Environmental
Permit No. EP-513/2016
Àô¹Ò³\¥iÃÒ½s¸¹ EP-513/2016
ENVIRONMENTAL
IMPACT ASSESSMENT ORDINANCE
(CHAPTER
499)
Section
10
Àô¹Ò¼vÅTµû¦ô±ø¨Ò
(²Ä499³¹)
²Ä10±ø
ENVIRONMENTAL
PERMIT TO CONSTRUCT AND
OPERATE
A DESIGNATED
PROJECT
«Ø³y¤ÎÀç¿ì«ü©w¤uµ{¶µ¥ØªºÀô¹Ò³\¥iÃÒ
A³¡ (³\¥iÃÒ¥Dn³¡¤À)
Pursuant to Section 10 of the Environmental
Impact Assessment Ordinance (EIAO), the Director of Environmental Protection
(the Director) grants this environmental permit to the Civil Engineering and Development Department
(hereinafter referred to as the "Permit Holder") to construct and operate the designated project
described in Part B subject to the conditions
specified in Part C. The issue of this environmental permit
is based on the documents, approvals or permissions described below :-
®Ú¾Ú¡mÀô¹Ò¼vÅTµû¦ô±ø¨Ò¡n(Àôµû±ø¨Ò)²Ä10±øªº³W©w¡AÀô¹Ò«OÅ@¸p¸pªø¡]¸pªø¡^±N¥»Àô¹Ò³\¥iÃҧ天¤g¤ì¤uµ{©Ý®i¸p(¤UºÙ³\¥iÃÒ«ù¦³¤H)¥H«Ø³y¤ÎÀç¿ìB³¡©Ò»¡©úªº«ü©w¤uµ{¶µ¥Ø¡A¦ý¶·¿í¦uC³¡©Ò¦C©úªº±ø¥ó¡C¥»Àô¹Ò³\¥iÃÒªºµo¥X¡A¤D¥H¤Uªí©Ò¦Cªº¤å¥ó¡B§åã©Î³\¥i§@¬°®Ú¾Ú¡G-
Application No. ¥Ó½Ð®Ñ½s¸¹ |
AEP-513/2016 |
Document in the Register |
(1) Development of Anderson Road Quarry Site - Road
Improvement Works (Register No.: AEIAR-195/2016) ¡V
Environmental
Impact Assessment Report (January 2016) [Hereinafter
referred to as the ¡§EIA Report¡¨] ¡V
Environmental
Monitoring and Audit Manual (January 2016) [Hereinafter
referred to as the ¡§EM&A Manual¡¨] ¡V
Executive Summary (January 2016) [Hereinafter referred to as the ¡§EIA Executive
Summary¡¨] ¦w¹F¦Ú¹D¥ÛÄq³õ¥Î¦aµo®i - ¹D¸ô§ïµ½¤uµ{ (µn°O¥U½s¸¹: AEIAR-195/2016) ¡V
Àô¹Ò¼vÅTµû¦ô³ø§i(2016¦~1¤ë) [¤UºÙ¡uÀôµû³ø§i¡v] ¡V
Àô¹ÒºÊ¹î¼f®Ö¤â¥U(2016¦~1¤ë) [¤UºÙ¡uÀôºÊ¤â¥U¡v] ¡V
¦æ¬FºKn(2016¦~1¤ë) [¤UºÙ¡uÀôµûºKn¡v] (2) The Director¡¦s letter of approval of the EIA report
dated 22 March 2016 referenced (
) in EP2/K14/A/17 Pt.3 ¸pªø©ó2016¦~3¤ë22¤éµo¥X§åãÀôµû³ø§iªº«H¥ó¡AÀÉ®×½s¸¹: ( ) in EP2/K14/A/17 Pt.3 (3)
Application for an Environmental Permit submitted on 21 June 2016 (Application No.:
AEP-513/2016) ©ó2016¦~6¤ë21¤é´£¥æªºÀô¹Ò³\¥iÃҥӽР(¥Ó½Ð®Ñ½s¸¹: AEP-513/2016) |
20 July
2016
2016¦~7¤ë20¤é
Date ¤é´Á |
|
(Ken
Y.K. Wong) Principal Environmental Protection Officer for
Director of Environmental Protection Àô¹Ò«OÅ@¸p¸pªø (º®uÀô¹Ò«OÅ@¥D¥ô ¶ÀÄ£¥ú¥N ¦æ) |
PART
B ( DESCRIPTION OF DESIGNATED PROJECT)
B³¡ («ü©w¤uµ{¶µ¥Øªº»¡©ú)
Hereunder is the description of the designated
project mentioned in Part A of this environmental
permit (hereinafter referred to as the ¡§Permit¡¨):-
¤U¦C¬°¥»Àô¹Ò³\¥iÃÒ(¤UºÙ¡§³\¥iÃÒ¡¨)A³¡©Ò´£¤Îªº«ü©w¤uµ{¶µ¥Øªº»¡©ú:
Title of Designated Project(s) «ü©w¤uµ{¶µ¥Øªº¦WºÙ |
Development of Anderson Road
Quarry Site - Road Improvement Works [This designated project is hereinafter referred
to as "the Project"] ¦w¹F¦Ú¹D¥ÛÄq³õ¥Î¦aµo®i - ¹D¸ô§ïµ½¤uµ{ |
Nature of Designated Project(s) «ü©w¤uµ{¶µ¥Øªº©Ê½è |
A road which is an expressway, trunk
road, primary distributor road or district distributor road including new
roads, and major extensions or improvements to existing roads. Äݧֳt¤½¸ô¡B·F¹D¡B¥Dn·F¸ô©Î¦a°Ï·F¸ôªº¹D¸ô¡A¥]¬A·s¸ô¤Î¹ï²{¦³¹D¸ô§@«¤jÂX«Ø©Î§ïµ½ªº³¡¤À¡C |
Location of Designated Project(s) «ü©w¤uµ{¶µ¥Øªº¦aÂI
|
The locations of
this Project are shown in Figures
1a ¡V 1d attached to this Permit. ¤uµ{¶µ¥Øªº¦ì¸m¨£¸ü©ó¥»³\¥iÃÒ§¨ªþªº¹Ï1a ¡V
1d¡C |
Scale and Scope of Designated Project(s) «ü©w¤uµ{¶µ¥Øªº³W¼Ò©M½d³ò |
Construction
and operation of the following key elements: (a)
Lengthening of existing lay-bys from 12m and 18m to 70m and
addition of 2 new lay-bys of 26m long at Lin Tak Road; (b) Realignment of Lin Tak Road
towards south; (c)
Enlargement of existing roundabout at the junction of Lin Tak
Road and Pik Wan Road; (d) Cutting of slope works at the
southern side of Lin Tak Road; (e)
Widening of small section of slip road towards Tseung Kwan O
(TKO) Road eastbound with associated slope works for retaining walls ; (f)
Construction of a new
westbound flyover from Sau Mau Ping Road to Lin Tak Road; (g) TKO Road slip road to Sau Mau
Ping Road will be shifted southwards; (h) Improvement works on Clear
Water Bay Road and detouring right-turn movement from On Sau Road northbound
onto Clear Water Bay Road eastbound by construction of a new U-turn facility; (i)
Widening a section of 130m long of the existing New Clear Water
Bay Road westbound carriageway opposite to Shun Lee Estate from one lane to
two lanes; and (j)
Construction of a new Shun Lee Tsuen Road slip road (about 350m)
and a merging lane (about 170m) with associated slope works for retaining
walls. «Ø³y¤ÎÀç¿ì¥H¤Uªº¥Dn³¡¥÷: (a)
±N³s¼w¹Dªº²{¦³Áר®³B¥Ñ²{®É 12¦Ì©M18¦Ì©µªø¦Ü70¦Ì¡A¨Ã¼W¥[¨â±øªø¹F26¦ÌªºÁר®³B¡F (c)
ÂX¤j²{¦³³s¼w¹D¤ÎºÑ¶³¹D¥æ¬É³Bªº°j±Û³B¡F (d) ©ó³s¼w¹D¥H«n¶i¦æ¤Á«d±×©Y¤uµ{¡F (e)
ÂXÁ啕±Nx¿D¹DªF¦æ½uªºªº¤ä¸ô¤Î¬ÛÃöªº±×©Y¾×¤gÀð¤uµ{¡F (f)
¿³«Ø¤@±ø¥Ñ¨qZ©W¹D¦Ü³s¼w¹Dªº·s¦è¦æ¦æ¨®¤Ñ¾ô¡F (g) ±Nx¿D¹D©¹¨qZ©W¹D¤è¦V¤ä¸ô±N«n²¾¡F (h) ©ó²M¤ôÆW¹D¶i¦æ§ïµ½¤uµ{¡A¿³«Ø¤@Ó·sªº±¼ÀY³]¬I¡F (i)
±N¶¶§Q邨¹ï¶}¤@¬qªø¹F130¦Ìªº²{¦³·s²M¤ôÆW¹D¦è¦æ½u±q³æ½u¦æ¨®¹DÂXÁï¦ÜÂù½u¦æ¨®¹D¡F¤Î (j)
¿³«Ø¤@±øªø¬ù350 ¦Ìªº·s¤ä¸ô©Mªø¬ù170 ¦Ìªº·s¦X¬y¨®¹D¤Î¬ÛÃöªº±×©Y¾×¤gÀð¤uµ{¡C |
C³¡ (³\¥iÃÒ±ø¥ó)
1. General
Conditions
¤@¯ë±ø¥ó
1.1 The Permit Holder and any person
working on the Project shall comply with all conditions set out in this Permit.
Any non-compliance by any person may constitute a contravention of the
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) and may become the
subject of appropriate action being taken under the EIAO.
1.2 The Permit Holder shall ensure
full compliance with all legislation from time to time in force including,
without limitation to, the Air Pollution Control Ordinance (Cap. 311), Waste
Disposal Ordinance (Cap. 354), Water Pollution Control Ordinance (Cap. 358) and
Noise Control Ordinance (Cap. 400). This Permit does not of itself constitute
any ground of defence against any proceedings instituted under any legislation
or imply any approval under any legislation.
1.3 The Permit Holder shall make
copies of this Permit together with all documents referred to in this Permit
and the documents referred to in Part A of the
Permit readily available at all times for inspection by the Director or his
authorised officers at all sites/offices covered by this Permit. Any reference
to the Permit shall include all documents referred to in the Permit and also
the relevant documents in the Register.
1.4 The Permit Holder shall give a
copy of this Permit to the person(s) in charge of the site(s) and ensure that
such person(s) fully understands all conditions and all requirements
incorporated in the Permit. The site(s) refers to site(s) of construction of
the Project and shall mean the same hereafter.
1.5 The Permit Holder shall display
conspicuously a copy of this Permit on the Project site(s) at all vehicular
site entrances/exits or at a convenient location for public¡¦s information at
all times. The Permit Holder shall ensure that the most updated information
about the Permit, including any amended Permit, is displayed at such
locations. If the Permit Holder surrenders a part or the whole of the
Permit, the notice he sends to the Director shall also be displayed at the same
locations as the original Permit. The suspended, varied or cancelled
Permit shall be removed from display at the Project site(s).
1.6 The Permit Holder shall
construct and operate the Project in accordance with the project description in
Part B of this Permit.
1.7 The Permit Holder shall ensure
that the Project is designed, constructed and operated in accordance with the
information and recommendations described in the EIA Report (Register No.
AEIAR-195/2016), the application document for environmental permit (Application
No.: AEP-513/2016),
other relevant documents in the Register, the information and mitigation
measures described in this Permit, mitigation measures to be recommended in
submissions that shall be deposited with or approved by the Director as a
result of permit conditions contained in this Permit, and mitigation measures
to be recommended under on-going surveillance and monitoring activities during
all stages of the Project. Where recommendations referred to in the documents
of the Register are not expressly referred to in this Permit, such
recommendations are nevertheless to be implemented unless expressly excluded or
impliedly amended in this Permit.
1.8 All deposited submissions, as
required under this Permit, shall be rectified and resubmitted in accordance
with the comments, if any, made by the Director within one month of the receipt
of the Director¡¦s comments or otherwise as specified by the Director.
1.9 All submissions approved by the
Director, all submissions deposited without comments by the Director, or all
submissions rectified in accordance with comments by the Director under this
Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the
submissions shall be approved by the Director in writing or as prescribed in
the relevant permit conditions. Any non-compliance with the submissions may
constitute a contravention of the Environmental Impact Assessment Ordinance
(Cap. 499). All submissions or any variation of the submissions shall be
certified by the Environmental Team (ET) Leader and verified by the Independent
Environmental Checker (IEC) referred to in Conditions 2.2 and 2.7 below, before
submitting to the Director under this Permit.
1.10 The Permit Holder shall release all
finalized submissions as required under this Permit, to the public by
depositing copies in the Environmental Impact Assessment Ordinance Register
Office, or in any other places, or any internet websites as specified by the
Director, or by any other means as specified by the Director for public
inspection. For this purpose, the Permit Holder shall provide sufficient copies
of the submissions.
1.11 All submissions to the Director required under
this Permit shall be delivered either in person or by registered mail to the
Environmental Impact Assessment Ordinance Register Office (currently at 27/F,
Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong). Electronic copies of
all finalized submissions required under this Permit shall be prepared in Hyper
Text Markup Language (HTML) (version 4.0 or later) and in Portable Document
Format (PDF version 1.3 or later), unless otherwise agreed by the Director and
shall be submitted at the same time as the hard copies.
1.12 The Permit Holder shall notify the Director
in writing the commencement date of construction of the Project no later than 1
month prior to the commencement of construction of the Project. The Permit
Holder shall notify the Director in writing immediately if there is any change
of the commencement date of the construction.
1.13 For the purpose of this Permit,
¡§commencement of construction¡¨ does not include works related to site clearance
and preparation, or other works as agreed by the Director.
1.14 The Permit Holder shall notify the Director
in writing the commencement date of operation of the Project no later than 1 month prior to the commencement of
operation of the Project. The Permit Holder shall notify the Director in
writing immediately if there is any change of the commencement date of
operation.
2. Specific
Conditions
Submission and/or Measures before
Commencement of Construction of the Project
Employment
of Environmental Team (ET)
2.1
A single full time on-site ET, unless otherwise approved by the Director, shall be employed by the Permit Holder no later than one month before the commencement of
construction of the Project. The ET shall be directly supervised by the Engineer¡¦s Representative of the
Permit Holder (ER) and shall not be in any way an associated body
of the Contractor or the IEC for the Project. The Permit Holder shall
provide a site office to the ET for use. The ET
shall be headed by a full time on-site ET Leader. The ET
Leader shall be a person who has
at least 7 years of experience in environmental monitoring and auditing
(EM&A) or environmental management.
2.2
The ET and the ET Leader shall be responsible for:
(i)
implementing the
EM&A programme in accordance with the EM&A requirements as contained in
the EM&A Manual of the Project;
(ii)
certifying the environmental acceptability
of permanent and temporary works, relevant design plans and submissions required in the EM&A Manual and under this Permit;
(iii)
carrying out
site inspections to audit the Contractor¡¦s site practice and work methodologies
with respect to environmental mitigation measures contained in the EM&A
Manual of the Project and to take pro-active actions to pre-empt environmental
problems;
(iv)
notifying the IEC within one working
day of the occurrence of each and every instance or circumstance or change of
circumstances, which may affect the compliance with the recommendations of the approved EIA Report (Register No. AEIAR-195/2016)
and this Permit; and
(v)
keeping a contemporaneous log-book of
any such instance or circumstance or change of
circumstances.
The
log-book shall be kept readily available for inspection by all persons
assisting in supervision of the implementation of the recommendations of the approved EIA Report (Register No. AEIAR-195/2016)
and this Permit or by the Director or his authorized officers.
2.3
Failure to maintain records in the log-book, failure
to discharge the duties of the ET Leader as defined in the EM&A Manual or
failure to comply with this Condition would entitle the Director to require the
Permit Holder by notice in writing to replace the ET Leader. Failure by
the Permit Holder to make replacement, or further failure to keep
contemporaneous records in the log-book despite the employment of a new ET Leader may render the Permit liable to
suspension, cancellation or variation.
Employment of Registered Landscape Architect
2.4
The Permit Holder
shall, no later than one month before the commencement of the construction of the
Project, appoint a Registered Landscape Architect to form part of the ET to
carry out work relating to landscape aspects including but not limited to
auditing the implementation of landscape mitigation measures to ensure
compliance with the recommendations of the approved EIA Report (Register No.
AEIAR-195/2016) and to certify submissions for the Project as required under
Condition 2.12. The qualification
and experience of the Registered Landscape Architect shall be certified by the
ET Leader and verified by the IEC.
Employment of Qualified Ecologist
2.5
The Permit Holder
shall, no later than one month before the commencement of the construction of
the Project, appoint a Qualified Ecologist to form part of the ET to carry out
work relating to ecological aspects including but not limited to advising on,
monitoring and ensuring proper implementation of measures for habitat loss due
to the Project, and preparing submissions for the Project as required under
Condition 2.14. The Qualified Ecologist shall be a person
who has at least 7 years of relevant experience. The qualification and experience of the
Qualified Ecologist shall be certified by the ET Leader and verified by the
IEC.
Employment of IEC
2.6
A single IEC with a supporting team shall be
employed by the Permit Holder no later than one month before the commencement of
construction of the Project. The IEC and his team shall not be in any way an associated body of the ER, the Contractor or the ET for the Project. The IEC shall be approved by the Director before appointment by the
Permit Holder. The IEC shall be a person who has
at least 7 years of experience in EM&A or environmental management.
2.7
The IEC shall report directly to the Director and shall be responsible for duties defined in the EM&A Manual
and this Permit, including
but not limited to the following:
(i)
to audit the overall EM&A
performance, including the implementation of all environmental mitigation
measures and monitoring
activities on site;
(ii)
to verify the
environmental acceptability of permanent and temporary works, relevant design
plans and submissions required in the EM&A Manual and under this Permit;
(iii)
to verify the log-book(s) mentioned
in Condition 2.2(v);
(iv)
to notify the Director
by fax or email, within one working day of receipt of notification from the ET Leader, or identification by the IEC and his team, of each and every change of circumstances, emergency events relating to violation of environmental
legislation (such as illegal dumping and landfilling) or non-compliance (including suspects of non-compliance) with the recommendations (such as construction methods, mitigation measures, and environmental
standards) of the approved EIA Report (Register No. AEIAR-195/2016), the EM&A Manual and this Permit, which might affect the monitoring or control of
adverse environmental impacts from the Project;
(v)
to liaise closely with the
Director;
(vi)
to accompany the Director in carrying out site inspections and to offer objective
and professional advice on environmental issues when requested; and
(vii)
to allocate adequate resources, including any necessary specialist
support, for discharging the duties required in this Permit and the EM&A
Manual.
2.8
If the Director considers the IEC fails to
discharge the duties of the IEC as defined in the EM&A Manual or in this Permit, the Director may require the Permit Holder by notice in writing to
replace the IEC. Failure to replace the IEC as directed or further
failure to so notify the Director despite employment of a new IEC may render
the Permit liable to suspension, cancellation or variation. Notification
by the Permit Holder is the same as notification by the IEC for the purpose of
this Condition.
Community Liaison Hotline
2.9
A hotline shall be set up prior to the commencement of
construction and shall be operated during the construction of the Project to
handle complaints, comments, suggestions or requests for information from the
public. The Permit Holder shall notify the Director the date of setting up the
hotline and the contact details of the hotline at least 2 weeks before the
commencement of construction of the Project. The contact details of the hotline
shall be made available to the public via the dedicated website to be set up by
the Permit Holder as described in Condition 4.2 of this Permit.
Management Organization of Main Construction Companies
2.10
The
Permit Holder shall, no later than one month before the commencement of construction of
the Project, inform the Director in writing with the following
information, which shall include at
least an organization chart, names of responsible persons and their contact
details:
(i)
the management organization of the main construction companies and/or any
form of joint ventures associated with the construction of the Project;
(ii)
the management organization of the ET; and
(iii)
the management organization of the IEC and his supporting team.
Submission of Design Drawing of the Project
2.11
The Permit Holder
shall, no later than one month before the commencement of the construction
works of the Project, deposit four hard copies and one electronic copy of
design drawing(s) of the Project with scale of at least 1:1000. The
drawing(s) shall be submitted with an explanatory statement detailing the works boundaries, the
works areas, vertical and horizontal alignments of the roads and any
other major facilities; and the locations of key environmental mitigation
measures, including noise enclosures/semi-enclosures and barriers as mentioned
in Condition 2.18 of this Permit.
Submission of Landscape and Visual Mitigation Plan(s)
2.12
The Permit Holder shall, at least one month before the
commencement of construction of the Project, deposit with the Director five hard
copies and one electronic copy of Landscape and Visual Mitigation Plan(s), which shall be certified by the Registered
Landscape Architect and the ET Leader and verified by the IEC as conforming to
the recommendations of landscape and visual mitigation measures contained in
Section 10 of the EIA Report (Register No. AEIAR-195/2016).
2.13
The Landscape and Visual Mitigation Plan(s)
shall include the locations, size, number and species of planting, design details, implementation
programme, maintenance and management schedules of the landscape and visual
mitigation measures recommended in the EIA Report (Register No. AEIAR-195/2016)
and drawings in the scale of 1:1000 or other appropriate scale showing the
landscape and visual mitigation measures of the Project.
Submissions for
Mitigating Impact on Plant
Species of Conservation Importance
2.14
To
reduce the impact on plant species of conservation importance due to construction of the
Project, including Incense Tree (Aquilaria sinensis), Luofushan
Joint-fir (Gnetum luofuense) and any other plant species of conservation importance identified during the detailed
vegetation survey, the Permit Holder shall:
(a) no later than one month before commencement
of any works (including ground investigation) of the Project, deposit with the Director
four hard copies and one electronic copy of a Detailed Vegetation Survey Report showing the methodology as well as survey results, including the updated
conditions, number and locations of the individuals of flora species of
conservation importance to be affected, and the suitability and / or
practicality of the transplantation of these individuals;
(b) no later than one month before commencement of
plant transplantation, deposit with the Director four hard copies and one
electronic copy of Transplantation Proposal showing:
(i)
species and locations of
plants for transplantation identified in the detailed vegetation
survey;
(ii)
locations and conditions of
receptor sites for transplantation;
(iii)
methodology and implementation programme of
transplantation; and
(iv)
the 3-year post-transplantation monitoring and
maintenance programme;
(c) no later than one month
after completion of transplanting work, deposit with the Director four hard
copies and one electronic copy of a set of report showing the
transplanting work carried out under Condition 2.14 (b). Before submission to the Director, this
set of report shall be certified by the ET Leader and
verified by the IEC to demonstrate that Condition 2.14 (b) is fulfilled;
and
(d) no later than one
month after completion of post-monitoring and
maintenance works, deposit with the Director four hard copies and one electronic copy of
a set of report showing the post-transplantation monitoring and maintenance works carried out under
Condition 2.14 (b).
Before submission to the Director, this set of report
shall
be certified by the ET Leader and verified by the IEC to demonstrate that
Condition 2.14 (b) is fulfilled.
2.15
The
Detailed Vegetation Survey Report and the Transplantation Proposal shall be prepared
by the Qualified Ecologist appointed under Condition 2.5 and shall be certified by the ET Leader and
verified by the IEC as conforming to the information and recommendations
contained in the EIA Report (Register No.
AEIAR-195/2016). All recommended measures as set out in
the deposited Transplantation Proposal shall be fully and properly
implemented.
Submissions and/or Measures to be Implemented During
Construction of the Project
Measures for Mitigating Construction Environmental Impact
2.16
To minimize construction environmental impact, the following
mitigation measures shall be implemented:
(a) The use of Quality Powered Mechanical
Equipment (QPME) as recommended in Appendix 5.9 of the EIA Report (Register No.: AEIAR-195/2016), or Powered Mechanical Equipment (PME) having sound power level equivalent to or less than these QPME;
(b) The use of noise mitigation measures
including construction noise barriers, enclosures, acoustic sheds or acoustic
mats as recommended in Section
5.8.3 to Section 5.8.5 of
the EIA Report (Register No.: AEIAR-195/2016) to minimize the construction noise; and
(c) Watering once per hour on active
construction works area,
as recommended in Section 4.15.1 of the EIA Report (Register No.: AEIAR-195/2016) to
reduce construction dust emission.
Submissions and/or Measures to
be Implemented Before
and During Operation of the
Project
Submission for Mitigating Landscape and Visual
Impact before operation of the Project
2.17
The
landscape and visual mitigation measures shall be implemented in accordance
with the recommendations of the Landscape and Visual Mitigation Plan(s) deposited under
Condition 2.12 above. The Permit Holder shall, at least one month
before the commencement of operation of the Project, deposit with the Director
four hard copies and one electronic copy of the As-Built Drawing(s) of the Project,
which shall be certified by the ET Leader and verified by the IEC as conforming
to the recommendations of the Landscape and Visual Mitigation Plan(s) deposited under
Condition 2.12 above. The landscape and visual mitigation measures
shall be properly maintained during operation of the Project.
Measures
for Mitigating Noise Impact during operation of the Project
2.18
To mitigate traffic noise impact arising from the Project, the Permit
Holder shall implement all noise mitigation measures as shown in Table 1 and Figures 2a to 2c of
this Permit, before commencement of operation of the Project. All
noise mitigation measures implemented shall be properly maintained during
operation of the Project.
3. Environmental Monitoring and Audit (EM&A)
Requirements
3.1 The EM&A
programme shall be implemented in accordance with the procedures and
requirements as set out in the EM&A Manual. Any change to the EM&A requirements
or programme shall be justified by the ET Leader and verified by the IEC as
conforming to the relevant requirements set out in the EM&A Manual and
shall seek the prior approval from the Director before implementation.
3.2 Samples, measurements
and necessary remedial actions shall be taken in accordance with the
requirements of the EM&A Manual by:-
(a)
conducting baseline environmental monitoring;
(b)
conducting impact monitoring;
(c)
carrying out remedial actions described in the Event/Action
Plans of the EM&A Manual in accordance with the time frames set out in the
Event/Action Plans, or as agreed by the Director, in case where specified
criteria in the EM&A Manual are exceeded; and
(d)
logging and keeping records of details of all parameters
within 3 working days of the collection of data or completion of remedial
action(s), for the purpose of preparing and submitting the monthly EM&A
Reports and to make available for inspection on site.
3.3 Four
hard copies and one electronic copy of the Baseline Monitoring Report shall be
submitted to the Director at least 2 weeks before the commencement of
construction of the Project. The submissions shall be
certified by the ET Leader and verified by the IEC as complied with the
requirements as set out in the EM&A Manual before submission to the
Director. Additional copies of the submission shall be provided upon
request by the Director.
3.4 Four hard copies and one electronic copy of monthly EM&A
Report shall be submitted to the Director within 2 weeks after the end of each
reporting month throughout
the entire construction period. The EM&A Reports shall include a summary of
all non-compliance. The submissions shall be certified by the ET Leader and
verified by the IEC as complying with the requirements as set out in the
EM&A Manual before submission to the Director. Additional copies of the
submission shall be provided to the Director upon request by the
Director.
3.5 All EM&A data
submitted under this Permit shall be true, valid and correct.
4. Electronic Reporting
of EM&A Information
4.1 To facilitate public
inspection of EM&A Reports via the EIAO Internet Website and at the EIAO
Register Office, electronic copies of these Reports shall be prepared in Hyper
Text Markup Language
(HTML) (version 4.0 or later) and in Portable Document Format (PDF version 1.3
or later), unless otherwise agreed by the Director and shall be submitted at
the same time as the hardcopies as described in Conditions 3.3 and 3.4 of
this Permit. For the HTML version, a content page capable of providing
hyperlink to each section and sub-section of these Reports shall be included in
the beginning of the document. Hyperlinks to all figures, drawings and tables
in these Reports shall be provided in the main text from where the respective
references are made. All graphics in these Reports shall be in interlaced GIF, JPEG or PDF format unless otherwise agreed
by the Director. The content of the electronic copies of these Reports must be
the same as the hardcopies.
4.2 The Permit Holder shall set up a dedicated website and
notify the Director in writing the internet address where the environmental
monitoring and project information is to be placed
within one month after the commencement of construction of the
Project. All environmental monitoring results described in
Condition 4.1 above and all submissions required by this
Permit shall be made available to the public via this dedicated website to be
set up by the Permit Holder in the shortest time practicable, and in no event
later than 2 weeks after the relevant environmental monitoring data are
collected or become available, unless otherwise agreed with the Director. The
Permit Holder shall maintain the dedicated website for public access of the
environmental monitoring data and reports throughout the entire construction
period and until two months after the last EM&A
report is uploaded,
or otherwise as agreed by the Director.
4.3 The internet website as described in Condition 4.2 above shall
enable user-friendly public access to the monitoring data and project information
including the EIA report, the environmental permit(s) and project profile of the
Project. The internet website shall have features capable of:-
(a) providing access to
all environmental monitoring data collected since the commencement of
construction and all submissions under this permit;
(b) searching by date;
(c) searching by types of
monitoring data; and
(d) hyperlinks to
relevant monitoring data after searching;
or otherwise as agreed by the Director.
Table 1 - Noise mitigation measures
to mitigate traffic noise impact (referred in Condition 2.18)
|
ID |
Type of Mitigation Measures |
Approximate Length |
Figure
/ Location |
(a) |
SE1 |
7m tall semi-enclosure |
59m |
Figure
2a Sau Mau Ping Road |
(b) |
CT1 |
7m tall cantilevered noise barrier with 3.5m long cantilever (at
45¢X) |
97m |
Figure 2a Sau Mau Ping Road |
(c) |
CT2 |
5.5m tall cantilevered noise
barrier with 3.5m long cantilever (at 30¢X) |
77m |
Figure
2a Sau Mau Ping Road |
(d) |
CT3 |
5.5m tall cantilever noise barrier with 3.5m long cantilever (at
45¢X) |
91m |
Figure
2a Lin Tak Road flyover |
(e) |
VB1 |
3m vertical noise barrier |
92m |
Figure
2a Sau Mau Ping Road |
(f) |
CT4 |
7m tall cantilevered noise barrier with 3.5m long cantilever (at
45¢X) |
24m |
Figure
2b Clear Water Bay Road /On Sau Road |
(g) |
SE2 |
7m tall semi-enclosure |
146m |
Figure
2b Clear Water Bay Road /On Sau Road |
(h) |
FE1: |
7m tall full-enclosure |
130m |
Figure
2c New Clear Water Bay Road |
(i) |
CT5 |
7m tall cantilevered noise barrier with 3.5m long cantilever (at
45¢X) |
45m |
Figure
2c New Clear Water Bay Road |
(j) |
CT6 |
7m tall cantilevered noise barrier with 3.5m long cantilever (at
45¢X) |
40m |
Figure
2c New Clear Water Bay Road |
Remarks: This table is to be read in
conjunction with Figures 2a to 2c of
this Permit.
Notes:
µù:
1. This Permit consists
of three parts, namely, Part A (Main Permit), Part B (Description of Designated Project) and Part C (Permit Conditions). Any person relying on this
permit should obtain independent legal advice on the legal implications under
the EIAO, and the following notes are for general information only.
¥»³\¥iÃÒ¦@¦³3³¡¡A§YA³¡
(³\¥iÃÒ¥Dn³¡¤À)¡FB³¡
(«ü©w¤uµ{¶µ¥Øªº»¡©ú) ¤ÎC³¡
(³\¥iÃÒ±ø¥ó)¡C¥ô¦ó´©¤Þ¥»³\¥iÃÒªº¤H¤h¶·´NÀôµû±ø¨Òªºªk«ß§t·N¼x¸ß¿W¥ßªk«ß·N¨£¡A¤Uzµù¸Ñ¥u¨Ñ¤@¯ë°Ñ¦Ò¥Î¡C
2. If there is a breach
of any conditions of this Permit, the Director or his authorized officer may,
with the consent of the Secretary for the Environment, order the cessation of
associated work until the remedial action is taken in respect of the resultant
environmental damage, and in that case the Permit Holder shall not carry out
any associated works without the permission of the Director or his authorized
officer.
¦p¹H¤Ï¥»³\¥iÃÒªº¥ô¦ó±ø¥ó¡A¸pªø©ÎÀò±ÂÅv¤Hû¼x±oÀô¹Ò§½§½ªøªº¦P·N«á¥i°Ç¥O°±¤î¬ÛÃö¤uµ{¡Aª½¦Ü³\¥iÃÒ«ù¦³¤H¬°©Ò³y¦¨ªºÀô¹Ò·l®`±Ä¨ú¸É±Ï¦æ°Ê¬°¤î¡C¦b¦¹±¡ªp¤U¡A³\¥iÃÒ«ù¦³¤H¥¼¸g¸pªø©ÎÀò±ÂÅv¤Hû¦P·N¡A¤£±o¶i¦æ¥ô¦ó¬ÛÃö¤uµ{¡C
3. The Permit Holder
may apply under Section 13 of the EIAO to the Director for a variation of the
conditions of this Permit. The Permit Holder shall replace the original permit
displayed on the Project site by the amended permit.
³\¥iÃÒ«ù¦³¤H¥i®Ú¾ÚÀôµû±ø¨Ò²Ä13±øªº³W©w¦V¸pªø¥Ó½Ð§ó§ï¥»³\¥iÃÒªº±ø¥ó¡C³\¥iÃÒ«ù¦³¤H¶·§â¸gק諸³\¥iÃÒ´À´«¦b¤uµ{¶µ¥Ø¤u¦a¤º®i¥Üªºì¦³³\¥iÃÒ¡C
4. A person who assumes
the responsibility for the whole or a part of the designated project(s) may,
before he assumes responsibility of the designated project(s), apply under
Section 12 of the EIAO to the Director for a further environmental permit.
©Ó¾á¤uµ{¶µ¥Ø¾ã¶µ©Î³¡¤À¤uµ{ªº³d¥ôªº¤H¡A¦b©Ó¾á³d¥ô¤§«e¡A¥i®Ú¾ÚÀôµû±ø¨Ò²Ä12±øªº³W©w¦V¸pªø¥Ó½Ð·sªºÀô¹Ò³\¥iÃÒ¡C
5. Under Section 14 of
the EIAO, the Director may with the consent of the Secretary for the Environment,
suspend, vary or cancel this Permit.
The suspended, varied or cancelled Permit shall be removed from display
at the Project site.
®Ú¾ÚÀôµû±ø¨Ò²Ä14±øªº³W©w¡A¸pªø¥i¦bÀô¹Ò§½§½ªøªº¦P·N¤U¼È®É¦Q¾P¡B§ó§ï©Î¨ú®ø¥»³\¥iÃÒ¡C¾D¼È®É¦Q¾P¡B§ó§ï©Î¨ú®øªº³\¥iÃÒ¥²¶·±q¤uµ{¶µ¥Ø¤u¦a°£¤U¡A¤£¦A®i¥Ü¡C
6. If this Permit is
cancelled or surrendered during construction or operation of the Project,
another environmental permit must be obtained under the EIAO before the Project
could be continued. It is an
offence under Section 26(1) of the EIAO to construct or operate a
designated project listed in Part 1 of
Schedule 2 of the EIAO without a valid environmental permit.
¦pªG¥»³\¥iÃÒ¦b¤uµ{¶µ¥Ø«Ø³y©ÎÀç¿ì´Á¶¡¨ú®ø©Î¥æ¦^¡A«h¦bÄ~Äò¶i¦æ¤uµ{¶µ¥Ø¤§«e¡A¥²¶·¥ý®Ú¾ÚÀôµû±ø¨Ò³W©w¨ú±o¥t¤@¥÷Àô¹Ò³\¥iÃÒ¡C®Ú¾ÚÀôµû±ø¨Ò²Ä26(1)±øªº³W©w¡A¥ô¦ó¤H¦b¨S¦³¦³®ÄÀô¹Ò³\¥iÃÒªº±¡ªp¤U«Ø³y©ÎÀç¿ìÀôµû±ø¨Òªþªí2²Ä1³¡©Ò¦C©úªº«ü©w¤uµ{¶µ¥Ø¡A§YÄݥǸo¡C
7. Any person who
constructs or operates the Project contrary to the conditions in the Permit,
and is convicted of an offence under the EIAO, is liable:
¦p¥ô¦ó¤H¦b¹H¤Ï¥»³\¥iÃÒªº±ø¥ó¤U«Ø³y©ÎÀç¿ì¤uµ{¶µ¥Ø¡A®Ú¾ÚÀôµû±ø¨Ò¡A§YÄݥǸo-
(i)
on a first conviction on
indictment to a fine of $2 million and to imprisonment for 6 months;
¤@¸g´`¤½¶Dµ{§Çº¦¸©w¸o¡A¥i³B»@´Ú200¸U¤¸¤ÎºÊ¸T6Ó¤ë¡F
(ii)
on a second or subsequent
conviction on indictment to a fine of $5 million and to imprisonment for 2
years;
¤@¸g´`¤½¶Dµ{§Ç²Ä¤G¦¸©Î¨ä«á¨C¦¸©w¸o¡A¥i³B»@´Ú500¸U¤¸¤ÎºÊ¸T2¦~¡F
(iii)
on a first summary conviction to
a fine at level 6 and to imprisonment for 6 months;
¤@¸g´`²©öµ{§Çº¦¸©w¸o¡A¥i³B²Ä6¯Å»@´Ú¤ÎºÊ¸T6Ó¤ë¡F
(iv)
on a second or subsequent summary
conviction to a fine of $1 million and to imprisonment for 1 year; and
¤@¸g´`²©öµ{§Ç²Ä¤G¦¸©Î¨ä«á¨C¦¸©w¸o¡A¥i³B»@´Ú100¸U¤¸¤ÎºÊ¸T1¦~¡F¤Î
(v)
in any case where the offence is
of a continuing nature, the court or magistrate may impose a fine of $10,000
for each day on which he is satisfied the offence continued.
¦b¥ô¦ó±¡ªp¤U¦p¸Ó¸o¦æÄݳsÄò©Ê½è¡Aªk°|©Îµô§P©x¥i´N¨ä«H¯Ç¸Ó¸o¦æ³sÄòªº¨C¤@¤Ñ¥t³B»@´Ú10,000¤¸¡C
8. The Permit Holder
may appeal against any condition of this Permit under Section 17 of the EIAO
within 30 days of receipt of this Permit.
³\¥iÃÒ«ù¦³¤H¥i¦b±µÀò¥»³\¥iÃÒ«á30¤Ñ¤º¡A®Ú¾ÚÀôµû±ø¨Ò²Ä17±ø´N¥»³\¥iÃÒªº¥ô¦ó±ø¥ó´£¥X¤W¶D¡C
9. The Notes are for
general reference only and that the Permit Holder should refer to the EIAO for
details and seek independent legal advice.
¤Wzµù¸Ñ¥u¨Ñ¤@¯ë°Ñ¦Ò¥Î¡A±ýª¾¦³Ãö¸Ô±¡¡A³\¥iÃÒ«ù¦³¤H¶·°Ñ¾\Àôµû±ø¨Ò¤Î¼x¸ß¿W¥ßªk«ß·N¨£¡C
Environmental Permit
No. EP-513/2016
Àô¹Ò³\¥iÃÒ½s¸¹EP-513/2016
| Figure 1a ¡V 1d || Figure 2a ¡V 2c |
[ Back to First Page ] / [ Back to Main Index ]