal advice on the legal
implications under the EIAO, and the following notes are for general
information only.
2.
If there is a breach of any condition of this Permit, the Director or
his authorized officer may, with the consent of the Secretary for the
Environment, order the cessation of associated work until the remedial action
is taken in respect of the resultant environmental damage, and in that case the
Permit Holder shall not carry out any associated works without the permission
of the Director or his authorized officer.
3.
The Permit Holder may apply under Section 13 of the EIAO to the Director
for a variation of the conditions of this Permit. The Permit Holder shall
replace the original permit displayed on the Project site by the amended
permit.
4.
A person who assumes responsibility for the whole or a part of the
Project may, before he assumes responsibility of the Project, apply under
Section 12 of the EIAO to the Director for a further environmental permit.
5.
Under Section 14 of the EIAO, the Director may with the consent of the
Secretary for the Environment, suspend, vary or cancel this Permit. The suspended, varied or cancelled
Permit shall be removed from display at the Project site.
6.
If this Permit is cancelled or surrendered during construction or operation of the Project, another
environmental permit must be obtained under the EIAO before the Project could
be continued. It is an offence under Section 26(1) of the EIAO to construct or operate a designated project listed in Part I
of Schedule 2 of the EIAO without a valid environmental permit.
7. Any person who constructs or
operates the Project contrary to the conditions in the Permit, and is convicted
of an offence under the EIAO, is liable:
(i)
on a first conviction on indictment to a fine of $2 million and to imprisonment
for 6 months;
(ii)
on a second or subsequent conviction on indictment to a fine of $5 million and
to imprisonment for 2 years;
(iii)
on a first summary conviction to a fine at level 6 and to imprisonment for 6
months;
(iv)
on a second or subsequent summary conviction to a fine of $1 million and to
imprisonment for 1 year; and
(v) in any case where the offence is of a
continuing nature, the court or magistrate may impose a fine of $10,000 for
each day on which he is satisfied the offence continued.
8.
The Permit Holder may appeal against any condition of this Permit under
Section 17 of the EIAO within 30 days of receipt of this Permit.
9.
The Notes are for general reference only and that the Permit Holder
should refer to the EIAO for details and seek independent legal advice.